CONTRACTOR
SUMITOMO CORPORATION
Black & Veatch (B&V)
Mitsui Engineering & Shipbuilding Co.,Ltd. (MES)
SUB-CONTRACTOR
Jurong Engineering Limited (JEL)
Babcock & Wilcox (B&W)
Toshiba Corporation (TSB)
Contents
1. INTRODUCTION ........................................................................................................................................... 2
2. DOCUMENTS REFERENCE ............................................................................................................................ 3
2.1 ANSI/ASME Code for Process Piping B31.3, ASME 1 (latest revision). .......................................... 3
2.2 Local Authority and / or local regulations for system of pressure vessels related testing. ................. 3
2.3 Final Design Report. ............................................................................................................................ 3
2.4 DH3Ext.EVN Specification on CWP. .................................................................................................... 3
3. SCOPE OF WORKS ........................................................................................................................................ 4
3.1 Requirement for Specification Piping System ..................................................................................... 4
3.2 General requirements and preparation for test ................................................................................. 4
3.3 System Inspection ............................................................................................................................... 4
4. ERECTION EQUIPMENTS, MATERIALS & TOOLS .......................................................................................... 5
5. WORKING SEQUENCE/PROCEDURE ............................................................................................................ 6
5.1 Hydrostatic test ................................................................................................................................... 6
5.2 Retest .................................................................................................................................................. 7
5.3 Test Completion .................................................................................................................................. 7
5.4 Verification of Test .............................................................................................................................. 7
6. QUALITY CONTROL (INSPECTION TEST PLAN) ............................................................................................. 9
7. DETAIL ERECTION SCHEDULE......................................................................... Error! Bookmark not defined.
8. ORGANIZATION CHART ............................................................................................................................. 10
9. MANPOWER MOBILIZATION ......................................................................... Error! Bookmark not defined.
10. RISK ASSESSMENT/JOB SAFETY ANALYSIS (JSA) .................................................................................... 11
11. TEST PACKAGE DOCUMENT .................................................................................................................. 14
1
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
INTRODUCTION
The purpose of this procedure is to provide the guidance for conducting field hydrostatic test for the
Circulating Water piping and test the integrity of the site welding prior to the operation / service of system.
2
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
1. DOCUMENTS REFERENCE
Unless otherwise specifically indicated in writing, all work shall be performed in accordance with requirements
of below code and standard and those of the latest editions at the time of call for tender of the documents listed
hereafter:
1.1 ANSI/ASME Code for Process Piping B31.3 (2014 edition), Local Authority and / or local regulations for
system of pressure vessels related testing.
1.2 Final Design Drawing.
1.3 DH3Ext.EVN Specification on CWP. Refer to (Part 2, Vol. 2 Specific Technical Specifications Section 4: Balance
of Plant from page 61 to 80)
3
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
2. SCOPE OF WORKS
This procedure describes the general requirements and procedure for field pressure testing of CW piping
system which has been fabricated, installed and connected to equipment integral components and is to assure
mechanical strength and tightness for Project.
Following piping system need not be field tested:
Instrument piping lead lines between the root valve at the process or utility line and the connected
instrument, and control piping used to connect air or hydraulically operated control apparatus.
The lines and system which are open to the atmosphere, such as vents or drains downstream of the last
shutoff valve.
valve so that the pressure applied under the seat. If this is not possible, remove or jack up the check valve
completely or provided necessary filler piece.
-
3. MATERIALS & TOOLS
5
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
4. WORKING SEQUENCE/PROCEDURE
6
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
Time (hr)
Pressure Chart Table
4.2 Retest
If any leakage is found during the pressure test, the test shall be repeated to the specified pressure after
required Repair had been made.
Any lines changed after they have been tested shall be retested or relevant NDT shall be carried out as an
alternate based on commissioning / operation schedule. Refer to Part 2, Vol. 1 General Technical
Specifications Page 69, Section 1: Project Requirements and ASME BPVC-IX-2015
4.3 Test Completion
In the event that repairs or additions are made following the pressure test, the affected piping shall be
retested at the pressures originally specified for the test. Retesting of minor repairs or additions may be
waived subject to owner approval. All tests should be carried out in accordance with the agreed
procedures as detailed in the Inspection and Test Plan.
After completing of testing, all temporary blank and blinds shall be removed; all operating blinds returned
to proper position and short pieces of piping which have been removed shall be reinstalled with new
gaskets. All valves that were closed during hydrostatic test shall be opened to insure draining the bonnet
cavity. Lines which are being drained after testing shall have all vents open. Piping system downstream of
check valves should be inspected to insure complete drainage.
After line have been drained, temporary support shall be removed.
Flange joints all the test blind has been removed shall be retested.
Special length bolting and flat non-asbestos gaskets shall be removed and replaced with line class and new
gaskets after completion of hydrostatic test.
Instruments which were removed or blocked out for test shall be reinstalled and blocks placed in the
normal operating position after test.
4.4 Verification of Test
The execution of the test shall be witnessed and approved by all corresponding parties and the test results
be recorded in the specific Records (Pressure Test Record - Form), which must include all essential
7
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
information and details such as; (ITP reference, Procedure, Test pressure, Medium, Duration, etc.).
8
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
9
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
10
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
Ensure the equipment/tools used for pressure testing are free from
Defective tools and equipment Major Occasional High
defect and good enough to do hydro testing.
Pipe line vibration more. Moderation Occasional Medium Check for proper supports
Improper tools Moderation Occasional Medium To make tools inventory prior to work
Pump failure Moderation Occasional Medium Electrician and Mechanic always stand by to solve problems
Flow meter failure Moderation Occasional Medium Calibration certificate verification and remedial action will be taken.
Water spillage Moderation Occasional Medium All leaks will be arrested during initial start of pump.
11
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
Heavy leaks-boiler water wall Upon observation of heavy leaks, the boiler will be depressurized.
Major Occasional High
panels The water will collected through flash tank.
3 Pressurizing Exceeding the test pressure Major Occasional High Ensure that relief valve at the pump is set at the same pressure.
Damage to the
Moderation Occasional Medium Observe and act not to increase the pressure beyond the limit
equipment/system
Unattended pressurizing Do not leave the pressurizing pump un attended when the hydro
Moderation Occasional Medium
pump/pressure regulation test is ongoing.
12
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
13
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
14
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
15
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
16
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
17
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
18
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
19
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
20
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
21
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
22
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
23
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
24
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
25
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
26
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
27
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
28
JURONG ENGINEERING LTD.
PRESSURE TEST PROCEDURE FOR
CIRCULATING WATER PIPING REV : A
DUYEN HAI 3 EXTENSION THERMAL POWER PLANT PROJECT, VIETNAM
29