Professional Documents
Culture Documents
The Government of the The Republic of Mozambique has secured a loan from the African
Development Bank (AfDB) towards the cost of Rehabilitation and Upgrading of the N13 Road
Between Muita and Massangulo (94Km) in Niassa Province. The project supervised by: LEA
Associates South Asia Private in JV with LUXCONSULT in association with COTOP.
The N13, between Cuamba and Lichinga, runs from city of Cuamba to the town of Lichinga in
Niassa province, a total of 313 Km. Lichinga is the provincial capital of Niassa. The project Road,
Muita to Massangulo, is a section of NH13, lying between Cuamba and Lichinga. At Mandimba,
along the Project Road, the R1213 prosodies the connection between the N13 and the M3
Mangochi-Liwonde road in Malawi.
Objectives of The Reports
The purpose of the report is to summarize and analyse the performance of safety and
environmental works carrying out for rehabilitation and construction of N13 roads, between
Muita and Massangulo during the month of August 2018.
Objectives of the environmental management plan
The main objectives of an environmental management plan are,
1) OBJECTIVES OF THE ENVIRONMENTAL MANAGEMENTPLAN
2) KEY ENVIRONMENTAL ISSUES
3) KEY ENVIRONMENTAL ISSUES INDENTIFIED IN E.M.P
4) A BRIEF SUMMARY OF ACTION TAKEN IN JULY
5) ENVIROMENTAL MONITORING ACTIVITIES AND RESULTS
6) IMPLEMENTATION OF THE ENVIRONMENTAL PROTECTION MEASURES
7) WASTE MANAGEMENT
8) QUARRY AND BORROW PITS
9) DUST AND NOISE
10)SAFETY AND SECURITY PRECAUTION
11)H.IV AND AIDS
12)FUTURE KEY OF THE PROGRAM AND WORKING METHOD
13)COMPLAINTS AND NOTIFICATION
14) SCHEDULE OF ENVIRONMENTAL MITIGATION MEASURES
AUGUST, 2018 Appendix – 13
Observation:-
The contractor shall take necessary measures on the closed borrow areas to control water
inundation on site, returning the top soil In the borrow pits that may be used for agriculture since
they will act us water collectors.
C. WASTE MANAGEMENT
Necessary precaution are implemented to ensure effectiveness of environmental appropriate
system of collecting transporting and depositing of waste are implemented.
Waste came from workers accommodation are deposited in designated places within the camp
before delivery to the approved local camp site.
Used oil and other machinery waste are deposited on the approved location
Oil is keened in tanks to prevent it from contamination of soil.
NOTE;
STILL SAME WORKERS DO NOT HAVE PROTECTIVE EQUIPMENT ON THE SITE THIS
ALRADY REPORTED TO THE CONTRACTOR WITHIN THE REPORTING MONTH.
DUST;
In dusty areas such as the new embankment construction areas or temporary unpaved deviation
and access roads the surface is sprayed with water using trucks equipped with sprinklers.
This procedure is executed effectively to control
AUGUST, 2018 Appendix – 13
NOTE;
Watering is only done in the working sections only, I recommend that at the mandimba town roads
should be watered always all because same road are used as road diversions consider this facts
that their have schools,hospital,government offices, market,houses. For this reason ,
ALL ROAD SHOULD BE WATERED,
Special cleaning activities ware held at the vehicle and equipment maintenance areas.
Temporary warning boards such as (Danger, Authorized personnel is allowed ,No smoking
etc)were erected at the storage areas of fuel and dangerous materials.
Construction activities were stopped when there is a bad weather condition to prevent accident.
Construction vehicles had technical inspection and proper maintenance on regular basis.
Background:
LEA Associates have contracted Mr. Eduardo Langa to undertake Environmental Supervision
Services of a total of 91 km of road construction between Massangulo and Muita in Niassa province.
The scope of activities include also the following:
Rehabilitation of the road section between Muita to Mandimba;
Rehabilitation of a 3,5 km of road section from the center of Mandimba town to the border
gate between Mozambique and Malawi;
Construction of a 6,5 km of a by-pass road section from the Mandimba border to link directly
to the N13 road without going through the Mandimba town;
Rehabilitation of an approximately 1 km of Town-link between Mandimba by-pass to Km 0
road;
Rehabilitation of a total of 5,1 Km of road within the town of Mandimba;
Rehabilitation of the road section between Mandimba and Massangulo.
The scope of services comprises all activities pertaining to Environmental and Social management
of the Main Contract as provided for Phase II Contact Supervision Services as well as those under
technical proposal for carrying out of Works on Environmental and Social management of the main
contract.
Methodology:
The key methodology for the site visit was based on direct observation as well as discussions held
with the representatives of the Contractor, Supervising Engineer and the workers in different work
fronts, whereby staff involved in the activities provided inputs on the various aspects of
environmental, health and safety of the project.
Observations:
Work Progress – The Contractor’s representative indicated that a good progress has been made,
however, part of the equipment is not yet on site and is expected to reach the site by September.
AUGUST, 2018 Appendix – 13
Despite this delay in equipment mobilization, the road works have progressed significantly, having
completed the cement stabilization work between Muita to Mandimba (15 km), and with ongoing
progress on this activity on the road section between Mandimba and Massangulo (18 km). In
addition, 40 of the total 70 culverts have been completed and clearing and grabbing and
construction of detour toads has been completed in all fronts. The quarry site remains productive
and at least one active borrow site is supplying the inserts materials for the active work fronts.
Dust Emission:
Dust emission remain a significant challenge given that the works are continually stretching, making
it difficult to control dust emission effectively in all the road sections. Vehicles were seen in priority
areas suppressing dust with water sprinkling, however, effective dust emission control will remain a
challenge particularly during the coming hot and dry season. Dust emission is an issue of concern
since many families sell their products (beans, maize, vegetables among others) along the roadside
markets and in general dust issue is not taken into account. It is recommended that the Contractor
and Supervision work to identify sensitive areas and ensure dust suppression on daily basis. Local
communities should also be warned about the need to protect their food,water, market products
against dust emission.
Signage:
Road signage shall be reviewed to ensure that more visible and communicative signs are placed in
all adequate locations. Signage should at all times be translated into to ensure that road users as
well as workers follow the instructions and minimize the potential for hazards. Chinese and English
signage may not be understood by local workers and road users who are Portuguese speakers.
On the other hand, and in general, the project observes good road signage with clear instructions for
the road users, and allocation of flagman to direct traffic in critical areas. In order to improve road
signage, it is recommended that the Contractor work effectively to translate to Portuguese all road
signage as well as other signage in the different areas of the project.
almost 1.5m hall with no masks or ladder to facilitate their exit in case of collapse. The Contractor
took an immediate action, having stopped the works and instructed the site Team Leader to make
the necessary corrections. Risk assessment needs to be undertaken and adequate use of PP shall
be enforced to minimize the potential for hazards in carrying out of works.
9. Mixture of waste deposited in an open space. 10. Used oils left exposed to rain and spills.
11. Borrow pit exploration with topsoil’s stockpiled for later use during site reinstatement
AUGUST, 2018 Appendix – 13
Both the Contractor and the Supervising engineer will be located at the same construction work
camp. The new workshop area will also be located inside the camp, and will be equipped with all
needed facilities including wastewater management to separate used oils from water and ensure
that no contaminants are released to the environment. The camp includes also a fuel storage that is
well built in a bounded location to restrict access and to avoid spills of fuels that would contaminate
the soils and groundwater.
Good progress in the construction of bridges and culverts along the project. Challenges are with
regards to the need to control soils erosion and sedimentation as a result of storm water during the
current rain season.