You are on page 1of 10

ARTICLE IN PRESS

Waste Management xxx (2006) xxx–xxx


www.elsevier.com/locate/wasman

Evaluation of investments in recycling centres for construction


and demolition wastes in Brazilian municipalities
a,*
K.R.A. Nunes , C.F. Mahler b, R. Valle a, C. Neves a

a
Department of Production Engineering, Federal University of Rio de Janeiro, C.P. 68507, CEP 21945-970, Rio de Janeiro, RJ, Brazil
b
Department of Civil Engineering, Federal University of Rio de Janeiro, C.P. 68506, CEP 21945-970, Rio de Janeiro, RJ, Brazil

Accepted 22 September 2006

Abstract

There are very few construction and demolition (C&D) waste recycling centres in Brazil. To encourage the building and operation of
new units, data were collected and analysed relating to C&D waste management and recycling in Brazil. Based on the results of this
analysis, a conceptual model is presented for conducting viability studies of future C&D waste recycling centres.
Applying this model to verify the viability of private recycling centres, the results show that under current market conditions in Brazil,
C&D waste recycling centres are not financially feasible based solely on revenue from the sale of processed products. Nevertheless, under
the same market conditions, the recycling centres could be economically viable for public authorities depending on the particular circum-
stances of each municipality. The feasibility, however, depends on continuity and the production volume reached.
The conceptual model, the results of its applications and the discussions about the experiences of existing centres can strongly support
public authorities and private initiatives in their decision-making about investments in Brazil and in other developing countries.
Ó 2006 Elsevier Ltd. All rights reserved.

1. Introduction and just a part (5.5%) of the remainder was recycled


(IBGE, 2000).
In 2000, according to IBGE (2000), 99.4% of Brazilian There is still no detailed information about the quantity
municipalities had some public collection of domestic of C&D (construction and demolition) waste produced in
waste, but only 33.1% of the municipalities had 100% of Brazil, but some large cities, such as São Paulo, Rio de
their housing units attended with public waste collection. Janeiro and Salvador, have specific estimates. In these
A daily production of 150,000 t of solid waste represented three cities, the average C&D waste production was
approximately 0.90 kg per inhabitant. For the sake of com- 0.49 kg per inhabitant/day, corresponding to around 31%
parison, Germany (in 2000) had a daily generation per of the total collected domestic waste (Nunes, 2004).
capita of 0.90 kg, USA (in 2004), 2.0 kg and Canada (in According to Ingalls (2000), C&D waste in the USA was
2004), 1.7 kg (Boranga, 2005; Calderoni, 2004). between 15% and 30% of the collected waste disposed in
In Brazil, 21.3% of the disposal of collected domestic landfill sites. It was estimated that in 1996, 136 million t
waste was in waste dumps, without protection to prevent of C&D waste (except for wastes from road and bridge
environmental impacts on the neighbourhood. Besides, construction and excavations) were produced daily in the
only 5.5% of all collected domestic waste was sent to other USA, which represented approximately 1.27 kg per inhab-
destinations (such as composting plants, incineration and itant. In the USA, 3500 C&D waste recycling centres pro-
recycling plants). This means that 94.5% of collected cessed between 20% and 30% of this produced C&D waste
domestic waste was sent to waste dumps or to landfill sites (EPA, 2000).
In EEA (2002) information is given about C&D waste
*
Corresponding author. Tel.: +55 21 2562 7848; fax: +55 21 2290 6626. recycling in some European countries. Denmark, Germany
E-mail address: katia_nunes@web.de (K.R.A. Nunes). and Holland recycle more than 80% of the C&D waste pro-

0956-053X/$ - see front matter Ó 2006 Elsevier Ltd. All rights reserved.
doi:10.1016/j.wasman.2006.09.007

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

2 K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx

duced; Finland, Ireland and Italy recycle between 30% and a. Market and competition analysis;
50% and Luxembourg only 10%. b. Estimated generation of C&D waste;
Among the 5507 Brazilian municipalities, only 11 c. Estimated revenues and costs;
(0.2%), besides the Federal District, have C&D waste recy- d. Analysis of investments; and
cling centres. Thirteen centres (of which seven are operat- e. Breakeven point.
ing, one is restarting the operation and five have stopped
operating) are stationary plants and recycle part of the These elements form a conceptual model for viability
C&D waste produced in local communities. It can, there- studies for C&D waste recycling centres. Stages (a) and
fore, be concluded that a large part of the C&D waste pro- (b) depend on the geographic location of the centre. Since
duced in Brazil is not recycled. a location for the recycling centre project is not always
Nonetheless, this situation is changing. Since the publi- specified when preliminary studies are being conducted,
cation of CONAMA1 Resolution no. 307, dated 5th July the viability study that has been carried out in this study
2002, all Brazilian municipalities are obliged to prepare only includes the other stages: estimated revenues and costs
and implement strategies for sustainable management of (a stage that is also influenced by location, but only par-
C&D waste (MMA, 2002). In the justifications for this res- tially), analysis of investments and breakeven point.
olution, mention was made of the feasibility of the produc- It should be emphasised that, once the region is chosen
tion and use of C&D waste materials. However, there has in which a certain centre will be constructed, it is essential
been relatively little research in Brazil to prove the techni- that the first two stages be included in the viability studies,
cal and economic viability of C&D waste recycling centres. as well as the estimated revenues and costs, which depend
Results of economic viability analyses for C&D waste on location (e.g., cost of land and transport and waste dis-
recycling facilities in the USA, India and Taiwan were posal costs).
quoted in some studies, but few details about the method-
ology used and data collection were presented (MAC- 3. Methodology
REDO, 2006; TIFAC, 2006; Huang et al., 2002). Kohler
(1997) showed economic results of some German facilities, The data collection involved four activities. Initially, a
which incorporate a significant number of machines, in bibliographic review was carried out. Then, a number of
contrast to the simple C&D recycling facilities common professionals from the sector were consulted (such as
in countries such as Brazil, India, Taiwan and Denmark equipment and material suppliers, businessmen from the
(Nunes, 2004; TIFAC, 2006; Huang et al., 2002). mining and recycling sectors and producer federations),
This study was carried out with the objective of compil- who were qualified to provide essential data about C&D
ing data relating to C&D waste management and recycling waste recycling. The data on the thirteen Brazilian C&D
in Brazil. The data was then evaluated and a conceptual waste recycling centres were obtained through question-
model for financial viability studies of C&D waste recy- naires sent to municipalities and visits to some of the
cling centres proposed. The model was applied to deter- municipalities and facilities. Most of the data were col-
mine the feasibility of private recycling centres in Brazil. lected between January and November 2003.
In addition, the economic viability of existing recycling This phase of the research showed that there are no
centres was examined, as well as the reasons for the suc- large-scale private C&D waste recycling centres in Brazil.
cessful and the unsuccessful experiences. As a result, the remainder of the study was divided into
two parts. One study, aimed at private enterprise, esti-
2. Viability analysis: concepts mated the costs for future C&D waste recycling centres,
one on a small scale and the other medium scale, with data
The decision to set up a recycling centre should only be collected in the market. The scenario technique with alter-
made if its economic and financial viability can be proven nating hypotheses was used in this analysis, providing
in a pre-project analysis that covers, among other aspects, results through the Net Present Value method (NPV),
the location of the plant, market studies, initial contacts which indicated under which conditions the facilities stud-
with local public authorities to clarify possible require- ied would be viable.
ments and consultations for the licensing of the facility In a second study concerned with the public arena,
(Kohler, 1997). actual data was used in the financial viability analysis.
UNIDO (1987) presents a structural model for conduct- Input data was obtained from the management of existing
ing viability studies of complex projects, involving large recycling centres to compare costs and benefits.
investments from various sources of financing. Simplifying
this structure and adding the elements described by Kohler 4. Conceptual model: comparison between operating
(1997), the essential stages in pre-viability studies of C&D privately run and state run recycling centres
waste recycling centres were identified, as follows:
Economic and financial viability studies are usually con-
ducted in the case of private recycling centres (not financed
1
Brazilian Environmental Protection Agency. by the state). Public recycling centres, however, are often

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx 3

built without an in-depth analysis of economic and finan- fractions and a magnetic component removes the metallic
cial viability. The decision-making criteria of public fraction. The other fractions, excluding the mineral and
authorities (improvement of social living conditions, regio- metallic ones, are previously removed by hand before the
nal economic development, environmental protection, etc.) beginning of the crushing process. Table 1 shows the main
differ from the criteria used by private enterprises, which stages in the recycling process of the Brazilian facilities, the
are essentially based on financial return (Motta and main equipment used in this process and additional
Caloba, 2002; UNIDO, 1987). equipment.
During the data collection of the existing public waste Nunes (2004) presents the physical compositions of
recycling centres, it was observed that all of them were built C&D wastes of three large Brazilian cities (São Paulo,
on municipal land. Therefore, there was no investment in Rio de Janeiro and Salvador) and one medium size city
the acquisition of the land for the recycling centres. It (São Carlos). Among these four cities, the sum of mineral
was also found that some equipment, such as loaders and fractions (compound of materials such as concrete, bricks
dump trucks, were not considered investments because they and mortar) in the C&D waste was 96% on average (Salva-
wee on loan from other municipal bodies or were leased. dor had the lowest value at 94%). Research on national
In the viability study for private enterprise recycling cen- averages for physical compositions are still not available,
tres, the investments in procurement of land and equip- but as these cities use construction materials and building
ment must always be considered. In a study for public processes that are widespread in the urban areas of Brazil,
recycling centres, the investments in equipment should be a national average is probably close to the averages of the
taken into account, even when they are not always allo- aforementioned cities. Of the Brazilian population, 81%
cated to the centre. live in urban areas (IBGE, 2000).
Municipalities can consider in the viability analysis
some benefits of recycling facilities, such as savings in 5.2. Estimate of costs
C&D waste disposal and transport to landfills, and savings
in material procurement. 5.2.1. Fixed capital investment
The equipment used in C&D waste recycling centres
5. Results 1: Financial viability study for private enterprise requires substantial investment. Since the used equipment
recycling centres market, based on the mining sector, is strong in Brazil, this
was taken into account in the analysis. Table 2 illustrates in
5.1. Introduction a summarised form the fixed capital investments necessary

According to Peng et al. (1997), ‘‘the true success of a


C&D recycling operation must be determined by establish- Table 1
C&D waste recycling process and secondary operationsa
ing the scale of the operation to be implemented and its
resulting economics’’. The consultations of professionals Stages Equipment
in the sector in Brazil showed that private projects with less C&D waste recycling process
than 20 tonnes per hour (t/h) of C&D waste processing Planning of granulometric profile Computer, office and
instruments
flow will probably not be financially viable, due to low pro-
Reception of trucks and measurement Scale (for production around
ductivity and low prices of the processed product. It was of weight and volume 100 t/h) and instruments
also found that a centre with a nominal processing capacity Truck guided to unloading point –
of about 50 t/h would have implementation and opera- Unloaded material inspected; unusable Tools and mechanical
tional costs equivalent to those of a 100 t/h centre. large-scale and contaminated excavator
material removed
Therefore, it was concluded that two different recycling
Material sent to secondary separation Mechanical excavator,
centre projects needed to be analysed: one on a small scale line, where it is cleaned conveyer belt and vibrating
(20 t/h) and the other medium size (100 t/h). It was also belt feeder
assumed that, due to the lack of tradition in the use of pro- Material sent to storage pile Conveyer belt
cessed products, as well as to the lack of C&D waste recy- Material crushed and classified Vibrating grid, conveyer belt,
conical crusher and vibrating
cling projects in the country, the viability of future private
sieve
recycling centres will initially be somewhere between the Product sent to storage pile Conveyer belt
two capacities above.
Additional equipment
According to MACREDO (2006), for C&D waste recy- Crushing, transport and classification Particle control pulverising
cling in the USA to be economically feasible, it has to be system
high-volume. In the American equipment market the major Operation of wheeled equipment Workshop, lubrication and
C&D debris processing facilities have daily capacities that fuel tank
range from less than 50 t to more than 2500 t. Secondary operations
The technology adopted in Brazil for the recycling of Handling of stock Dump truck
C&D waste is simple and labour intensive. In those pro- Freight Dump truck
a
jects, the required equipment processes only the mineral Basically for processing mineral and metal fractions.

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

4 K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx

Table 2 used, the dynamic methods are one of the best tools for
Investment in fixed capital (summary)a decision-making in Economic Engineering. The method
Item Details 20 t/h Capacity 100 t/h Capacity used in the financial analysis of this research was the Net
Total Costs (in Total Costs (in Present Value (NPV) that is one of the most frequently
US$) US$)
used dynamic methods. Besides the NPV, the scenario tech-
Used New Used New nique is also applied in the analysis. This technique allows,
Equip. Equip. Equip. Equip.
in a financial analysis, the estimate of favourable and unfa-
1 Construction 13,300 13,300 13,300 13,300 vourable results under the considerations of the occurrence
works
2 Equipment 150,000 309,000 370,000 776,500
of different hypotheses (Alexander, 1997; Motta and
3 Special 13,300 13,300 26,600 26,600 Caloba, 2002).
facilities Eight scenarios were used in the analysis, based on three
Total (not 176,600 335,600 409,900 816,400 hypotheses:
including
land) a. Nominal capacity: 20 t/h or 100 t/h;
Total/capacityb 8835 16,770 4090 8170 b. Equipment: new or used;
a c. Revenue from acceptance of C&D waste: yes or
Sources: SINDIBRITA, suppliers of crushing equipment and pro-
ducers of finished products. no.Hypotheses (a) and (b) have already been discussed.
b
Using the exchange rate of US $1 = R$ 3.00 (November 2003). Hypothesis (c) refers to charging of users (generators,
transporters and public authorities), a so-called ‘‘gate
fee’’, for each tonne of waste delivered to the centre.
for 20 t/h and 100 t/h recycling centres, according to pro- In addition to the above three, another two hypotheses
duction volumes and choice of new or used equipment. were included:
d. Is the cost of land included?
5.2.2. Operational Costs e. Are transport and waste disposal costs included?
Table 3 summarises the fixed and variable operational
costs of 20 t/h and 100 t/h recycling centres. The fixed costs In the simulated scenarios, the answers to (d) and (e)
include costs for labour, energy, maintenance, deprecia- were taken to be negative, since the corresponding esti-
tion, insurance, sales, consulting, interest and financing. mates depend on the location of the project, which is not
The variable costs refer basically to costs of spare parts defined in the viability study done in this research. It must
and fuel. This data gives the operational costs used in the be considered that when these costs are included, the over-
financial analysis carried out in Section 5.3. all costs of the project increase and the viability of the pro-
ject is affected. So, the results obtained by the simulation of
5.3. Investment analysis this research, which do not include all the possible costs,
would be worse should all costs be considered.
5.3.1. The scenarios When the scenario includes revenue from the acceptance
The comparison methods between alternative invest- of C&D waste, a financial simulation based on spread-
ments can be grouped into static and dynamic methods. sheets is used to estimate the lowest gate fee or price that
The dynamic methods differ from the static methods due can be charged per tonne (among the conditions of each
to time factors in the inputs and outputs of the each of scenario) to allow the project to be financially viable. This
the cash-flows by the use of interest rates. When properly happens when the financial analysis results in a NPV of
zero for the specific rate of return.
According to companies that produce finished products
Table 3 and employee federations from the area, the price of the
Operational costs (summary)a processed C&D product is a direct function of the conven-
Item Details 20 t/h Capacity Total 100 t/h Capacity Total tional product market. The hypothesis adopted in this
Costs (in US$) Costs (in US$) research was that the price of the processed product should
Used New Used New be at least 30% lower than the price of the conventional
Equip. Equip. Equip. Equip. product. Since the average price of the product for use as
Fixed costs base and sub-base materials for road building in Rio de
1 Labour 39,400 39,400 84,800 84,800 Janeiro is currently2 US $4.00/t (not including taxes or
2 Other fixed 98,200 114,070 420,280 460,980
freight) (SINDIBRITA, 2003), it is estimated that the price
costs
of the processed product should be around US $3.00/t (not
Variable costs including tax or freight).
3 Variable costs 36,000 36,000 140,000 140,000
Total 173,600 189,467 645,080 685,780
a
Sources: SINDIBRITA, suppliers of crushing equipment and pro-
ducers of finished products. 2
In November 2003.

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx 5

The percentage of rejects in C&D waste processing is that the BP in scenarios 1, 3, 5 and 7, will be reached at
assumed to be 20%3. This percentage is not significant in prices of US $1.67/t and US $3.33/t; recycling centres
the eight scenarios discussed here, since transport and processing 20 t/h will not reach the BP at the price of
other waste disposal costs associated with these rejects were US $1.67/t. Larger, 100 t/h recycling centres reach their
not included. The production volume of the product was BP around 110,000 t (production obtained from 65% of
assumed to be 80% of the nominal equipment capacity, days worked per year4). By charging US $3.33/t, 20 t/h
as usual in industrial projects. recycling centres reach their BP with a production of
27,000 t (production obtained from 80% of days worked
5.3.2. Results of the analysis per year), while 100 t/h recycling centres reach their BP
Using an annual interest rate of 12%, after tax (the at 78,000 t (production obtained from 45% of days
minimum value to be expected in the current Brazilian worked per year).
financial situation) the results for the eight scenarios In India, a feasibility analysis has been carried out for a
mentioned in Section 5.3.1 are given in Table 4. The recycling plant to process 25,000 t/y for mineral fractions
negative results of the even-numbered scenarios show of the C&D waste. According to TIFAC (2006), ‘‘due to
that C&D waste recycling centres under current market market preference of the customers to use natural aggre-
conditions are not financially viable. Recycling centres gate, recycled aggregates have to be marketed at a discount
fail to become financially viable solely through revenue to achieve sale of 25,000 t/y in 2/3 years time. The unit is
from the sale of processed products. The results are more viable but its operations highly sensitive to fluctuations in
negative if the price of land and waste disposal costs are sale price of recycled aggregate and capacity utilisation of
taken into account. For recycling centres to become the plant’’.
viable under current conditions, other sources of funds In Germany, because of such aspects as the high fixed
are indispensable, such as revenue from the capital investment and planning permits, C&D waste facil-
acceptance of C&D waste, tax benefits or other public ities can be economically viable only from a production of
subsidies. around 200,000 t/y (around 800 t/d) or more (Kohler,
Charging gate fees for the acceptance of C&D waste cre- 1997).
ates an additional option for revenue. Table 4 shows that in
the scenarios that include the charge, the best results (low- 6. Results 2: financial viability study for public recycling
est price paid per tonne to make the project viable) are centres
those of scenarios 5 and 7, with prices of US $0.40/t if sec-
ond-hand equipment is used and US $0.60/t if new equip- 6.1. General information about the recycling centres under
ment is employed, respectively, for 100 t/h recycling study
centres.
For the 20 t/h recycling centres in scenarios 1 and 3 to Some of the recycling centres included in this study
be viable, much higher prices are needed (US $2.52/t with had ceased operations for some time (weeks, months or
second-hand equipment and US $2.89/t with new equip- years) due to a variety of reasons, such as changes in
ment) than in scenarios 5 and 7. This indicates that a municipal recycling policy, cuts in municipal budgets,
greater production of the processed product facilitates the theft, vandalism of facilities, or problems with local
financial viability of the recycling centres. communities.
These results prove the previously adopted premise: the As can be seen from the age of equipment and time
financial viability of privately run recycling centres with operating columns in Table 5, the recycling centres that
processing capacities less than 20 t/h will probably be neg- have been operating continuously since their start-up are
ative, due to low production and low prices of processed recycling centres E, H, I, K and M. The recycling centres
products. It was found that even 100 t/h recycling centres that have been most idle are C, D, F and L. The ratio
need to charge an acceptance price to have a positive cash between age of equipment and time operating is 0.59,
flow. meaning that the equipment is halted for an average of
41% of the normal operating time.
5.4. Breakeven point Excluding the five recycling centres not in operation and
the recycling centre that is restarting production opera-
The breakeven point (BP) is the point at which total tions, the ratio of (installed) capacity and (current) produc-
sales revenue and production costs are financially equal. tion for the seven active recycling centres is 0.55, meaning
In the case herein, the BP will be defined in terms of ton- that the operating recycling centres only use an average of
nes produced. Assuming that users (private or public) will 55% of their installed capacity.
pay the value fixed by the recycling centre, it is estimated

3
The mathematical average of the wastage found in ten of the recycling
centres researched. The other three centres did not provide this figure
4
(Nunes, 2004). Considering 264 working days per year.

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

6 K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx

6.2. Estimate of costs and revenues

NPV value without C&D waste


acceptance value (in US$)
Despite sending questionnaires and visiting C&D waste
recycling centres, not all data required for this research
was obtained, especially cost-related data. In some cases
the reason appears to be that because the centres were
run by public authorities, cost control in the majority of
496,890

568,999

395,866

585,920
recycling centres is not seen to be important.
In other centres, since the operation is outsourced,


some contract managers were not willing to provide costs
for commercial reasons. In addition, some of the data
Price charged for accepting C&D

received from recycling centres was incomplete and con-


waste for NPV = 0 (in US$/t)

tained errors. To deal with these problems, some informa-


tion had to be estimated based on comparisons with other
similarly sized recycling centres. The investment of costs
and revenues consists of fixed capital investments, opera-
tional costs, and revenues and savings.

6.2.1. Fixed capital investment


2.52

2.89

0.40

0.60

When information was being collected during the first


stage of this research, it was found that items such as load-


ers and dump trucks were not included in some of the
Expenses with transport
and disposal of waste?

fixed capital investments supplied by municipalities, since


they were loaned from other municipal bodies or were
leased. In order to standardise this information, the
cheapest possible nominal purchase of used equipment
was added to the fixed capital investments. The correc-
tions were presented in Table 6. All recycling centres
No
No
No
No
No
No
No
No

researched are located on municipal land. Therefore,


investment in land procurement was not included.
acceptance of C&D

The investment average of US $12,500/t investment in


installed capacity is obtained by dividing the totals of
Revenue from

municipal fixed capital investments by the installed capac-


ity in the recycling centres. This average is within the
waste?

interval of values obtained for installed capacity in new


Yes

Yes

Yes

Yes
No

No

No

No

projects (Table 3) of US $16,770/t (20 t/h capacity –


new equipment) and US $8,170/t (100 t/h capacity –
new equipment).
Land included?

6.2.2. Total operational costs


No
No
No
No
No
No
No
No

Table 7 shows the total operational costs of produc-


tion estimated for existing recycling centres. As can be
seen in Table 3, according to quotations made in the
Secondhand
Secondhand

Secondhand
Secondhand
Equipment

market, the annual operating costs for 20 t/h recycling


centres are US $189,467, compared to US $685,780 in
New
New

New
New

the case of 100 t/h recycling centres (both using new


equipment). These costs are above those found for the
recycling centres under study. The reason for this may
capacity (t/h)

be that, despite the extra costs, these costs were still


Nominal

insufficient to represent actual operational costs of the


Scenarios and results

recycling centres under study.


100
100
100
100
20
20
20
20

In addition, since they are functioning below their


capacities, operating recycling centres have lower opera-
Scenarios

tional costs that those operating at full production. Fur-


Table 4

thermore, the historical data obtained for halted


facilities could be out of date or under-reported.
1
2
3
4
5
6
7
8

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx 7

Table 5
General information about recycling centresa
Recycling Commencement Age of equipment Time operating Capacity Capacity Current production:Statusc
centres date (Years) (Years) (t/h) (t/day)b
A 1991 13 7 100 800 Halted
B 1996 8 6 40 320 Halted
C 1996 8 1 40 320 Halted
D 1997 7 1 15 120 Produces an average of
170 t/dd
E 2001 3 3 10 80 Produces an average of
10 t/d
F 1999 5 0.25 15 120 Restarting operations
G 2002 2 1 25 200 Produces an average of
30 t/d
H 1995 9 9 40 320 Produces an average of
210 t/d
I 1996 8 8 40 320 Produces an average of
210 t/d
J 1994 10 n.a. 15 120 Halted
K 2001 3 3 40 320 Produces an average of
100 t/d
L 2001 3 0 40 320 Halted
M 2000 4 4 8 64 Produces an average of
32 t/d
a
n.a.: information not available.
b
Assuming 8 h of production per day.
c
November 2003.
d
Working for more than 12 h per day.

An average unit cost of US $4.47/t is obtained for the 6.2.3.1. Revenues. Only three C&D waste recycling centres
thirteen recycling centres by dividing the total production sell processed products to private clients, although the
costs, shown in Table 7, by the production capacity. How- quantities sold are tiny. Facility E sold around 1500 m3
ever, dividing total production costs by actual production of processed product between July 2002 and June 2003,
results in a real average unit cost of US $14.40/t5. It can at an average price of US $0.80/m3, including freight. Total
be seen that the average of real unit costs is approximately revenues in those 12 mo were US $1200. In recycling cen-
225% higher than the average unit costs for a scenario tres H and I, processed products could be obtained for
involving the operation of recycling centres at full capacity. US $0.50/t (US $0.80/m3), not including freight. The total
It also should be taken into account that for the production sales of these recycling centres were not available.
of C&D waste recycling centres to have outlets, the maxi-
mum price of the processed product must be around US 6.2.3.2. Savings in C&D waste disposal and transport to
$3.00/t (not including freight or taxes). The costs found landfills. Table 8 contains information on approximate dis-
are above this value. tances from centres of municipalities, landfills and recy-
cling centres. In some cases, the recycling centres are
6.2.3. Revenues and savings closer to the centres of municipalities than to landfills. This
According to Kartam et al., 2004, ‘‘the economics of means that by directing C&D waste to these recycling cen-
recycling has to be viewed in relation to the cost of alterna- tres, municipalities are saving on transport.
tive waste management options such as landfilling and The table also contains landfill disposal costs in some of
incineration. The cost of virgin raw materials . . . is another the municipalities under study. These costs vary from US
important factor for the economic attractiveness of $3.00/t to US $40.00/t. Adding transport costs6 and com-
recycling’’. paring them with production costs (average of US
Concerning the revenues and possible savings for own- $14.40/t), it can be concluded that for some municipalities
ers (municipal governments), the most significant are reve- C&D waste processing can be advantageous based on the
nues from the sale of processed products, savings in C&D cost savings on transport and landfilling alone.
waste disposal, and transport and savings in procurement
of material. 6.2.3.3. Savings on acquisition of materials. Table 9 shows
the annual savings that municipalities would obtain

5 6
For recycling centres that are halted, the costs refer to the 12 mo before Transport costs can be considered to be US $0.073/(m3 km) (SIN-
production was stopped. DIBRITA, 2003).

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

8 K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx

Table 6
Composition of fixed capital investmentsa
Recycling Fixed capital investment (in 103 US$) Total uncorrected (103 Total corrected (103
centres US$) US$)
Equipment Loader Block factory Construction Dump truck
works
A 1,000.0 1000.0 1000.0
B 125.4 100.0 – 92.6 65.0 218.0 383.0
C 83.0 100.0 – n.a. 65.0 83.0 248.0
D 100.0 100.0 16.7 15.0 65.0 158.4 323.4
E 36.0 100.0 – n.a. 65.0 36.0 201.0
F 66.7 100.0 – n.a. 65.0 66.7 232.0
G n.a. 100.0 – n.a. 65.0 100.0 265.0
H 96.9 100.0 n.a. 52.1 65.0 150.0 315.0
I 134.4 100.0 n.a. 48.0 65.0 182.4 347.4
J 100.0 65.0 100.0 265.0
K n.a. 100.0 – n.a. 65.0 80.3 245.3
L n.a. 100.0 – n.a. 65.0 84.8 250.0
M n.a. 100.0 – n.a. 65.0 115.0 280.0
a
n.a.: information not available.

Table 7 – motivation of local inhabitants to use the solutions


Operational costs: Summarya offered for disposal of C&D waste, avoiding illegal dis-
Recycling Annual fixed costs Variable costs Total production posal (such as cleaning and environmental restoration);
centres (103 US$) (103 US$) costs (103 US$) – less need for locations for C&D waste disposal,
Labour Other increasing the working life of inert and domestic waste
fixed costs landfills;
A 94.0 80.2 140 474.6 – reduction in environmental impact of extraction,
B 78.0 85.4 36 199.4 transport and processing of natural resources; and
C 58.0 60.9 36 154.9 – improvement in municipal public image.
D 66.0 74.3 36 176.3
E 50.0 86.3 36 136.3
F 54.0 54.9 36 144.9
G 58.0 73.7 36 167.7 6.3. Investment analysis
H 70.0 76.9 36 182.9
I 70.0 83.8 36 189.8 Operating below their capacities, existing recycling cen-
J 54.0 61.6 19 134.9
K 54.0 58.0 36 148.0
tres are losing the opportunity of reducing production
L 54.0 59.0 36 149.0 costs. In the case of halted recycling centres, there is bad
M 54.0 64.3 19 137.8 use of public investment. The main reasons for this low
a
Estimates made by the authors based on data collected. utilisation are changes in municipal recycling policy, cuts
in municipal budgets, low demand for C&D recycled prod-
ucts (weak sales and marketing strategies), maintenance
through the acquisition of processed road building materi- failures, equipment theft, vandalism of facilities and prob-
als, assuming that the recycling centres were working at lems with local communities.
planned capacity. The average price of these products is For municipalities, the most significant revenues and
US $4.00/t (not including taxes or freight)7. It should be savings from recycling centres are revenues from the sale
noted that in eight of the thirteen recycling centres the pos- of processed product, savings in procurement of materials
sible savings from materials are higher than the operational and savings in C&D waste disposal and transport.
costs. In the other five, the values are lower, although still It was found that for some municipalities, C&D waste
significant. recycling can be advantageous, even in relation to savings
on transport and landfilling only. Besides, in most of the
6.2.3.4. Other savings and intangible benefits. Besides the analysed municipalities, possible savings from use of pro-
savings and the revenues from C&D waste recycling centres cessed products are higher than the operational costs of
that were estimated (either fully or partially), there are the recycling facilities.
other benefits from these facilities, which are difficult to
measure and quantify in financial terms, including (Nunes, 7. Comparison between results 1 and results 2
2004):
The case studies analyzed show that the majority of
recycling centres in Brazil have been badly administered
7
Products mainly for use as base and sub-base (SINDIBRITA, 2003). by public authorities (weak cost control, idle recycling

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx 9

Table 8
Distances between centres of municipalities, recycling centres and landfill sitesa
Recycling Approximate distances between Landfill disposal costs Collection and transport costs
centres (US$/t) (US$/t)
Centre-recycling Centre- Recycling centre-
centre landfill landfill
A n.a. n.a. n.a. 3.00 n.a.
B n.a. n.a. n.a. n.a. n.a.
C 2.0 10.0 8.0 26.70 n.a.
D 9.0 20.0 11.0 n.a. n.a.
E 1.5 40.0 40.0 40.00 n.a.
F 6.0 10.0 4.0 35.70
G 3.0 n.a. n.a. 32.00
H 10.0 12.0 10.0 3.62 12.38
I 15.0 12.0 8.0 3.62 12.38
J 10.0 8.0 5.0 3.29 9.00
K n.a. n.a. 0.0 n.a. n.a.
L n.a. n.a. n.a. n.a. n.a.
M 4.0 15.0 13.0 n.a. n.a.
a
n.a.: information not available.

Table 9 8. Conclusions and recommendations


Savings with procurement of materials
Recycling Installed Annual estimated Annual Savings The CONAMA Resolution no. 307 obliges all Brazilian
centres capacity production operational (103 municipalities to prepare and implement strategies for the
(t/h) of project costs US$) sustainable management of C&D waste. In the justifica-
(103 t/year) (103 US$) tions for this resolution, mention was made of the eco-
A 100 169.0 474.6 676 nomic feasibility of the production and use of C&D
B 40 67.6 199.4 270 waste materials. However, there is little research in Brazil
C 40 67.6 154.9 270
to confirm it.
D 15 25.3 176.3 101
E 10 16.9 136.3 68 This work was divided into two parts. One study, aimed
F 15 25.3 144.9 101 at private enterprise, estimated the costs for future C&D
G 25 42.3 167.7 169 waste recycling centres. In a second study, concerned with
H 40 67.6 182.9 270 the public area, real data was used in the analysis of finan-
I 40 67.6 189.8 270
cial viability.
J 15 25.3 134.9 101
K 40 67.6 148.0 270 It could be concluded that the C&D waste recycling cen-
L 40 67.6 149.0 270 tres operating under current Brazilian market conditions
M 8 13.5 137.8 54 are not financially viable for private enterprises. Revenue
from the sale of the processed product alone is not enough
to make these recycling centres viable. It is suggested that
plants, and so on). This situation and its consequences on other sources of revenue be sought, such as charging for
the performance of the facilities have to be taken into acceptance of C&D waste in recycling centres and the
account by municipalities in future investment analyses. reduction in taxes and loans at lower rates than practised
Municipal managers also need to evaluate whether it is in the market.
economically more viable for public authorities to be the C&D waste recycling centres can be economically viable
administrators of these recycling centres or to let them to for public authorities under current market conditions
be privately run. An option can also be public-private part- depending on the particular circumstances of each munici-
nerships, where governments and private sector work pality (landfill disposal costs, transport costs from C&D
together, which are becoming popular in Europe (UNECE, waste to landfills and price of acquisition of natural prod-
2006). ucts). The viability, however, also depends on continuity of
The introduction of recycling incentives can benefit the operation and the production volume reached in the recy-
financial viability of private recycling centres. The potential cling centres.
consumption of processed products by local and govern- The unsuccessful experiences of the public authorities
ment markets has to be estimated, while municipalities with the administration of C&D waste recycling facilities
can make contact and establish partnerships with neigh- must be considered by municipalities in their investment
bouring municipalities, state and federal governmental analysis. It should be evaluated whether it is more econom-
organisations and with the private sector. The technical ically viable for public authorities to be the administrators
and financial viability of actions must always be key deci- of these recycling centres or to allow them to be privately
sion criteria. run.

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007
ARTICLE IN PRESS

10 K.R.A. Nunes et al. / Waste Management xxx (2006) xxx–xxx

Since the use of recycled products is still not widespread Kartam, N. et al., 2004. Environmental management of construction and
in Brazil, investments in large-scale recycling centres with demolition waste in Kuwait. Journal of Waste Management 24, 1049–
1059.
complex facilities will have more chances of failure com- Kohler, G., 1997. Recyclingspraxis Baustoffe (Practice of Recycling:
pared to simpler ones. Construction Materials). TÜV Rheinland, Köln, Germany.
The study was carried out in Brazil, but the proposed MACREDO (Mid-Atlantic Consortium of Recycling and Economic
conceptual model for financial viability studies of future Development Officials), 2006. Recycling and Reuse in the Residential
C&D waste recycling centres can be applied to other coun- Construction Industry. Philadelphia, USA. <http://www.liberty-
net.org/maredo/recost.htm> (Accessed on: 05/03/2006).
tries. The conclusions and perspectives that result from the MMA (Ministry of the Environment), 2002. CONAMA Resolution
analysis of the existing Brazilian centres can also strongly no. 307, dated 05/07/2002. Established directives, guidelines and
support public authorities and private enterprise in deci- procedures for the management of construction waste. Brasilia,
sions about investments in Brazil and other countries. Brazil.
Motta, R.R., Caloba, G.M., 2002. Análise de Investimentos:
Tomada de Decisão em Projetos Industriais (Investment Anal-
References ysis: Decision-Making in Industrial Projects). Atlas, São Paulo,
Brazil.
Alexander, C., 1997. The Handbook of Risk Management and Analysis. Nunes, K.R.A., 2004. Avaliação de Investimentos e de Desempenho de
John Wiley, New York, USA. Centrais de Reciclagem para Resı́duos Sólidos de Construção e
Boranga, J.A., 2005. Resı́duos Sólidos (Solid Waste). Revista Brasileira de Demolição (Investment and Performance Analysis in Construction
Saneamento e Meio Ambiente (Brazilian Journal of Sanitation and and Demolition Waste Recycling Plants). Ph.D. Thesis. Federal
Environment). ABES, Rio de Janeiro, Brazil. January/March, p. 5. University of Rio de Janeiro, COPPE, Production Engineering, Rio
Calderoni, S., 2004. A reciclagem vista sob dois ângulos diferentes de Janeiro, Brazil.
(Recycling from two different points of view). CEMPRE Informa, no. Peng, C.L., Scorpio, D.E., Kibert, C.J., 1997. Strategies for successful
76. <http://www.resol.com.br/textos/> (Accessed on: 28/08/2005). construction and demolition waste recycling operations. Journal of
EEA (European Environment Agency), 2002. Review of Selected Waste Construction Management and Economics 15, 49–58.
Streams. Copenhagen, Denmark. Technical Report 69. SINDIBRITA (Federation of the Gravel Mining Industry of the State of
EPA (Environmental Protection Agency), 2000. Buildings Savings: Rio de Janeiro), 2003. Data provided between January and November
Strategies for Waste Reduction of Construction and Demolition 2003.
Debris from Buildings. USA (EPA-530-F-00-001). <http://www.epa.- TIFAC (Technology Information Forecasting & Assessment), 2006.
gov/osw> (Accessed on: 10/05/2003). Utilisation of Waste from Construction Industry: Executive Summary.
Huang, W.L. et al., 2002. Recycling of construction and demolition waste New Delhi, India. <http://www.tifac.org.in> (Accessed on: 05/03/
via a mechanical sorting processResources, Conservation and Recy- 2006).
cling, 37. Elsevier, pp. 23–27. UNECE (United Nations Economic Commission for Europe), 2006.
IBGE (Brazilian Institute of Geography and Statistics), 2000. Estimativa Public Private Partnership. Geneva, Switzerland. <http://www.une-
de população: Ano 2000 (Population estimatie: Year 2000). Rio de ce.org/ie/ppp> (Accessed on: 15/02/2006).
Janeiro, Brazil. UNIDO (United Nations Industrial Development Organisation), 1987.
Ingalls, K.M., 2000. Trend Settters: Recovering C&D. Waste Age. Manual for the preparation of industrial feasibility studies. Atlas, São
Atlanta, USA, July, pp.76–82. Paulo, Brazil.

Please cite this article in press as: Nunes, K.R.A. et al., Evaluation of investments in recycling centres for construction ..., Waste
Management (2006), doi:10.1016/j.wasman.2006.09.007

You might also like