Professional Documents
Culture Documents
TECHNICAL SPECIFICATIONS
SCOPE OF WORK
I. CONCRETE REINFORCEMENT
A. Scope of Works
The WORK includes fabrication and installation of all steel bars and steel tie
wire, clips, supports, chairs, and spacers required for the reinforcement of
concrete as shown on the Drawings.
C. Submittals
D. Quality Assurance
The Contractor is responsible for the performance of all tests and inspection
required by this Standard Specification. However, the owner reserves the right
to perform any or all prescribed tests and inspection where such is deemed
1 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
E. Products
E.1 Materials
Steel wire for tying reinforcing bars and waterstops shall conform to ASTM
A82.
The following reinforcing steel bar sizes shall be used for all reinforced
concrete design under this Contract.
#10 78 0.616
#12 113 0.888
#16 201 1.579
#20 314 2.466
2 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
c. Should the Contractor wish to use reinforcing steel bars having areas
different from those shown (with consequent different designations), the
following requirements shall apply:
If the proposed substitute bar has an area from 97% to 105% of the
designated bar, a direct substitution may be made without changes to bar
spacing.
If the proposed substitute bar has an area less than 97% of the designated
bar, substitution may be allowed provided bar spacing is reduced to not
less than the minimum clear distance between bars.
If the proposed substitute bar has an area more than 105% of the
designated bar, changes in spacing is limited to a maximum spacing of
300mm. All proposed changes shall be submitted to the Engineer for
approval.
Approval by the Engineer of bar size substitutions does not relieve the
Contractor of other specified requirements, including steel grade and bar
deformations.
F. Execution
b. All reinforcing bars shall be bent cold around a pin with a free revolving
collar having a diameter of the bar of not less than the following:
3 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
c. Reinforcement steel shall not be straightened nor rebent. Bars with kinks
or bends not shown on the Drawings will not be accepted.
e. Welded wire fabric (WWF) shall conform to ASTM A-185. Welded Wire
Fabric in suspended slabs shall have Fy = 60 Ksi. Lap 152mm. Minimum
or one full mess, whichever is greater for slabs on grade.
4 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
g. Reinforcing bars for vertical surfaces in beams, columns and walls shall be
properly and firmly positioned from the forms by means of stainless steel
(tipped) bolsters or other equal methods approved by the Engineer
h. Reinforcement steel projecting from structures that are to be concreted or
where concrete has already been poured shall not be bent out of its
correct position.
II. CONCRETE
B. Scope of Work
The scope of work includes all operations necessary for the supply
and delivery of materials, labor, plant and equipment for the
manufacture and the forming, mixing, placing, finishing and curing
of concrete works required by the contract, be it a job mixed
concrete or a ready-mixed concrete.
C. General
5 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
D. Materials
1.) Cement
Cement to be used shall be Portland cement.
2.) Aggregate
3.) Water
4.) Reinforcement
E. Concrete Quality
F. Construction
1.) General
2.) Deposition
6 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
7 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
a) an impervious membrane or
b) sand kept wet for the curing period.
6.) Finishing
8 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
ii. Mortar filling shall be used for repairing defects which are
too wide for dry pack filling, too shallow for concrete filling
and no deeper than the far side of the reinforcement that
is nearest to the surface.
G. Formworks
1.) General
2.) Materials
3.) Construction
9 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
6.) Deflection
H. Construction Joints
10 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
I. Construction Tolerance
III. MASONRY
A. Materials
All units shall be stored for a period of not less than 28 days
(including curing period) and shall not be delivered to the job site
prior to that time unless the strengths equal or exceed those
mentioned in these specifications.
3. Sand shall be river sand, well screened, clean, hard, free loam,
silt or other impurities, composed of grains of varying sizes
within the following limits:
11 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
B. Erection
1. All masonry shall be laid plumb, true to line, with level and
accurately spaced courses, and with each course breaking joint
with the source below. Bond shall be kept plumb throughout;
corners and reveals shall be plumb and true. Units with greater
than 12 percent absorption shall be wet before laying. Work
required to built-in with masonry, including anchors and
accessories, shall be built-in as the erection progresses.
C. Workmanship
Plastering: Clean and evenly wet surfaces. Apply scratch coat with
sufficient force to form good keys. Cross scratch upon attaining its
initial set; keep damp.
D. Scaffolding
A. Scope of Works
The work under this section shall include the furnishing of all
materials, labor, equipment and other facilities necessary to install
and complete all steel and iron works shown in the plan, details and
as specified herein.
B. Materials
12 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
C. Workmanship
D. Cleaning
All exposed metal surface shall be rid of grease, dirt or other foreign
materials. Chrome or nickel-plated pipings, fittings and trimmings
shall be polished upon completion.
E. Guarantee
The contractor shall guarantee that the metal works are free from
improper installation and defective materials for a period of one (1)
year from the date of final acceptance of the work. Any defects
within the aforesaid shall be remedied by the contractor at his own
expense.
V. PAINTING WORKS
A. Scope of Work
B. Inspection of Surfaces
Before applying any finishing works, the contractor shall inspect all
surfaces to be painted and all defects shall be remedied. For
13 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
C. Materials
E. Preparation Surfaces
E.1 General
14 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
F. Painting Application
Finish shall be applied only over preceding coats which are hard
and dry. Finish shall be evenly and smoothly applied and shall be
free from runs, sages or crawling.
G. Painting Schedule
a. Exterior Painting
H. Cleaning
Upon completion of the work the contractor shall remove from the
building, all used materials, debris, all paint spots on the floors,
washing of the window glass, hardware fixture, etc. All work
performed under this section shall be left clean and acceptable to
the CO.
I. Guarantee
The contractor shall guarantee his work for a period of one (1) year,
when using the materials specified by the CO. The contractor shall
repair any defect or defects due to the faulty materials or
workmanship caused by him, without any additional compensation
for the period specified.
VI. WATERPROOFING
15 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
A. Scope of Work
B. General
E. Surface Preparation
16 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
F. Inspection
Verify that the concrete work done under other section meets the
following requirements:
G. Application
17 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
J. Cleaning
K. Performance of Waterproofing
L. Submittal Requirements
A. Scope of Works
The work shall include the furnishing of all materials, labor tools and
other equipment/ facilities to complete all the architectural works herein
included under this item.
18 | T e c h n i c a l S p e c i fi c a ti o n
PROJECT : Repair of St. Joseph Low Rise Building
LOCATION : St. Joseph LRB, Brgy. St. Joseph, San Juan City
19 | T e c h n i c a l S p e c i fi c a ti o n