Employer :

Engineer :
PROJECT: BALADNA DAIRY FARM PHASE-2 Consultant :
Contractor :

DEFINITION OF INSPECTION AND TEST PLAN SYMBOLS

"H" HOLD POINT - A Point beyond which work shall not proceed with out formal approval from the Engineer.
Inspection for Hold Points shall be notified to the Engineer through Inspection Requests.

"W" WITNESS POINT - A Point beyond which work can proceed without formal approval from the Engineer.
Inspection for witness points will not be notified to any of the inspection parties.

"S" SURVEILLANCE POINT - A Point where inspection parties may carry-out surveillance of work in progress
and relevant documentation without any notification.

"R" REVIEW POINT - A Point where appropriate quality records shall be available for verification.
Work can proceed if all the documents are appropriate as per project requirements.

"M" MANDATORY POINT - A Mandatory activity to be carried-out by the contractor as per contractual requirement.

"NA" - Not Applicable