Professional Documents
Culture Documents
40%
FS
PJ Cost
±30%-
Estimate
Conceptual
Design
PJ Cost
Estimate
±20-30%
Front End
Engineering
±10%
PJ Cost
FEED
Estimate
Estimate
Bidding
E
Engineering
Basic Design
Procurement
P
Detail Design
C
Construction
Typical Flow Scheme of PJ
Operation
&
Maintenance
O&M
What is Commissioning?
A process of documentation, adjustment, testing,
verification, and training, performed specifically to
ensure that the finished facility operates in
accordance with the owner’s documented project
requirements and the construction documents.
• Chemical Cleaning
• Punch Lists • Handover Packages
• Mechanical Running Test
• Commissioning Procedures • Punch Lists
• Inerting & System Drying
Dynamic • Process Unit Operation
• Refractory Dry-Out
• As Installed Documents
Parameters • Operator Training Docs
Commissioning • Control Logic Review
• Control Logic Verification
• Warranty/Remedial Work
• Steam Blowing
• Vendor Coordination/Support • Statuary Compliance
• Commissioning by System
• Competence Resources
• Operating Procedures • Safe Start-Up Activities • Sustainable Production
• Start-Up • Feed Stock • Performance Testing • Performance Report and
• Stabilize Operation • Final Project Documents
• Vendor Supports
(Equipment/Unit/Overall Plant) Defficiencis Report if any
• Ramp-Up • Product Commissioning by • Target Operation Efficiency for 1st
• Operation Consumables and Contract
• Continuous Operation Supports Operable System year operation (min. 80%)
• Maintenance & Integrity System
What is Commissioning?
(validates the “design”!) “retro” ;
“re”; or
Commissioning “ongoing”
Cx
Commissioning
validates the design!
Design That the design works and
Intent meets the “design intent”
Changing
That the construction is installed “Inspections”
Needs
validate
correctly per the “design”
construction This is not commissioning!
What Commissioning is NOT?
– Completing Standard Forms
– Contractors’ QA/QC Program
– Verification of the Contractors’ QA/QC
Program
– Construction Inspection
– Construction Management Substitute
Commissioning Process
Expectation:
What performance
should look like
Performance
Historical:
Typical Plant
Performance Curve
over time
– Comprehensive Commissioning
Retrocommissioning (RetroCx)
(Existing Construction)
3.0 to 5.0 Percent of Total Operating Cost
Commissioning Costs
Without Commissioning
First Year Warranty
Design Phase Construction Phase Costs
Period Costs
Costs
With Commissioning
Design Phase Construction Phase Costs First Year Warranty
Costs Period Costs
Commissioning of a project
TITLE SLIDEis a term
that has different interpretations
depending on who is using it.
Team Effort
READY FOR COMMISSIONING…Occurs when the plant or any part of the plant has been erected in accordance
with drawings and specifications and the pre-commissioning activities have been completed to the extent necessary to permit
commissioning activities to begin.
MECHANICAL COMPLETION… Occurs when the plant or any part of the plant has been erected in accordance with drawings,
specifications and applicable codes and the pre-commissioning activities have been completed to the extent necessary to
permit the client to accept the plant and begin commissioning activities. The terms ready for commissioning and mechanical
completion are often synonymous.
COMPLETION OF WORK…Means that the contractor has erected the plant in accordance with drawings and
specifications completed his specified pre-commissioning work and completed his final cleanup, painting and thermal
insulation work.
COMMISSIONING…Commissioning activities are associated with preparing or operating the plant or any part of the plant
prior to the initial start up and some project will be the owner’s work responsibilities. The Commissioning activities such as
tightness test, inerting, system drying, etc.
INITIAL START UP…occurs when feedstocks are introduced to the plant for the express purpose of producing a product
for the first time.
The clue for Commissioning
Planning
How planning completes commissioning on paper?
As a commissioning team, people learn the
thought, the logic, and approach that led to the
plan.