You are on page 1of 9

IEEE Transactions on Power Delivery, Vol. 11, No.

2, April 1996 635

Development of 500-kV XLPE Cables and Accessories


for Long-Distance Underground Transmission Lines
-- Part IV: Electrical Properties of 580-kV Extrusion Molded Joints --
Naoki Takeda ShouichirouIzumi Kazunari Asari
Tokyo Electric Power Co., Inc. Chubu Electric Power Co., Inc. The Kansai Electric Power Co., Inc.
Tokyo, Japan Nagoya, Japan Osaka, Japan

Atsushi Nakatani Hajime Noda Masayuki Yamaguchi Masayuki Tan


Sumitomo Electric Industries, Ltd. The Furukawa Electric Co., Ltd. Hitachi Cable, Ltd. Fujikura Ltd.
Osaka, Japan Tok:yo, Japan Hitachi, Japan Tokyo, Japan

Joints for 500-kV XLPE cable are now under development in


Japan to enable the long-distance transmission of high-capacity
power to urban areas. Basic research was carried out from 1989
to 1992 that determined joint type and design values. This
paper reports on the electric performance of the fabricated
joints. Various tests were conducted to evaluate the (c) Mold h e a t i n g 1 ,Mold kettle
performance and the design values. As a results of this
evaluation it was found that it was possible to realize joints for
S
500-kV XLPE cable. on
Field tests will be conducted as the final stage to confirm the
long-term performance of the system.

1. Introduction
500-kVXLPE cables are scheduled to be installed to urban Treated portion of cable screen ~$~t~~i;forcing
areas in order to cope with the growing demand for electric
power in recent years. Jointless 500-kV XLPE cable has
already been in practical use for underground transmission layer
ReinforciAg insulationUSemiconductor
cables in power generation stations [l], however its
application to long-distance power transmission lines tl :Thickness of reinforcing
requires development of highly reliable joints. Iin response insulation
to this need, we have conducted various basic research on t2:Thickness of cable
einforcing insulati o
extrusion molded joints (EMJ) [2]. Also, based on the data insulation
which was obtained in the basic research, actual-size EMJs
were designed and fabricated, their elecaical performance
was evaluated, and the validity of the design was c o n f i e d .

95 SM 485-3 PWRD A paper recommended and approved


by the IEEE Insulated Conductors Committee of the
IEEE Power Engineering Society f o r presentation at Figure 1: Fabrication process and structure of EMJ
the 1995 IEEE/PES Summer Meeting, July 23-25', 1995,
Portland, OR. Manuscript submitted January 3, 1995;
made available for prlnting May 3, 1995. This paper outlines the results of the basic research and
reports mainly on the results of the electrical tests and what
they mean. Basic research was undertaken independently by
three major electric power utilities and their designated cable
manufacturers. However, to improve efficiency in the
development, the results obtained have been shared and the
work pursued jointly.

0885-8977/96/$05.000 1995 IEEE


63 6
Table 1: ENJ defeets

2. Structural design Although semiconductive protrusions sometimes occur on


2-1. Overview the interface between cable and reinforcing insulation near
Figure 1 presents the installation procedure and structure the edges of reinforcing insulation (Figure l), it is clear that
of an EMJ. The same type of resin as the cable is extruded this can be suppressed by controlling the temperature
into a mold on site using a small-size extrusion machine, and conditions during crosslinking [5]. Such unique defects are
the cable insulation and its reinforcing insulation are formed not an important factor.
integrally. The EMJ requires technology of cable
manufacturing at construction site. 2-3. Design approach
For designing an EMJ, two important thicknesses,
2-2. Factors governing the performance reinforcing insulation portion and the treatment portion of
An EMJ, which is fabricated with the same material as the cable screen must be considered. The following is a
XLPE cable can be expected to have superior insulation discussion on the design approach for each.
performance. However in order to obtain higher reliability,
the factors that govern the insulation performance of an EMJ A. Reinforcing insulation
must be evaluated and controlled. Table 1 lists the defects The thickness of the reinforcing insulation is placed so as
that should be considered for fabrication of EMJ. Inspection to withstand the voltage determined by the required life time;
of the insulation layer of an EMJ reveals that the EM3 has specifically, the greater of the values given by formulas (1)
somewhat larger contaminants and semiconductor and (2) is adopted [SI.
protrusions as compared with XLPE cable. However - Insulation thickness required for
otherwise there are no great differences in voids in the commercial-frequency voltage: t,,
insulation layer, degree of crosslinking, residual strain, or
crystalline structure [2]. The factors governing the
performance of XLPE cable are the contaminants and
protrusions in the insulation layer [3]. These results suggest - Insulation thickness required for
that the factors governing the performance of an EMJ are, as Lightning impulse voltage: t
with cable, the contaminants and protrusions. This fact is LIWL x k,'xk,'xk3y
supported by a report that PPD tests on model EMJs show t. = (2)
that every breakdown originated from the contaminants [4]. EL,
where
Contaminants in Protrusion of Voids in insulation
insulation conductor Screen V,: normal maxi" circuit voltage (550 kV)
LTWL: lightning impulse intensity (1425 kV)
k,, temperature coefficients
$I:

10 10
c:
k, degradation coefficients
b;, h':tolerances with respect to uncertain elements (1.1)
k,ELrrp:minimum insulation breakdown stress with
1 0' 10'
respect to commercial frequency and lightning impulse
-:

e e e
n : Cumulative counts of defects e . Size (,urn)
contaminants o r voids (counts/mm')
semiconductors layer protrusions (counts/mm*)
Figure 2: Comparison of 275-kV EMJ and cable defects
637

The temperature coefficients are determined fkoim the ratio


where
of the breakdown test data at room temperature and at a d,: outside diameter of
conductor temperature of 90°C. The degradation (coefficient conductor screen
k, is determined based on the lifetime index n, which is 4: inside diameter of
obtained from the -V-t characteristics of the long-term cable screen
breakdown test data, and is determined based on the
results of repeated impulse tests. E, and Eu,are determined
by analyzing the breakdown test data using a Weibull
distribution. Breakdown tests on XLPE cables having
different insulation thicknesses show thickness dependence
of of the crosslinked polyethylene insulatiom, and the
relationship given in formula (3) was obtained.
E, (t) cc A x t4.'* (3)
where A is a coefficient and t is the thickness of the
insulation.
The temperature coefficients and degradation coefficients
used in the foregoing are summarized in Tablt: 2. These
coefficients or thickness dependence were detennined based
on breakdown test data for XLPE cables [7]. But as shown
above, the performance-governing factors for EMJs are, as
for XLPE cables, the contaminants and the protrusions. So
it is thought that these coefficients can be used provisionally
for Ems as well.

ac imr,
E, before improvement (kV/mITI) 28 74
1.20 1.25 2.3 1.0
E,after improvement (kv/mm) 37 85
B. Treatmentportion of cable screen Performance improvementratio (%) 132 115
The required insulation thickness as determined in cable
design is 25 mm[3], but the insulation thickness of a 500-kV
XLPE cable having intermediate joints is determined by the
performance of the treatment portion of the cable screen of
the EMJ.
The electrical field Emin of the treatment portion of
cable screen is determined by the structure of the cable. The
minimum insulation breakdown stress Kmin required for this
portion is given by formulas (4) and (3,which the cable
must be designed to satisfy.
-.U
10
1- 6- 11- 16- 21-
-Performance required for commercial-frequency voltage e" , (
%xk, xk, xk, Figure 3: Protrusion level of treated portion of cable screen
Emin = 4 3 and performance improvement ratio
(+) x In( ?)
(4)

-Performancerequired for lightning impulse voltage


Emin = (9
(+) x In($)
638

2-4. Specific design


Figure 4 shows the 500-kV EMJ structural dimensions Table 4: Breakdown test conditions
designed based on the approach described in the preceding
section.

cross-sectional area
01 conductor : 2500mm'

21=130--155mm, 11 =36mm.
fiz=105-160mm t=27mm
3-2. Tests of Breakdown Stress for Reduced Insulation Joint
Figure 4: Structural dimensions of 500-kVEMJ The thickness of the reinforcing insulation was designed in
consideration of the fact that the reinforcing insulation has
The minimum breakdown stress, E, for 500kV EMJ, which the same kind of thickness dependence of E, as cable. This
serves as the basis for calculating the reinforcing insulation test was carried out for the purpose of confming the validity
thickness, is determined by the E, of 12 mm thick EMJ and of this approach. The samples were made to the same size
the formula(3) including 10% safety allowance. The results as a 500-kV EMJ represented in Figure 6 , except the
are given in Table 3. According to this, when the required reinforcing insulation thickness above the conductor sleeve.
insulation thickness for commercial-frequency voltage and The reinforcing insulation thickness was reduced to 9, 15,
lightning impulse voltage were calculated using (1) and (2), and 20 mm in order to make breakdown at this portion. A
we get tac = 35.7 mm, timp = 32.7 mm, thus the reinforcing breakdown test was performed for both ac and imp, with 4
insulation thickness was set to 36 mm [2]. samples each (a total of 24 samples). The test voltage
The Kmin for the treatment portion of cable screen was conditions are listed in Table 5. The starting voltage was
calculated by taking the value for a 275kV EMJ fabricated by equivalent to 90% of minimum breakdown stress
the conventional technique, multiplying it by the Et ,obtained by thickness dependence formula of Figure 5.
performance improvement factor (ac:1.32 imp:1.15). The
results are given in Table 3. From this, the insulation Table 5: Breakdowntest conditions
thickness of the cable required by the performance of
treatment portion of cable screen was set to 27 mm.

3. Development test items and methods


Based on the structural design described in the previous
chapter, 500-kV EMJs were fabricated, and the following
evaluation tests were performed on it.

3-1. Tests of Minimum Insulation Breakdown Stress


Breakdown tests were conducted under the conditions of
Table 4 on 8 samples each (a total of 32 samples), in order to
confirm whether it has voltage withstanding performance I I 1
10 20 30 40
with respect to the design ELvalues of Table 3 and evaluate Thickness of the reinforcing insulation
the appropriateness of the design E, values and the : t (mm)

temperature coefficients. For the test voltage conditions,


Figure 5: Thickness dependence of reinforcing insulation
starting voltage was equivalent to the design E, of the main
t=9,15,20mm
design location, then applied voltage was increased. Also, the
confirmation voltage for the 90°C test was determined from
the value obtained by dividing the room-temperature
Figure 6: Structure of evaluation test samples
confirmation voltage by the temperature coefficient of Table
2.
639

3-3. Evaluation Test of Crosslinking Temperature Control investigation method would be the n-1 distribution, which
As stated in the previous chapter, according to the determined in detail the distribution of type and number of
crosslinking temperature conditions, the unique defects (see defects from 1 slice. In addition, this time, 100 slices (x 4
Figure 1) can arise at the edges of reinforcing insulation of companies) would be sampled from the reinforcing
the EMJ, which reduce the electrical performance. The insulation and the largest contaminants (blacWmetal) in each
crosslinking temperature conditions were conducted for the slice would be examined, and their distribution would be
purpose of evaluating whether there is a tolerance with evaluated.
respect to the reduction in performance arising fiom these
unique defects. 4. Results of development tests
Shown in Figure 7, T1 is defined as the temperature of the 4-1. Tests of Minimum Insulation Breakdown Stress
conductor sleeve, when crosslinking degree of reiiforcing The test results are summarized in Figures 8 and 9. The
insulation near the conductor sleeve reaches 90%. T2 is results of the reinforcing insulation and the treated portion of
defined as the temperature of the conductor sleeve, when cable screen were evaluated by stress separately. In each case,
crosslinking degree at edge of reinforcing insulation reaches the data exceeded the design value and it has sufficient
90%. And A T is defined as the difference between T1 and initial value.
T2.It has been reported that the unique defects tend to occur , -
as A T is large 161. Thus samples were fabricated under E
E 70 ............
special crosslinking temperature conditions whereby a 3
5
temperature difference is A T'( = A T(standard condition) E
..................................................................................................
+ 10' c ). E
W
(Designed ELimp)
The test voltage conditions are given in Table 6. v1

E
v)

I t e m e r a t u r e of conductor sleeve E
2
2I 10 -.............................................. I...................................................
T2
100 ; f 0
' AC breakdown dala
6 AC cut-on dala
9 ' IMP breakdown data
6 IMP cui-otfdam 1
L m temDerature 1 QO'C

n
f Figure 8: Breakdown stress of reinforcing insulation
of r e i n f o r c i n g insulation
crosslinked degree
near conductor sleeve
.
x
0 0
Passed Tine 1 hours

Figure 7 A T at crosslinking process

Table 6: Breakdown test condition


Item IElectrification conditions (at R.T.)
ac (970kV/lh -t 99OkV/lh,then50kV/lh steps
970kV means designed voltage to withstand. Figure 9: Breakdown stress of treated portion of cable
99OkV means the voltage to confirm designed .EL.
screen

4-2. Tests of Breakdown Stress of Reduced Insulation Joint


3-4. Material test The test results are given in Table 7. In all cases breakdown
In the EMJ it was assumed occurred in the reinforcing insulation portion. m e stress at
*at factors governing performance ate the 'ame as for each breakdown point is given in Table 8. Higher values
This test was carried Out for the purpose Of w e e obtained for the breakdown stress than E, value
evaluating whether this assumption is effective. Sample c.culated from the thickness dependence
slices (about 1 mm thick) were taken from the reinforcing
insulation and the treated portion of cable screen, and the
type and distribution of the defects in the insulation and on
the semiconducting layer interface were examined by
microscope observation. It was determined that the
640

2 50
-0=2 40 n d a r d deviation
Table 7: Electrical test results I .-
a
3
) 30
~

$? 20
z8 10

1 2 3 4 5 6 7 8- 9 10 11 12 13 14 15 16 17 18 19 2021 2 2 2 3
Size of contaminants (pm)

Figwe 10: Distribution of size of largest contaminant


lO.0l
The up-arrow in the above table indicates that breakdown
did not occur at that voltage.

Breakdown point calculated


stress &V/mm) EL -
56.2 62.4 65.2 68.4 38.4 -
0
z
-
~1 (Conductor
25 50 75 100
(Cable
49.7 50.7 58.7 71.9 35.0 screen side) screen side)
n
45.0 50.0 52.5 60.0 t 33.2 Proportion of insulation radial direction (%)

119 125 127 129 86.2 Figure 11: State of distribution of largest contaminants in
106 114 115 125 78.6 raw direction
101 105 110 122 74.6
5. Evaluation and conclusions
4-3. Evaluation Tests of Crosslinking Temperature Control 5-1. Temperatme coefficients
The electrical test results are given in Table 9. It was The E, values, as well as the 63.2%breakdown probability
confirmed that the performance is about the same as for test values, at room temperature and at 90" C were determined
samples made under standard crosslinking temperature by the results of the Tests of Minimum Insulation Breakdown
condition (see ac data at r.t. in Figure 9). Also, after Stress (E3. The ratio of values at room-temperature and at
dismantling, no unique defects were found near the edge of 90" C was determined, and it was selected as a temperature
reinforcing insulation by microscopic observation. These coefficient. These values are presented in Table 10. From
results confmed that the current crosslinking conditions are these evaluation results, the temperature coefficients for
adequate with respect to occurrence of the unique defects commercial-frequency voltage were 1-1.05, and those for
near the edge of reinforcing insulation. lightning impulse voltage were 1.15-1.21. It was confirmed
that adopting the design values (ac: 1.20, imp: 1.25) results
Table 9: .Electricaltest results on the safe side.

4-4. Material test


The defects found in the reinforcing insulation and
treatment portion of cable screen were the same as those
found in cable: contaminants, protrusions, and voids. The
investigation results at the n-l distribution were similat to the 5-2. Design value E,
data obtained from basic research shown in Figures 2 and-3. Design value E, was evaluated by the results of the Tests of
The distribution of the size of the largest contaminant is Minimum Insulation Breakdown Stress. The cut-off data
shown in Figure 10. The radial-direction distribution mode is was taken as breakdown data, and the 90" C breakdown test
shown in Figure 11, and it is confmed the contaminants are data was multiplied by the design temperature coefficients
randomly distributed in the radial direction. (ac: 1.20 imp: 1.25) in order to evaluate as breakdown data at
room temperature. The results of the Weibull analysis are
641

shown in Figures 12 and 13. It was confirmed ithat the E, 5-4. Performance improvement factor at treated portion of
value obtained from the breakdown test data is gireater than cable screen
the design value, and that there is a tolerance with respect For 500-kV EMJ a cable insulation thickness of 27 mm was
to the design value. adopted, identical to the 275-kV case, as a result of
improvement of the treated portion of cable screen by
treatment method improvements. Table 11 shows the
results of calculating the performance improvement ratio of
the E, value determined in the preceding section and the E,
value of 275-kV EMJ (cable insulation thickness 27 mm)
without improvement of the treatment method.
1 5 I 5 10 50 100 Approximately the same value was obtained as that of a
IkVfmml
model EMJ with a cable insulation thickness of 10 mm.
Figure 12 Weibull analysis results (reinforcing insulation)
Table 11: Comparison of improvementratio
of minimum breakdown stress

137% 132%
121% 115%

Figure 13: Weibull analysis results (treated portion of cable


screen)
6. Conclusion
5-3. Thickness dependence of breakdown stress In order to realize 500kV long distance transmission lines,
Figure 14 presents the breakdown stress for an insulation factors governing the performance were considered. EMJs
thickness of 36 mm (Figure 8), and the breakdown stress for are designed by constants obtained at basic research, and
an reduced insulation thickness of 9-20 mm (Table 8), with actual-size EMJs were manufactured.
the design thickness-dependence graph (Figure 5). The The breakdown test for actual-size EMJ with reinforcing
value for an insulation thickness of 36 mm might be lower insulation thickness of 36" was conducted, then the design
than the actual value, because these include some cut-off values, temperature coefficients and E,, were evaluated, and
data which withstood the maximum voltage of the facility, or it was confmed that these constants and design approach of
which occurred breakdown at the other portion. Considering performance improvement factor at treated portion of cable
only the breakdown stress for an insulation thickness of 9-20 screen were appropriate.
mm, it shows properties that are generally similar to the The breakdown test for EMJ with reduced reinforcing
design value, and it is thought that the thickness (dependence insulation thickness of 9-20" was conducted, then it was
formula adopted for design is generally appropriate. confirmed that the design approach of thickness dependence
of breakdown stress at reinforcing insulation was
- '" I 0 AC I appropriate.
The breakdown test for EMJ fabricated by special
crosslinking temperature control was conducted, then it was
confmed that it was not important to consider reduction of
T
performance by the unique defects at edges of reinforcing
insulation under the current condition.
T
Microscopic observation for slices of EMJ was conducted,
then it was confirmed that the approach taken concerning the
I ! I
0' 10 20 30 40 factors governing performance was appropriate.
Thickness of reinforcing insulation ( m m ) In addition to the tests described herein, "Required
Performance Voltage Withstand Test" have been performed
Figure 1 4 Results of evaluation of thickness dependence to confirm the ability of a 500kV EMJ to withstand the
formula various voltages occurring in actual systems. Also "Long-
term Performance Verification Test? confirms that the design
lifetime can be achieved. These test results are reported in
642

subsequent paper [7]. Transmission Line -- Part 11: Jointing Techniques --",
Based on the results of this development program, a model EEEE 1994 PES Winter Meeting, 94WM040-6PWR-D
line with eight EMJs was installed using the same techniques [3] T. Kubota et al.: "Development of 500-kV XLPE
as commercial lines, and subjected to long-term loading CabIes and Accessories for Long-Distance Underground
cycle tests at 450 kV for approximately 10 months. Details Transmission Line -- Part I: Insulation Design of Cables -
will be presented in a subsequent report, but as of December -",IEEE 1994 PES Winter Meeting, 94WM097-6PWRD
1994, long-term tests have been satisfactorily completed, [4] Kohashi et al.: "Research on Extrusion Molded Joint
verifying the long-term reliability of commercial-scale Defect Factors by Previous Cutoff Tests", 1993 Electrical
systems. Association Power and Energy Division Conference, 467
With a view to the construction of commercial lines, we [SI H. Ishihara et al.: "Improvement in Reliability of
are working on a comprehensive quality control method Extrusion Type Molded Joint for 275-kV XLPE Cable",
covering everything from materials acceptance to final h e EEE Transactions on Paper Delivery, Vol. 7, No. 4,1992
commissioning. [6] Takahashi et al.: "Study of Performance Improvements
for Extrusion Molded Joints", 1992 Electrical Association
National Convention, 1477
[7] M. Fukawa et al.: "Development of 500-kV XLPE Cables
and Accessories for Long-Distance Underground
References Transmission Line -- Part IU: Electrical Properties of
[l] K. Kaminaga et al.: "Research and Development of 500-kV XLPE Cables --",E E E 1995 PES Summer
500-kV XLPE Cables", IEEE Symposium on Electrical Meeting proceedings, submitted.
Insulation, 1986
[2]T. Kubota et al.: "Development of 500-kV XLPE Cables
and Accessories for Long-Distance Underground
643
Biography

Naoki Takeda was born in Kanagawa, Japan, on Atsushi Nakatani was born in Ishikawa, Japan on
November 27, 1963. He received a B.S. degree in November 11,1950. He graduated from Kanazawa
electrical engineering from Nihon University, Technical Collage, Ishikawa, Japan in 1971.
Japan in 1986. He joined Sumitomo E l d c Industries, Ltd. in
He joined the Tokyo Eledric Power Co., Inc., in 1971, He has been engaged in research and
1986. He has been engaged in design of development of accessories of EHV cables.
underground transmission lines and research and
development of EHV cables and their accessories.
He is a menber of the Institute of Electrical
Engineers of Japan 0.

Haiime Noda was born in Kanagawa, Japan on


December 4, 1956. He received a B.S. degree in
metallurgy from Tokyo University, Japan, in 1981.
Shouichirou h m i was born in Aichi, Japan, on He joined the Furukawa Electric Co., Ltd. in
December 27, 1961. He graduated from 1982. He has been engaged in research and
Ichinomiya Technical High School, Aichi, Japan in development of Heat Recovery Systems and
1980 and from the electrical engineering course of accessories of EHV cables.
Gifu University, Japan in 1984.
He joined Chubu Electric Power Co., Inc. in
1980. He has been engaged in research and
development for electric power system.
He is a menber of the IEEJ. Masawki Yamamchi was born in Hokkaido,
Japan, on October 4, 1943. He graduated from
Otaru Senshuu Technical High School, Japan, in
1962. Since then he has been in The 1st
Department of Cable Research Laboratory.
He has been engaged in research and
Kazunari Asari was born in Nara, Japan on development and development of EHV cable
February 22, 1959. He graduated from Nara accessories.
Technical Collage, Japan in 1979. He is a menber of the IEEJ.
He joined Kansai Electric Power Co., Inc. in
1979. He has been engaged in research and
development of underground transmission M a s a m Tan was born in Chiba, Japan, on July
technology. 24, 1958. He received a B.S. and M.S. degree of
He is a meqber of the IEEJ. synthetic chemistry from Shinshy University,
Japan, in 1981and 1983 respectively.
He joined Fujikura Ltd. in 1983. He has been
engaged in research and development of high

You might also like