PEKERJAAN : DESAIN RINCI PENYEDIAAN AIR BAKU PEDESAAN


LOKASI : KABUPATEN TANGGAMUS

PROYEK : PENYEDIAAN AIR BAKU LAMPUNG


TAHUN ANGGARAN : 2004

A. BIAYA LANGSUNG PERSONIL

A.1. BIAYA PERSONIL

JUMLAH JUMLAH HARGA


NO URAIAN MM
ORANG (Rp) (Rp)
1 2 3 4 5 6
1 Ketua Tim/Ahli PSDA (SI - 8 Thn) 1 6 7,800,000.00 46,800,000.00
2 Ahli Struk. Bangunan Air (SI - 5 Thn) 1 5 5,500,000.00 27,500,000.00
3 Ahli Hidrologi dan Hidrolika (SI - 5 Thn) 1 2 5,500,000.00 11,000,000.00
4 Ahli Mekanika Tanah (SI - 5 Thn) 1 3 5,500,000.00 16,500,000.00
5 Ahli Teknik Geodesi (SI - 5 Thn) 1 4 5,500,000.00 22,000,000.00
6 Ahli Teknik Penyehatan (SI - 5 Thn) 1 2 5,500,000.00 11,000,000.00
7 Cost Estimator (SI - 5 Thn) 1 2 5,500,000.00 11,000,000.00
Jumlah A.1 145,800,000.00

A.2. SUB PROFFESIONAL STAFF

JUMLAH JUMLAH HARGA


NO URAIAN MM
ORANG (Rp) (Rp)
1 2 3 4 5 6
1 Chief Surveyor Topografi 1 3.5 2,550,000.00 8,925,000.00
2 Surveyor Topografi 3 3 1,800,000.00 16,200,000.00
3 Surveyor Mekanika Tanah 3 2 1,800,000.00 10,800,000.00
4 Surveyor Hidrometri 3 3 1,800,000.00 16,200,000.00
5 Juru Gambar 2 3 1,550,000.00 9,300,000.00
6 Operator CAD 1 3 925,000.00 2,775,000.00
7 Enumerator 2 1 1,800,000.00 3,600,000.00
Jumlah A.2 67,800,000.00

A.3. TENAGA PENDUKUNG

JUMLAH JUMLAH HARGA(Rp)


NO URAIAN MM
ORANG (Rp) (Rp)
1 2 3 4 5 6
1 Kepala Kantor/Administrasi 1 6 775,000.00 4,650,000.00
2 Operator Komputer 2 6 725,000.00 8,700,000.00
3 Pesuruh 1 6 400,000.00 2,400,000.00
4 Tenaga Lokal
- Topografi 9 3 350,000.00 9,450,000.00
- Mektan 6 2 350,000.00 4,200,000.00
- Hidrometri 6 3 350,000.00 6,300,000.00
Jumlah A.2 35,700,000.00

Page 1
B. BIAYA LANGSUNG NON PERSONIL

B.1. BIAYA KOMUNIKASI


JUMLAH HARGA(Rp)
NO URAIAN SATUAN VOL
(Rp) (Rp)
1 2 3 4 5 6
1 Faksimile dan Telephon Bulan 6 415,000.00 2,490,000.00
2 Surat Menyurat Bulan 6 54,000.00 324,000.00

Jumlah B.1 2,814,000.00

B.2. BIAYA SEWA KANTOR LAPANGAN (BASE CAMP)


JUMLAH HARGA(Rp)
NO URAIAN SATUAN VOL
(Rp) (Rp)
1 2 3 4 5 6

1 Biaya Sewa Base Camp 2 Lokasi Bulan 8 450,000.00 3,600,000.00

Jumlah B.2 3,600,000.00

B.3. BIAYA TRANSPORTASI


a. Mobilisasi dan Demobilisasi
JUMLAH HARGA(Rp)
NO URAIAN Jml Orang Trip
(Rp) (Rp)
1 2 3 4 5 6

1 Proff. Staf 9 1 - -
2 Sub Proff. Staf 15 1 - -
3 Peralatan Survey (Topografi, Mektan) 1 1 - -

Jumlah B.3.a -

b. Biaya Transport Lokal


JUMLAH HARGA(Rp)
NO URAIAN UNIT SATUAN VOL
(Rp) (Rp)
1 2 3 4 5 6

1 Sewa Kendaraan Roda 4 2 6 Unit-Bulan 3,850,000.00 46,200,000.00


2 Sewa Kendaraan Roda 2 2 4 Unit-Bulan 400,000.00 3,200,000.00
Jumlah B.3.b 49,400,000.00
Jumlah B.3.a + 3b 49,400,000.00

B.4 BIAYA PERJALANAN DINAS


Jml Hari JUMLAH HARGA(Rp)
Jumlah
NO URAIAN Kunjungan Ke
Orang (Rp) (Rp)
lokasi
1 2 3 4 5 6
Kunjungan Kelapangan
1 Ketua Tim 1 10 60,000.00 600,000.00
2 Ahli Struktur bangunan Air 1 20 60,000.00 1,200,000.00
3 Ahli Hidrologi dan Hidrolika 1 10 60,000.00 600,000.00
4 Ahli Mekanika Tanah 1 10 60,000.00 600,000.00
5 Ahli Teknik Geodesi 1 12 60,000.00 720,000.00
6 Ahli Teknik Penyehatan 1 5 60,000.00 300,000.00
7 Cost Estimator 1 5 60,000.00 300,000.00
Jumlah B.4 4,320,000.00
B.5. BIAYA PERALATAN KANTOR
JUMLAH HARGA
NO URAIAN UNIT VOLUME SATUAN
(Rp) (Rp)
1 2 3 4 5 6

1 Sewa Komputer + Printer 2 6 Unit-Bulan 400,000.00 4,800,000.00


2 Sewa Plotter 1 3 Unit-Bulan 820,000.00 2,460,000.00
3 Sewa Digitizer 1 1 Unit-Bulan 500,000.00 500,000.00
4 Sewa Komputer CAD 1 3 Unit-Bulan 500,000.00 1,500,000.00

Jumlah B.5 9,260,000.00

B.6 BIAYA PERALATAN KHUSUS


JUMLAH HARGA
NO URAIAN UNIT VOL SATUAN
(Rp) (Rp)
1 2 3 4 5 6
1 Peralatan Survey Topografi
- Sewa T2 1 2 Bulan 700,000.00 1,400,000.00
- Sewa T0 2 2 Bulan 700,000.00 2,800,000.00
- Sewa Waterpass 2 3 Bulan 400,000.00 2,400,000.00
- Sewa Meet Band 4 2 Bulan 50,000.00 400,000.00
2 Peralatan Survey Mektan
- Sewa Hand Boring 2 2 Bulan 500,000.00 2,000,000.00
- Sewa Sondir 1 2 Bulan 850,000.00 1,700,000.00
- Tabung Sampel tanah 1 60 Buah 14,000.00 840,000.00
3 Peralatan Survey Hidrometri
- Sewa Current Meter 2 3 Bulan 500,000.00 3,000,000.00
- Sewa Water Checker 1 2 Bulan 1,000,000.00 2,000,000.00
- Peilschaal 4 3 Bulan 50,000.00 600,000.00
Jumlah B.6 17,140,000.00

B.7 BIAYA PENGGANDAAN LAPORAN


JUMLAH HARGA(Rp)
NO URAIAN UNIT KUANTITAS SATUAN
(Rp) (Rp)
1 2 3 4 5 6
1 Laporan Pendahuluan
a. Konsep (bahan diskusi) 1 30 Buku 40,000.00 1,200,000.00
b. Setelah perbaikan (hasil diskusi) 1 5 Buku 40,000.00 200,000.00
c. Rencana Mutu Kontrak (RMK) 1 5 Buku 40,000.00 200,000.00
2 Laporan Bulanan (5 bk x 6 bln) 1 30 Buku 17,500.00 525,000.00
3 Laporan Interim
a. Konsep (bahan diskusi) 1 30 Buku 45,000.00 1,350,000.00
b. Setelah perbaikan (hasil diskusi) 1 5 Buku 45,000.00 225,000.00
4 Draft (Konsep) Lap. Akhir 1 30 Buku 65,000.00 1,950,000.00
5 Laporan Akhir
a. Ringkasan Eksekutif 1 5 eksemplar 40,000.00 200,000.00
b. Laporan Utama 1 5 eksemplar 75,000.00 375,000.00
c. Laporan Survey Topografi 1 5 eksemplar 47,500.00 237,500.00
d. Laporan Survey Mekanika Tanah 1 5 eksemplar 45,000.00 225,000.00
e. Lap. Surv. Hidrologi & Hidrometri 1 5 eksemplar 47,500.00 237,500.00
f. Laporan Sosial Ekonomi 1 5 eksemplar 47,500.00 237,500.00
g. Design Note 1 5 eksemplar 44,000.00 220,000.00
h. Rencana Anggaran Biaya 1 5 eksemplar 44,000.00 220,000.00
i. Spesifikasi Teknik 1 5 eksemplar 50,000.00 250,000.00
j. Dokumen Lelang 1 10 eksemplar 44,000.00 440,000.00
k. Petunjuk Operasi dan Pemeliharaan 1 5 eksemplar 35,500.00 177,500.00
l. Gambar Perencanaan (A1) + Kalkir 1 5 eksemplar 325,000.00 1,625,000.00
m.Gambar Perencanaan (A3) 1 5 eksemplar 115,000.00 575,000.00

Jumlah B.7 10,670,000.00


B.8 BIAYA LAIN - LAIN
JUMLAH HARGA(Rp)
NO URAIAN UNIT VOL SATUAN
(Rp) (Rp)
1 2 3 4 5 6
1 Biaya Bahan Lapangan
- Patok BM 1 20 Buah 75,000.00 1,500,000.00
- Patok kayu 1 1 LS 300,000.00 300,000.00
- Formulir 1 1 Ls 196,000.00 196,000.00
2 Biaya Laboratorium
- Kualitas Air (saat banjir dan surut) 1 8 Sampel 250,000.00 2,000,000.00
- Undisturbed sample 1 8 Sampel 300,000.00 2,400,000.00
- disturbed sample 1 16 Sampel 250,000.00 4,000,000.00
3 Dokumentasi Lapangan 1 3 Album 100,000.00 300,000.00
4 Pengumpulan Peta dan Data Sekunder 1 1 LS 1,500,000.00 1,500,000.00
Jumlah B.8 12,196,000.00
RINCIAN PERHITUNGAN BOBOT PEKERJAAN

M M
No. Administrasi Desk Studi Analisa Hidrologi Lap. Bulanan

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
A. BIAYA LANGSUNG PERSONIL
A.1 PROFFESIONAL STAFF
1 Ketua Team/Ahli PSDA 46,800,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00 1,950,000.00
2 Ahli Struktur Bangunan Air 27,500,000.00 825,000.00 - 825,000.00 1,650,000.00 825,000.00 550,000.00 1,375,000.00 550,000.00 - - - - - 6,875,000.00 4,125,000.00 275,000.00 275,000.00 7,562,500.00 935,000.00 550,000.00 165,000.00 137,500.00 - -
3 Ahli Hidrologi dan Hidrolika 11,000,000.00 550,000.00 440,000.00 275,000.00 550,000.00 550,000.00 330,000.00 880,000.00 220,000.00 - - 1,650,000.00 - 2,200,000.00 825,000.00 880,000.00 110,000.00 110,000.00 1,100,000.00 187,000.00 99,000.00 - 44,000.00 - -
4 Ahli Mekanika Tanah 16,500,000.00 495,000.00 577,500.00 330,000.00 330,000.00 412,500.00 330,000.00 825,000.00 247,500.00 - 11,550,000.00 - - - 247,500.00 - 165,000.00 165,000.00 330,000.00 - 165,000.00 165,000.00 165,000.00 - -
5 Ahli Teknik Geodesi 22,000,000.00 220,000.00 440,000.00 330,000.00 550,000.00 660,000.00 660,000.00 550,000.00 220,000.00 15,620,000.00 - - - - 1,540,000.00 - 330,000.00 330,000.00 330,000.00 - - - 220,000.00 - -
6 Ahli Teknik Penyehatan 11,000,000.00 110,000.00 - - - - - - - - - 8,800,000.00 - - 550,000.00 1,100,000.00 220,000.00 - - - - - 220,000.00 - -
7 Cost Estimator 11,000,000.00 - - - - - - - - - - - - - - - - 110,000.00 10,670,000.00 - 110,000.00 110,000.00 - - -

A.2 SUB PROFFESIONAL STAFF


1 Chief Surveyor Topografi 8,925,000.00 446,250.00 - - 446,250.00 - - - - 8,032,500.00 - - - - - - - - - - - - - - -
2 Surveyor Topografi 16,200,000.00 - - - - 16,200,000.00 - - - - - - - - - - - - - - -
3 Surveyor Mektan 10,800,000.00 - - - - - - - - - 10,800,000.00 - - - - - - - - - - - - -
4 Surveyor Hidrometri 16,200,000.00 - - - - - - - - - - 16,200,000.00 - - - - - - - - - - - - -
5 Juru Gambar 9,300,000.00 - - - - - - - - - - - - - - - - - - 9,300,000.00 - - - - -
6 Operator CAD 2,775,000.00 - - - - - - - - - - - - - - - - - - 2,775,000.00 - - - - -
7 Enumerator 3,600,000.00 - - - - - - - - - - - - - - - - - - 3,600,000.00 - - - - -

A.3 TENAGA PENDUKUNG


1 Kepala Kantor / Administrasi 4,650,000.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00 193,750.00
2 Operator Komputer 8,700,000.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00 362,500.00
3 Pesuruh Kantor 2,400,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00 100,000.00
4 Tenaga Lokal
a. Topografi 9,450,000.00 - - - - - - - - 9,450,000.00 - - - - - - - - - - - - - -
b. Mektan 4,200,000.00 - - - - - - - - - 4,200,000.00 - - - - - - - - - - - - - -
c. Hidrometri 6,300,000.00 - - - - - - - - - - 6,300,000.00 - - - - - - - - - - - - -

B. BIAYA LANGSUNG NON PERSONIL


B.1 Biaya Komunikasi
1 Telephone & Facsimile 2,490,000.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00 103,750.00
2 Surat Menyurat 324,000.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00 13,500.00

B.2 Biaya Sewa Kantor Lapangan (Base Camp)


1 Biaya Sewa Base Camp 2 Lokasi 3,600,000.00 - - - - - - - - 1,800,000.00 900,000.00 900,000.00 - - - - - - - - - - - -

B.3 Biaya Transportasi


a. Mobilisasi dan Demobilisasi
Proffesional Staff - - - - - - - - - - - - - - - - - - - -
Sub Proffesional Staff - - - - - - - - - - - - - - - - - - - -
Peralatan Survey (Topografi, Mektan, Hidro) - - - - - - - - - - - - - - - - - - - -

b. Biaya Transport Lokal


Sewa Kendaraan Roda 4 untuk Kantor 46,200,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00 1,925,000.00
Sewa Kendaraan Roda 2 3,200,000.00 - - - - - - - - 1,600,000.00 800,000.00 800,000.00 - - - - - - - - - - - - -

B.4 Biaya Perjalanan Dinas


1 Kunjungan ke lapangan
Ketua Tim / Ahli PSDA 600,000.00 - - - - - - - - 100,000.00 100,000.00 100,000.00 100,000.00 - - 100,000.00 - - 100,000.00 - - - - - -
Ahli Struktur Bangunan Air 1,200,000.00 - - - - - - - - 400,000.00 150,000.00 150,000.00 - - - 250,000.00 - - 250,000.00 - - - - - -
Ahli Hidrologi dan Hidrolika 600,000.00 - - - - - - - - 600,000.00 - - - - - - - - - - - - -
Ahli Mekanika Tanah 600,000.00 - - - - - - - - - 600,000.00 - - - - - - - - - - - - - -
Ahli Teknik Geodesi 720,000.00 - - - - - - - - 720,000.00 - - - - - - - - - - - - - - -
Ahli Teknik Penyehatan 300,000.00 - - - - - - 200,000.00 - - - 100,000.00 - - - - - - - - -
Cost Estimator 300,000.00 - - - - - - - - - - 150,000.00 - - 150,000.00 - - - - - -

B.5 Biaya Sewa dan OP Peralatan Kantor


Sewa Komputer + Printer 4,800,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00
Sewa Plotter 2,460,000.00 - - - - - - - - - - - - - - - - - - 2,460,000.00 - - - - -
Sewa Digitizer 500,000.00 - - - - - - - - 250,000.00 - - - - - - - - - 250,000.00 - - - - -
Sewa Komputer CAD 1,500,000.00 - - - - - - - - - - - - - - - - - - 1,500,000.00 - - - - -

B.6 Biaya Peralatan Khusus

1 Peralatan Survey Topografi


- Sewa T2 1,400,000.00 - - - - - - - - 1,400,000.00 - - - - - - - - - - - - - - -
- Sewa T0 2,800,000.00 - - - - - - - - 2,800,000.00 - - - - - - - - - - - - - - -
- Sewa WP 2,400,000.00 - - - - - - - - 2,400,000.00 - - - - - - - - - - - - - - -
- Sewa Meet Band 400,000.00 - - - - - - - - 400,000.00 - - - - - - - - - - - - - - -

2 Peralatan Survey Mektan


- Sewa Hand Boring 2,000,000.00 - - - - - - - - - 2,000,000.00 - - - - - - - - - - - - - -
- Sewa Sondir 1,700,000.00 - - - - - - - - - 1,700,000.00 - - - - - - - - - - - - - -
- Tabung Sample Tanah 840,000.00 - - - - - - - - - 840,000.00 - - - - - - - - - - - - - -

3 Peralatan Survey Hidrometri


- Sewa Currentmeter 3,000,000.00 - - - - - - - - - - 3,000,000.00 - - - - - - - - - - - - -
- Sewa Water Checker 2,000,000.00 - - - - - - - - - - 2,000,000.00 - - - - - - - - - - - - -
- Peilschal 600,000.00 - - - - - - - - - - 600,000.00 - - - - - - - - - - - - -

B.7 Biaya Penggandaan Laporan


1 Laporan Pendahuluan
a. Konsep (bahan diskusi) 1,200,000.00 - - - - - - 1,200,000.00 - - - - - - - - - - - - - - - - -
b. Setelah perbaikan (hasil diskusi) 200,000.00 - - - - - - - 200,000.00 - - - - - - - - - - - - - - - -
c. Rencana Mutu Kontrak (RMK) 200,000.00 - - - - - - - 200,000.00 - - - - - - - - - - - - - - - -

2 Laporan Bulanan ( 5 Bk x 6 bln) 525,000.00 - - - - - - - - - - - - - - - - - - - - - 525,000.00 - -

3 Laporan Interim
a. Konsep (bahan diskusi) 1,350,000.00 - - - - - - - - - - - - - - - 1,350,000.00 - - - - - - - -
b. Setelah perbaikan (hasil diskusi) 225,000.00 - - - - - - - - - - - - - - - - 225,000.00 - - - - - - -

4 Draft (Konsep) Laporan Akhir


a. Laporan Utama 1,950,000.00 - - - - - - - - - - - - - - - - - - - 1,950,000.00 - - - -

5 Laporan Akhir
a. Ringkasan Eksekutif 200,000.00 - - - - - - - - - - - - - - - - - - - - - - 200,000.00 -
b. Laporan Utama 375,000.00 - - - - - - - - - - - - - - - - - - - - - - 375,000.00 -
c. Laporan Survei Topografi 237,500.00 - - - - - - - - - - - - - - - - - - - - - - 237,500.00 -
d. Laporan Survei Mekanika Tanah 225,000.00 - - - - - - - - - - - - - - - - - - - - - - 225,000.00 -
e. Laporan Survei Hidro 237,500.00 - - - - - - - - - - - - - -

M
CURVE "S" (JADWAL WAKTU PELAKSANAAN)

Nama Proyek : Proyek Penyediaan Air Baku Lampung


Nama Pekerjaan : Desain Rinci Penyediaan Air Baku Pedesaan Kabupaten Tanggamus
Lokasi : Kabupaten Tanggamus
Jangka Waktu Pelaksanaan : 6 (Enam) bulan / 180 hari kalender
Tahun Anggaran : APBN 2004

2004
No. URAIAN KEGIATAN Bobot Juni Juli Agustus September Oktober Nopember Desember KET
(%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

A Pekerjaan Persiapan
100 %
1 Administrasi 2.08 1.04 1.04
2 Mobilisasi Peralatan 1.76 0.88 0.88

B Kegiatan Perencanaan Pendahuluan


1 Desk Studi 1.84 0.92 0.92
2 Penyusunan Rencana Kerja 2.34 1.17 1.17
3 Pengumpulan Data Pendukung/Sekunder 2.44 1.22 1.22 80 %
4 Survey Pendahuluan 1.86 0.93 0.93
5 Penyusunan Lap. Pendahuluan & Pra Lay Out 2.70 1.35 1.35
6 Diskusi Lap. Pendahuluan & Perbaikan 1.82 0.91 0.91

C Kegiatan Survei dan Investigasi


1 Survei Topografi & Penggambaran Existing 19.00 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58 1.58
2 Survei Mekanika Tanah dan Laboratorium 12.54 1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57
60 %
3 Survei Hidrometri dan Laboratorium Kualitas Air 13.44 1.12 1.12 1.12 1.12 1.12 1.12 1.12 1.12 1.12 1.12 1.12 1.12
4 Survei Sosial Ekonomi 1.38 0.35 0.35 0.35 0.35

D Kegiatan Sistem Planning


1 Analisa Hidrologi 1.98 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25
2 Penyusunan Kriteria Perencanaan & Sistem Planning 4.16 0.69 0.69 0.69 0.69 0.69 0.69
3 Analisa dan Alternatif Desain (Lay Out Definitif) 3.22 0.81 0.81 0.81 0.81
4 Penyusunan Lap. Interim 2.04 1.02 1.02 40 %

5 Diskusi Lap. Interim dan Perbaikan 1.70 0.85 0.85

E Kegiatan Desain Rinci


1 Perhitungan Desain (Hidrolika, Dimensi dan Analisa Struktur) 7.06 0.75 0.71 0.70 0.70 0.80 1.20 1.20 0.70 0.15 0.15
2 Penggambaran Detail Desain 7.20 0.60 0.60 0.60 0.60 1.20 1.20 1.00 0.90 0.20 0.10 0.10 0.10
3 Penyusunan Draft (Konsep) Lap. Akhir & Lap. Pendukung 2.16 1.50 0.66
4 Diskusi Draft Lap. Akhir dan Perbaikan 1.46 0.60 0.86
20 %

F Pelaporan

1 Laporan Bulanan 1.72 0.22 0.29 0.29 0.29 0.29 0.29 0.07

2 Penggandaan Lap. Akhir dan Lap. Pendukung 2.08 1.50 0.25 0.20 0.13

3 Album Gambar dan Perencanaan 2.02 1.20 0.30 0.52

0%
Jumlah Bobot (%) 100.00
Bobot Rencana 1.04 4.01 5.34 5.08 6.53 5.18 4.56 4.27 4.52 4.52 5.50 7.11 7.12 7.96 7.23 3.46 2.40 2.40 1.99 1.05 1.85 3.05 2.15 1.68
Kumulatif Bobot Rencana 0.000 0.000 1.04 5.05 10.39 15.47 22.00 27.18 31.74 36.01 40.53 45.05 50.55 57.66 64.78 72.75 79.98 83.44 85.84 88.24 90.22 91.27 93.12 96.17 98.32 100.00
Bobot Realisasi 0.000 0.000 0.000

Kumulatif Bobot Realisasi 0.000 0.000 0.000

Deviasi

Mengetahui, Bandar Lampung, Juni 2004


Direksi Pekerjaan Diperiksa Oleh PT. BINA BUANA RAYA

Ir. R i s m a n Firdy Hamzah, Amd. Ir. Harijadi


NIP. 460 009 342 NIP. 110 054 154 Ketua Team
CURVE "S" (JADWAL WAKTU PELAKSANAAN)

Nama Proyek : Proyek Penyediaan Air Baku Lampung


Nama Pekerjaan : Desain Rinci Penyediaan Air Baku Pedesaan Kabupaten Tanggamus
Lokasi : Kabupaten Tanggamus
Jangka Waktu Pelaksanaan : 6 (Enam) bulan / 180 hari kalender
Tahun Anggaran : APBN 2004

2004
No. URAIAN KEGIATAN Bobot Juni Juli Agustus September Oktober Nopember Desember KET
(%) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

A Pekerjaan Persiapan
100 %
1 Administrasi 2.09 1.04 1.04
2 Mobilisasi Peralatan 1.76 0.88 0.88

B Kegiatan Perencanaan Pendahuluan


80 %
1 Desk Studi 1.84 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23
2 Penyusunan Rencana Kerja 2.33 0.29 0.29 0.29 0.29 0.29 0.29 0.29 0.29
3 Pengumpulan Data Pendukung/Sekunder 2.45 0.41 0.41 0.41 0.41 0.41 0.41
4 Survey Pendahuluan 1.87 0.47 0.47 0.47 0.47 70 %

5 Penyusunan Lap. Pendahuluan & Pra Lay Out 2.70 0.45 0.45 0.45 0.45 0.45 0.45
6 Diskusi Lap. Pendahuluan & Perbaikan 1.81 0.45 0.45 0.45 0.45 70 %

C Kegiatan Survei dan Investigasi


80 %
1 Survei Topografi & Penggambaran Existing 19.00 2.38 2.38 2.38 2.38 2.38 2.38 2.38 2.38
2 Survei Mekanika Tanah dan Laboratorium 12.54 1.57 1.57 1.57 1.57 1.57 1.57 1.57 1.57
3 Survei Hidrometri dan Laboratorium Kualitas Air 13.44 2.24 2.24 2.24 2.24 2.24 2.24
4 Survei Sosial Ekonomi 1.38 0.35 0.35 0.35 0.35 70 %

D Kegiatan Sistem Planning


60 %
1 Analisa Hidrologi 1.97 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
2 Penyusunan Kriteria Perencanaan & Sistem Planning 4.15 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52
3 Analisa dan Alternatif Desain (Lay Out Definitif) 3.22 0.81 0.81 0.81 0.81
50 %
4 Penyusunan Lap. Interim 2.03 1.02 1.02
5 Diskusi Lap. Interim dan Perbaikan 1.69 1.69

40 %
E Kegiatan Desain Rinci
1 Perhitungan Desain (Hidrolika, Dimensi dan Analisa Struktur) 7.06 0.71 0.71 0.71 0.71 0.71 0.71 0.71 0.71 0.71 0.71 0.00 0.00 0.00
2 Penggambaran Detail Desain 7.21 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72 0.72
30 %
3 Penyusunan Draft (Konsep) Lap. Akhir & Lap. Pendukung 2.15 1.08 1.08 0.00 0.00
4 Diskusi Draft Lap. Akhir dan Perbaikan 1.47 1.47 0.00

20 %
F Pelaporan

1 Laporan Bulanan 1.72 0.29 0.29 0.29 0.29 0.29 0.29 0.29

2 Penggandaan Lap. Akhir dan Lap. Pendukung 2.09 1.04 1.04 10 %

3 Album Gambar dan Perencanaan 2.01 1.01 1.01

0%
Jumlah Bobot (%) 99.99
Bobot Rencana 1.04 2.21 3.49 8.30 8.30 8.59 8.30 9.81 10.53 7.72 7.11 3.93 4.38 2.98 1.43 2.50 2.50 2.48 0.72 0.72 0.72 1.01 2.05 2.34
Kumulatif Bobot Rencana 0.000 0.000 1.04 3.26 6.74 15.04 23.34 31.93 40.23 50.04 60.57 68.29 75.40 79.33 83.71 86.69 88.12 90.62 93.13 95.60 96.33 97.05 97.77 98.77 97.65 99.99
Bobot Realisasi 0.000 0.000

Kumulatif Bobot Realisasi 0.000 0.000

Deviasi

Mengetahui, Bandar Lampung, Juli 2001


Direksi Pekerjaan Diperiksa Oleh CV. Sumber Tehnik

Ir. R i s m a n Firdy Hamzah, Amd. Ir. Harijadi


NIP. 460 009 342 NIP. 110 054 154 Ketua Team