Unit Capacity Calculation

Aviva Ainnia
S1 Teknik Pertambangan 2011
Unit Capacity

? Kemampuan sebuah unit berproduksi dalam satu waktu


Example PC 1250 = 8000 BCM (1 day)

Goal
Determine Production Target
Mine Planning
Reference for pit design
Mine Operation Unit performance control

Mine Data Analyze and Evaluate Production Performance


Unit Capacity Calculation
Formula :
Unit Capacity = Effective Working Hour x Productivity

Unit Capacity = PA x UA x 24 Hrs x Productivity

24 Hrs = EWH + STB + BD

Effective Working Hour (EWH)


Standby Time
Breakdown Time
Unit Capacity Calculation

PA UA Pdty
Effect : Effect : Effect :
Breakdown Time Standby Time All of productivity component

𝑀𝑂𝐻𝐻 −𝐵𝐷 𝑀𝑂𝐻𝐻−𝐵𝐷−𝑆𝑇𝐵


PA = x 100% UA = x 100%
𝑀𝑂𝐻𝐻 𝑀𝑂𝐻𝐻−𝐵𝐷

BD = MOHH-(PA x MOHH) STB = Idle + Delay

Idle : uncontrolled
Delay : controlled
Unit Capacity Calculation

STEPS

1 Collect data PA from


plant/maintenance dept.

Determine Standby
2 Time Parameters &
EWH 3

3 Determine productivity
plan

Calculate loader &


4
hauler capacity
4
5 Production Target Plan 5
2 Standby Time Parameter & EWH
3 Determine Productivity Plan

Distance has impact for hauler productivity


4

5
Production Target Plan
TERIMA KASIH