You are on page 1of 39

Journal of Management in Engineering.

Submitted July 3, 2012; accepted May 31, 2013;


posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Risk Management Strategies for Privatized Infrastructure Projects:

A Study of the Build-Operate-Transfer Approach in East Asia and

the Pacific

Namhun Lee1 and John E. Schaufelberger2


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
ABSTRACT

d cr
Private-public partnerships have been adopted for the development of public infrastructure to

te s
meet the growing demand for public services. Many Asian countries have used the build-

di nu
operate-transfer (BOT) approach to develop pubic infrastructure projects. However, the

potential benefits of undertaking a BOT project are accompanied with corresponding risks from
ye a
the private sector’s perspective. The objectives of this study are (1) to identify and discuss major
op M
risks inherent in the East Asian and Pacific region and (2) to propose risk management strategies

for future BOT projects to be successful. This paper reports the results of five case study
C ted

analyses undertaken to review their primary risks and mitigated methods. In addition, this paper

proposes some strategies for future BOT projects. Two main categories of risks were analyzed:
ot p

general risks and project-specific risks. Risk management strategies were suggested for each
N ce

category of risk. The main finding of this study indicates that the private sector cannot be the
Ac

only participant in risk management. The host government’s active support is the most essential

for the profitability and economic viability of a BOT project in the East Asian and Pacific region.

1
Assistant Professor, Department of Construction Management, East Carolina University,
Greenville, NC 27858-4353, USA. Email: leenam@ecu.edu
2
Professor, Department of Construction Management, University of Washington, Seattle, WA
98195-1610, USA. Email: jesbcon@uw.edu

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Keywords: Risk management; Private-public partnerships; Build-operate-transfer; Privatized

infrastructure; Project management

INTRODUCTION

Rapid economic growth in Asian countries has resulted in increased demand for
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
development of additional infrastructure such as power plants, airports, highways, bridges, ports,

d cr
tunnels, and water treatment plants. However, the demand for development of government-

te s
initiated infrastructure projects has far surpassed the availability of public financing in the East

di nu
Asia and the Pacific region. To meet the growing demand for public services, many

governments have solicited private investments for public infrastructure projects by adopting the
ye a
idea of privatization which grants the private sector the right to finance, design, and construct a
op M
specific infrastructure and operate it for a concession period (Menheere et al. 1996).

Over 70% of Asian privatized infrastructure projects have been developed by


C ted

international sponsors (Kwak 2002). Most of these projects have been for power generation or

transportation. Unfortunately, about 30% of the privatized projects have had disappointing
ot p

results (Kwak 2002). In many Asian countries, the build-operate-transfer (BOT) approach has
N ce

been adopted to develop the needed infrastructure. The BOT approach has been considered the
Ac

best way to reduce sovereign loans and improve a government’s credit rating. The governments

in Asia are able to promote foreign direct investments in their infrastructure projects through the

BOT approach. The private sector can enjoy high returns on investments from successful BOT

projects. However, the participation of private companies in a BOT project means the project

risks and the financial and administrative burden are transferred from the public sector to the

private sector. Therefore, it is essential for the private sector to understand the inherent risks

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

associated with BOT projects in the East Asia and the Pacific region and to formulate

appropriate risk management strategies to deal with them.

RESEARCH BACKGROUND
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Basic Principles of the BOT Approach

d cr
The “Build-Operate-Transfer” is a project delivery method that uses private investments

te s
to undertake the development and operation of public infrastructure traditionally administrated

di nu
by the public sector (UNIDO 1996). The BOT approach may not be suitable for all types of

infrastructure privatization but can be considered a well-developed public-private partnership.


ye a
Under the BOT approach, the private sector is responsible for financing and constructing
op M
infrastructure facilities and operating them for a pre-determined concession period. During the

concession period, the private sector collects revenues from operating the facilities to repay the
C ted

project costs and make a profit. On expiration of the concession, the ownership of the facilities

is transferred to the host government at no cost.


ot p

Investing in BOT project can be a highly complex and risky undertaking because of the
N ce

requirement of large capital outlays, long lead-times, and major regulatory changes (Rubin and
Ac

Wordes 1998). The private sector’s greatest concern is whether returns on investments can

justify the risks or not. Therefore, the following factors must be considered significant from the

outset: time to develop and negotiate, host government support, a suitable economic climate,

political stability, a stable legal and regulatory environment, and a foreign currency’s free

convertibility and remittance (UNIDO 1996). In addition, it is extremely important to

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

understand the role of each party involved in a BOT project and the contractual relationships

among the participants for effective risk management.

Major Participants in BOT Projects

Project participants include the granting authority which is typically a government


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
agency; the concessionaire; and one or more financial institutions (Tiong 1990a). The granting

d cr
authority identifies project requirements, establishes the concession period, solicits tenders, and

te s
awards the contract. The concessionaire typically is a consortium or joint venture of

di nu
engineering, construction, and venture capital firms and may include equity investors such as the

host government or institutional investors. Investment capital may come from commercial
ye a
banks, insurance companies, or the sale of bonds. The general relationships among the project
op M
participants are shown in Figure 1. Constructors typically invest equity during the early phases

on the project, but often sell their own position upon the completion of construction. At the end
C ted

of the concession period, all operating rights and operational responsibilities revert to the

granting authority.
ot p
N ce

Basic Characteristics of BOT Projects


Ac

BOT projects are highly risky undertakings because of many uncertainties involved in the

projects. These uncertainties may lead to unnecessary delays and cost overruns, turn a

potentially profitable project into an unprofitable one, and eventually result in suspension or

cancellation of the project. Some causes of BOT project failure are as follows: delays in

completion, cost overruns, technical failure, the concessionaire’s financial failure, expropriation

by the host government, poor management, and legislative or regulatory changes (Nevitt and

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Fabozzi 2000). Understanding these causes can be the key to the successful performance for

future BOT projects. Therefore, before undertaking a BOT project, one of the most important

tasks is the accurate identification, correct allocation, and optimal management of the potential

risks.
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Risk Management on BOT Projects

d cr
Risk management is the discipline that identifies all risks in an environment, assesses

te s
their potential impact on critical performance measures, and employs direct and indirect means

di nu
for either reducing the exposure of the underlying risks in project activities or shifting some of

the risks to third or external parties (Smith et al. 2006). The principal issue related to risk
ye a
management is how to quantify and deal with the risks. Effective risk management demands the
op M
rapid and realistic forecasts of the future and the practical, reasonable, and cost-effective hedging

tools. In addition, it requires flexible attitudes and procedures since the accuracy of expectations
C ted

decrease with time.


ot p

Risks Inherent in BOT Projects


N ce

Risk management starts with identification of the risks that could be encountered in BOT
Ac

projects. As compared to other project delivery methods, it is more complicated to address the

risk issues in BOT projects because of the wider scope of work, the length of the concession

period, and the scope of contractual responsibilities undertaken by the concessionaire.

Furthermore, the risks inherent in the development of a BOT project can vary, depending on the

country and the project. Nevertheless, classifying the identifiable risks in meaningful categories

is useful for a systematic risk management (Al-Bahar and Crandall 1990). In general, the

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

primary risks associated with a BOT project can be broadly grouped into two categories: general

risks and project-specific risks (Ng and Loosemore 2007).

General Risks

General risks are mainly related to macro-environmental factors of the host country such
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
as the political environment, economic condition, the legal system, taxation, or fluctuations in

d cr
currency exchange rate. Each country holds a unique set of general risks. The risks may

te s
severely affect the project’s viability during the entire lifetime of a BOT project. Therefore, it is

di nu
extremely important to identify the risks thoroughly before undertaking a project, particularly in

a developing country. General risks can be subdivided into political risks, financial risks, and
ye a
legal risks.
op M
Political risks are associated with the internal and external political situation of the host

country. These risks can be also classified into sovereign risks and instability risks. Sovereign
C ted

risks include expropriation of assets by the government, restriction of operating freedom,

increased taxes or other financial penalties, constraints of the ability to repatriate profits, and any
ot p

other government interference that could jeopardize a BOT project (Lang 1998). Instability risks
N ce

are related to cancellation or revision of contracts and damage to property from terrorism or riot.
Ac

In Asian developing countries, it is significant to mitigate political risks since major political

changes may often occur (Tam 1999).

Financial risks relate to the host country’s economic environment surrounding the

project. These risks include currency devaluation, foreign exchange fluctuations, fluctuations in

interest rate, and inflation. These risks should be mitigated for a BOT project in the East Asia

and Pacific region since revenues, expenses, capital expenditures, and loans are typically in more

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

than one currency, which can directly affect the cost of debt service and the real value of the

projected revenue.

Legal risks result from changes in laws or regulations and immature legal systems that

may adversely affect the BOT undertakings. The host country’s changes in tax codes,

environmental regulations, labor regulations, import restrictions, and corporate regulations


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
during a concession period may undermine the long-term viability of a BOT project.

d cr
te s
Project-Specific Risks

di nu
Project-specific risks can be controlled by the private sector. These risks can be

classified into development, construction, and operation risks (Tiong 1996). First, development
ye a
risks include defects in the request for proposal, planning and approval delays, errors in
op M
economic, environmental, or technological assessment, and rejection of the proposal by the

granting authority. Among these risks, bid risks may be the most important at this stage due to
C ted

the loss of expenditures for various feasibility studies and preparations for the bid package.

Construction risks relate to delays in completion and cost overruns. Completion delays
ot p

directly affects the generation of revenue since investors of the BOT project rely on income from
N ce

the completed project to recover their investment. Cost overruns may impact the profitability of
Ac

the project by increasing construction and financing costs. In addition, a possibility of force

majeure events and liability for the accident should be considered careful at this stage.

Operation risks relate to an increased cost of operation and maintenance and insufficient

revenue from the completed project. Market-based operation risks have two components:

demand risks and price risks. Demand risks result from the uncertainty of the demand for the

product or service provided by the completed project. Price risks are associated with the fees

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

that can be charged for the product or service, which directly affects the project’s profitability

and economic viability. Regardless of actual operational costs, an unreasonable fee may be set

by the granting authority or due to competing facilities. Therefore, risk identification and

management through contractual agreements and arrangements are essential to success of BOT

projects.
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
d cr
METHODOLOGY

te s
Case study analysis was selected to identify the unique or critical risks and develop risk

di nu
mitigation strategies for BOT projects in East Asia and the Pacific. Table 1 presents five BOT

projects selected from various countries within the East Asia and Pacific region, considering
ye a
their different levels of general risks. The selected projects have been classified into contract-
op M
based projects (e.g. power plants) and market-based projects (e.g. transportation systems) based

on the revenue types. These case study projects were analyzed to determine the primary risks the
C ted

concessionaires faced, their mitigation methods, and the results obtained.


ot p

CASE STUDY ANALYSES


N ce
Ac

Laibin ‘B’ Power Plant, China

The Laibin ‘B’ power plant was the first state-approved privatized project in the Guangxi

province to be financed entirely by foreign investors and developed by a foreign company (Wang

and Tiong 2000). The risks associated with the Laibin ‘B’ project were evenly allocated through

the comprehensive and well-structured provisions in the project agreements such as concession

agreement, power purchase agreement, and fuel supply and transportation agreement shown in

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Figure 2. Hence, the risk management framework of this project became a benchmark for future

BOT power projects in China (Chan et al. 2005).

Project Analysis

Sovereign risks were managed effectively by considering them political force majeure
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
under the concession agreement. In the event of the project’s termination resulting from political

d cr
force majeure events, the Guangxi government guaranteed that loans from lenders would be

te s
repaid and the concessionaire would be compensated for the invested equities in accordance with

di nu
the concession agreement. Legal risks were also mitigated through the concession agreement. In

case that the concessionaire is not able to fulfill its obligations because of any changes in laws,
ye a
tax regulations, or environmental standards, the Guangxi government guaranteed that the costs
op M
resulting from such changes would be compensated.

Under the power purchase agreement, the price of electricity from the Laibin ‘B’ power
C ted

plant would be denominated in RMB and divided into a fixed portion and a floating portion. To

mitigate variations in the currency’s exchange rate against the US dollar, the concessionaire
ot p

obtained the right to adjust the floating portion on a monthly basis.


N ce

The State Administration of Exchange Control approved the concessionaire’s right to


Ac

convert and remit foreign currency and ensured that this right would not be affected by any

future adverse events. In addition, the concessionaire made an agreement with China Bank to

convert the concessionaire’s RMB receipts into US dollars.

The project rate of return for foreign investors in China had been indirectly limited to

about 15% by Chinese authorities. Because of this requirement, foreign investors were reluctant

to invest their money on this project, and the concessionaire had difficulty in obtaining funding.

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

To assist the concessionaire in project financing, the Guangxi government agreed to mortgage or

transfer to the right to operate the facilities for purpose of financing. The concessionaire was

responsible for obtaining necessary approvals. The Guangxi government ensured that the State

Planning Commission and the Ministry of Power Industry would support the concessionaire in

obtaining necessary approvals smoothly. To confirm this, the concession agreement specified
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
that an arbitrary denial or withdrawal of the necessary approvals was to be regarded as political

d cr
force majeure.

te s
The concessionaire procured an additional US$ 40 million letter of standby credit in case

di nu
of cost overruns and any contingencies during the construction stage. The concessionaire

purchased appropriate insurance policies to mitigate force majeure events. In addition, in case of
ye a
force majeure events, the concession agreement specified that all the concessionaire’s obligations
op M
were to be suspended and the suspended days were to be compensated by extending milestone

dates and the concession period.


C ted

The Guangxi government had insisted on negotiation of power rates every operating year

to control inflation, which made overall project revenues unpredictable. Thus, the adjustment of
ot p

the price of electricity by the government was the most significant risk in the Laibin ‘B’ project
N ce

since it might reduce the economic viability of the project. This risk was mitigated by agreeing
Ac

that the concessionaire would propose the basis of the price structure, payment mechanism, and

price adjustment. This matter was approved by the Guangxi government and the State Planning

Commission and included in the power purchase agreement. In addition, a specific provision

stating that the central or provincial pricing bureau would comply with the pricing formula was

incorporated into the concession agreement. Under the fuel supply and transportation agreement,

the Guangxi Power Industry Bureau was obliged to purchase at least 63% of the plant’s capacity

10

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

per operating year from the concessionaire. In addition, the Guangxi government guaranteed the

supply of fuel conformable to the specifications to the concessionaire. An analysis of the risks

and mitigation methods for the Laibin ‘B’ power plant project is summarized in Table 2.

Pagbilao Power Plant, Philippines


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
The Pagbilao power plant is a large coal-fired thermal power plant. Competitive bids for

d cr
the BOT contract were invited, and Hopewell Power Philippines Corp. was selected to finance,

te s
construct, and operate the electric generating plant for the concession period of 25 years (Lysy et

di nu
al. 2000). Hopewell Power Philippines Corp. was required to develop and maintain the power

station, a bridge linking Pagbilao Grande Island to the main island, and a paved road necessary
ye a
for the power plant. In addition, Hopewell Power Philippines Corp. was responsible for
op M
arranging the project financing and operating the Pagbilao power plant. Most risks associated

with this project were allocated to project participants through the contracts and agreements as
C ted

shown in Figure 3. The Philippine government guaranteed that the Philippines National Power

Corp.’s obligations under the concession agreement would be performed.


ot p
N ce

Project Analysis
Ac

The Philippines government assumed responsibility for all tasks within the control of the

government, government authorities, and the Philippines National Power Corp. Under the

concession agreement, the Philippines National Power Corp. was obliged to provide Hopewell

Power Philippines Corp. with the project site, build transmission facilities connecting the plant to

the electric power grid, supply the fuel for the power station, and purchase the electricity

generated by the power plant throughout the operation period. In addition, the Philippines

11

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

National Power Corp. was to purchase all the facilities of the power plant from Hopewell Power

Philippines Corp. if any political force majeure event impairs the project’s economic viability.

This obligation made it possible for Hopewell Power Philippines Corp. to efficiently deal with

any changes in Philippine laws or regulations.

In the concession agreement, the power price was structured in US dollars and Pesos
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
during the concession period. In addition, the Philippines National Power Corp. was to pay a

d cr
capacity fee and an energy fee to Hopewell Power Philippines Corp. every year. These fees were

te s
structured in two portions in US dollars and Pesos. In these ways, Hopewell Power Philippines

di nu
Corp. could alleviate losses resulting from currency fluctuations to some extent.

When the Pagbilao power plant was first proposed, it met all national environmental
ye a
standards required for such a large coal-burning power plant, and environmental inspectors
op M
confirmed Hopewell Power Philippines Corp.’s environmental plan. Nevertheless,

environmentalists and local community groups strongly forbade this project to be developed,
C ted

insisting upon public interest, public safety, and public health (Lam 1999). There was a legal

battle challenging the proper issuance of the Environmental Compliance Certificate. To handle
ot p

this protest, Hopewell Power Philippines Corp. had to not only expand the initial environmental
N ce

plan but also spend 16% of the total project cost on pollution control.
Ac

Under the turnkey contract, the construction consortium was entitled to an early

completion bonus if the construction could be completed ahead of schedule. On the other hand,

if construction delays and lack of plant performance occurred due to the fault of the construction

consortium, the turnkey contractors were to pay penalties and liquidated damages to Hopewell

Power Philippines Corp. To ensure that Hopewell Power Philippines Corp. could make the

payment under extremely adverse conditions, Hopewell Power Philippines Corp. procured a

12

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

letter of standby credit amounting to US$ 16 million from the banking syndicate. In the event of

Hopewell Power Philippines Corp.’s funding insufficiency resulting from any breach or default

by the construction consortium, the turnkey contractors were to make subordinated loans up to

US$ 200 million to Hopewell Power Philippines Corp (Woodhouse 2005). These obligations

were guaranteed by their parent companies.


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
The Pagbilao power plant was successfully completed ahead of schedule and within

d cr
budget. However, the operation was delayed since transmission facilities connecting the

te s
Pagbilao power plant to the electric power grid were not available on time. In accordance with

di nu
the concession agreement, all the costs resulting from this operation delay were compensated by

extending the concession period (Woodhouse 2005). An analysis of the risks and mitigation
ye a
methods for the Pagbilao power plant project is summarized in Table 3.
op M

North-South Highway, Malaysia


C ted

The North-South Highway (NSH) was the first private toll road project in Malaysia. This

project had been first developed by the Malaysian Highway Authority. However, due to
ot p

financial difficulties, the government decided to complete the remaining work under the BOT
N ce

approach. United Engineers Malaysian Bhd (UEM) was selected to complete the rest of the
Ac

highway (500 km) and rehabilitate the existing road (370 km) (Fishbein and Babbar 1996). The

concession agreement was signed for the entire highway. UEM formed a multinational joint

venture of Projek Lebuhraya Utara-Selatan (PLUS) Berhad to undertake this project (Walker and

Smith 1995). Figure 4 shows the contractual structure of the NSH project.

Project Analysis

13

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

The NSH project received the Malaysian government’s full support through an extensive

security package. The government assumed primary responsibility for traffic and revenues,

currency fluctuations, and political actions to attract project financing. Moreover, the

government provided substantial loans and financial guarantees to PLUS. Therefore, most of the

risks under the responsibility of PLUS were related to construction, force majeure, and tort
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
liability.

d cr
The Malaysian government provided PLUS with a hedge against foreign exchange and

te s
interest rate fluctuations by guaranteeing soft loans (Tiong 1990b). Each subcontractor was

di nu
required to make an obligatory contribution (13% of the contract price) to equity financing. In

this way, the equity burden of PLUS was partially transferred to the subcontractors .
ye a
The construction cost was initially estimated to be US$ 1.3 billion, but it enormously
op M
escalated to approximately US$ 3.2 billion due to design changes, local inflation, and difficult

terrain (Fishbein and Babbar 1996). This cost overrun risk could be shared with subcontractors
C ted

by lump-sum construction contracts. In addition, the Malaysian government set aside a standby

credit (10% of the total project cost) for the NSH project.
ot p

The Malaysian government and PLUS agreed to share force majeure risks through a
N ce

guarantee of extending the concession period if any force majeure event occurred. The
Ac

government also guaranteed minimum revenues to PLUS in case operation became disrupted or

temporarily suspended due to any force majeure events. These risks were also managed by

private insurance contracts.

PLUS was granted the right to collect all toll charges. However, an increase in toll rates

had to be approved by the Malaysian government. If project revenues fell below a predicted

target level for the first 17 years of operation, the government would provide standby financing

14

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

to PLUS under the traffic volume supplement agreement (Tiong 1990b). Table 4 summarizes

the unique or critical risks and effective mitigation methods identified in this project.

High Speed Rail System, Taiwan

The Taiwan High Speed Rail (THSR) system project was the first BOT project in Taiwan
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
and one of the largest privatized projects (in dollar terms) to be undertaken in Asia (Lu et al.

d cr
2010). Taiwan High Speed Rail Co., Ltd., a consortium of five prominent local business groups,

te s
was selected to finance, design, construct, and operate the THSR project. The Ministry of

di nu
Transportation and Communication (MOTC) and the consortium signed the concession

agreement (Ho 2004). Figure 5 shows the contractual structure of the THSR project.
ye a
op M
Project Analysis

In the concession agreement, the Taiwanese government guaranteed the loss resulting
C ted

from policy changes to the consortium. This clause also made the Taiwanese government take

the political risk. Besides, the Taiwanese government guaranteed tax incentives during the
ot p

operation phase to reduce the risk of change of policy. The consortium and the Taiwanese
N ce

government agreed to establish a mediation committee for this project to negotiate and resolve
Ac

disputes. Most of the risks related to delays in land acquisition, financing problems, and drawn-

out decision on the core systems, which were the main reasons why this project fell behind from

its initial schedule.

The MOTC was to be responsible for the preparatory tasks listed in the concession

agreement. Nevertheless, this obligation was not fulfilled as planned. The land acquisition for

15

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

the THSR line was delayed and the losses resulting from this delay were as not compensated on

the grounds that a schedule for delivery of the land was not specified.

The consortium encountered difficulties to acquire sufficient loans for the THSR project.

The government played a key role in assisting the consortium in project financing. First, the

MOTC made a tripartite agreement with a banking syndicate. Under the tripartite agreement, the
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Taiwanese government deposited NT$ 240 billion (US$ 7.06 billion) into the banking syndicate

d cr
(25 local banks) to provide the source of a syndicated loan (85.7% of the total required debt)

te s
(Sun 2000). Second, the Taiwanese government guaranteed to both the consortium and the

di nu
banking syndicate that the government would take over the project and assume the debt

responsibility of the consortium if the project is terminated by the government or the consortium
ye a
defaults. Finally, the Taiwanese government invested NT$ 8 billion (US$ 235.3 million) in the
op M
consortium’s equity.

The income risk was solely assumed by the consortium. In a typical market-based
C ted

project, the host government subsidizes the concessionaire based on a minimum number of

passengers. However, the consortium was not subsidized by the Taiwanese government. Due to
ot p

lack of confidence in returns on the project, the banking syndicate insisted on the following
N ce

clause in the tripartite agreement: The equity to debt ratio was limited at 3 to 7. This clause
Ac

resulted in the consortium’s failure of meeting its funding targets due to intensive capital

spending during the construction period.

The East Asian financial crisis in 1997 caused Taiwanese currency to be devaluated to

almost 30%. Fortunately, the main financial frame mainly consisted of domestic funds and the

revenues and loans were to be collected and repaid in Taiwanese currency. In addition, the

construction fees were to be paid all in Taiwan dollars. However, some expenses such as

16

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

consulting fees, railway electrical sub-system construction, and imported materials were to be

paid in US dollars (more than US$ 2.8 billion). Ultimately, the devaluation of Taiwanese

currency resulted in the increase of project costs amounting to approximately US$ 500 million.

No one could predict such a financial crisis because the Taiwan economy had grown very

rapidly. Thus, the consortium did not have a strategy for handling potential currency fluctuation
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
and was exposed to financial loss due to the significant devaluation of the local currency.

d cr
The construction was delayed due to changes in building codes resulting from the

te s
earthquake in 1999 (THSRC 2009). To make matters worse, the decision on integrating

di nu
European and Japanese technology and insufficient preparation for operations caused the

operation delay (Taipei Times 2005). Table 5 summarizes the primary risks and their mitigation
ye a
methods reviewed in this project.
op M

Second Stage Expressway, Thailand


C ted

The Second Stage Expressway (SSE) project is an extension of the First Stage

Expressway system developed by the Expressway and Rapid Transit Authority of Thailand
ot p

(ETA) (Tam 1999). The ETA commissioned a detailed design of the SSE project. To lessen the
N ce

citizens’ tax burden and make rapid progress, the ETA invited competitive bids for a BOT
Ac

proposal and selected Bangkok Expressway Co., Ltd. (BECL), and signed the concession

agreement (Levy 1996). Figure 6 illustrates the contractual structure of the SSE project.

Project Analysis

The SSE project proceeded smoothly until the military coup d’etat in 1991. After the

change of regime by the coup d’etat, several problems were encountered due to different contract

17

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

interpretations. The new government changed a land evaluation basis to gain popular support,

which resulted in an enormous increase of land acquisition cost. Consequently, the construction

work for sector B fell behind schedule because the ETA had financial difficulties in delivering

the land necessary for the sector B construction to BECL as planned. BECL claimed for the

damages, but the ETA refused to indemnify BECL for any expenses incurred.
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Even though the construction work for sectors A and C was completed, the completed

d cr
route of about 20.4 kilometers could not be opened to traffic because of the following reasons:

te s
BECL required the ETA to set toll rates for the urban section to 30 Baht (US$ 1.40) in

di nu
accordance with the concession agreement. However, two weeks before opening sectors A and

C, the new government insisted on lowering the predetermined toll rates from 30 Baht to 20 Baht
ye a
(US$ 0.94). In response to this government action, BECL refused to open sectors A and C. The
op M
new government seized all assets of the completed expressway to ease the traffic crisis of the

Bangkok metropolitan area. BECL filed a claim against the new government in an international
C ted

court. The court ordered opening these sectors at the toll rates as specified in the concession

agreement.
ot p

All toll rates collected in the urban area were to be shared according to the revenue
N ce

sharing proportions stipulated in the concession agreement. However, the ETA contended that
Ac

this revenue sharing scheme was to be enforced when all the sectors were opened. BECL argued

that the SSE project’s substantial parts were already completed and the completion delay of

sector B was attributed to the ETA’s delay in delivering the land necessary for the sector B

construction. BECL’s appeal for the revenue sharing was not accepted.

Due to continual disputes between the ETA and BECL, BECL was faced with serious

financial difficulties. Lending institutions suspended BECL’s loan payments (Ogunlana 1999).

18

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Consequently, the new government expropriated this project. The SSE project was classified as

a failure from the private sector’s perspective (Zhang and Kumaraswamy 2001). No effective

risk mitigation methods were identified for this project.

FINDINGS AND DISCUSSIONS


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
For effective risk management in future BOT projects, it is important to understand the

d cr
risks encountered on previous projects and what mitigation strategies were adapted to manage

te s
those risks. One of the most important tasks for BOT projects’ successful performance is to

di nu
measure and mitigate those risks prior to undertaking a BOT project. Table 6 shows the main

causes and consequences of risk mitigation failure analyzed from the case study projects
ye a
discussed previously.
op M
Analysis of the case study projects indicates that the level of general risks depends on the

project location. Even though two similar projects are developed in the same country, the
C ted

general risks may be different depending on the extent of the host government’s support. It is

extremely difficult for the private sector to control the general risks. Therefore, the private
ot p

sector should maintain a good working relationship with the host government over the
N ce

concession period and even before the concession. Analysis of the case study projects suggests
Ac

adoption of the risk management strategies for general risks shown in Table 7.

Project-specific risks can be controlled by the private sector. For this reason, the project-

specific risks inherent in a BOT undertaking should be identified at the beginning of the project,

allocated to the party best able to control them, and mitigated by contractual agreements. The

nature of project-specific risks depends on the type of infrastructure project and its contractual

19

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

framework. As mentioned earlier, these risks can be classified into development, construction,

and operation risks.

The private sector should assume most of the development stage risks. However, the

most effective strategy in managing development risks is to obtain the host government support

and active involvement in the project. During the construction stage of a BOT project, a large
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
amount of money is consumed without generating any revenue. Hence, the private sector should

d cr
identify potential construction risks and carefully manage them. Operation risks are directly

te s
associated with the BOT project’s profitability and economic viability since project revenues are

di nu
collected during the operation period. Thus, operation risks should be carefully identified and

allocated to the party best able to manage them in a reasonable way.


ye a
Finally, this paper also categorizes BOT projects into two categories, contract-based
op M
projects and market-based projects, based on the revenue types. In market-based projects (e.g.

transportation systems), it is the most important to manage revenue risks carefully during the
C ted

operation period because such projects rely on market-based income (the actual number of

passengers). In contract-based projects (e.g. power plants), inflation risks should be managed
ot p

carefully since it is extremely difficult to forecast the cost escalation of fuel supply. Table 8
N ce

shows risk management strategies of project-specific risks identified from the analysis of the
Ac

case study projects.

CONCLUSIONS

BOT projects may not be successful because the concessionaire did not understand the

risks to be faced or failed to adopt appropriate mitigation strategies. From the case study

analyses, the main causes of failure in risk management were the host government’s

20

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

interference, conflict of interest among parties, delays in the government agency support,

political force majeure, and immature legal systems of the host government. These risks must

be identified at an early stage of the BOT project development and managed through contractual

agreements and financial arrangements clearly specified in terms and conditions.

The BOT approach is considered one of the most appropriate delivery systems, especially
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
when the government does not have sufficient funding to develop public infrastructure facilities.

d cr
The host government can maximize the benefits from the private sector’s investments, whereas

te s
the private sector can enjoy a high rate of return from a BOT project in spite of highly risky and

di nu
long-term investments. However, analysis of the case study projects indicates that the host

government’s support and active involvement will be indispensable for effective risk
ye a
management. In addition, both the public sector and the private sector must have collaborative
op M
working relationships to create win-win situations.

In conclusion, the private sector cannot be the only participant in risk management.
C ted

Without the host government’s active support, it may be extremely difficult to achieve the

profitability and the economic viability of a future BOT project in the East Asian and Pacific
ot p

region.
N ce
Ac

REFERENCES

Al-Bahar, J. and Crandall, K. (1990). “Systematic Risk Management Approach for Construction

Projects.” J. of Construction Engineering and Management, 116(3), 533–546.

Chan, W. T., Chen, C., Messner, J. I., and Chua, D. K. H. (2005). “Interface Management for

China’s Build-Operate-Transfer Projects.” J. of Construction Engineering and

Management, 131(6), 645-655.

21

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Fishbein, G. and Babbar, S. (1996). “Private Financing of Toll Roads.” World Bank’s RMC

Discussion Paper Series 117. Available from

http://documents.worldbank.org/curated/en/1996/12/16253070/private-financing-toll-

roads

Ho, J. (2004, September 18). “THSRC Allays Fears of Gross Overspending.” Taipei Times.
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Retrieved May 17, 2012, from

d cr
http://www.taipeitimes.com/News/biz/archives/2004/09/18/2003203387

te s
Kwak, Y. H. (2002). “Analyzing Asian Infrastructure Development Privatization Market.” J. of

di nu
Construction Engineering and Management, 128(2), 110-116.

Lam, P. T. I. (1999). “A Sectoral Review of Risks Associated with Major Infrastructure


ye a
Projects.” Int. J. of Project Management, 17(2), 77-87.
op M
Lang, L. H. P. (1998). Project Financing in Asia: Advances in Finance, Investment and Banking.

North Holland, Amsterdam.


C ted

Levy, S. M. (1996). Build, Operate, Transfer: Paving the Way for Tomorrow’s Infrastructure.

John Wiley & Sons, New York, NY.


ot p

Lu, I., Guo, S., and Pan, Y. (2010). “Owner-Controlled Insurance Program and Construction
N ce

Project Management for Taiwan High Speed Rail Project.” J. of Management in


Ac

Engineering, 26(4), 164-175.

Lysy, F. J., Bouton, L., Karmokolias, Y., Somensatto, E., and Miller, R. R. (2000). The Private

Sector and Development: Five Case Studies. International Finance Corporation,

Washington, D. C.

Menheere, S. C. M., Pollalis, S. N., and Huijbregts, R. (1996). Case Studies on Build Operate

Transfer. Project Management and Real Estate Development, Delft, Netherlands.

22

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Nevitt, P. K. and Fabozzi, F. J. (2000). Project Financing, 7th edn. Euromoney Publications,

London.

Ng, A. and Loosemore, M. (2007). “Risk Allocation in the Private Provision of Public

Infrastructure.” Int. J. Proj. Manage., 25(1), 66–76.

Ogunlana, S. O. (1999). Profitable Partnering in Construction Procurement. E & FN Spon, New


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
York, NY.

d cr
Rubin, R. and Wordes, D. (1998). ”FEATURE: Risky Business.” J. Manage. Eng., 14(6), 36–43.

Smith, N. J., Merna, T., and Jobling, P. (2006). Managing Risk in Construction Projects, 2nd edn.

te s
di nu
Blackwell Science, Malden, MA.

Sun, S. (2000, February 3). “Banks Ante up for Rail Project.” Taipei Times. Retrieved May 17,
ye a
2012, from http://www.taipeitimes.com/News/biz/archives/2000/02/03/0000022681
op M
Taipei Times. (2005, August 10). “High-Speed Rail Delayed.” Retrieved May 17, 2012, from

http://www.taipeitimes.com/News/taiwan/archives/2005/08/10/2003267114
C ted

Taiwan High Speed Rail Corporation (THSRC). (2009).

http://www.thsrc.com.tw/en/about/ab_comp.asp (accessed May 17, 2012)


ot p

Tam, C. M. (1999). “Build-Operate-Transfer Model for Infrastructure Developments in Asia:


N ce

Reasons for Successes and Failures.” Int. J. of Project Management, 17(6), 377-382.
Ac

Tiong, R. (1990a). ”Comparative Study of BOT Projects.” J. Manage. Eng., 6(1), 107–122.

Tiong, R. (1990b). “BOT Projects: Risks and Securities.” Construction Management and

Economics, 8(3), 315-328.

Tiong, R. (1996). “CSFs in Competitive Tendering and Negotiation Model for BOT Projects.” J.

of Construction Engineering and Management, 122(3), 205-211.

23

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

United Nations Industrial Development Organization (UNIDO). (1996). Guidelines for

Infrastructure Development through Build-Operate-Transfer (BOT) Projects. United

Nations Industrial Development Organization, Vienna.

Walker, C. and Smith, A. J. (1995). Privatized Infrastructure: the Build Operate Transfer

Approach. Thomas Telford, New York, NY.


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Wang, S. Q. and Tiong, L. K. (2000). “Case Study of Government Initiatives for PRC’s BOT

d cr
Power Plant Project.” Int. J. of Project Management, 18(1), 69-78.

te s
Woodhouse, E. J. (2005). The IPP Experience in the Philippines, Retrieved May 13, 2012, from

di nu
http://iis-db.stanford.edu/pubs/20816/PhilippinesIPP.pdf

Zhang, X. and Kumaraswamy, M. M. (2001). “Hong Kong Experience in Managing BOT


ye a
Projects.” J. of Construction Engineering and Management, 127(2), 154-162.
op M
C ted
ot p
N ce
Ac

24

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
)LJXUH&DSWLRQ/LVW

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Figure Caption List:

Figure 1. Typical Relationships among BOT Project Participants

Figure 2. Contractual Structure of Laibin B Power Plant Project

Figure 3. Contractual Structure of Pagbilao Power Plant Project


Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

t
ip
Figure 4. Contractual Structure of North-South Highway Project

d cr
Figure 5. Contractual Structure of Taiwan High Speed Rail Project

te s
Figure 6. Contractual Structure of Second Stage Expressway Project

di nu
ye a
op M
C ted
ot p
N ce
Ac

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
)LJXUH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Granting Authority

Facilities Contract with


Concession Agreement
Lenders Debt Repayment
Debt Limited Equity
Concessionaire
Equity
Contractor
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Sponsors Dividends
Construction Costs

Facilities Operation Fees

Operator

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
)LJXUH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Guangxi
Government
Guangxi Construction Guangxi Power
& Fuel Company Ltd. Industry Bureau
Concession
Agreement
Fuel Supply &
Transportation Agreement Power Purchase
Agreement
Project Company
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Financing Construction Service &


Operation & Maintenance Agreements Equipment Supply Contracts
Agreement

Électricité de France Construction


International Lenders Consortium

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
)LJXUH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

The Philippines Hopewell Energy IFC CDC ADB


Government International Ltd.

Government Shareholders Agreement


Equity
Guarantees
Operation &
Concession Hopewell Maintenance Hopewell
National Agreement Agreement
Power Tileman
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Power Corp. Philippines Power


C
Corp. S t
Systems Corp.
C
Sales
Trust & Retention
Revenue Construction Service &
Agreement Financing Agreement
Equipment Supply Contracts

Offshore Banking Construction


Escrow Account Repayment Syndicate Consortium

IFC: International Finance Corporation


ADB: Asian Development Bank
CDC: Commonwealth Development Corporation

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
)LJXUH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Malaysian Concession
Government Agreement UEM

Joint Venture
Financing
Agreement
Agreement

Stock PLUS Financing


Lenders
Market Shareholding Agreement
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Construction
Equity
Contracts

Subcontractors

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
)LJXUH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Taiwanese
Tripartite
Government Agreement
(MOTC)
Independent
Mediation Consultant
Committee Concession
Agreements

Banking
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Insurers Insurance Taiwan High


Contracts Speed Rail Co.,
Co Financing
Fi i Syndicate
Ltd. Agreements

Civil Work Contracts Core System Contract

Contractors Taiwan Shinkansen Co.

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
)LJXUH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Thai Government
(ETA)
Traffic
Tolls Project Manager
(Kumagai Gumi)
Concession
Revenue Share Agreement
PM Agreement Construction
Service Agreement
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Escrow Revenues
Accountt
A BECL
Trust & Retention Contractors
Agreement

Loan Financing Agreements Shareholders Agreement


Repayment

Lenders Investors

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
7DEOH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Table 1. General Information of Case Study Projects

Project Est. Cost Concession


Project Scope Concessionaire
Name/Country (US$) Period
Contract-based projects
Électricité de France
Laibin ‘B’ power plant, 700 MW Coal-fired Power
International & GEC 616 Million 18 Years
China Plant
Alsthom
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Pagbilao power plant, 700 MW Coal-fired Power Hopewell Power


933 Million 25 Years
Philippines Station Philippines Corp.
Market-based projects
North-south highway, United Engineers
870 km Highway 1.3 Billion 30 Years
Malaysia Malaysia
High speed rail system, 345 km High Speed Rail Taiwan High Speed
15.1 Billion 35 Years
Taiwan System Rail Corp., Ltd.
Second stage expressway, Bangkok Expressway
38.5 km Expressway 1.15 Billion 30 Years
Thailand Co., Ltd.

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
7DEOH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Table 2. Risks and Mitigation Methods for Laibin ‘B’ Power Plant Project

Risk Identified Mitigation Strategies


- Guarantee of repayments for loans and compensations for
Political force majeure
invested equities
Changes in laws and - Guarantee of compensations for the costs resulting from the
regulations changes
Fluctuations in foreign - Guarantee of the adjustment of the floating portion in the
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

exchange rate price of electricity


Foreign currency’s
convertibility and - Guarantee of the right to convert and remit foreign currency
remittance
Difficulty in project
- Support of government and government agencies
financing
Delays in necessary - Guarantee of assistance of Guangxi government, State
approvals Planning Commission, and Ministry of Power Industry
Cost overruns - Procurement of US$40 million letter of standby credit
- Purchase of appropriate insurance policies
Force majeure - Extension of milestone dates and the concession period to
compensate for suspended days
- Guarantee of supplying the fuel conformable to the
Supply risk
specifications
- Guarantee of complying with the pricing formula specified
in the power purchase agreement
Revenue risk
- Obligation to purchase at least 63% of the plant’s capacity
per operating year

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
7DEOH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Table 3. Risks and Mitigation Methods for Pagbilao Power Plant Project

Risk Identified Mitigation Strategies


- Government’s obligation to purchase all the facilities
Political force majeure
from the concessionaire
Fluctuations in foreign exchange - Power rates and fees structured in both US dollars
rate and local currency
Environmental concerns by the
- Amending the initial environmental plan
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

public
- Subordinated loans provided by the turnkey
Cost overruns contractors
- Procurement of a letter of standby credit
Completion delays - Early completion bonuses and liquidated damages
Supply risk - Guarantee of supplying the fuel
Revenue risk - Obligation to purchase the electricity
Operation delays caused by the
- Guarantee of Extension of the concession period
government

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
7DEOH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Table 4. Risks and Mitigation Methods for North-South Highway Project

Risk Identified Mitigation Strategies


Fluctuations in foreign
- Guarantee of soft loans against unanticipated fluctuations
exchange & interest rates
Lack of equity - Obligatory contributions to equity financing
- Lump-sum construction contracts
Cost overruns
- The Malaysian government’s standby credit
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Completion delays - Early completion incentives & penalties


- Purchase of appropriate insurance policies
Political force majeure - Guarantee of Extension of the concession period
- Guarantee of minimum revenues
- Guarantee of providing any shortfall financing for the first 17
Revenue risks
years of operation

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
7DEOH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Table 5. Risks and Mitigation Methods for Taiwan High Speed Rail Project

Risk Identified Mitigation Strategies
- Guarantee of compensations for the loss resulting from policy changes
Political/regulatory
- Guarantee of tax incentives during the operation phase
changes
- Mediation Committee to negotiate and resolve disputes
Completion delays - Performance and completion bond
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

- The government’s investment in the consortium’s equity financing


Lack of Financing
- Tripartite agreement to secure the lender’s senior debt
Fluctuations in
- Main financial frame in the local currency
foreign exchange
Force Majeure - Purchase of appropriate insurance policies

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
7DEOH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Table 6. Causes and Consequences of Risk Mitigation Failure in Case Study Projects

Identified Causes of
Case Project Consequences
Mitigation Failure
Pagbilao Environmentalists and local The concessionaire had to expand the initial environmental plan and
Power Plant, residents’ strong opposition also spend 16% of the total project cost on pollution control.
Philippines
High Speed Unclear contract clause Despite the government agency’s responsibility for land acquisition,
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

Rail Project, the concessionaire was not compensated for the losses resulting from
Taiwan delays in land acquisition.
No guarantee of a minimum Due to lack of confidence in returns on the project, the
number of passengers concessionaire had difficulty in project financing.
Changes in building codes The construction was delayed.
Changes in the core system The decision of switching the core system contractor led to
contractor insufficient preparations for operations caused the operation delay.
Negligence of currency Local currency devaluated almost 30%, which resulted in an increase
fluctuations of project costs amounting to approximately US$ 500 million.
Second Military coup d’etat The change of regime by the coup d’etat results in different contract
Stage interpretations on the concession agreement.
Expressway, Change in a land evaluation The cost of land acquisition was increased and the government
Thailand basis agency failed in delivering the land necessary for the construction.
Consequently, the construction work was delayed.
Unclear contract clause The concessionaire was not compensated for damages resulting from
delays in land acquisition.
Default of the government’s The operation of the completed expressway was delayed for four
agreement on toll rates months.
Default in the government’s The toll revenues collected in the urban area were not shared in
obligation to revenue sharing accordance with the revenue sharing scheme.
Continual disputes between The concessionaire faced serious financial difficulties and raised
the concessionaire and the tensions among parties.
government

Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
7DEOH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Table 7. Risk Management Strategies of General Risks

Identification Management Strategies


- Include the government agencies in equity or debt financing
- Include contractual provisions to bind the host government to pay
Sovereign risk
Political risks liquidated damages
- Establish a dispute resolution process
Instability risk - Purchase political force majeure insurance
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

- Include an adjustable portion in service fees to compensate for


foreign exchange fluctuations
- Obtain the host government’s guarantee of foreign currency
Foreign exchange risk
convertibility and remittance
Financial - Purchase financial instruments such as option contracts, forward
risks and futures contracts, or currency swaps
- Obtain fixed interest loans
Interest rate risk - Purchase financial instruments such as interest rate swap, interest
rate cap, or interest rate collar
Inflation risk - Add specify price escalation clauses to the contract
Changes in laws or - Obtain the host government’s guarantee of compensation for
regulations additional costs resulting from any changes in laws or regulations
Legal risks
- Obtain the host government’s guarantee of transparency in legal
Immature legal systems
procedures


Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.
7DEOH

Journal of Management in Engineering. Submitted July 3, 2012; accepted May 31, 2013;
posted ahead of print June 3, 2013. doi:10.1061/(ASCE)ME.1943-5479.0000225

Table 8. Risk Management Strategies of Project-Specific Risks

Identification Management Strategies


- Establish a creditworthy consortium with technical and
Bid risk
managerial competence
Errors in feasibility studies - Employ independent consultants for careful feasibility studies
Development Credit risk - Obtain the host government’s support and active involvement
risks Local communities’ strong
- Make all administrative procedures transparent
Downloaded from ascelibrary.org by Istanbul Universitesi on 08/09/13. Copyright ASCE. For personal use only; all rights reserved.

opposition
- Obtain consistency in the host government’s BOT policies
Delay in approval risk
through all levels of government agencies
Construction difficulties - Request performance bonds from contractors
- Use lump-sum construction contracts
Cost overruns - Bind contractors to participate in project equity sharing
- Obtain standby credit as contingency
Construction
- Request completion bonds from contractors
risks
Completion risk - Add specific provisions for early completion incentives and
liquidated damages to contract
- Obtain the host government’s commitments and obligations
Force majeure
- Purchase proper insurance policies
- Require maintenance bonds and extended warranties for the
Performance risk facilities
- Add clauses of performance bonuses & penalties to the contract
- Obtain standby credit as contingency
Operation cost overruns
- Require operator’s guarantee for subordinated loans
- Obtain alternative supply sources as contingency
Supply risk
Operation - Include penalty provisions of the supplier’s default in the contract
risks - Obtain the host government’s guarantee for minimum purchase
agreement or revenue level
Revenue risk
- Include contractual provisions of compensation for damages by
any default in the host government’s obligations
- Charge the host government with obligations and responsibilities
Force majeure - Obtain standby credit as contingency
- Purchase proper insurance policies


Accepted Manuscript
Not Copyedited

Copyright 2013 by the American Society of Civil Engineers

J. Manage. Eng.

You might also like