0-0603-05- 0A
DAT SHEET 1 of 101
PREP’
D
CHK’D
APP’D
PART V
PROJECT SPECIFICATION
CONTENTS
1 PROJECT INFORMATION............................................................................................................ 6
1.1 PROJECT BACKGROUND AND PURPOSE.........................................................................6
1.2 PROJECT LOCATION........................................................................................................... 6
1.3 PLOT PLAN............................................................................................................................ 6
1.4 PROCESS DESCRIPTION.................................................................................................... 6
1.5 DESIGN BASIS...................................................................................................................... 7
1.5.1 General........................................................................................................................... 7
1.5.2 Priority of Documents...................................................................................................... 7
2 SCOPE OF WORK........................................................................................................................ 7
2.1 GENERAL.............................................................................................................................. 7
2.2 SCOPE OF PLANT /FACILITIES........................................................................................... 9
2.3 PERTAMINA SCOPE............................................................................................................. 9
2.4 ENGINEERING.................................................................................................................... 17
2.4.1 Basis of Execution Manner for Engineering..................................................................17
2.4.2 Engineering Design Review.......................................................................................... 17
2.4.3 Software Use................................................................................................................ 17
2.4.4 Process Work................................................................................................................ 18
2.4.5 Civil & Structure Engineering Work...............................................................................21
2.4.5.1 General..................................................................................................................... 21
2.4.5.2 Scope for DGT Unit................................................................................................... 22
2.4.6.3 Scope for OSBL........................................................................................................ 23
2.4.6 Mechanical (Static) Engineering Work..........................................................................23
2.4.6.1 General..................................................................................................................... 23
2.4.6.2 Scope for DGT.......................................................................................................... 24
2.4.6.3 Scope for OSBL........................................................................................................ 24
2.4.7 Rotary Machinery Engineering Work............................................................................25
2.4.7.1 General..................................................................................................................... 25
2.4.7.2 Applicable Code/Standard......................................................................................... 26
2.4.7.3 Scope for DGT.......................................................................................................... 26
2.4.7.4 Scope for OSBL........................................................................................................ 26
2.4.8 Piping Engineering Work.............................................................................................. 26
2.4.8.1 General..................................................................................................................... 26
2.4.8.2 Scope for Unit DGT................................................................................................... 29
2.4.8.3 Scope for OSBL........................................................................................................ 29
2.4.9 Instrument Engineering Work........................................................................................ 29
2.4.9.1 General..................................................................................................................... 29
2.4.9.2 Scope........................................................................................................................ 30
2.4.10 Electrical Engineering Work.......................................................................................... 32
2.4.10.1 General.................................................................................................................. 32
2.4.10.2 Scope for DGT...................................................................................................... 33
2.4.10.3 Scope for OSBL.................................................................................................... 33
2.5 PROCUREMENT................................................................................................................. 35
2.5.1 Source of Equipment & Material...................................................................................35
2.5.1.1 Approved Manufacturer List/Supplier List (AML).......................................................35
2.5.2 Purchasing.................................................................................................................... 36
2.5.2.1 Purchasing Control.................................................................................................... 36
2.5.2.2 Inquiry Document...................................................................................................... 36
2.5.2.3 Follow Up Service..................................................................................................... 37
2.5.2.4 Bid Evaluation........................................................................................................... 37
2.5.2.5 Purchase Order......................................................................................................... 37
2.5.2.6 Document Identification............................................................................................. 37
2.5.2.7 Material Substitution.................................................................................................. 38
2.5.2.8 Supplier Drawing Data.............................................................................................. 38
2.5.3 Expediting..................................................................................................................... 38
1 PROJECT INFORMATION
1.1 PROJECT BACKGROUND AND PURPOSE
PT PERTAMINA (PERSERO) - Refinery Unit (RU) III, Plaju (hereinafter called
PERTAMINA) plans to build a dry gas treating unit at Area 21.
Main purposes of PERTAMINA for the plant modification are:
The facility that will be installed should be fulfilling the following project requirement:
1. The facility will serve 165 ton sour dry Gas per day
2. The facility will produce Sweet Dry Gas, that has sulfur content maximum 50
ppmvol as H2S content
3. The facility can be operated on 50 ~ 100% capacity continuously in safe and
reliable operation
4. The sweet dry gas could be injected to the existing refinery fuel gas system
that operated at 6.5 kg/cm2g
5. All waste product from the facility is disposal to the environment on compliance
to the government regulation
For further detail process descriptions and process flow diagrams refer to the
following document:
1. S-21-1222-001J Design Basis For Dry Gas Treater FCC Unit
2. S-21-1222-002J Process Description For Dry Gas Treater FCC Unit
3. D-21-1223-601J Process Flow Diagram (PFD) For Absorption Section Dry Gas
Treater FCC Unit (Case 1)
4. D-21-1223-602J Process Flow Diagram (PFD) For Regeneration Section Dry
Gas Treater FCC Unit (Case 1)
5. D-21-1223-603J Process Flow Diagram (PFD) For Absorption Section Dry Gas
Treater FCC Unit (Case 2)
6. D-21-1223-604J Process Flow Diagram (PFD) For Regeneration Section Dry
Gas Treater FCC Unit (Case 2)
7. D-21-1223-401J Process Flow Diagram Light Ends Section
2 SCOPE OF WORK
2.1 GENERAL
CONTRACTOR shall perform all necessary Engineering, Procurement,
Construction and Commissioning activities to complete the work as defined in, but
not limited to the Project Specifications supplied by PERTAMINA.
1. The Scope of Work is generally summarized in this section. However, all
information contained in the PERTAMINA Specifications should be considered
as preliminary and subject to further verification, correction, and update as
necessary by CONTRACTOR during the EPC Work. CONTRACTOR to note
that it shall not mean to override any other requirements covered elsewhere
as a part of the specifications.
2. Section 2.2 generally describes the scope of the facilities for which
CONTRACTOR shall provide all necessary services, materials and labor.
CONTRACTOR shall comply with all governing Indonesian regulations and
codes for design, engineering, procurement, construction and commissioning
of all facilities.
3. CONTRACTOR shall provide all documents and drawings for PERTAMINA’s
review/approval during the execution of the PROJECT. 'Final as Built' (not for
construction change sheet) drawings shall be issued for the entire facilities
prior to the COMMERCIAL COMPLETION CERTIFICATE / FINAL
ACCEPTANCE CERTIFICATE maximum two (2) months after
OPERATIONAL ACCEPTANCE.
4. To ensure that the CONTRACTOR's work performance is as per the
PERTAMINA Specifications, PERTAMINA has the right to inspect any aspect
of work and material during the Project execution.
5. CONTRACTOR shall supply fully detailed and comprehensive final issue of
operation and maintenance manuals, covering start-up and operating
procedures along with all technical information necessary for proper operation
and maintenance of the plant.
6. CONTRACTOR shall be responsible for employing approved third party
inspection agencies as required by the Indonesian Regulatory Authorities.
7. CONTRACTOR shall be responsible for purchasing and supplying all
materials and equipment required for constructing the FACILITIES. For those
purchasing items, CONTRACTOR shall provide all process licenses for
PERTAMINA's use of proprietary process technology and/or know-how in any
part of the plant and process design package incorporating such process
technology and/or know how.
8. CONTRACTOR shall be responsible for all aspects of material handling from
source to SITE, including:
Packing: Ensuring that all equipment/material required for the
construction of the PROJECT is packed, marked and
protected.
Freight: All land, sea and air transportation.
Documentation: All equipment/material to be supplied and supported by
documentation.
Marking: All materials and equipment shall be permanently
identified with the PROJECT and code of accounts clearly
shown. Die stamping is strictly prohibited.
Records: Maintaining clear and accurate records of shipping status
of all purchase orders.
Planning: Provision of adequate staff to plan the shipping program
and material deliveries to ensure that the construction
program is fulfilled.
Customs Supply of all necessary documentation and clearance
Clearance: through customs.
SPLIT OF
DOC WORK
NO DESCRIPTION
SOURCE
PN EPC
1 PROJECT MANAGEMENT Documents
1.1 Project Schedule (see ITB Part VII) New O
1.2 Drawing and Document Control Procedure New R
1.3 Project Control Procedure New O
1.4 Progress Measurement Procedure New O
1.5 Project Reporting Procedure New O
1.6 Invoicing Procedure New O
2 Permitting
2.1 Government related Permits and Approvals New O
3 Engineering General
3.1 Equipment List FEED S R
3.2 Piping Interconnection Tie-In List FEED S R
3.3 Drawing and Document List FEED S R
3.3 Data books New O
3.4 Manufacture catalogues, O&M manuals New O
3.5 Spares list based on selected equipment New O
4 PROCESS Engineering Documents
4.1 Design Basis FEED S R
4.2 Process Description FEED S R
4.3 PFD & Material Balance FEED S R
4.4 P & ID FEED S R
a. P & ID Nomenclature
b. Process P&ID FEED S R
c. Demolition P&ID NEW O
4.5 Utility Flow Diagram (UFD) FEED S R
4.6 Process data sheet for equipments : FEED S R
a. Pressure Vessels, Drums & Columns FEED S R
b. Trays & Packings FEED S R
c. Shell and Tube Heat Exchangers FEED S R
d. Air Cooled Heat Exchangers FEED S R
e. Pump FEED S R
4.7 Process data sheet for instruments FEED S R
4.8 Line Index (Line Lists) FEED S R
Hydraulic calculation based on final piping
4.9 FEED S R
arrangement
4.10 Utility Summary FEED S R
4.11 Chemical and Catalysts Summary FEED S R
4.12 Effluent Summary FEED S R
FEED
4.13 Flare Load Summary S R
(ISBL)
4.14 Material Selection Basis FEED S R
4.15 Cause and Effect Chart FEED S R
Project Specification for Fire Protection
4.16 New O
Equipments
4.17 Layout Drawing for Fire Water, Foam New O
HAZOP and HAZID on completion of EPC
4.18 New O
and vendor input
4.19 General Operating Guidelines / Manual FEED S R
SPLIT OF
DOC WORK
NO DESCRIPTION
SOURCE
PN EPC
5 PIPING Engineering Documents
5.1 General procedure for :
a. Engineering Execution Plan New O
b. 3D Modeling & Review Procedure New O
c. 2D CAD Procedure New O
5.2 General Specification for :
a. Piping Design FEED S R
c. Piping Flexibility Analysis New O
d. Piping Material Code and Stamping New O
e. Hot Insulation New O
f. Painting & Coating New O
g. Tie-in Method FEED S R
5.3 Project Specification for :
a. Piping Material FEED S R
b. Data Sheet for Piping Material New O
c. Requisition for Piping Material New O
d. TBE for Piping Material New O
e. Tie-In List Summaries FEED S R
f. Piping Line Index Summaries FEED S R
g. Pipeline Wall Thickness Design New O
5.4 Standard Drawings :
a. Standard Pipe Support New O
b. Typical Piping Arrangement New O
5.5 Detail Drawings for :
a. Plot Plan FEED S R
b. Demolish Plot Plan (if any) New O
c. Key Plan FEED S R
d. Design File Map New O
e. Tie-in Location Map FEED S R
f. Piping Lay Out FEED S R
g. Isometric New O
h. Tie-in Isometric New O
i. Special Pipe Support New O
5.6 PDS for new & modified all area New O
5.7 BM/BQ New O
6 MECHANICAL Engineering Documents
6.1 Equipment List FEED S R
Additional Equipment Data Sheets, as
6.2 New O
necessary
6.3 Project Specification for :
a. Vessel, Drum, Column and Its Tray FEED S R
b. S/T Heat Exchanger FEED S R
c. Air Cooled Heat Exchanger FEED S R
d. Pump FEED S R
e. Insulation & Painting New O
f. Rust Prevention New O
6.4 Data sheet for
a. Vessel, Drum, Column and Its Tray FEED S R
SPLIT OF
DOC WORK
NO DESCRIPTION
SOURCE
PN EPC
b. S/T Heat Exchanger FEED S R
c. Air Cooled Heat Exchanger FEED S R
d. Pump FEED S R
e. Air Dryer FEED S R
6.5 Loading Data Calculation for :
a. Vessel, Drum, Column and Its Tray FEED S R
b. S/T Heat Exchanger FEED S R
6.6 Standard Dwgs :
a. Name Plate New O
b. Skirt/Base Plates New O
c. Saddle New O
d. Lifting Lug New O
e. Manhole New O
f. Demister New O
g. Davit New O
h. Baffle/Vortex Breaker New O
i. Insulation Support New O
j. Platform & Stairway New O
k. Tolerance for Installation of Tray Support New O
6.7 Preliminary Mechanical DWGs for :
a. Vessel, Drum and Column FEED S R
b. S/T Heat Exchanger FEED S R
6.8 All Mechanical Equipments
a. Layout and Elevations FEED S R
b. Estimate Equipment Weights and
FEED S R
Dimensions
c. Material Requisitions for Mechanical
New O
Equipment
d. Prepare Requisition, inquiry and evaluate
New O
bids
e. Vendor document review New O
f. Project Specific Mechanical Specifications FEED S R
6.9 Vessels & Columns FEED S R
a. Vessel Material Class FEED S R
b. Nozzle and Platform Location Sketch FEED S R
c. Vessel Orientation Sketches FEED S R
d. Minimum calculated thickness of Vessel FEED S R
e. Location of clips for platforms, insulation,
FEED S R
pipe supports, etc
f. Details of internals FEED S R
g. Major instrument nozzles FEED S R
Shell & Tube and Air Cooled Heat
6.10 FEED S R
Exchangers
b. Preliminary shell and tube mechanical
FEED S R
Design
c. API Data sheet FEED S R
d. Final thermal rating / Guarantee and
FEED S R
Mechanical Design
6.11 Speciality Heat Exchangers FEED S R
a. API Data sheet FEED S R
b. Initial Mechanical Vendor Information FEED S R
c. Final thermal rating / Guarantee and FEED S R
DRY GAS TREATING FCC UNIT PROJECT
PT. PERTAMINA (PERSERO) RU-III PLAJU
ITB PART V
PROJECT SPECIFICATION
Page 13 of 101
SPLIT OF
DOC WORK
NO DESCRIPTION
SOURCE
PN EPC
Mechanical Design
6.12 Rotary Machinery Equipments FEED S R
a. Preliminary Driver Sizing FEED S R
b. Equipment Data sheet FEED S R
c. Supplier Documentation Requirements FEED S R
d. Vendor Technical support FEED S R
e. Quality Surveillance FEED S R
f. Requirement for Spare Part Lists FEED S R
6.13 BM/BQ New O
7 INSTRUMENT
7.1 Detail Design Document New Control Valve New O
7.2 Detail Design New Safety and Relief Valve New O
7.3 Detail Design New Field Instrument New O
7.4 Check & Evaluate and Detail Design Analyser New O
7.5 New and Modified Instrument & Function List New O
7.6 Instrument Alarm/Set Point List New O
Requirement for Design document Fire & Gas
7.7 New O
Detection System
7.8 General Specification of Instrument FEED S R
Project Specification Instrument & Data sheet
7.9
such as :
- Field Instrument New O
- Control Valve & Safety Relief Valve FEED S R
- Analyzer New O
- Fire & Gas Detection System New O
- Instrument Cable New O
- Instrument Installation Material etc New O
Design Information & Definition for DCS
7.10 New O
Modification
Instrument Data Sheet for Detailed Design
7.11 FEED S R
Information (Valve)
Summary New Instrument Cable (Cable
7.12 New O
Schedule)
Instrument Process Piping Hook-ups (Field
7.13 FEED S R
Instrument)
Instrument Process Piping Hook-ups
7.14 New O
Pneumatic
Instrument Steam Tracing & Insulation Hook-
7.15 FEED S R
ups
7.16 Instrument Miscellaneous Hook-ups FEED S R
Typical Installation Drawing for Pressure
7.17 FEED S R
Gauge
7.18 Instrument Loop FEED S R
7.19 ESD Interlock and Sequence Logic Diagram New O
7.20 Instrument Location Plan New O
Instrument Area Classification for Fireproofing
7.21 New O
& Details
Layout of Instrument Main Cable, Cable Way
7.22 FEED S R
and Tray & Detail Supporting
7.23 Layout of Instrument Wiring, Piping & Tubing New O
7.24 Instrument Wiring & Tubing Connection List New O
SPLIT OF
DOC WORK
NO DESCRIPTION
SOURCE
PN EPC
and JB & Cabinet Termination Diagram
Layout Signal Cabling & Wiring Control
7.25 New O
Room/Outstation
Layout of Instrument Grounding and Power
7.26 New O
Supply & Grounding
Layout Instrument Panel/Equipment in
7.27 New O
Control Room/Outstation
Instrument Demolish / Modification Drawing (if
7.28 New O
any)
Take Off Material for New Instrument &
7.29 Cable, Piping Hook Up and Material New O
Installation
Requisition for New Equipment Instrument &
7.30 New O
Cable
7.31 Tie-in list and hot change over procedure New O
8 ELECTRICAL Engineering Documents
8.1 Electric Load Calculation FEED S R
8.2 Short Circuit Calculation New
8.3 Load Flow Calculation New
8.4 Motor Starting Study New
8.5 Load Shedding Study New
8.6 Stability System Study New
8.7 Relay Coordination Study New
8.8 Lighting Illumination Level Calculation FEED S R
8.9 Cable Sizing Calculation New
8.10 Tie-in list New
8.11 Electrical General Specification FEED S R
Electrical Specification for Package
8.12 New
Equipment
8.13 Specification for LV Switchgear/ MCC FEED S R
8.14 Specification for LV Cables FEED S R
8.15 Specification for Electrical Cable Tray FEED S R
8.16 Specification for Induction Motor FEED S R
8.17 Data Sheet for LV Switchgear/ MCC FEED S R
8.18 Data Sheet for Induction Motor FEED S R
8.19 Hazardous Area Classification FEED S R
8.20 Electrical Cable Schedule FEED S R
8.21 Electrical Cable Tray Layout New
8.22 Power & Control Cables Routing Layout FEED S R
8.23 Lighting Layout FEED S R
8.24 Grounding Layout FEED S R
8.25 Key Line Diagram FEED S R
8.26 One Line Diagram SS No. 8B (New) FEED S R
8.27 One Line Diagram Power Station II FEED S R
8.28 Schematic Diagram New O
8.29 Connection Diagram New O
8.30 Typical Drawing for Installation Standard FEED S R
Take Off Material for new Electric Equipment
8.31 New O
& Materials
Requisition for new Electric Equipment &
8.32 New O
Materials
SPLIT OF
DOC WORK
NO DESCRIPTION
SOURCE
PN EPC
8.34 Vendor Document/ Drawing Review New O
SPLIT OF
DOC WORK
NO DESCRIPTION
SOURCE
PN EPC
to Vendor
12.8 Rust Prevention Procedure
14 QA/QC Plan
14.1 Project Quality Plan New O
14.2 General requirement of QC New O
14.3 Shop Inspection and Test Plan New O
14.4 Site QC Procedure New O
Special Instruction for Shop Insp. (MIGAS O
14.5 New
Inspection)
Instruction of Welder Performance Welding O
14.6 Procedure New
Qualification Test (MIGAS Insp.)
14.7 Non-Conformance Procedure New O
14.8 Shutdown Inspection Procedure New O
2.4 ENGINEERING
CONTRACTOR’S design and engineering execution will be based on procedures
agreed with PERTAMINA including local laws and regulations. Further, in order to
maintain a high level of efficiency and consistency and to keep the schedule,
PERTAMINA’s standards, drawings and data will be used to the maximum extent
possible. Such documents and data will be revised or developed by CONTRACTOR as
required to meet the project requirements. Soon after the Contract Award,
CONTRACTOR shall prepare the Engineering Execution Plan to establish efficient
execution procedures for Engineering work.
Safety in design and engineering is a prime consideration for CONTRACTOR. Safety is
built into the facilities throughout the design and engineering phase by incorporating
specifications of proven refinery standards, which are supplemented by project
standards and specific project safety requirements. The incorporation of the safety
requirements in the discipline design and engineering will be ensured by planning,
reviewing and approval processes.
SITE survey shall be carried out by CONTRACTOR to understand the existing facilities
for completion all EPC work. The SITE survey and data collection shall be conducted
soon after the contract award. CONTRACTOR shall specify what data is necessary for
this project, and PERTAMINA will provide the data.
2.4.1 Basis of Execution Manner for Engineering
The CONTRACTOR shall do the engineering design work based on the following
Execution manner:
1. CONTRACTOR shall complete design based on FEED document package.
2. The project will be conducted as modification work in the existing plant therefore
the CONTRACTOR shall refer to the existing design philosophy.
3. CONTRACTOR shall conform to the standards & codes which are included in
FEED document.
2.4.2 Engineering Design Review
CONTRACTOR should consider the PERTAMINA engineers participation during
Detail Engineering Stage, Procurement and Constructions in order to give the
PERTAMINA engineers chance in developing of their understanding and
engineering sense in the EPC Work.
CONTRACTOR shall hold join review meeting with PERTAMINA for the following:
1. Licensor Meeting (if any)
2. Plot Plan Review
3. P&ID and PFD Review
4. HAZOP & HAZID Review
5. 3D Model Review (initial, intermediate, final) consist of Mechanical Equipment,
Piping, Civil, Instrument and Electrical.
2.4.3 Software Use
PERTAMINA request to the CONTRACTOR to use an integrated suite of
Commercial/Proprietary software packages and systems for various engineering
applications:
1. SPP&ID (Smart Plant P&ID)
2. 3D PDS Model
3. Pipe stress analysis (CAESAR II)
4. Process Design (HYSYS, PRO-II, HTRI, Flare Net)
All software listed above shall have genuine licenses and CONTRACTOR shall
attach the certificates from government or authorized association.
CONTRACTOR shall procure software: 2 licenses of SPP&ID and 2 licenses of 3D
viewer (Smart Plant Review/Navis) for PERTAMINA’S personnel. The IT
infrastructure for this shall be considered.
2.4.4 Process Work
CONTRACTOR shall review and finalize the following Design basis for each
process units:
(1) Design Basis
Refer to document S-21-1222-001 Design Basis and Philosophy for Dry Gas
Treating Unit
1.4.4.1. Vessels
Sour Gas Scrubber (DGT-D-601)
Rich Amine Flash Drum (DGT-D-602)
Stripper Overhead Drum (DGT-D-603)
Amine Drain Drum (DGT-D-604)
Sweet Gas Scrubber (DGT-D-605)
1.4.4.2. Columns
Absorber Colum (DGT-T-601)
Stripper Column (DGT-T-602)
1.4.4.4. Pumps
1.4.4.5. Packages
Dryer Air Package (FC-A-310)
Amine Pre Filter (DGT-ME-601)
Amine After Filter(DGT-ME-603)
Amine Drain Filter (DGT-ME-604)
(3) Piling
CONTRACTOR shall refer to General Specification for Civil, Structure and
Foundation (Doc. No. S-21-1310-001J) which outlines the minimum technical
requirements for piling.
The pile foundation will use bored pile:
Diameter : 400 mm and 600 mm
Concrete Compressive Strength (fc’) : 28 MPa
Re-bar Yield Strength (fy) : 390 MPa
Allowable Bearing Capacity
- Diameter 400 mm : 59 Ton
- Diameter 600 mm : 120 Ton
The piling drawings attached in the FEED documents were developed based
on information from available soil investigation report. CONTRACTOR shall
review the piling drawing against the results of new soil investigations.
CONTRACTOR shall carry out the piling test by using PDA (Piling Dynamic
Analysis).
(4) Foundations
CONTRACTOR shall refer to General Specification for Civil, Structure and
re-design the structure following the final vendor equipment data. Refer to
drawing no. D-21-1331-011J and D-21-1332-041J
B. Pipe Stanchion
New steel pipe support/stanchion for pipe refer to drawing no. D-21-1337-011J.
C. New Foundation
New foundation to be installed by CONTRACTOR shall refer to D-21-1323-051J
and D-21-1323-052J
B. Column
Absorber Colum (DGT-T-601)
Stripper Column (DGT-T-602)
C. Heat Exchanger
Lean Reach Exchanger (DGT-E-601 A/B/C)
Stripper Overhead Condenser (DGT-E-602)
Stripper Reboiler (DGT-E-603)
Lean Amine Cooler (DGT-E-604)
D. Packages
Amine Pre Filter (DGT-ME-601)
Amine After Filter(DGT-ME-603)
Amine Drain Filter (DGT-ME-604)
1. Project Specifications
All piping design and engineering shall meet the requirements of the
specifications and standards provided in the PROJECT SPECIFICATION. Any
proposed deviation from the specifications and standards provided shall be
agreed in writing with PERTAMINA.
2. Plot Plan
CONTRACTOR to develop, verify and update Plot Plan and demolished Plot
Plan. CONTRACTOR shall develop the Plot Plans provided in the FEED
documents for final equipment sizing, equipment spacing and the economical
plant layout and design development occurred during the detailed engineering
of the project.
4. Isometric Drawings
Perform isometrics for all piping system related to revamp works including
existing piping to be relocated due to obstruction and steam tracing system. All
isometrics necessary to fabricate and erect on plot facilities shall be provided
and each shall be associated with bill of materials which is equivalent to PDS
model output. Isometrics are to be provided for all lines. CONTRACTOR shall
propose his method in his proposal.
5. Tie-ins
CONTRACTOR to verify, develop and update piping tie-ins, also verify that the
location is workable and agreed with PERTAMINA. CONTRACTOR shall verify
the schedule of tie-in works and provide tie-in isometrics.
CONTRACTOR has to mark-up existing lines and provide tie-in tag no.
7. 3D Modeling
CONTRACTOR has to develop PDS Model for all piping system related to DGT
Unit.
2.4.9.2 Scope
CONTRACTOR shall verify FEED documents listed below:
1. Adequacy check for the following instruments.
a) Relief Valves
b) Control Valves and Self-actuating valves
c) Flow elements
d) Transmitter Range,
2. Site check to verify.
a) Availability of existing field instruments.
b) Spare slots availability in the Auxiliary consoles in the Central Control
Room to add shutdown push-buttons.
c) Spare windows availability in the Auxiliary consoles in the Central Control
Room to add new annunciator points.
d) Spare terminal availability in the Marshalling cabinets in Central Control
Room.
e) Spare I/O slot availability in the DCS cabinet.
f) Spare I/O slot availability in the ESD/PLC cabinet.
g) Spare terminal availability in the Power distribution Board.
h) Availability of space for New Analyzer Skid.
i) Availability of space for Main cable way in existing Ladder/Duck
3. Job Specifications
4. Instrument list and instrument dismantling list.
5. Specifications for new instruments and existing instruments to be replaced
(base on adequacy check report).
6. DCS related documents such as Specification, DCS I/O List.
7. Cause and Effect Diagram.
Adequacy check for relief valves, Control and self-actuated valves, Flow
elements shall be carried out based on the Instrument Process data sheets.
Instrument Location plans indicating the exact elevation and location of the
instruments shall be finalized during the detail engineering phase based on
the piping routing, instrument location.
The cable schedule including the cable length and size shall be prepared
during the detail engineering phase.
Site survey to study the existing spare I/O availability, spare terminal/space
availability in marshalling cabinets and ESD cabinets shall be carried out.
The DCS I/O points and instruments for shut-down for FEED documents
are defined by the P&IDs and is listed in the DCS I/O list (S-21-1371-001J)
as references, indicating the new DCS I/O points and instruments
(2) CONTRACTOR shall update and make in detail construction drawing of cable
tray layout, power wiring layout, lighting layout, grounding layout and
interconnection diagrams.
(3) CONTRACTOR with his VENDOR shall update and make in detail
construction drawing of schematic diagrams.
(4) CONTRACTOR shall supply all necessary materials required for the site
installation of equipment and connection to the existing power/ control circuits.
(5) CONTRACTOR shall carry out the test of extension MCC or Motor Starter
Drawers together with the existing MCC.
(6) CONTRACTOR shall also perform the settings and testing of protection
devices in the panel before turning on the power supply.
(a) The installation of Local Control Stations shall be completed with proper
frames, stanchions, concrete foundation and conduit stud-up.
(b) CONTRACTOR shall carry out the testing and commissioning of them.
(a) Due to replacement of pumps that indicated in Cable Schedule, Tie-in List
and One Line Diagram:
oCONTRACTOR shall study and finalize the Cable Schedule, Tie-in List
(b) CONTRACTOR shall supply and install all the power and control cables
including connection to the new Substation No. 8B according to the
requirements as indicated in final design documents.
(c) CONTRACTOR shall supply of all materials for cabling as per relevant
specifications/ drawings/ installation standard.
(10) Grounding
(a) CONTRACTOR shall supply and install the grounding network shown in
the final design drawing.
(11) Lighting
(a) CONTRACTOR shall supply and install the lighting fixtures and its cables
including its cable ways and its accessories.
(a) CONTRACTOR shall supply and install the welding outlets and their
cables including their cable ways and accessories.
(13) Miscellaneous
2.5 PROCUREMENT
CONTRACTOR shall perform all necessary procurement activities (from potential
suppliers nomination to SITE delivery) to secure on a timely basis and in
satisfactory conditions materials, equipment, equipment information and services
required for the completion of the project. CONTRACTOR'S responsibility include
all associated activities such as, purchasing, material management, subcontracting,
expediting, inspection and traffic management functions required for the
construction and commissioning of the project. CONTRACTOR'S scope also
includes initial and long-term spare part procurement, special tool and the supply of
supplier information needed for operation and maintenance of the project.
CONTRACTOR shall designate a Project Procurement Manager to coordinate all
CONTRACTOR 'S procurement activities and to act as liaison/contact on
procurement matters between the CONTRACTOR'S organization and
PERTAMINA. The Project Procurement Manager will be assisted by specific
coordinators for Purchasing, Expediting/Inspection, Traffic and Custom Clearance.
CONTRACTOR shall ensure that the procurement activities undertaken in
connection with the project shall be in accordance with the following guideline: "It is
the policy of the company to purchase or provide materials and services of all types,
including construction work, from whatever source, taking into consideration quality,
price, delivery, reliability and service. Purchases should be accomplished through
transactions with financially sound, reputable firms capable of satisfying all needs,
and should be consistent with the efficient management and utilization of
inventories where applicable."
2.5.1 Source of Equipment & Material
Materials and equipment shall be procured from acceptable sources within the Free
World Market. CONTRACTOR shall endeavor to supply local materials to the extent
available, maximize the amount of goods and services purchased locally
consistently with quality, time and cost objective of the project.
2.5.1.1 Approved Manufacturer List/Supplier List (AML)
Approved Manufacturers/Suppliers list are provided on APPENDIX VA. This AML
were prepared based on technical capability and acceptability of Manufacturer in
considering with:
1. Successful Local Manufacturer
2. Pass Technical Evaluation in other Revamp Project
3. Has been applied and successful in PERTAMINA Existing Refinery
4. Well known as successful Vendor in Other Project and Pass Technical
Evaluation
information those manufacturer have been listed has bad record on others
Company/Project that they supplied.
CONTRACTOR shall purchase Equipment/material direct to the manufacturer or via
their agent when CONTRACTOR purchase Equipment /Material from
manufacturer's Agent. The agent shall be supported by supporting letter signed by
authorize person of Manufacturer and shown it to PERTAMINA.
The Manufacturers on AML just as Recommended Manufacturer List,
CONTRACTOR shall evaluate technical Bid Evaluation (TBE) proposed by
Manufacturer.
2.5.2 Purchasing
All purchase commitments made for material supplies and all major spare parts
shall be made in the name of CONTRACTOR.
CONTRACTOR purchasing practices should conform to all local laws and should
be consistent with good business practices. Within one month from contract award
and prior to beginning purchasing activities, CONTRACTOR shall present to
PERTAMINA review a purchasing plan and procedures defining the objectives,
schedule, critical items, strategy, procurement resources, coordination procedures,
expediting/inspection plan, etc.
CONTRACTOR shall ensure that all equipment and material warranties and
services agreements which extend beyond the time of CONTRACTOR’S warranty
of the plant will be passed on to PERTAMINA. The terms of warranties and service
agreements shall be documented for transfer to PERTAMINA’S records.
2.5.2.1 Purchasing Control
CONTRACTOR shall issue a monthly report for purchasing activities, the report
shall include at least:
1. Status of inquiries indicating the suppliers inquired, material requisition, inquiry
number, date of issue, bid due date, bids received and present status of the
inquiry.
2. Order List indicating the item/material purchased, the material requisition, the
supplier selected, dale of order, delivery date.
3. Purchasing schedule detailing planned and actual release date of material
requisition, inquiries bid evaluation submission, purchase order, arrival date at
SITE.
4. Expediting report
2.5.3 Expediting
CONTRACTOR shall prepare a detailed expediting procedure to permit timely and
efficient monitoring of all supplier activities needed to meet required delivery of all
equipment and materials.
CONTRACTOR shall expedite all purchase orders, revisions, and amendments to
these orders, (including supplier's quotations, engineering design calculations,
drawings, spare parts data, installation, operating and maintenance instructions,
welding procedures, invoices, import licenses, supplier's sub-orders and spare
parts) from placement of purchase order to receipt of the materials, equipment,
supplies, and/or services at the SITE.
CONTRACTOR'S expediters shall maintain control of delivery dates that are
established for the project. Where material delivery is critical as indicated by
construction schedules, CONTRACTOR shall carry out an assessment on supplier
before placement of the purchase order to determine if its delivery promises can be
meet.
The expediter's main objective is to maintain on-time delivery of deliverables to the
SITE. Equally important, the expediter must immediately report any indications or
occurrences which may impede supplier's ability to maintain its scheduled
deliveries.
CONTRACTOR shall keep continuously update the shipping status and issue the
same to PERTAMINA on monthly basis.
2.5.6 Custom Clearance
CONTRACTOR shall become familiar with the importing and exporting laws of
Indonesia.
CONTRACTOR shall be responsible for delivering materials to the SITE.
CONTRACTOR may engage specialist agents for this work subject to
PERTAMINA’S approval. PERTAMINA will assist CONTRACTOR as required.
Import duties and surtax, if any payable or due in Indonesia for equipment and
material for the project shall be paid by CONTRACTOR and included in Lump Sum
Price.
All other charges will be payable directly by CONTRACTOR together with port
unloading fees, demurrage, etc.
For materials which CONTRACTOR may wish to import on a temporary basis,
CONTRACTOR should arrange to make application to the customs office detailing
the descriptions and value of the materials to be temporarily imported and setting
out the period of intended use.
2.5.7 Packing and Preservation Requirement
CONTRACTOR shall be responsible for ensuring that the packing, marking
instructions, shipment, and storage of the materials are in accordance with the
following requirements.
2.5.7.1 General Packing Requirement
CONTRACTOR shall consider the SITE climatic conditions when evaluating
requirements for shipment.
DRY GAS TREATING FCC UNIT PROJECT
PT. PERTAMINA (PERSERO) RU-III PLAJU
ITB PART V
PROJECT SPECIFICATION
Page 40 of 101
e) Air Coolers
Requirements for motor bearings, shafts, sheaves, hubs, gear, electrical, and
flanged or threaded openings are covered elsewhere and must be adhered to
especially to ensure that moisture does not creep into the motor via the drive
shaft.
Tube bundles, plain and finned, shall be crated with special care taken to
provide fin protection from physical damage. Fan blades shall be crated with
suitable blocking and bracing and with Type C coating on finished parts. Fan
drive belts shall be sealed in a finished container. Hardware (nuts, bolts, lock-
washers) shall be protected with rust preventative Type C and shall be shipped
in waterproof containers.
2.6 CONSTRUCTION
CONTRACTOR shall construct the DGT unit in accordance with the requirements of
the Contract, accepted industry practices, applicable industry Codes, Standards
and procedures. The facilities shall be constructed in a safe and reliable manner
and suitable for their intended purpose.
CONTRACTOR shall provide all management supervision, technical support, labor,
transportation, construction/erection/marine equipment, tools, construction material
and consumables, temporary facilities, construction services and utilities, and so on,
and render all other support services necessary to complete the construction.
CONTRACTOR is deemed to have full knowledge of the applicable laws and
regulations, conditions of labor, local conditions, SITE conditions and environmental
requirements, and shall comply with all of the requirements therein.
CONTRACTOR is responsible to coordinate activities with other CONTRACTORS
responsible for adjacent plant construction.
CONTRACTOR'S construction work shall include but not be limited to the
followings:
1. Master Project Schedule and updates
2. Plan, coordinate and control the activities of all SUBCONTRACTORS.
3. Plan and schedule the construction work and take action to maintain schedule
4. Plan schedule and allocate manpower and construction equipment to maintain
schedules.
5. Supervise and certify the quality of all SUBCONTRACTORS work to ensure
that all work is adequate for the purpose intended and is in accordance with
good engineering, construction standards and practices, design drawings and
specifications. CONTRACTOR shall report to PERTAMINA of any
unsatisfactory work that requires correction and action required to correct the
work.
6. Report progress of the construction work in accordance with the ITB Part VIII.
7. Report immediately any misuse of the EQUIPMENT AND MATERIALS not in
accordance with the drawings, specification and the CONTRACT and action
required to correct the misuse.
8. Execute all activities required for change of the WORK approved by
PERTAMINA.
9. CONTRACTOR shall provide all necessary tools and facilities in a way so that
construction worker can work safely and comfortably.
10. CONTRACTOR shall provide all necessary additional temporary supports
including the foundations for temporary stand of the existing and new Reactor
& Regenerator top head including Plenum and Cyclone.
11. Erect and install the EQUIPMENT AND MATERIALS according to the
approved codes, specifications and procedures.
12. Carry out inspection, non-destructive tests, and analyze and certify
acceptability of all welds. All welding work shall be as specified in codes and
engineering specifications.
13. Prepare and submit record of all SITE meetings and any other related
documents to all parties concerned
14. Prepare and submit safety and labor relations procedures in accordance with
all applicable codes, regulations and PERTAMINA requirements.
15. Supervise and ensure all safety and labor relations and report to PERTAMINA
immediately all violations and injuries.
16. The refinery will be operating while pre-TA work is executed. It is essential that
safety rules be prepared and implemented for all work with specific focus on
'hot work' critical lifting and rigging activities
17. Ensure minimum interruption to the operation of other services and facilities.
The continuous operation of other services and facilities will be given priority as
compared to Plant Construction Activities.
18. Undertake housekeeping during all segments of construction including
sweeping, cleanup, cleanliness, removal excess materials, removal of excess
debris, temporary facilities, 'unnecessary scaffolding, etc.
19. Prepare and submit to PERTAMINA the following daily log of construction
activities:
a. Weather
b. Summary of construction activities for each SUBCONTRACTOR
c. Manpower, highlighting expatriates, personnel distribution for each
SUBCONTRACTOR or direct hire.
d. Construction equipment in use
e. Problems encountered and corrective action taken
f. Work progress and quantities Installed
g. Injuries and accidents and steps taken to avoid future incidents
h. SITE visitors
i. Planned activities for the next day to allow of work permits/safety checks.
2.6.1 Construction During Operation
For construction activities during plant in operation, CONTRACTOR shall be aware
of existing equipment and safety of workers. Safety supervisor/inspector shall be
standby at the critical area and periodically check the gas content around works
area base on PERTAMINA’S safety requirement & regulation.
Barricade & insulation of work area are required to protect existing equipment from
construction activities.
Some demolition of existing equipment and installation of new equipment will be
conducted during operation.
2.6.2 Construction During Turn Around
Considering to the time limitation and the work must be finished during the period of
TA, the construction work must be finished within 43 (forty three) mechanical days
counted from plant ready for activity (after plant cleaned up and cooling down) until
plant ready to start up..
2.6.3 Subcontractor List
BIDDER shall include in the proposal and submit for PERTAMINA review and
approval a preliminary list of SUBCONTRACTOR from whom it wishes to solicit
bids for each category of field works or services expected to be sub-contracted.
BIDDER shall provide a summary of each SUBCONTRACTOR qualifications to
perform the work proposed.
Sub-contracts may be solicited from any acceptable source in the World Free
Market, however, Indonesian suppliers should be used in most cases where quality,
schedule and costs are not compromised. Acceptability of any potential
SUBCONTRACTOR will be based solely upon technical, project execution and
financial considerations.
BIDDER shall submit a list of the agencies which it proposes to use for
PERTAMINA’S review and approval. This should include shipping, forwarding,
expediting, testing, inspection and any other agencies as appropriate. BIDDER shall
provide a summary of each agency's qualifications to perform the work proposed.
During EPC execution, CONTRACTOR shall select his preferable Subcontractors
from the approved Subcontractor List during the Tender and CONTRACTOR is not
allowed to use SUBCONTRACTOR from his in-house SUBCONTRACTOR list.
2.6.4 Subcontracting
CONTRACTOR shall perform all necessary SUBCONTRACTOR qualification,
Subcontracting strategy, planning, development, award, implementation and
administration activities required to accomplish the sub-contracted work (including
procurement of agency services) under the contract.
CONTRACTOR shall develop and implement sub-contracting procedures that
satisfy local laws as well as PERTAMINA’S requirements for the project. In addition,
within three months after initiation of CONTRACTOR'S engineering work but no
later than two months prior to any sub-contract bid solicitation activity,
CONTRACTOR will prepare and submit to PERTAMINA’S for review a Master
Subcontracting Plan. This plan will:
1. Define type extent, scope and volume of the work to be sub contracted;
2. Describe overall sub-contracting strategy, policy and bidding philosophy;
3. Provide outline of scope of work, extent, magnitude and expected man-hours
and type of contract for each package to be sub-contracted;
4. Include on overall sub-contracting schedule and a detailed schedule for each
sub contract;
5. Include the overall Project SUBCONTRACTOR List providing a list of proposed
SUBCONTRACTOR for each of the package of work intended to be sub-
contracted, and their qualification and previous experience with
SUBCONTRACTOR (preference shall be given to local SUBCONTRACTOR
with previous experience at PERTAMINA PLAJU SITE)
6. Describe the approach and plan to ensure the safe and legal performance of
the work by SUBCONTRACTOR
7. Provide comprehensive description of CONTRACTOR'S organization and
staffing to carry out SUBCONTRACTOR selection and sub-contract
administration including duties, responsibilities, authority and interfaces of
proposed staff.
8. Include detailed procedures (including flowchart) for bidder qualifications, for
bid solicitation, bid receipt, bid review and sub-contract award.
9. Detailed procedures for carrying out sub-contract administration
10. List of construction facilities available to SUBCONTRACTOR, source and on
what basis
11. Definition of extent of materials to be supplied by SUBCONTRACTOR
12. Sub-contract standard terms and condition, sub-contract language tailored to
the project and other standard bidding documents such as information and
instruction to bidders, etc.
13. Sub-contract change provision information
CONTRACTOR shall periodically review the Master Sub-contracting Plan until all
works to be sub-contracted have been a warded.
2.6.4.1 Subcontracting Report
CONTRACTOR shall issue a monthly report on sub-contracting activities with the
same content of the Procurement report above. In addition, CONTRACTOR will
provide a detailed reporting on each SUBCONTRACTOR’S SITE activities and
progress as part of the construction progress report. Level of detail to which sub-
contracted work progress shall be prepared, will be agreed between
CONTRACTOR and PERTAMINA.
The CONTRACTOR'S Plan shall be prepared with sufficient coordination among its
engineering, procurement and pre commissioning personnel of this Project.
The Plan shall be up-dated, revised or supplemented by CONTRACTOR as
required by PERTAMINA.
Sections herein describe the minimum requirement to the CONTRACTOR'S Plan.
designed and laid out and secured so as to provide controlled access and prevent
access by unauthorized persons. The following guidelines shall be applied:
a) Warehouses which are located adjacent to the SITE perimeter fence and
contain high risk materials (valves, fittings, small parts, etc.) must be provided
with security screens over glass windows and doors.
b) Access doors from warehouse office into the warehouse or storage areas
should be fitted with controlled access locks to restrict personnel access.
c) Warehouse buildings, equipment and material storage areas should have a
minimum number of access locations and minimum number of personnel
authorized to enter these areas.
d) Shops, labor rest and change rooms shall be separate from the warehouse
area.
the PERTAMINA hospital. Charges for this service will be in accordance with
PERTAMINA rates. However, Contractor shall provide the Site Clinic completed
with the medical equipment and personal including 1 (one) ambulance and driver.
CONTRACTOR shall provide all qualified personnel, medical facilities, supplies
and equipment necessary to provide emergency and first aid treatment for all
CONTRACTOR and SUBCONTRACTOR personnel who may be suffering from
illness or injury.
CONTRACTOR shall engage a licensed professional physician to advice on
medical supplies, equipment, and selection of medical attendants; prepare
procedures for first aid care, personnel evacuation and care of employees
requiring hospitalization or specialist treatment.
CONTRACTOR shall record all cases which involve illness or injury on the job.
The record shall be submitted to PERTAMINA weekly and include the following
minimum information:
1. Employee's name and pass number
2. Date of injury
3. Nature of injury or illness
4. Treatment and further care for injured party
5. Any restrictions to employee or affects to SITE personnel resulting in illness,
injury and/or treatments.
6. Estimate or forecast and actual amount of employee's lost time resulting from
illness or injury.
For all fatalities, cases requiring hospitalization, or possible lost time injuries, the
CONTRACTOR'S Construction Manager is to be notified immediately and he shall
immediately report the incident to PERTAMINA and appropriate government
authorities.
Additional records of health-related activities at the SITE shall be maintained by
the CONTRACTOR and be available for review by PERTAMINA and Government
Health Agencies.
1. Medical examination of food handlers
2. SITE sanitation inspections
3. Control of vermin and pests
4. Laboratory Tests for food, water, services and facilities
All SITE offices, warehouses, shops etc shall have fire extinguishers and smoke detectors
permanently located at all doors and within 10 meters distance from one another.
CONTRACTOR shall inspect and certify all fire fighting equipment monthly to ensure proper
location and condition of equipment. Missing or faulty equipment is to be promptly replaced
or repaired.
CONTRACTOR, through its supervisory organization, shall indoctrinate all employees on the
availability and use of the fire fighting equipment.
PERTAMINA will endeavor to maintain the reliability and continuity of these services but not
responsible for the consequences of any failures of or breaks in services, Total responsibility
for the provision of utilities remains with the CONTRACTOR. CONTRACTOR shall define
utilities specification and total consumption required.
CONTRACTOR shall install his own tie-ins, meters, and run lines as approved by
PERTAMINA. The location of all tie-ins will be given by PERTAMINA and CONTRACTOR’S
proposed installations is required prior to approval of PERTAMINA.
2.6.7.1 Water
The CONTRACTOR shall be charged for all potable water (accordance with PERTAMINA
rates) and shall be responsible for supplying and installing all water meters, including the
maintenance thereof. During periods of meter failure, deemed usage will be invoiced.
2.6.7.2 Electricity
All electrical power supply & installation will be Contractor's responsibility (if PERTAMINA
CONTRACTOR shall submit any other schedule and status reporting information
or data that is available, upon request from PERTAMINA.
2.6.9 SITE Quality Control
CONTRACTOR shall prepare and implement a quality control program and procedures to
ensure that the quality of the WORK to be performed at the SITE is completed in accordance
with the contract documents, drawings, specifications and applicable codes. The quality
control program shall provide for rigorous inspection and documentation verification for the
quality of the WORK in accordance with Quality Assurance Program and the following
requirements:
1. Establish an independent Quality Control Department at the SITE and appoint
supervisory and inspection personnel with high professional skills and sufficient
experiences in the similar type of job.
2. Recruit and employ technicians with the required skills and qualifications.
3. Maintain necessary documentation and qualification records of construction specialist
personnel and traceability of the work they have completed.
4. Ensure that materials installed comply with the relevant drawings and specifications.
Verify the use of proper construction equipment, tools, materials and consumables
which conforms to the applicable specifications, codes and standards.
5. Verify implementation of the established construction specifications, procedures and
methods.
6. Ensure that equipment and tools used for measuring and testing conform to the
Applicable codes and standards and have been properly calibrated copies of the test
records and calibration certificates shall be submitted to PERTAMINA.
7. Inspect and verify treated water used for mixing cement and concrete or cleaning,
testing. flushing and drinking-conforms with specifications and codes.
a) Any construction activity shall not start until all prescribed quality control procedures
are approved and prerequisites have been met.
b) Work shall not proceed beyond specified "Hold" points without the responsible
inspector's clearance.
c) Work that is not conforming to specifications and drawings is documented and the
inspector is responsible for control of that work until corrective action is implemented
and satisfactorily completed.
d) In those situations where continued work would cause damage, preclude further
inspection, or make remedial action ineffective, and where there is no authorized
representative of the superintendent or supervisor immediately available at the work
location, the inspector responsible for that work shall stop further progress. He shall
immediately notify the superintendent or his designee of such action.
e) The Inspection/Documentation Control Program shall consist of approved status
reports, forms and check-off lists and functions which shall include but not be limited
to the following:
1) Inspection procedures consistent with specifications, contract documents,
codes or governmental regulations.
2) Monitoring and update and report daily on construction, fabrication, and
welding status and inspection activities.
3) Qualified welding procedures status and control.
4) Welder qualifications certifications control and register.
5) Qualified non-destructive examination procedures, weld identification, joint
numbers, status and control.
6) Procedures for material identification, post-weld heat treatment, identification,
status and control.
7) Documentation control of audit reports, test results, non-conformances, and
other quality control and inspection reports.
8) Equipment and material storage and maintenance quality control and
inspection documentation.
permit or license shall be submitted to PERTAMINA and the CONTRACTOR shall display
copies of the permits and licenses in the SITE office.
CONTRACTOR shall give all notices and comply with all laws, ordinances, rules, regulations,
codes and orders of any public authority. CONTRACTOR shall comply with all rules and
regulations of any insurance company which shall have issued a policy or policies upon any
part of the WORK. [f the CONTRACTOR performs any WORK contrary to such laws,
ordinances, rules, and regulations, the CONTRACTOR shall assume full responsibility and
shall bear all costs incurred to rectify the nonconformance.
The Security Supervisor shall be responsible for maintaining the following records:
1. Security chronological record of events by shifts.
2. Special report of security incidents.
3. Daily Patrol log for each shift and each security guard.
4. Key log for all buildings and facilities with an emergency key maintained for each
building at Security Supervisor post.
5. Material and equipment gate pass system for all deliveries and vehicles exiting SITE
construction areas.
6. Name and type of security pass issued:
a) Name of Employer
b) Date Issued
c) Employee's Address
d) Name and Address to notify in case of emergency
e) Date cancelled
f) Other information
7. Visitor's log showing:
a) Date
b) Visitor's name (printed) and signature
c) Visitor's Employer
d) Purpose of visit and/or name of person to be visited
e) Name of person authorizing visit
f) Time arrived and departed
g) Visitor security pass number
h) Signature of person issuing visitor security pass
8. Vehicle entry log showing:
a) Date
b) Vehicle registration number
c) PERTAMINA or Company Name
d) Name of person in vehicle
e) Material shipping document number and brief description of load
f) Person to whom material is consigned
g) Time in and out
h) Material gate pass number if materials are leaving SITE
i) Gate security signature
2.6.12 Mechanical Completion
CONTRACTOR shall perform works (pre-commissioning) pertaining with of facilities prior to
plant start-up and plant performance test such as individual mechanical test, system
cleaning, inerting, piping leak test, loop test, line check, instrument & electrical calibration
and test, system interlock test, pressure relieving test, etc,.
CONTRACTOR shall compile all documents relating with pre-commissioning activities into a
dossier which is arranged per sub-system to show that such sub-system has been completed
mechanically and ready for start-up. Mechanical Completion Dossier shall contain the
following final documentation but not necessary limited to:
1. Mechanical Completion Certificate, per sub-system
2. Punch List
3. Sub-System and Mark up drawings
4. All relevant pre-commissioning procedures
5. Pre-commissioning check list and test report
6. Mark-up AFC (approved for construction drawings)
7. Quality Control Record, including NDT record
8. Vendor shop test record
9. Supplier documentations that is required for commissioning such as operation and
maintenance manual.
10. Individual Run-in test record
11. All certificate related with pre-commissioning such as system cleaning record, leak
test, inerting, chemical and catalyst loading etc.
12. All certificate released from authorized party (DEPNAKER, MIGAS, DIMET, etc)
Within fourteen (14) days of receiving the notice, PERTAMINA shall send
CONTRACTOR either:
1) A NOTICE OF READY FOR START-UP acknowledging that PERTAMINA accepts
the PLANT or any agreed part thereof as having achieved READY FOR START-UP,
which NOTICE shall be effective as of the date of signature by PERTAMINA. Such
NOTICE will not prejudice PERTAMINA'S rights and remedies as set forth under the
CONTRACT or affect CONTRACTOR GROUP'S obligations hereunder; or
2) A NOTICE that PERTAMINA will not accept the PLANT or any part thereof until the
remedy of certain specified omissions or defects and/or the completion of certain
specified portions of the related WORK or the PLAN, in which case CONTRACTOR
GROUP shall present satisfactory evidence that he has remedied such omissions
and/or defects and shall again notify PERTAMINA.
PERTAMINA’S operator who have been trained will perform Start-up and Commissioning
work shall be guided and accompanied by CONTRACTOR Commissioning Team until
getting good result in accordance with process performance requirements. CONTRACTOR
shall also be responsible for providing supervisors, labors and commissioning/start-up spare
parts.
Operational cost for providing consumables, tools, lube oil, grease, chemical/catalyst,
utilities, etc during commissioning and start-up will be borne by CONTRACTOR.
In the case where commissioning or start-up operation or performance test cannot be carry
out due to reasons not to attributable to CONTRACTOR within 60 (sixty) days after
Mechanical Completion, then PERTAMINA will be considered has approved the Operational
Acceptance. However PERTAMINA may ask CONTRACTOR to resume work when plant
becomes ready for operation within a certain reasonable period of time after such deemed
acceptance under a separate mutual agreement between PERTAMINA and CONTRACTOR.
After plant has reached process performance requirement, PERTAMINA will issue
Operational Acceptance Certificate to CONTRACTOR. Thereafter all plant operations will be
PERTAMINA’S responsibility including all costs for plant operation. However,
CONTRACTOR shall provide continuously Operation/Commissioning team to give
assistance and supervision to PERTAMINA’S operator until Warranty Period (12 Months
after Operational Acceptance) is expired. CONTRACTOR will still be responsible for any
defects founded in the plant and cost to repair or replace spare parts of those defects shall
be borne by CONTRACTOR. During warranty period, PERTAMINA has right to call
equipment and material suppliers for trouble shooting, maintenance and operation with
CONTROCTOR’S cost.
After warranty period is expired, PERTAMINA will issue Final Acceptance certificate signing
that CONTRACTOR has no more responsibilities for the plant facilities. From this time,
PERTAMINA shall call directly material and equipment supplier or licensor in case
PERTAMINA founds defects in the plants.
include:
a) Head protection
b) Eye protection
c) Hearing protection
d) Foot protection
e) Hand protection
f) Respiratory protection
g) Body protection
h) Safety belts and life vests
i) Electrical tools and equipment grounding
5. Traffic regulations at the SITE.
6. Requirements and standards for use of scaffolding ladders and excavation
shoring
7. Requirements for grounding electrical construction equipment and tool.
8. Requirements, procedures, and responsibility for fire prevention and use of
firefighting equipment program to be provided as specified in ITB Section
Temporary Facilities.
9. Work permits procedures.
10. Procedures to be followed when an accident, injury, or fire occurs.
11. Evacuation procedures to be followed by entire CONTRACTOR’S organization
should be a major catastrophe occurs such as a large fire, a large release of
flammable gas or liquid, severe weather conditions, etc.
Investigation shall begin promptly after the incident and results of investigation,
including recommendations for preventive action, shall be documented to the
CONTRACTOR'S Construction Manager and PERTAMINA representative at the
SITE within five (5) days of the incident.
This investigation and report shall not preclude any similar investigations and
reports required by Governmental regulations, but may be handled concurrently
with them.
a. Cold Work - any work which involves no fire ignition sources, electrical
hazards or excavation work.
b. Hot Work - any work performed which involves open flames, sparks or
other potential sources of fire ignition.
c. Electrical Work - work associated with electrical equipment, energized or
not, which poses electrical hazards.
d. Excavation Work - excavation work which is potentially hazardous
because of structures, foundations, underground piping, electrical, sewer
systems or hazardous deep excavations.
e. Piling Work - piling work which transmits harmful vibrations to control
systems.
f. Hot Tap Work - work involving the installation of connections on
equipment or piping which is in service and/or pressurized.
g. Confined Space Entry- work involving personnel entry to tanks, vessels,
sealed manholes, piping etc, where hydrocarbons or other gases may be
preserved.
h. Vehicle Entry - allows a vehicle to enter plant premises to carry out a
specific job.
i. Radiography Permit work involving the Radiography of finished piping
system within the plant.
j. RT is considered harmful to un-protected personnel, if present in a
confined / non-cordoned off area.
The enforcement of the work permits regulations lies with the CONTRACTOR.
During the Tender, BIDDERS shall prepare a recommended list of spare parts for
two (2) years. This list will be based on the BIDDERS'S practical experience and
know-how of the particular systems and equipment and Suppliers recommendation.
The quantities and costs of each spare part will be reviewed and approved by
PERTAMINA in regard to the provisional budget. The successful BIDDER shall
provide the agreed upon spare parts and special tools on approval as a portion of
his EPC work.
CONTRACTOR may utilize the two-year operating spare parts in the case of an
emergency. Any parts used during construction, pre-commissioning,
commissioning, start-up and replacement during warranty period shall be replaced
at CONTRACTOR’S expense.
Maintenance 12
Dept.
Instrument
Leader
Production
Dept.
DCS
Operator
2. ESD System Vendor Technical 3 Days - 5 Days
Dept. 2
Instrument 1
Engineer 2
Equipment
Rel.
Process 2
Engineer
Maintenance 4
Dept.
Instrument
Leader
Production
Dept.
Operator
3. MCC Vendor Technical 3 Days - 5 Days
Dept. 2
Electrical
Engineer
2
Maintenance
Dept.
Electrical 3
Leader
Production
Dept.
Distribution
Operator
4. Basic Contractor Technical 3 Days - 10 Days
Process and Dept. 2
Operation Stationary 1
Philosophy of Engineer 2
Dry Gas Equipment 1
Treater Rel. 1
(DGT) Unit Process 1
Engineer
Instrument
Engineer 3
Electrical 2
Engineer
Production
Dept.
Operator
4 PROJECT PROCEDURES
Throughout the life of the project it will be necessary for CONTRACTOR to produce
for PERTAMINA'S written approval a number of "Project Procedures", intended to
supplement, amplify and clarify the procedures and documentation to be used for
the application of specific requirements of the Agreement and/or of the execution of
specific project activities. These Project Procedures, while subservient to the
Agreement, constitute contractual documents and shall have such status.
These Project Procedures will be detailed in nature and contain the responsibilities
and liabilities of the different parties, approval requirements and levels, time frames,
documentation to be used, reporting requirements, safety requirements, etc.
The items and activities to be covered by such Project Procedures will be at the
discretion of PERTAMINA. It is expected that PERTAMINA will generally follow the
practice established on previous project.
The following list is intended for information only and is in no way to be interpreted
as a definitive list of the required Project Procedures. The actual number of and
activities items to be covered by Project Procedures will be determined by
PERTAMINA during the course of the project.
4.1 CORRESPONDENCE
As soon as CONTRACTOR receives notice from PERTAMINA to start work on the
project shall:
Prepare project co-ordination procedures to be followed both within the
CONTRACTOR'S organization and between CONTRACTOR and PERTAMINA for
the duration of the project.
Set up a file code which corresponds with the proposed reporting system.
All communication between PERTAMINA and CONTRACTOR shall carry reference
numbers. These communications shall include minutes of meetings and records of
telephone, conversations between parties which are to be considered as
communications under this procedure and shall be CONTRACTOR 'S responsibility
to prepare.
All correspondence including telex, facsimile, electronic mail and teletype messages
shall be adequately identified and referenced with CONTRACTOR'S Project
Number, Project Title, and Specific Subject covered. Generally, individual
correspondence shall be limited to one subject.
A letter of transmittal shall accompany all drawings, requisitions, and similar
documents listing the quantities, titles, and numbers (revision numbers if
appropriate) of the information being transmitted. These transmittal letters can be
DRY GAS TREATING FCC UNIT PROJECT
PT. PERTAMINA (PERSERO) RU-III PLAJU
ITB PART V
PROJECT SPECIFICATION
Page 80 of 101
form letters.
All drawings shall be folded to International A4 (297 rum x 210 mm) except for
master or original drawings which shall not be folded but rolled and protected by
tubes, etc.
4.3 REPORT
The reports required by PERTAMINA for coordination, guidance, monitoring, and
information during the course of engineering and construction are summarized
below. It is the intent of PERTAMINA to use CONTRACTOR'S normal procedures
and forms as much as possible. CONTRACTOR should review these requirements
so that omissions and discrepancies can be reconciled and still fulfill the intent of
these documents.
4.3.1 Progress Report
CONTRACTOR shall prepare at the beginning of the project and reissue by the end
of each month a comprehensive general report on the progress of the project. This
shall as a minimum, include:
1. Achievement of significant project milestones.
2. Engineering disciplines and drafting based on physical percent complete
3. Material requisition based on physical percent complete
4. Material received at SITE based on physical percent complete
5. Construction based on physical percent complete
6. Problem areas and corrective actions to be implemented
7. Next month's proposed project schedule.
The report shall also indicate charts or graphs showing actual versus predicted
progress for these items. Both monthly and cumulative totals are to be indicated.
4.3.2 Deliverable List Report
CONTRACTOR shall prepare a monthly report showing Drawing Numbers and
Titles, with their scheduled and actual issue date, scheduled and actual issue for
construction; date and any revision date of those drawings. Similar data for
specifications shall be issued, either as part of the drawing report or as a separate
report.
4.3.3 Vendor Document Report
CONTRACTOR shall prepare, maintain, and issue monthly Vendor drawing index
which shall indicate dates received, drawing approval status and date sent to
PERTAMINA.
4.3.4 Purchasing Report
CONTRACTOR shall prepare a report to ·indicate status of all equipment and
materials requisition from inception of the requisition to delivery to the Work SITEs.
This report shall indicate schedule and actual dates for requisition issue, quotes
received, Purchase Order placement, and delivery. This report shall also indicate
point of origin for shipping purposes. This report shall be issued every month.
4.3.5 Expediting and Inspection Report
CONTRACTOR shall issue to PERTAMINA all expediting and inspection reports
including reports by third party inspectors based on telephone contact or actual
shop visits.
4.3.6 Material Control Report
CONTRACTOR shall issue Material control report as a follow up to actual receipts
at the Work SITEs. The following information is required on the Report.
1. Quantity
2. Description of material or transaction
3. Purchase Order Number
4. Shipper's name and shipping point
5. Condition of shipment and whether complete or partial shipment
4.3.7 Material Exception Report
CONTRACTOR shall prepare reports on all material overages, shortages and
damages. A record shall be maintained of exception items which shall reflect their
COPY REQUIRED TO
SUBJECT
PERTAMINA
Miscellaneous Documents 3
Field Modification Requests 3
Approved for Construction
3
Drawings
Equipment List 3
(2) Material
ASTM
ASME
AWS
4. Machinery
(1) Pumps
Centrifugal Pumps (Process)
(2) Compressor
API Std. 617 “Centrifugal Compressors for General Refinery
Service”
(3) Gear
API Std 670, machinery protection System
API Std. 671, Special Purpose Coupling for Petroleum, Chemical
and Gas Industry service
API Std. 613, Special Purpose Gear Units for Petroleum,
Chemical and Gas Industry service Petroleum, Chemical and
Gas Industry service
API Std. 677, General Purpose Gear Units for Refinery Service
Manufacturer’s Standard
7. Fired Heaters
API Std. 650. Fired Heater for General Refinery Service
API Std. 585. Burners for Fired Heaters in General Refinery Service
8. Pressure Relieving System
Design and Installation
API RP520 Sizing, Selection, and Installation of Pressure-Relieving
Devices in Refinery
API RP52 I Guide For Pressure-Relieving on a Depressuring Systems
9. Foundation and Concrete Structure
(1) Design
ACT (American Concrete Institute)
AU (Architectural institute of Japan)
(2) Material
ASTM (American Society for Testing and Material)
JIS (Japanese Industrial Standards)
10. Road
(1) Design
AASI-ITO (American Association of State Highway and Transportation
Officials)
(2) Material
AASHTO
ASTM (American Society for Testing and Material)
ITS (Japanese Industrial Standards)
Al (Asphalt Institute)
11. Building
(1) Design
Building Standards Law of Japan
AlJ (Architectural Institute of Japan)
ACE (American Concrete Institute)
AISC (American Institute of Steel Corporation)
(1) Design
AISC (American Institute of Steel Corporation)
All (Architectural Institute of Japan)
AWS (American Welding Society)
UBC (Uniform Building Code)
(2) Material
ASTM (American Society for Testing and Material)
JIS (Japanese Industrial Standards)
13. Piping
(1) Piping System Design
ANSI B31.1 Power Piping
B31.3 Chemical Plant and Petroleum Refinery Piping
(2) Valves and Material
ASTM (American Society for Testing and Material)
ASNM (American Society of Mechanical Engineers)
ANSI (American National Standard Institute)
API (American Petroleum Institute)
JIS (Japanese Industrial Standards)
(3) Dimension
ANSI (American National Standard institute)
API (American Petroleum Institute)
MSS (Manufacturers Standard Sizetion Society)
ITS (Japanese Industrial Standards)
14. Insulation
ASTM (American Society for Testing and Material)
JIS (Japanese Industrial Standards)
15. Painting
ASTM (American Society for Testing and Material)
SSPC (Steel Structures Painting Council)
JIS (Japanese Industrial Standards)
BS (British Standard)
16. Electrical
(1) IEC (International Electro technical Commission)
Main applicable codes:
IEC 60034 “Rotating Electrical Machines”
IEC 60038 “IEC Standard Voltages”
IEC 60056 “High-Voltage Alternating-Current Circuit Breakers”
IEC 60076 “Power Transformers”
(3) Japan
JIS (Japanese Industrial Standards)
JEC (Japanese Electrotechnical Commission)
JEM (The Standard of the Japan Electrical Manufacturer’s
Association)
PITS (Ministry of Labor, Research institute of Industrial Safety,
Japan)
Main applicable codes:
JIS A4201 “The Protection of Structures Against Lightning”
JEC 37 “induction Machines”
JEC 54 “Direct Current Machines”
JEC 135 “Current Carrying Capacities of 600 V PVC Insulated Wires
and 600 V Rubber insulated Wires”
JEC 204 “Transformers”
JEC 2300 “AC Circuit Breakers”
JEC 1195 “Motor Control Centers”
JEC 1225 “High-Voltage Combination Starters”
JEC 1425 “AC Metal-Clad Switchgear and Control gear for Rated
Voltages from 3.6 kV to 30 kV”
RIIS-TR-85-l “Recommended Practice for Explosion-Protected Electrical
(4) British Standard
BS 171 “Power Transformers”
BS 4999 “General Requirements for Rotating Electrical Machines”
BS 5000 “Rotating Electrical Machines of Particular Types or for
Particular Application”
BS 5227 “Specification for A.C. Metal-Enclosed Switchgear and
Control gear for Rated Voltages above 1 kV and up to and
including 52 kV”
BS 5467 “ Specification for Cables with Thermosetting Insulation for
Electricity Supply for Rated Voltages of up to and including
100/1000 V and up to and including 1900/330 V”
BS 5486 “Low-Voltage Switchgear and Controlgear Assemblies”
BS 5501 “Electrical Apparatus for Potentially Explosive Atmosphere”
BS 6622 “Specification for Cables with Extruded Cross-Linked
Polyethylene or Ethylene Propylene Rubber Insulated for
Rated Voltages from380016600 Vup to 19000/38000 V”
BS 6941 “Specification for Electrical Apparatus for Explosive
Atmosphere with Type of Protection N”
ANSI
JIS
21. Elevator
ANSI (American National Standard Institute)
MS (Japanese Industrial Standards)
Building Standard Law of Japan
JEAS (Japan Elevator Association Standards)
ES (British Standards)
DThT/VDE
22. Plumbing
Design
National Plumbing code
HASS
Indonesian Code
INSTRUMENT
No. TAG NO. NEW INSTRUMENT TYPE DESCRIPTION
TYPE
INSTRUMENT
No. TAG NO. NEW INSTRUMENT TYPE DESCRIPTION
TYPE
36 DGT-LCV-6001 LCV CONTROL VALVE
37 DGT-LCV-6002 LCV CONTROL VALVE
38 DGT-LCV-6003 LCV CONTROL VALVE
39 DGT-LCV-6006 LCV CONTROL VALVE
40 DGT-LCV-6008 LCV CONTROL VALVE
41 DGT-LG-6001 LG REFLEX TYPE LEVEL GAUGE
42 DGT-LG-6002 LG REFLEX TYPE LEVEL GAUGE
43 DGT-LG-6003 LG REFLEX TYPE LEVEL GAUGE
44 DGT-LG-6004 LG REFLEX TYPE LEVEL GAUGE
45 DGT-LG-6005 LG REFLEX TYPE LEVEL GAUGE
46 DGT-LG-6006 LG REFLEX TYPE LEVEL GAUGE
47 DGT-LG-6007 LG REFLEX TYPE LEVEL GAUGE
48 DGT-LG-6008 LG REFLEX TYPE LEVEL GAUGE
49 DGT-LG-6009 LG REFLEX TYPE LEVEL GAUGE
50 DGT-LG-6010 LG REFLEX TYPE LEVEL GAUGE
51 DGT-LG-6011 LG REFLEX TYPE LEVEL GAUGE
52 DGT-LI-6007 LI DCS INDICATION FUNCTION
53 DGT-LI-6011 LI DCS INDICATION FUNCTION
54 DGT-LIC-6001 LIC DCS CONTROL FUNCTION
55 DGT-LIC-6002 LIC DCS CONTROL FUNCTION
56 DGT-LIC-6003 LIC DCS CONTROL FUNCTION
57 DGT-LIC-6006 LIC DCS CONTROL FUNCTION
58 DGT-LIC-6008 LIC DCS CONTROL FUNCTION
59 DGT-LIC-6010 LIC DCS CONTROL FUNCTION
60 DGT-LT-6001 LT DISPLACER LEVEL TRANSMITTER
61 DGT-LT-6002 LT DISPLACER LEVEL TRANSMITTER
62 DGT-LT-6003 LT DISPLACER LEVEL TRANSMITTER
63 DGT-LT-6006 LT DISPLACER LEVEL TRANSMITTER
64 DGT-LT-6007 LT DISPLACER LEVEL TRANSMITTER
65 DGT-LT-6008 LT DISPLACER LEVEL TRANSMITTER
66 DGT-LT-6010 LT DISPLACER LEVEL TRANSMITTER
67 DGT-LT-6011 LT DP LEVEL TRANSMITTER
68 DGT-LY-6001 LY E/P POSITIONER
69 DGT-LY-6002 LY E/P POSITIONER
70 DGT-LY-6003 LY E/P POSITIONER
71 DGT-LY-6006 LY E/P POSITIONER
72 DGT-LY-6008 LY E/P POSITIONER
73 DGT-PCV-6001 PCV PRESSURE REGULATOR VALVE
INSTRUMENT
No. TAG NO. NEW INSTRUMENT TYPE DESCRIPTION
TYPE
74 DGT-PCV-6002 PCV CONTROL VALVE
75 DGT-PCV-6003 PCV CONTROL VALVE
76 DGT-PCV-6005A PCV CONTROL VALVE
77 DGT-PCV-6006 PCV PRESSURE REGULATOR VALVE
78 DGT-PCV-6007 PCV PRESSURE REGULATOR VALVE
79 DGT-PDG-6011 PDG DIFFERENTIAL PRESSURE GAUGE
80 DGT-PDG-6012 PDG DIFFERENTIAL PRESSURE GAUGE
81 DGT-PDG-6013 PDG DIFFERENTIAL PRESSURE GAUGE
82 DGT-PDG-6014 PDG DIFFERENTIAL PRESSURE GAUGE
83 DGT-PDI-6001 PDI DCS INDICATION FUNCTION
84 DGT-PDI-6004 PDI DCS INDICATION FUNCTION
85 DGT-PDT-6001 PDT DIFFERENTIAL PRESSURE TRANSMITTER
86 DGT-PDT-6004 PDT DIFFERENTIAL PRESSURE TRANSMITTER
87 DGT-PG-6001 PG PRESSURE GAUGE
88 DGT-PG-6002 PG PRESSURE GAUGE
89 DGT-PG-6003A PG PRESSURE GAUGE
90 DGT-PG-6003B PG PRESSURE GAUGE
91 DGT-PG-6004A PG PRESSURE GAUGE
92 DGT-PG-6004B PG PRESSURE GAUGE
93 DGT-PG-6005A PG PRESSURE GAUGE
94 DGT-PG-6005B PG PRESSURE GAUGE
95 DGT-PG-6006A PG PRESSURE GAUGE
96 DGT-PG-6006B PG PRESSURE GAUGE
97 DGT-PG-6007 PG PRESSURE GAUGE
98 DGT-PG-6008 PG PRESSURE GAUGE
99 DGT-PG-6009A PG PRESSURE GAUGE
100 DGT-PG-6009B PG PRESSURE GAUGE
101 DGT-PG-6010 PG PRESSURE GAUGE
102 DGT-PG-6011 PG PRESSURE GAUGE
103 DGT-PG-6012 PG PRESSURE GAUGE
104 DGT-PG-6013 PG PRESSURE GAUGE
105 DGT-PG-6014 PG PRESSURE GAUGE
106 DGT-PG-6015 PG PRESSURE GAUGE
107 DGT-PG-6016 PG PRESSURE GAUGE
108 DGT-PG-6017 PG PRESSURE GAUGE
109 DGT-PI-6002 PI DCS INDICATION FUNCTION
110 DGT-PI-6006 PI DCS INDICATION FUNCTION
111 DGT-PIC-6003 PIC DCS CONTROL FUNCTION
INSTRUMENT
No. TAG NO. NEW INSTRUMENT TYPE DESCRIPTION
TYPE
112 DGT-PIC-6005 PIC DCS CONTROL FUNCTION
113 DGT-PSV-6001A PSV SAFETY RELIEF VALVE
114 DGT-PSV-6001B PSV SAFETY RELIEF VALVE
115 DGT-PSV-6002A PSV SAFETY RELIEF VALVE
116 DGT-PSV-6002B PSV SAFETY RELIEF VALVE
117 DGT-PSV-6003A PSV SAFETY RELIEF VALVE
118 DGT-PSV-6003B PSV SAFETY RELIEF VALVE
119 DGT-PSV-6005 PSV SAFETY RELIEF VALVE
120 DGT-PT-6002 PT PRESSURE TRANSMITTER
121 DGT-PT-6003 PT PRESSURE TRANSMITTER
122 DGT-PT-6005 PT PRESSURE TRANSMITTER
123 DGT-PT-6006 PT PRESSURE TRANSMITTER
124 DGT-PY-6002 PY E/P POSITIONER
125 DGT-PY-6003 PY E/P POSITIONER
126 DGT-PY-6005A PY E/P POSITIONER
127 FLRS-PY-3837A PY DCS CONTROL FUNCTION
128 DGT-RO-6001 RO RESTRICTION ORIFICE
129 DGT-RO-6002 RO RESTRICTION ORIFICE
130 DGT-RO-6003 RO RESTRICTION ORIFICE
131 DGT-RO-6004 RO RESTRICTION ORIFICE
132 DGT-RO-6005 RO RESTRICTION ORIFICE
133 DGT-RO-6006 RO RESTRICTION ORIFICE
134 DGT-RO-6007 RO RESTRICTION ORIFICE
135 DGT-RO-6009 RO RESTRICTION ORIFICE
136 DGT-RO-6010 RO RESTRICTION ORIFICE
137 DGT-RO-6011 RO RESTRICTION ORIFICE
138 DGT-SDV-6001 SDV SHUTDOWN VALVE
139 DGT-SDV-6002 SDV SHUTDOWN VALVE
140 DGT-SDV-6004 SDV SHUTDOWN VALVE
141 DGT-SDY-6001 SDY SOLENOID VALVE
142 DGT-SDY-6002 SDY SOLENOID VALVE
143 DGT-SDY-6004 SDY SOLENOID VALVE
144 DGT-TCV-6001 TCV CONTROL VALVE
145 DGT-TDIC-6001 TDIC DCS CONTROL FUNCTION
146 DGT-TG/TW-6001 TG/TW TEMPERATURE GAUGE WITH WELL
147 DGT-TG/TW-6002 TG/TW TEMPERATURE GAUGE WITH WELL
148 DGT-TG/TW-6003 TG/TW TEMPERATURE GAUGE WITH WELL
149 DGT-TG/TW-6005 TG/TW TEMPERATURE GAUGE WITH WELL
INSTRUMENT
No. TAG NO. NEW INSTRUMENT TYPE DESCRIPTION
TYPE
150 DGT-TG/TW-6006 TG/TW TEMPERATURE GAUGE WITH WELL
151 DGT-TI-6001 TI DCS INDICATION FUNCTION
152 DGT-TI-6002 TI DCS INDICATION FUNCTION
153 DGT-TI-6003 TI DCS INDICATION FUNCTION
154 DGT-TI-6005 TI DCS INDICATION FUNCTION
155 DGT-TI-6008 TI DCS INDICATION FUNCTION
156 DGT-TIC-6006 TIC DCS CONTROL FUNCTION
157 DGT-TT/TW-6001 TT/TW TEMPERATURE TRANSMITTER WITH WELL
158 DGT-TT/TW-6002 TT/TW TEMPERATURE TRANSMITTER WITH WELL
159 DGT-TT/TW-6003 TT/TW TEMPERATURE TRANSMITTER WITH WELL
160 DGT-TT/TW-6005 TT/TW TEMPERATURE TRANSMITTER WITH WELL
161 DGT-TT/TW-6006 TT/TW TEMPERATURE TRANSMITTER WITH WELL
162 DGT-TT/TW-6008 TT/TW TEMPERATURE TRANSMITTER WITH WELL
163 DGT-TY-6001 TY E/P POSITIONER
164 DGT-VAH-6001 VAH DCS ALARM FUNCTION
165 DGT-VAH-6006 VAH DCS ALARM FUNCTION
166 DGT-VS-6001 VS VIBRATION SWITCH
167 DGT-VS-6006 VS VIBRATION SWITCH
168 DGT-XH-2010 XH I/E INTERFACE RELAY
169 DGT-XL-2010 XL I/E INTERFACE RELAY
170 DGT-XL-6001 XL DCS INDICATION FUNCTION
171 DGT-XL-6002 XL DCS INDICATION FUNCTION
172 DGT-XL-6003 XL DCS INDICATION FUNCTION
173 DGT-XL-6004 XL DCS INDICATION FUNCTION
174 DGT-XL-6005 XL DCS INDICATION FUNCTION
175 DGT-XL-6006 XL DCS INDICATION FUNCTION
176 DGT-XL-6007 XL DCS INDICATION FUNCTION
177 DGT-XY-2010 XY I/E INTERFACE RELAY
178 DGT-XY-6001 XY I/E INTERFACE RELAY
179 DGT-XY-6002 XY I/E INTERFACE RELAY
180 DGT-XY-6003 XY I/E INTERFACE RELAY
181 DGT-XY-6004 XY I/E INTERFACE RELAY
182 DGT-XY-6005 XY I/E INTERFACE RELAY
183 DGT-XY-6006 XY I/E INTERFACE RELAY
184 DGT-XY-6007 XY I/E INTERFACE RELAY
185 DGT-ZLC-6001 ZLC DCS ALARM FUNCTION
186 DGT-ZLC-6002 ZLC DCS ALARM FUNCTION
187 DGT-ZLC-6004 ZLC DCS ALARM FUNCTION
INSTRUMENT
No. TAG NO. NEW INSTRUMENT TYPE DESCRIPTION
TYPE
188 DGT-ZSC-6001 ZSC LIMIT SWITCH
189 DGT-ZSC-6002 ZSC LIMIT SWITCH
190 DGT-ZSC-6004 ZSC LIMIT SWITCH