Professional Documents
Culture Documents
Tel.: + 47 22073500
Fax: + 47 22073768
E-mail: firmapost@vegvesen.no
ISBN 82-7207-540-7
03.04
Norwegian Public Roads
Administration
Road Tunnels
April 2004
Norwegian Public Roads Administration
Handbooks
This is one of a series of handbooks prepared and
issued by The Norwegian Public Roads
Administration - a collection of consecutetively
numbered books which primarily are written for
use within the Administration.
Road Tunnels
No. 021 in the series of handbooks
Design:Graphic Division NPRA
Issued: 1000 copies
ISBN 82-7207-540-7
2
R O A D T U N N E L S P R E FA C E
Preface
The manuals pertaining to the Public the choice of solutions and technical
Roads Administration are given pursuant equipment is made on the basis of life-
to the regulations relating to the Roads Act expectancy where operation and mainte-
concerning highway construction. nance costs are evaluated.
This Design manual applies to all types of Compared to the 1992 edition, most chap-
road tunnels. The manual apply for new ters have been largely rewritten. A number
tunnels but do not apply retrospectively. of subjects which may be considered to fall
Initially, the manual shall apply in respect outside the manual material have been
of upgrading of safety aspects of existing included with regard to accessibility.
tunnels. Any deviation from the specifica- Reference is also made to other norms and
tions in the norm must be approved by the guidelines rather than these texts being
Directorate of Public Roads. copied here.
The manual replace those stated in the Work with revising the design manual was
edition of August 1992. undertaken in the period 1997 - 2001.
Regional offices, consultants, constructors
The manual cover all aspects of the plan- and others have made important contribu-
ning of a tunnel project, from the early tions.
planning stages to completion of the proj-
ect, together with operation and mainte- The Design Manual will be available on
nance. Tunnels comprise a considerable the Norwegian Public Roads
part of the highway network in Norway. Administration´s internet pages
Particular attention is given to the envi- www. vegvesen.no.
ronment relating to the requirements of
nature conservation and the urban envi-
ronment. The Directorate of Public Roads,
June 2003.
Tunnel construction implies long-term Responsible Department:
maintenance. It is important therefore that Road Development Department
3
4
ROAD TUNNELS CONTENTS
Contents
Contents 5
2 Geological Investigations 21
201 Introduction 19
202 The preliminary plan 21
203 General plan 20
204 Zone plan 22
205 The Construction plan/Tendering 23
205.1 Supplementary geological investigations 23
205.2 Geological and geotechnical reports as a part of tendering 23
3 Consideration of the local environment 25
301 Introduction 25
302 Requirements and constraints 25
303 Registration and investigation programmes 25
304 Vibrations and building inspection 25
305. Requirements for water control 26
305.1 Water tightness criteria 26
305.2 Methods for meeting the sealing requirements. Organisation of the task 26
306 Temporary water effluent 27
306.1 General 25
306.2 Contents of the application 26
306.3 Control and supervision 28
307 Use of chemicals in tunnel construction 28
308 Permanent drainage 28
309 Emission of gas and particles 29
309.1 Impact analysis 29
309.2 Recommended air quality criteria 29
309.3 Emissions through ventilation shafts 29
310 Cleansing tunnel air 29
311 Noise in the proximity of the tunnel entrances 30
4 Geometric design 31
401 General 31
402 Selection of tunnel category 31
403 Tunnel cross-sections 32
5
ROAD TUNNELS CONTENTS
6
ROAD TUNNELS CONTENTS
7
ROAD TUNNELS CONTENTS
705.1 General 79
705.2 Frost penetration 80
706 Water and frost protection methods 80
706.1 General 80
706.2 Choice of construction 80
707 Frost protection with the aid of thermal doors 81
708 Portals 82
8 Drainage 83
801 General 83
802 The drainage system 83
803 Drainage trench 83
804 System for accumulation of washwater 84
805 Water reserves for fire emergencies 85
806 Pumping stations, pumping system 85
10 Technical Equipment 91
1001 Specifications for technical equipment 91
1001.1 General requirements for electrical equipment 91
1001.2 Protection against corrosion of technical equipment 91
1001.3 Degree of armouring 91
1001.4 Cables 91
1001.5 Technical rooms 92
1002 Power supply 92
1003 Lighting 92
1003.1 General 92
1003.2 Lighting in the tunnel approach - adaptation luminance 92
1003.3 Lighting in the tunnel 93
1003.31 Lighting level (luminance) in the tunnel. Zone demarcation 93
1003.32 Lighting in lay-bys 94
1003.4 Distance between light fittings 94
1003.5 Light fittings 95
1003.6 Priority lighting / emergency lighting 95
1004 Ventilation 95
8
ROAD TUNNELS CONTENTS
9
ROAD TUNNELS CONTENTS
10
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
11
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
The Nature Conservancy Act the Planning and Building Act and
Highway construction conflicting with Manual 054 “General planning”.
protected areas as defined by the Nature (The titles of the relevant documents are
Conservancy Act including areas of land- translated,but are issued only in
scape preservation, national parks, nature Norwegian). In general, when planning
reserves or significant geological features, projects which are subject to the Planning
will not be permitted without prior dispen- and Building Act contact should be made
sation being granted for the protected area at an early stage with the respective
as required by the Nature Conservancy authorities in order to obtain their opinion
Act (§ 23). Initially it is the government on the extent to which it may be necessary
which is the dispensation authority, but in to apply for dispensation for the projects
certain instances these powers are delegat- in addition to clarifying the provisions of
ed to the County Governor. the Planning and Building Act.
12
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
for decisions on the choice of a road route • The influence areas or resources which
and highway standards, specifications are are preserved according to the Nature
included in the guidelines for national and Conservancy Act. Contact should be
county roads in the PBA (T-1057, Chap. made with the County Governor in
4.3). order to clarify whether the construc-
Preparation of the general plan will nor- tion conflicts with the conservation
mally require a number of fairly compre- order. The question of dispensation
hensive reports. In the guidelines, there from the conservation requirements
are, for example, requirements that the must be clarified before the plan is
costs of the various alternatives for the approved according to the Planning
parts of the municipal plan are prepared and Building Act.
within a margin of ± 25%. This necessi- • In the guidelines for fire protection in
tates geological investigations and reports tunnels it is stated that the Norwegian
which are designed to meet these require- Public Roads Administration in asso-
ments. (See Chapter 2 ) ciation with the local fire authorities
At an early stage in the preparation of undertake a general evaluation of fire
the general plan, a programme should to protection measures in the proposed
be prepared in association with the plan- tunnel. In general resolutions on safety
ning authorities to include the main ele- measures for tunnels is not included in
ments of the planning process. If an the principal design. Questions which
impact study is to be prepared as part of can have considerable significance for
the process, this will be included as a part the project’s total costs should, how-
of the design. ever, be clarified at his stage.
Certain aspects of tunnel construction
require to be specially evaluated or Structure of the Design
clarified during this planning stage of the Regarding the county plan, no further
tunnel, including: details are given in the Planning and
• Circumstances which may require Building Act as to how this plan shall be
approval according to the Pollution Act prepared. The guidelines are given in the
§ 11. “Guidelines for national and county roads
• Possible consequences for water cours according to the Planning and Building
es (including ground water). Act” (T-1057) published jointly by the
Clarification with the NVE is required Ministry of the Environment and the
where dispensation has to be sought in Ministry of Transport, and also in the
accordance with the Water Resources Ministry of the Environment’s guide
Act “Municipal Land-use Planning” (T-1382).
• Conflict with cultural monuments In Manual 054, specific examples are
which are automatically protected given of the presentation of route choices
and/or monuments included under the in accordance with the guidelines in the
Historic Monuments Act §§ 15, 19 and above documents.
20. Concerning roads which may con- If the tunnel is to impose restrictions on
flict with listed monuments and which existing land-use, this should be stated in
will require dispensa tion or exception the plan. This is important both for those
by the Director General for Cultural who will be affected by the project and to
Heritage the question of dispensation/- ensure better control by the Norwegian
exception must be taken up during Public Roads Administration such that
the general planning. measures are not commenced which may
13
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
be an obstacle to the plan, and that other more detailed information regarding the
measures are not permitted which may administrative process concerning impact
have unfortunate effects for the completed analyses. The Ministry of the Environment
project. In addition to the tunnel route on has also prepared a separate guide to inter-
the map being indicated as “… an impor- preting the criteria in the regulations.
tant link in the communications system”,
or as “..restricted areas..”, a description of 102.2 Zone Plan
the restrictions expected to be incurred by With the exception of minor projects, a
the tunnel project for activity on the sur- zone plan has to be prepared for all nation-
face should also be given. If these areas al and county road construction as laid
are “built-up areas” (for example housing down in the Planning and Building Act. A
development) or “agriculture, natural and zone plan shall always be made for tun-
recreation areas” where dispersed settle- nels. Similarly to the land-use plan in the
ment is permitted, then to a certain extent municipal plan, a zone plan is legally
these restrictions may be included in the binding as determined by the PBA § 31.
provisions of the plan. Regarding other A zone plan which has been approved,
land-use categories where the possibility provides the basis for expropriation as
for determining provisions is more limit- determined by the Highways Act § 50.
ed, the restrictions for the area above the The tunnel route shall be specified in the
tunnel are commented upon in the plan zone plan.
details.
Content
Impact studies in accordance with The requirements for zone plan is
Planning and Building Act. described in the guidelines for national
The Planning and Building Act (Chapter and county road plans according to the
VII-a) and accompanying regulations on Planning and Building Act.
impact studies contain more specific regu- The requirements in the guidelines are,
lations regarding the planning of the indi- among other things, that supplementary
vidual measures. It is assumed that the investigations shall be carried out.(See
impact study will be carried out according Chapter 2) The costs shall be calculated
to the regulations in coordination with the with a precision of ± 10 %. If a broader
evaluation of the first formal plan where range is required, the reason for this has to
the route or corridor is approved. be given.
Which measures shall be the subject of The legally binding design includes a
an impact analysis are given in the regula- map showing one or more objects of
tions. The client shall then prepare a note development. The fact that the zone plan is
proposing a programme of the impact legally binding implies that there will not
studies to be included in the report. On the be opportunity to carry out subsequent
basis of the proposal the Directorate of measures which conflict with land-use
Public Roads (in regard of trunk roads and approved by the plan, with the exception
new roads) or the planning authority (for that smaller adjustments may be made
other roads) shall determine that a pro- through a formal dispensation of the exist-
gramme be drawn up stating which reports ing plan, changes to the plan, or in con-
are to be prepared, and of the content of nection with a new general or zone plan.
the impact study which the client shall In the Ministry of the Environment’s
prepare. guide “Development plan. Building plans”
The Ministry of the Environment give (T-1381), detailed norms are given for
14
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
maps of development and building areas. that restrictions on the surface must be
A number of examples are included in the shown on the map and/or in the provi-
guidelines which provide directions sions. Examples of such restrictions are
preparations of the map and the accompa- the prohibition of specified construction
nying design measures. work, blasting or boring in the ground.
There are no special requirements in the Alternatively, it may be stated that any
law or regulations relating to the formula- work which may cause damage to the tun-
tion of zone plans for tunnels. In each indi- nel is prohibited, and that specific meas-
vidual case it must be determined which ures must be approved by the Public
aspects are required to be clarified in the Roads Administration.
design. The assumption that the zone plan shall
Based on the following, the design of the be the basis for acquiring land and rights
tunnel including the approach zones, to proceed with the construction and pro-
should be established: vide those affected with the best possible
• It is assumed that a detailed account of understanding of the consequences of the
fire-safety measures is included in the project require that any restrictions
preparation of the zone plan accord imposed are clearly described.
ing to “Guidelines for fire protection in
road tunnels”, Chap. 3.2. Some basic points concerning zone plans
• Exceptions to procedural handling of for tunnels:
tunnel construction are conditional • Regarding the tunnel construction it-
upon the location of the tunnel, the self together with the associated safety
design of the entrances and possible zone (assuming this is regulated) and
restrictions in use of the area above the the approach zones, the objectives
tunnel having been incorporated in the “Public traffic areas” as stated in the
design as outlined in the thematic guide PBA § 25, No. 3 is commonly used.
“Public road construction and building • Even though the tunnel might not have
projects” (Report HO-2/2000). any physical impact on the surface, it
In particular, the location of the tunnel would be appropriate to combine the
and restrictions for use of the area objectives of “public traffic areas” with
above the tunnel are most conveniently the regulations which is relevant to the
handled in the zone plan. area above the tunnel. Particularly
Other circumstances which will be signi- where it is necessary to impose restri-
ficant in determining the detail of the ctions on land-use above the tunnel, it
design in connection with development of will be proper to indicate the area cov
the tunnel area include: ered by such restrictions by combin-
• existing, planned and expected activity ing purposes, or by adopting other
on the surface or in the ground development objectives.
• the type of tunnel, rock cover and • Concerning the portal construction and
ground conditions concrete tunnels, the construction
• control of sealing measures carried out. phase will result in temporary upheaval
The plan must indicate the necessary pro- on the surface which will frequently
tective measures against activity which have broader consequences for the
can cause damage of the tunnel construc- landowners and those licensed to use
tion. Consideration should therefore be the area than the permanent restric
made as to whether a safety zone should tions. These circumstances should be
be defined around the tunnel. This implies clearly indicated in the zone plan.
15
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
16
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
such that they are a hindrance to normal that the client supplies corresponding
public access or recreation area or in other information on the progress.
way are detrimental to the surroundings. In the thematic guide “Public road con-
Even though public road projects will be struction and building projects” (Report
largely exempt from building regulations, HO-2/2000), the requirements for admin-
a number of regulations will always apply. istrative procedures are described for a
See “Public road construction and build- large number of elements incorporated in
ing projects”: road construction. A summary of those
• § 74, no. 2 on aesthetics most relevant to tunnel construction are
• § 77 on construction procedures and included below, Those included under (A)
requirements for products used in con should be considered as elements for
struction which it is absolutely necessary that a
• § 92 on changes to or removing con detailed description is given, such that
structions demands are not made for application or
• Chapter XVIII on liabilities notification. Those listed under (B) are not
• Chapter IX on illegal contruction activ absolute requirements, but documentation
ity. should nevertheless be presented.
Reference is also made to Section 102.33
for processing of applications and notifi- “Tunnels
cations. (A) Exception from administrative con-
struction processes is dependent upon the
102.32 Further information on excep- location of the tunnel, the design of the
tions to construction applications tunnel portals and any restrictions in the
Where the road construction is not use of the area above the tunnel being
described in detail in the zone plan or con- determined in the planning process. Any
struction plan, an application must be restrictions in use of the area above the
made for the remaining details associated tunnel must be clearly stated in the provi-
with the project. As mentioned, the regula- sions of the plan. Further, reference must
tions on liability and control are not appli- be made to the necessary technical draw-
cable. ings which show the design of the portals
Where it is desired that the zone plan is and any other related building measures.
to be described in such detail as to exempt (B) Subsidiary information should be sup-
the road project from administrative pro- plied in the form of illustrations which
cedures, it is important to understand that provide the involved parties with an
this will result in less room for adjustment impression of the appearance of the tunnel
in later stages of the project and that this portals.
can result in the need for a new evaluation Reference is also made to “Guidelines
of the plan to include circumstances which for considering fire protection in road tun-
would have been sufficiently considered nels” of July 2000, issued jointly by the
in an initial administrative evaluation. Ministry of Transport and the Ministry of
Through the application or notification, Local Government. The guidelines have
residents and others in the vicinity will been prepared within the existing regula-
often be informed of the period of the tions and are based upon a draft from the
project and practical circumstances during Directorate for Fire and Electrical Safety
the construction period. For measures (DBE) and the Directorate of Public
which are exempt from construction Roads in association with the National
administrative procedures, it is assumed Office of Building Technology
17
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
18
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS
19
20
R O A D T U N N E L S G E O L O G I C A L I N V E S T I G AT I O N S
2 Geological Investigations
21
T U N N E L S G E O L O G I C A L I N V E S T I G AT I O N S
(scale 1:1000 – 1:5000). These maps ensure that the technical solutions pro-
will be used to determine the distribu posed may be implemented and that these
tion of soils and rock, weakness zones provide the basis for quantitative esti-
and the orientation of faults and joints. mates.
• Field and site investigations. Following the completion of the inves-
The investigations and evaluations tigations a report is prepared in sufficient
shall include the following: detail as is required for the plan.
- Soil cover. Type and thickness. A distinction has to be made between
Water depth for sub sea tunnels. measurements, actual observations and
- Rock type and boundaries interpretations.
For sub-sea tunnels rock types on
both sides of the fjord or sound 204 The Zone Plan
should be stated. The need for supplementary investigations
- Bedding and foliation made in connection with the general plan
- Joint orientation and frequency must be considered.
- Weakness zones The purpose of the evaluations at this
- Rock cover stage are :
- Hydrological and hydrogeological • To establish the geological basis for
registration: cost estimates
• Measuring programme for • Report the degree of uncertainty in
groundwater level and pore pres- the investigation results and the conse
sure where necessary, including quences of this for cost estimates
registration of water reservoirs The impact of the tunnel in the neighbour-
and marsh areas together with ing district must be examined and evaluat-
seasonal variation for these ed in detail.
• Sensitivity with regard to flora
and fauna The following must be carried out:
• Registration of areas liable to • A scrutiny of the results of previous
subsidence investigations
• Requirements for control of • Planning and execution of supplemen
leakage into the various tary investigations together with a
sections of the tunnel verification of previous conclusions
- Quality of rock material with a • Vibrations
view to possible use in road con- The limits for permitted vibrations
struction within the area of influence are deter
- Investigation for dumping sites mined and a measurement programme
- Tunnel entrance site alternatives, prepared for follow-up. Plan for build
cuttings, danger of rockslides ing inspection, registration of settle-
- Need for core drilling ments and damage and the time when
- Need for seismological investiga- this shall be carried out is to be deter-
tions mined.
If measurements are to be taken of the sta- • Groundwater, pore pressure and settle
tus of the water table and pore pressure, ment. Using investigations undertaken
frequent measuring should be taken to as part of the general plan an eva-
document natural variations over time (for luation must be made of possible dam
example, at monthly intervals). age arising and necessary protective
The investigations undertaken shall measures. Consideration must be made
22
T U N N E L S G E O L O G I C A L I N V E S T I G AT I O N S
23
24
R O A D T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T
25
R O A D T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T
26
T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T
27
T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T
28
T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T
309 Emission of gas and particles 309.2 Recommended air quality criteria
The recommended values for air quality
309.1 Impact analysis
determined by the Norwegian Pollution
The ventilation method in road tunnels
Control Authority are given in Table 3.1
can be decisive for the level of emission
and location of the emission points. In
309.3 Emissions through ventilation
connection with the zone plan, an impact
shafts
analysis is required of the tunnel ventila-
Where it is difficult to achieve the recom-
tion including the possible need for and
mended levels of air quality criteria
location of a ventilation tower, cleaning
through emission at the tunnel entrances,
plant, etc.
emission via a ventilation shaft is an alter-
In the impact analysis the level of air pol- native.
lution in the vicinity of housing is calcu- The dispersion of the emission from
lated based on the recommended criteria ventilation shafts is calculated with the aid
determined by the Norwegian Pollution of dispersion models used for chimneys.
Control Authority (SFT). Simultaneously, The ventilated air jet stream is directed
it should be ensured that the levels of vertically upwards. This implies that the
pollution defined in the Pollution Act pollution is lessened before reaching
covering local air pollution and noise are ground level.
not exceeded. The height and the dimensions of the
On the basis of the estimated concentra- shaft are determined by the air volume and
tion of pollution in the emission, the level demands for air quality at ground level. In
of pollution in the immediate vicinity must addition, consideration shall be made for
be evaluated. The term ‘concentration of noise emanating from the ventilation shaft
pollution’ implies a comparison of the (especially with high air speeds).
actual level with that of the recommended
air quality criteria as given by the 310 Cleansing tunnel air
Norwegian Pollution Control Authority. Today, equipment is available which
See Appendix A for an evaluation and enables tunnel air to be cleansed both of
calculation of air pollution for road tun- particles and NO2.
nels. The necessity of cleansing measures is
determined by the permitted concentra-
tion in the tunnel or the recommended air
quality criteria outside the tunnel.
Table 3.1 Recommended air quality criteria for air outside the tunnel
CO mg/m3 80 25 10
NO2 µg/m3 500 100 75 50
Airborne articles PM10 µg/m3 35
Airborne articles PM2,5 µg/m3 20
* The period of measurement is that for which the mean level of pollution shall be calculated.
From SFT-report no. 92:16 “Effects of air pollution on health and the environment. Recommended air quality criteria”.
29
R O A D T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T
Cleansing NO2
In order to clear the tunnel of NO2, a spe-
cial type of active carbon is used resulting
in up to 70% of the NO2 content in the tun-
nel air being removed. On account of the
restricted space, the cleaning equipment is
placed in a side-tunnel.
30