Manual 021

Norwegian Public Roads Norwegian Public Roads


Administration
Administration
Standard

The Manuals may be ordered from:

The Norwegian Public Roads

Administration Road Tunnels


Book Distribution

Box 8142, Dep.,

0033 Oslo, Norway

Tel.: + 47 22073500

Fax: + 47 22073768

E-mail: firmapost@vegvesen.no

ISBN 82-7207-540-7

03.04
Norwegian Public Roads
Administration

Road Tunnels

April 2004
Norwegian Public Roads Administration
Handbooks
This is one of a series of handbooks prepared and
issued by The Norwegian Public Roads
Administration - a collection of consecutetively
numbered books which primarily are written for
use within the Administration.

This English version is a translation of the


Norwegian one. In case of linguistic differences
between the two versions, the Norwegian version
is the valid one.

The books are for sale and may be ordered from


the Directorate of Public Roads at prices given in
the their book-list - Handbook no. 022.
Preparing and updating the books is a responsibi-
lity for the Directorate of Public Roads.

Graphic Division at the Administration is general-


ly responsible for designing and printing the
books.

The handbooks are issued on two levels:


Level 1: Red marks on the cover indicates
Regulations, Standards and Guidelines approved
by the authority responsible or The Directorate of
Public Roads with authorisation.

Level 2: Blue marks on the cover indicates


Instructions, Teaching Manuals and Road Data
approved by individual departments authorised
by the Directorate of Public Roads.

Road Tunnels
No. 021 in the series of handbooks
Design:Graphic Division NPRA
Issued: 1000 copies

Printed by: NPRA Printing Center

ISBN 82-7207-540-7

2
R O A D T U N N E L S P R E FA C E

Preface
The manuals pertaining to the Public the choice of solutions and technical
Roads Administration are given pursuant equipment is made on the basis of life-
to the regulations relating to the Roads Act expectancy where operation and mainte-
concerning highway construction. nance costs are evaluated.

This Design manual applies to all types of Compared to the 1992 edition, most chap-
road tunnels. The manual apply for new ters have been largely rewritten. A number
tunnels but do not apply retrospectively. of subjects which may be considered to fall
Initially, the manual shall apply in respect outside the manual material have been
of upgrading of safety aspects of existing included with regard to accessibility.
tunnels. Any deviation from the specifica- Reference is also made to other norms and
tions in the norm must be approved by the guidelines rather than these texts being
Directorate of Public Roads. copied here.

The manual replace those stated in the Work with revising the design manual was
edition of August 1992. undertaken in the period 1997 - 2001.
Regional offices, consultants, constructors
The manual cover all aspects of the plan- and others have made important contribu-
ning of a tunnel project, from the early tions.
planning stages to completion of the proj-
ect, together with operation and mainte- The Design Manual will be available on
nance. Tunnels comprise a considerable the Norwegian Public Roads
part of the highway network in Norway. Administration´s internet pages
Particular attention is given to the envi- www. vegvesen.no.
ronment relating to the requirements of
nature conservation and the urban envi-
ronment. The Directorate of Public Roads,
June 2003.
Tunnel construction implies long-term Responsible Department:
maintenance. It is important therefore that Road Development Department

3
4
ROAD TUNNELS CONTENTS

Contents
Contents 5

1. The Formal Basis for Planning Tunnels 11


101 A brief summary of relevant laws and regulations 11
102 Procedures according to the Planning and Building Act 12
102.1 General planning 12
102.2 Zone plan 14
102.3 The contruction process 16
102.31 Application and notification requirements in general for road projects 16
102.32 Further information on exceptions to contruction applications 17
102.33 Administrative processes for applications and notifications 18

2 Geological Investigations 21
201 Introduction 19
202 The preliminary plan 21
203 General plan 20
204 Zone plan 22
205 The Construction plan/Tendering 23
205.1 Supplementary geological investigations 23
205.2 Geological and geotechnical reports as a part of tendering 23
3 Consideration of the local environment 25
301 Introduction 25
302 Requirements and constraints 25
303 Registration and investigation programmes 25
304 Vibrations and building inspection 25
305. Requirements for water control 26
305.1 Water tightness criteria 26
305.2 Methods for meeting the sealing requirements. Organisation of the task 26
306 Temporary water effluent 27
306.1 General 25
306.2 Contents of the application 26
306.3 Control and supervision 28
307 Use of chemicals in tunnel construction 28
308 Permanent drainage 28
309 Emission of gas and particles 29
309.1 Impact analysis 29
309.2 Recommended air quality criteria 29
309.3 Emissions through ventilation shafts 29
310 Cleansing tunnel air 29
311 Noise in the proximity of the tunnel entrances 30

4 Geometric design 31
401 General 31
402 Selection of tunnel category 31
403 Tunnel cross-sections 32

5
ROAD TUNNELS CONTENTS

404 Verge area 38


405 Safety measures with dangerous side obstacles 38
406 Construction below the carriageway level. 38
407 The tunnel cross-section for concrete tunnels 39
408 Extension for lay-bys and niches 40
408.1 Design and location of emergency lay-bys and turning points 40
408.2 Niches for technical equipment 41
408.3 Extension in mountain tunnels in areas with convoy traffic 41
409 Interconnections 41
410 Single lane tunnels 42
411 Pedestrians and cyclists 42
412 Alignment 43
412.1 General 43
412.2 Design speeds 43
412.3 Horizontal curves/view 43
412.4 Vertical curves 44
412.5 Overtaking lanes 44
412.6 Vertical curve radius 45
413 Intersections 45
413.1 Intersections outside the tunnel entrance 45
413.2 Intersections inside the tunnel 46
413.21 General 46
413.22 Roundabouts 46
413.23 Exit and Entry slip roads - two-level junctions 47
413.24 T-junctions 48
414 Equipment, traffic signs and road marking 48
414.1 General 48
414.2 Equipment and traffic signs outside the tunnel 48
414.3 Traffic signs in the tunnel 50
414.4 Road marking and visibility 51

5 Aesthetics design of tunnels 53


501 The main objectives 53
502 The tunnel approach zone 53
502.1 General 53
502.2 Location 54
502.3 Design 56
502.31 Terrain and building constructions 56
502.32 Existing and new vegetation 56
502.33 Tunnel portals and other constructions 57
502.4 Vegetation and signs 59
503 The tunnel 59
503.1 General design 59
503.2 Line of the tunnel 59
503.3 Designing the tunnel space 60

6
ROAD TUNNELS CONTENTS

6 Traffic and fire safety 61


601 General 61
601.1 Existing tunnels 61
602 Safety equipment 62
602.1 Safety equipment in the various tunnel categories 62
602.2 Equipment specifications for tunnel safety equipment 65
602.201 Emergency power supply 65
602.202 Emergency escape route lighting 65
602.203 Emergency Exit signs 66
602.204 Emergency telephone 66
602.205 Fire extinguishers 67
602.206 Water for fire extinguishing 67
602.207 Flashing red stop signal 67
602.208 Remote-controlled barriers for tunnel closure 67
602.209 Changeable signs and lane signals 68
602.210 CCTV surveillance 69
602.211 Height barriers 69
602.3 Radio equipment 69
602.31 Communication equipment
602.32 Broadcasting equipment with “interruption facilities”.
602.33 Mobile telephones
603 Traffic control and incident detection 71
603.1 Means analysis 71
603.2 Main types of traffic control systems 72
603.21 Pre-programmed measures 72
603.3 Detection of incidents - technical solutions 73
603.31 Indirect detection 73
603.32 Direct detection 73
604 Warning of Road works 74
605 Fire protection 74
605.1 General 74
605.2 Fire load: specifications for constructions and equipment 74
606 Transport of hazardous goods 75
607 Emergency plans 76

7 The Workface, support, water and frost protection 77


701 Cuttings and the tunnel entrance 77
702 Work face assignments 77
702.1 Exploraty drilling 77
702.2 Pre-grouting 77
703 Support 78
703.1 General 78
703.2 Methods 79
704 Requirements for equipment and emergency plans for sub-sea tunnelling 79
705 Frost penetration in tunnels 79

7
ROAD TUNNELS CONTENTS

705.1 General 79
705.2 Frost penetration 80
706 Water and frost protection methods 80
706.1 General 80
706.2 Choice of construction 80
707 Frost protection with the aid of thermal doors 81
708 Portals 82

8 Drainage 83
801 General 83
802 The drainage system 83
803 Drainage trench 83
804 System for accumulation of washwater 84
805 Water reserves for fire emergencies 85
806 Pumping stations, pumping system 85

9 The sub-base and pavement 87


901 General 87
902 The formation level 87
903 Pavement without frost protection 87
903.1 Lower base course 87
903.2 The upper base course, binder and wearing course 88
904 Frost protected pavement 88
904.1 The frost protection layer 88
904.2 Insulation materials and cement-stabilised gravel (Cg) 88
904.3 The binder course and wearing course 89

10 Technical Equipment 91
1001 Specifications for technical equipment 91
1001.1 General requirements for electrical equipment 91
1001.2 Protection against corrosion of technical equipment 91
1001.3 Degree of armouring 91
1001.4 Cables 91
1001.5 Technical rooms 92
1002 Power supply 92
1003 Lighting 92
1003.1 General 92
1003.2 Lighting in the tunnel approach - adaptation luminance 92
1003.3 Lighting in the tunnel 93
1003.31 Lighting level (luminance) in the tunnel. Zone demarcation 93
1003.32 Lighting in lay-bys 94
1003.4 Distance between light fittings 94
1003.5 Light fittings 95
1003.6 Priority lighting / emergency lighting 95
1004 Ventilation 95

8
ROAD TUNNELS CONTENTS

1004.1 Air quality requirements in tunnels 95


1004.11 General 95
1004.12 Permitted concentration levels for carbon monoxide, nitrogen dioxide
and visibility pollution 95
1004.2 Mechanical longitudinal ventilation 95
1004.21 General 95
1004.22 Impulse ventilators 96
1004.23 Ventilators in ventilation shafts or side adits 96
1005 Fire ventilation 96

11 Operation and maintenance 99


1101 General 99
1102 Methods of maintenance 99
1102.1 General 99
1102.2 Calendar-based maintenance 99
1102.3 Operational-base maintenance 99
1102.4 Situation-based maintenance base on visual inspection 100
1102.5 Situation-based maintenance based on registration 100
1102.6 Experience from systematic maintenance 100
1103 Maintenance of constructions 100
1103.1 General 100
1103.2 Functional control 100
1103.3 Evaluation of condition (status reports) 101
1104 Maintenance of the pavement and drainage 101
1104.1 General 101
1104.2 Functional control 101
1104.3 Particular requirements 101
1105 Maintenance of technical installations 102
1105.1 General 102
1105.2 Maintenance manual 102
1105.3 Functional control 102
1105.4 Status reports 102
1106 Cleaning 102
1107 Winter maintenance 103

12 Documentation upon handover 105

Appendix A Evaluation and calculation of air pollution from


road tunnels 107

Appendix B Calculation of noise dispersion from road tunnels 111

Appendix C Ventilation 113


1. Calculation of air requirements 113
2. Calculation of required thrust for longitudinal ventilation 115

9
ROAD TUNNELS CONTENTS

Appendix D Calculation model for fire ventilation 119


Model for calculation of fan capacity for tunnels with a gradient 119
Ventilation data for tunnels with fires of 5 MW and 20 MW 119
Calculation of pressure contribution ∆p from natural wind and chimney effect 119
Applications and limitations 134
Designing the fan capacity 134
Calculated examples: 134

Appendix E Mean annual temperatures and frost levels 136

10
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

1. The Formal Basis for Planning


Tunnels
101 A brief summary of relevant laws Reference is also made to Chapter 3,
and regulations “Consideration of the local environment”.
The basic specifications relating to road
construction, including tunnels, are con- Act relating to water courses and ground-
tained in the “Plan- og bygningsloven” water
Planning and Building Act (PBA). A num- For highway construction which is includ-
ber of formal components are also gov- ed in the definition of water course meas-
erned by regulations including: ures in the Water Resources Act § 3, cer-
tain concessions may be necessary as
• Regulations to impact assesments, and determined in § 8. For example, conces-
• Regulations concerning procedures sion has to be given by the water resources
and control of the construction authority in order to “commence water
process.(SAK) course projects which may be detrimental
In addition to the requirements of the PBA to the public interest”. Initially, it is the
a number of other aspects of tunnel con- client who has to determine whether there
struction are required to be considered in is a responsibility to apply for concession.
accordance with other Acts. Those of par- Further, the Norwegian Water Resources
ticular importance are discussed below. and Energy Directorate(NVE) – may also
determine that concessions have to be
The Pollution Act applied for in respect of a specific con-
The Pollution Act applies to pollution aris- struction. The rights to, or control of
ing from the construction site activity as ground water, have to be granted by con-
well as pollution resulting from the actual cession where determined by the water
highway construction. course authority. As no regulations specify
Regarding pollution which may arise which type of construction is subject to
during the construction phase, dispensa- concession, it will largely be the responsi-
tion may be necessary from the relevant bility of the water course authority to
pollution authority (normally the County determine whether a concession has to be
Governor) according to §11 of the Act. It applied for in each individual project.
follows that consent is necessary, among Whether application has to be made for a
other things, for activity which breaches concession should be determined at an
that described as “normal pollution from early stage in the planning process, prefer-
temporary activity”. ably in connection with the general plan of
Permission may also be required for per- the highway project.
manent discharge into the atmosphere,
water or soil resulting from highway con- The Act relating to Historic Monuments
struction. Further, the Pollution Act § 9 Highway construction which comes into
also requires that ground levelling must be conflict with ancient monuments protect-
reported to the authorities as determined ed under §§ 15, 19 or 20 of the Historic
by the Ministry of the Environment, 3. Monuments Act will not be permitted until
April 1989. the Directorate for Cultural Heritage has
The necessity of obtaining permission granted dispensation or exception for con-
according to the Pollution Act should be servation. The status of specified monu-
clarified with the pollution authorities at ments (and the obligation to investigate
an early phase in planning, for example in this pursuant to § 9 in the Act) should be
connection with the approval of the princi- determined during the planning stage.
pal design of the highway construction.

11
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

The Nature Conservancy Act the Planning and Building Act and
Highway construction conflicting with Manual 054 “General planning”.
protected areas as defined by the Nature (The titles of the relevant documents are
Conservancy Act including areas of land- translated,but are issued only in
scape preservation, national parks, nature Norwegian). In general, when planning
reserves or significant geological features, projects which are subject to the Planning
will not be permitted without prior dispen- and Building Act contact should be made
sation being granted for the protected area at an early stage with the respective
as required by the Nature Conservancy authorities in order to obtain their opinion
Act (§ 23). Initially it is the government on the extent to which it may be necessary
which is the dispensation authority, but in to apply for dispensation for the projects
certain instances these powers are delegat- in addition to clarifying the provisions of
ed to the County Governor. the Planning and Building Act.

The Fire Protection Act 102 Procedures according to the


The Fire Protection Act applies to tunnels Planning and Building Act
in use and provides for the local fire pro- 102.1 General Planning
tection authority, among others, to deter- In the guidelines for planning state and
mine the necessary fire-protection meas- county roads according to the Planning
ures to be implemented (§ 25). Guidelines and Building Act (PBA), it is required that
for considering fire protection measures in the projected road shall comprise part of
road tunnels, approved jointly by the the general plan, either a municipal plan
Ministry of Local Government and the or a county plan. Detailed regulations for
Ministry of Transport ensure that fire safe- the administration of the municipal and
ty in new tunnels is determined in accor- county plans are given in the PBA,
dance with the Planning and Building Act. Chapters V and VI, particularly §§ 19-4
and 20-5.
Act relating to supervision of electrical In the initial phase of the general plan-
plant and equipment ning, a number of special reports may be
All electrical plant to be installed shall be required which may either be published as
in accordance with norms determined by separate reports or be incorporated in the
the Norwegian electro-technical commit- formal planning process.
tee (NEK 400), and the regulations relat- That part of the municipal plan which is
ing to low tension electrical installations. concerned with land-use for a specified
area will be legally binding as soon as it is
Other relevant Acts of significance for ratified (PBA § 20-6, No. 2). This implies
tunnel construction include: that there will not be opportunity to carry
• Harbour and Coastal Waters Act out measures which conflict with land-use
• Municipal Health Services Act already ratified and included in the plan,
• Game Management Act except under certain specified circum-
• Salmon and Inland Fisheries Act stances. A county plan is not legally bind-
• Reindeer Herding Act ing concerning land-use, but provides
• Cultivated Land Act guidelines for land-use both for municipal
• Forestry Act and state planning as well specific activi-
More information concerning these Acts is ties.
given in the Directorate of Public Road’s
information brochure Special Acts of rele- Plan content and reports
vance to road planning as determined by
Where the general plan provides the basis

12
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

for decisions on the choice of a road route • The influence areas or resources which
and highway standards, specifications are are preserved according to the Nature
included in the guidelines for national and Conservancy Act. Contact should be
county roads in the PBA (T-1057, Chap. made with the County Governor in
4.3). order to clarify whether the construc-
Preparation of the general plan will nor- tion conflicts with the conservation
mally require a number of fairly compre- order. The question of dispensation
hensive reports. In the guidelines, there from the conservation requirements
are, for example, requirements that the must be clarified before the plan is
costs of the various alternatives for the approved according to the Planning
parts of the municipal plan are prepared and Building Act.
within a margin of ± 25%. This necessi- • In the guidelines for fire protection in
tates geological investigations and reports tunnels it is stated that the Norwegian
which are designed to meet these require- Public Roads Administration in asso-
ments. (See Chapter 2 ) ciation with the local fire authorities
At an early stage in the preparation of undertake a general evaluation of fire
the general plan, a programme should to protection measures in the proposed
be prepared in association with the plan- tunnel. In general resolutions on safety
ning authorities to include the main ele- measures for tunnels is not included in
ments of the planning process. If an the principal design. Questions which
impact study is to be prepared as part of can have considerable significance for
the process, this will be included as a part the project’s total costs should, how-
of the design. ever, be clarified at his stage.
Certain aspects of tunnel construction
require to be specially evaluated or Structure of the Design
clarified during this planning stage of the Regarding the county plan, no further
tunnel, including: details are given in the Planning and
• Circumstances which may require Building Act as to how this plan shall be
approval according to the Pollution Act prepared. The guidelines are given in the
§ 11. “Guidelines for national and county roads
• Possible consequences for water cours according to the Planning and Building
es (including ground water). Act” (T-1057) published jointly by the
Clarification with the NVE is required Ministry of the Environment and the
where dispensation has to be sought in Ministry of Transport, and also in the
accordance with the Water Resources Ministry of the Environment’s guide
Act “Municipal Land-use Planning” (T-1382).
• Conflict with cultural monuments In Manual 054, specific examples are
which are automatically protected given of the presentation of route choices
and/or monuments included under the in accordance with the guidelines in the
Historic Monuments Act §§ 15, 19 and above documents.
20. Concerning roads which may con- If the tunnel is to impose restrictions on
flict with listed monuments and which existing land-use, this should be stated in
will require dispensa tion or exception the plan. This is important both for those
by the Director General for Cultural who will be affected by the project and to
Heritage the question of dispensation/- ensure better control by the Norwegian
exception must be taken up during Public Roads Administration such that
the general planning. measures are not commenced which may

13
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

be an obstacle to the plan, and that other more detailed information regarding the
measures are not permitted which may administrative process concerning impact
have unfortunate effects for the completed analyses. The Ministry of the Environment
project. In addition to the tunnel route on has also prepared a separate guide to inter-
the map being indicated as “… an impor- preting the criteria in the regulations.
tant link in the communications system”,
or as “..restricted areas..”, a description of 102.2 Zone Plan
the restrictions expected to be incurred by With the exception of minor projects, a
the tunnel project for activity on the sur- zone plan has to be prepared for all nation-
face should also be given. If these areas al and county road construction as laid
are “built-up areas” (for example housing down in the Planning and Building Act. A
development) or “agriculture, natural and zone plan shall always be made for tun-
recreation areas” where dispersed settle- nels. Similarly to the land-use plan in the
ment is permitted, then to a certain extent municipal plan, a zone plan is legally
these restrictions may be included in the binding as determined by the PBA § 31.
provisions of the plan. Regarding other A zone plan which has been approved,
land-use categories where the possibility provides the basis for expropriation as
for determining provisions is more limit- determined by the Highways Act § 50.
ed, the restrictions for the area above the The tunnel route shall be specified in the
tunnel are commented upon in the plan zone plan.
details.
Content
Impact studies in accordance with The requirements for zone plan is
Planning and Building Act. described in the guidelines for national
The Planning and Building Act (Chapter and county road plans according to the
VII-a) and accompanying regulations on Planning and Building Act.
impact studies contain more specific regu- The requirements in the guidelines are,
lations regarding the planning of the indi- among other things, that supplementary
vidual measures. It is assumed that the investigations shall be carried out.(See
impact study will be carried out according Chapter 2) The costs shall be calculated
to the regulations in coordination with the with a precision of ± 10 %. If a broader
evaluation of the first formal plan where range is required, the reason for this has to
the route or corridor is approved. be given.
Which measures shall be the subject of The legally binding design includes a
an impact analysis are given in the regula- map showing one or more objects of
tions. The client shall then prepare a note development. The fact that the zone plan is
proposing a programme of the impact legally binding implies that there will not
studies to be included in the report. On the be opportunity to carry out subsequent
basis of the proposal the Directorate of measures which conflict with land-use
Public Roads (in regard of trunk roads and approved by the plan, with the exception
new roads) or the planning authority (for that smaller adjustments may be made
other roads) shall determine that a pro- through a formal dispensation of the exist-
gramme be drawn up stating which reports ing plan, changes to the plan, or in con-
are to be prepared, and of the content of nection with a new general or zone plan.
the impact study which the client shall In the Ministry of the Environment’s
prepare. guide “Development plan. Building plans”
The Ministry of the Environment give (T-1381), detailed norms are given for

14
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

maps of development and building areas. that restrictions on the surface must be
A number of examples are included in the shown on the map and/or in the provi-
guidelines which provide directions sions. Examples of such restrictions are
preparations of the map and the accompa- the prohibition of specified construction
nying design measures. work, blasting or boring in the ground.
There are no special requirements in the Alternatively, it may be stated that any
law or regulations relating to the formula- work which may cause damage to the tun-
tion of zone plans for tunnels. In each indi- nel is prohibited, and that specific meas-
vidual case it must be determined which ures must be approved by the Public
aspects are required to be clarified in the Roads Administration.
design. The assumption that the zone plan shall
Based on the following, the design of the be the basis for acquiring land and rights
tunnel including the approach zones, to proceed with the construction and pro-
should be established: vide those affected with the best possible
• It is assumed that a detailed account of understanding of the consequences of the
fire-safety measures is included in the project require that any restrictions
preparation of the zone plan accord imposed are clearly described.
ing to “Guidelines for fire protection in
road tunnels”, Chap. 3.2. Some basic points concerning zone plans
• Exceptions to procedural handling of for tunnels:
tunnel construction are conditional • Regarding the tunnel construction it-
upon the location of the tunnel, the self together with the associated safety
design of the entrances and possible zone (assuming this is regulated) and
restrictions in use of the area above the the approach zones, the objectives
tunnel having been incorporated in the “Public traffic areas” as stated in the
design as outlined in the thematic guide PBA § 25, No. 3 is commonly used.
“Public road construction and building • Even though the tunnel might not have
projects” (Report HO-2/2000). any physical impact on the surface, it
In particular, the location of the tunnel would be appropriate to combine the
and restrictions for use of the area objectives of “public traffic areas” with
above the tunnel are most conveniently the regulations which is relevant to the
handled in the zone plan. area above the tunnel. Particularly
Other circumstances which will be signi- where it is necessary to impose restri-
ficant in determining the detail of the ctions on land-use above the tunnel, it
design in connection with development of will be proper to indicate the area cov
the tunnel area include: ered by such restrictions by combin-
• existing, planned and expected activity ing purposes, or by adopting other
on the surface or in the ground development objectives.
• the type of tunnel, rock cover and • Concerning the portal construction and
ground conditions concrete tunnels, the construction
• control of sealing measures carried out. phase will result in temporary upheaval
The plan must indicate the necessary pro- on the surface which will frequently
tective measures against activity which have broader consequences for the
can cause damage of the tunnel construc- landowners and those licensed to use
tion. Consideration should therefore be the area than the permanent restric
made as to whether a safety zone should tions. These circumstances should be
be defined around the tunnel. This implies clearly indicated in the zone plan.

15
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

This may be done, for example, by 102.3 The Construction Process


combining “public traffic area” with 102.31 Application and notification
the development objectives covering requirements in general for road projects
the future land-use of the surface area, According the Planning and Building Act
and the relationship between these two § 93, notification is required for all road
objectives is more precisely defined in projects. However, there are comprehen-
the design regulations. These regula- sive exceptions for public roads as defined
tions can, among other things, contain in “Regulations concerning procedures
a description of the effects during the and control of the contruction process” §§
construction period and rules relating 5 and 6. The exception to the general rule
to the preparation of – and restrictions of notification applies to all road projects
on – the area above the tunnel follow which are described in detail in the zone
ing the completion of construction. plan or construction plan as laid down in
• The plan should contain reference to the Planning and Building Act. Further,
temporary construction measures such public highway construction where the
as construction roads, temporary road Norwegian Public Roads Administration
diversions, construction plant areas, is the client is always exempted from the
deposition sites for waste (temporary regulations on liability and control.
and permanent), such that the plan The background for the exceptions
provides the basis for any necessary which apply to road construction where
expropriation associated with these the Norwegian Public Roads Administration
measures. is the client are as follows:
• All questions likely to arise associated • It is not necessary to conduct a new
with the environment should be de- evaluation of circumstances in con-
scribed in detail. If it has not been de- struction projects which are accounted
termined in any previous stage whether for in the previous plan.
the tunnel construction requires per- • The rights of consultation in respect of
mission or approval to be granted by planning affecting authorities, land-
special acts (for example, permission owners, those with rights of access
for run-off in respect of the Pollution and neighbours , shall be ensured
Act § 11, concession based on the during the process.
Water Resources Act etc.), an account • The regulations pertaining to the Roads
must be given in the zone plan. It is a Act and the experience and resources
requirement in the plan that an investi of the Norwegian Public Roads
gation is made into the effects that the Administration imply that this body
construction may have on monuments has the best assumptions for ensuring
automatically covered by the Historic road construction of a high technical
Monuments Act. standard.
• A detailed explanation of fire safety Work involving temporary or portable
measures shall be given as part of the buildings, constructions or plant is initial-
plan. ly subject to notification according to the
• The plan shall clearly determine Planning and Building Act. The regula-
whether expropriation of property is tions for notification do not, however,
necessary for the area above the tunnel apply to buildings, constructions, or instal-
where there is a thin rock cover and in lations on building or construction sites in
the case of concrete tunnels. the immediate vicinity of such sites.
Nevertheless, these shall not be placed

16
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

such that they are a hindrance to normal that the client supplies corresponding
public access or recreation area or in other information on the progress.
way are detrimental to the surroundings. In the thematic guide “Public road con-
Even though public road projects will be struction and building projects” (Report
largely exempt from building regulations, HO-2/2000), the requirements for admin-
a number of regulations will always apply. istrative procedures are described for a
See “Public road construction and build- large number of elements incorporated in
ing projects”: road construction. A summary of those
• § 74, no. 2 on aesthetics most relevant to tunnel construction are
• § 77 on construction procedures and included below, Those included under (A)
requirements for products used in con should be considered as elements for
struction which it is absolutely necessary that a
• § 92 on changes to or removing con detailed description is given, such that
structions demands are not made for application or
• Chapter XVIII on liabilities notification. Those listed under (B) are not
• Chapter IX on illegal contruction activ absolute requirements, but documentation
ity. should nevertheless be presented.
Reference is also made to Section 102.33
for processing of applications and notifi- “Tunnels
cations. (A) Exception from administrative con-
struction processes is dependent upon the
102.32 Further information on excep- location of the tunnel, the design of the
tions to construction applications tunnel portals and any restrictions in the
Where the road construction is not use of the area above the tunnel being
described in detail in the zone plan or con- determined in the planning process. Any
struction plan, an application must be restrictions in use of the area above the
made for the remaining details associated tunnel must be clearly stated in the provi-
with the project. As mentioned, the regula- sions of the plan. Further, reference must
tions on liability and control are not appli- be made to the necessary technical draw-
cable. ings which show the design of the portals
Where it is desired that the zone plan is and any other related building measures.
to be described in such detail as to exempt (B) Subsidiary information should be sup-
the road project from administrative pro- plied in the form of illustrations which
cedures, it is important to understand that provide the involved parties with an
this will result in less room for adjustment impression of the appearance of the tunnel
in later stages of the project and that this portals.
can result in the need for a new evaluation Reference is also made to “Guidelines
of the plan to include circumstances which for considering fire protection in road tun-
would have been sufficiently considered nels” of July 2000, issued jointly by the
in an initial administrative evaluation. Ministry of Transport and the Ministry of
Through the application or notification, Local Government. The guidelines have
residents and others in the vicinity will been prepared within the existing regula-
often be informed of the period of the tions and are based upon a draft from the
project and practical circumstances during Directorate for Fire and Electrical Safety
the construction period. For measures (DBE) and the Directorate of Public
which are exempt from construction Roads in association with the National
administrative procedures, it is assumed Office of Building Technology

17
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

Administration. The guidelines have been The requirements which nevertheless do


placed on the Internet by the Ministry of apply are indicated in SAK § 14.
Transport: Administrative procedures undertaken
http://www.odin.dep.no/sd/ in separate stages will apply only occa-
sionally for public road measures in so far
Concrete tunnels as Stage 2 of the administrative procedure
(A) Corresponding regulations apply to is essentially concerned with a clarifica-
concrete tunnels. In addition, the excep- tion of terms relating to liability and con-
tion to administrative procedures are on trol. It should thus be considered that
condition that the covering and use of the applications for public road construction
area above the tunnel having been speci- are considered in a single stage.
fied in the planning process. Resulting from the fact that highway
construction shall initially be considered
“Ventilation and electrical installations according the regulations relating to appli-
Ordinary ventilation and electrical instal- cations, the regulations relating to the
lations which are part of the road con- administrative process for notification in
struction, i.e. that they can be regarded as SAK Chapter IV are scarcely relevant for
road-technical installations, require nei- road construction. An exception to this
ther application or notification. would be that certain constructions could
This does not apply, however, to larger be considered according to the regulations
constructions such as ventilation shafts for notification. The administrative regu-
which are visible to neighbours. lations in §23 no. 2 will apply to these
(A) Where the location, design , choice of projects. Among other things this implies
material has been specified in the planning that notification to neighbours is not
process, there is no obligation to submit an required.
application.
Ventilation and electrical installations Summary of the process for handling
which are incorporated into buildings are applications and notifications
not included in the exceptions to adminis- It is emphasised that on account of the
trative evaluation.” exemption from the regulations on liabili-
A comparable review of other elements ty and control for public road construction
which may be relevant to road construc- where the Norwegian Public Roads
tion is given in Report HO-2/2000. Administration is the client, it will not be
necessary to complete those parts of the
102.33 Administrative processes for forms in the summary which related to
applications and notification these themes.
The regulations relating to applications
and notifications are given in the regula-
tions concerning procedures and control of
the construction process (SAK).
According to SAK § 5, the regulations on
liability and control do not apply where
the Norwegian Public Roads
Administration is the client. This also
means that the requirements of documen-
tation stipulated in §§ 14 and 15 do not
apply in respect of liability and control.

18
ROAD TUNNELS - THE FORMAL BASIS FOR PLANNING TUNNELS

Single stage administrative evaluation Notification


(Applies to temporary construction measures
Initial discussions which are subject to notification according to the
Planning and Building Act § 85)
(The need for discussion is determined in each
individual case) Initial discussions
Form NBR no. 5170 and no. 5169 Form NBR no. 5170 and no. 5169
Summary of initial discussions
Form NBR no. 5171
Summary of initial discussions
Advice to neighbours Form NBR no. 5171
Form NBR no. 5154 Advice to neighbours
Copy of Advice to neighbours Form NBR no. 5154
Form NBR no. 5155 Copy of Advice to neighbours
Form NBR no. 5155
Application to commence project
(Alt. application for individual measures) Notification of project
Form NBR no. 5151 Form no. NBR no. 5153

Permission for the project


Form NBR no. 5151

19
20
R O A D T U N N E L S G E O L O G I C A L I N V E S T I G AT I O N S

2 Geological Investigations

201 Introduction Tunnel projects extending under the sea


Modern road construction places special must be planned according to the require-
demands on geological investigations in ment of a minimum rock cover of 50 m.
connection with tunnel construction. The Special conditions apply to any deviation
investigations for tunnel projects shall from this (See Section 204).
provide an account of alternatives and As a minimum the investigation must
total costs together with a survey of condi- include:
tions relating to safety, the community, • Assembly and evaluation of existing
and the environment. Further details are information, geological and topo-
included in the Manuals 054 – graphic maps, and any reports from
“Development planning”, 140 – “Impact previous investigations.
analyses” and 151 – “Management of con- • Stereographical studies of air photo
struction projects”. graphs (Scale 1:15 000 – 1:30 000).
An important requirement, among oth- • Field investigations. Geological map
ers, is geological investigations which ping scale 1:5000.
comprise detailed geological mapping and • Evaluation of areas which may parti-
engineering geology. This is often supple- cularly be affected by the tunnel
mented by geotechnical, hydro-geological including drainage, subsidence,
and geophysical investigations. vibrations, runoff etc.
A rational and qualitative procedure • Maps which give a broad estimate of
requires that the investigation is carried the thickness of the soil cover
out systematically in stages and that the • Evaluation of uncertainty concerning
results are carefully evaluated before pro- the rock cover.
ceeding to the next stage. The extent of the The findings shall be summarised in a
investigations will depend upon the level report which includes:
of the specific plan. • A summary of the local geology, a
The procedure and reports associated description of structural geological and
with the investigations shall be carried out hydrogeological conditions of signi-
such that the data from one planning phase ficance for the feasibility of the project
may be satisfactorily transferred to the together with alternatives
next. The nature and extent of the investi- • Summary of areas which require
gations must be considered in relation to special measures in connection with
the actual projects in hand. (See also the project
Section 702 “Working face assignments”). • Feasibility study
• Suggestions for further investigations.
202 The preliminary plan
The investigations at this stage shall pro- 203 General plan (county plan/munici-
vide the basis for an evaluation whether pal plan)
the geological conditions are such that the An investigation at this level shall provide
project may be carried out. It is particular- the geological basis for the selection of the
ly important to obtain an impression of the road route.
regional geology. The following studies This investigation will be based on the
should be included: investigations from the previous planning
• Locate suitable tunnel routes phase and as a minimum will include:
• Mapping of those areas which may • Air photo studies based on stereoscop
be critical for costs and safety, and the ic photos /Scale 1:6000 - 1:15 000)
feasibility of alternative tunnel stretches collated with topographic maps

21
T U N N E L S G E O L O G I C A L I N V E S T I G AT I O N S

(scale 1:1000 – 1:5000). These maps ensure that the technical solutions pro-
will be used to determine the distribu posed may be implemented and that these
tion of soils and rock, weakness zones provide the basis for quantitative esti-
and the orientation of faults and joints. mates.
• Field and site investigations. Following the completion of the inves-
The investigations and evaluations tigations a report is prepared in sufficient
shall include the following: detail as is required for the plan.
- Soil cover. Type and thickness. A distinction has to be made between
Water depth for sub sea tunnels. measurements, actual observations and
- Rock type and boundaries interpretations.
For sub-sea tunnels rock types on
both sides of the fjord or sound 204 The Zone Plan
should be stated. The need for supplementary investigations
- Bedding and foliation made in connection with the general plan
- Joint orientation and frequency must be considered.
- Weakness zones The purpose of the evaluations at this
- Rock cover stage are :
- Hydrological and hydrogeological • To establish the geological basis for
registration: cost estimates
• Measuring programme for • Report the degree of uncertainty in
groundwater level and pore pres- the investigation results and the conse
sure where necessary, including quences of this for cost estimates
registration of water reservoirs The impact of the tunnel in the neighbour-
and marsh areas together with ing district must be examined and evaluat-
seasonal variation for these ed in detail.
• Sensitivity with regard to flora
and fauna The following must be carried out:
• Registration of areas liable to • A scrutiny of the results of previous
subsidence investigations
• Requirements for control of • Planning and execution of supplemen
leakage into the various tary investigations together with a
sections of the tunnel verification of previous conclusions
- Quality of rock material with a • Vibrations
view to possible use in road con- The limits for permitted vibrations
struction within the area of influence are deter
- Investigation for dumping sites mined and a measurement programme
- Tunnel entrance site alternatives, prepared for follow-up. Plan for build
cuttings, danger of rockslides ing inspection, registration of settle-
- Need for core drilling ments and damage and the time when
- Need for seismological investiga- this shall be carried out is to be deter-
tions mined.
If measurements are to be taken of the sta- • Groundwater, pore pressure and settle
tus of the water table and pore pressure, ment. Using investigations undertaken
frequent measuring should be taken to as part of the general plan an eva-
document natural variations over time (for luation must be made of possible dam
example, at monthly intervals). age arising and necessary protective
The investigations undertaken shall measures. Consideration must be made

22
T U N N E L S G E O L O G I C A L I N V E S T I G AT I O N S

as to whether concession must be 205.2 Geological and geo-technical


applied for in respect of water, reports as a part of tendering
drainage, etc. as an alternative to com A separate report shall be prepared for
prehensive water tightning measures. submission of tenders on the basis of the
investigations conducted. The report is
Reports are required for the following: specially formulated for tendering in so far
- areas of influence as job descriptions associated with seal-
- investigation of the thickness and ing, building, safety measures, completion
potential for settlement of sedi etc. are considered elsewhere in the tender
ments basis.
- registration of conditions for the The report shall provide the constructor
fundament for constructions with a basis for his own evaluations and
- determination of permitted leakage interpretations of the geological condi-
along the tunnel route tions.
- evaluation of necessary measures to
meet demands for leakage control. The report shall therefore include:
Special conditions relating to sub-sea tun- • A description of geological, hydro-
nels include: geological and geotechnical conditions
A rock cover of less than 50 m can only along the tunnel route
be accepted where it is well documented • Maps and longitudinal profiles which
that the rock mass conditions are show the occurrences of rock type,
favourable. A cover of less than 50 m must weakness zones and the rock cover.
be approved by the Directorate of Public It shall be stated whether these are
Roads. based on investigations, observations
or interpretations
Reports • Analysis of joints, frequency and
Special reports are required in connection direction
with preparation of the zone plan. • Summary of calibrations from the
detailed analyses. Reference to other
205 The Construction Plan/Tendering reports where further data is given
Complete construction plans shall be pre- • Particular local circumstances to which
pared such that these can be used as a special attention is drawn (e.g. water
basis for tenders. wells)
• Reference list. Reports in the reference
205.1 Supplementary geological investi- list shall be available for consultation
gations if required.
It may be appropriate to prepare supple-
mentary investigations in order to confirm
quantity estimated, or following other cir-
cumstances which emerge during the
course of the project, for example details
around the tunnel portals/cuttings which
are essential for openings.
Further, it may be necessary to adjust the
extent of registration and control planned
in the vicinity as a result of measurements
obtained.

23
24
R O A D T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T

3 Consideration of the local environment

301 Introduction • measurement for documentation of


It is the client’s responsibility to carry out water leakage in the tunnel in the light
an evaluation of risks to the environment of specified requirements.
and to ensure that the project proceeds • the quality of runoff water from the
with full regard to relevant laws and reg- tunnel following cleaning
ulations. • follow-up of water quality in the recip
ient area
With regard to the landscape, aesthetical
• noise measurements with a view to
values and so forth, reference is made to
documenting compliance with regu-
Chapter 5 “Aesthetic design of tunnels”
lations
These measurements are to provide the
302 Requirements and constraints
basis for a detailed investigation and
The construction shall be carried out such
measurement programme. It must be
that those regulations governing prepara-
determined who is to undertake the vari-
tion of plans and their approval shall be
ous investigations.
complied with.
Responsibility will be divided between
These requirements include, among oth- the client and the contractor:
ers, the following:
• settlements, vibrations, air shock, Client’s responsibility:
noise, dust • determine the necessary restrictions
• the natural environment, hydrologic and demands
balance • property inspection
• assumptions included in the approved • monitoring and follow-up programmes
plans (particularly the zone plan) • damage adjustment
• applications and reporting require
ments in accordance with the Planning Contractor’s responsibility:
and Building Act and other laws and • implementation according to the regu-
regulations lations
• Constraints of working hours • measurements which are specified as
• Neighbour contact and information. the responsibility of the contractor
• damage liability where the regulations
303 Registration and investigation have not been complied with.
programmes
On the basis of the investigations which 304 Vibrationrestrictions and building
have been carried out, an evaluation of inspection
the material to be registered and the Limitations have to be determined for
accompanying investigations has to be vibrations resulting from blasting. One
made to ensure completion of the project. method for determining this is given in
This will include, among other things: the Norwegian Standards publication NS
8141
• The need for, and extent of, building The limits are determined such that
inspection possible damage may be avoided.
• programme for measurement of Normally these values are determined
vibrations. such that they apply to the fundament or
• the need for registration and control the load-bearing construction in proximi-
of ground settlements. ty of the fundament.
• the need to register the ground-water The possible danger for disturbances/-
level (see section 203) settlements resulting from activities lead-

25
R O A D T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T

ing to vibrations shall be particularly (See Chap. 2, Geological Investigations”).


evaluated. This also applies to possible On the basis of these it should be
damage to sensitive inventory, computer determined whether specifications should
installations etc, and also the possible be made regarding maximum allowable
inconvenience to neighbours. The limits leakage into the tunnel. These may vary
apply to the maximum permissible peak along the tunnel route dependent upon
particle velocity given as mm/sec., and the conditions of the influence zone, set-
which are determined on the basis of the tlement conditions and the risk of damage
following: to the surrounding area.
• ground conditions where the construc-
tion is located 305.2 Methods for meeting the sealing
• the type of construction and the quality requirements. Organisation of the task
of building materials used If demands for sealing are determined for
• method by which the fundament is pre the whole or part of the tunnel, there are
pared number of circumstances which must be
• distance from the blast continually followed up in order to ascer-
• type of vibration (blasting, demolition, tain that these demands are complied with.
piling, etc.) Pre-grouting ahead of face is a normal
method of water control during tunnel
Special ground conditions, at distances of construction.
less than 5 m and other special circum- Post-grouting can easily result in poor
stances may require separate risk-analy- results as there are limitations on the pres-
ses. sure that may be applied and the grout
Inspection and registration of buildings material may easily return into the tunnel.
are to be undertaken in the presence of the If there is a danger that the water tight-
owner and conducted by an independent ness requirements cannot be met by sys-
specialist. The description should be sup- tematic pre-grouting methods, the relevant
plemented by photographs or video film. parts of the tunnel must then be sealed
In areas where specified limits have been with a membrane-isolated concrete con-
determined, vibration measurements struction designed to withstand the actual
should always be undertaken. The guide- water pressure. Preparation must be made
lines in NS 8141 state the required specifi- for this, for example in the design of the
cations of the investigation equipment and tunnel cross-section during construction.
how the vibration should be measured and Water injection from the surface or from
reported. The measurements should the tunnel can contribute to maintaining
ensure the necessary documentation and the groundwater and the pore pressure
provide the basis for continual adjustment during the construction periods. The effect
of the salvo. of water injection is, however, difficult to
predict. Water injection also requires con-
305 Requirements for water control tinual supervision and maintenance. The
method is consequently only exceptional-
305.1 Water tightness criteria
ly employed as a permanent measure.
The investigations and evaluation of the
In order to be able to carry out pre-
consequences for the environment result-
grouting based on systematic probe
ing from leakage in the tunnels should be
drilling criteria as to critical amount of
made as part of the geological investiga-
leakage from the probes must be deter-
tions.
mined.

26
T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T

In order that the need for grouting shall Environmental Department.


be precisely determined, the number of Smaller installations in categories A and B
probes should be carefully calculated. In may be handled by the municipality. These
the initial phase the number should be are defined as installations serving a max-
increased to above that which is normally imum of 25 persons or equivalent.
determined as necessary. Effluent resulting from chemical injec-
In addition careful consideration should tions must be considered separately.
be made of those circumstances which
could influence the content and perform- 306.2 Contents of the application
ance of the grouting work such that unex- Information about the applicant
pected consequences are avoided. These The applicant must be registered.
include circumstances such as: Normally this will be the client. If
• measurement of leakage in the tunnel. another is to be the registered appli-
This is carried out by measuring the cant (e.g. the constructor) this must
total leakage from the tunnel and over be agreed with the County
sections Governor’s Environmental Depart-
• measurement of ground water level, ment in advance.
pore water pressure and ground settle
ments Information about the project
• registration of the water level in A description of the project with esti-
streams and marshes mates of the extent and duration. In
• water seepage in injection wells. addition the rigging areas, waste tips
All the information assembled shall be etc., should be indicated. Any neces-
considered in total. sary maps should be attached.

306 Temporary water effluent The application coverage


The various forms of effluent and
306.1 General
estimated extent, water volume and
Permission must be applied for temporary
quality should be described.
effluent resulting for the construction
Regarding runoff and drainage from
work.
operations estimates should be given
The various forms of effluent may be clas-
of the suspended material, nitrogen
sified as follows:
from explosives and pH following
the use of cement products.
Category A:
Discharge from sanitation in connection
Description of the recipient
with workman’s sheds, offices etc.
Description of the water quality and
water volume throughout the year
Category B:
for the recipient.
Discharge from workshops and washing
places
Cleansing
-The planned cleansing plants shall
CategoryC:
be described.
Discharge from operations during tunnel
-Measures for effluent from work-
construction.
shops and washing places are
The application for temporary discharge is
designed according to “Regulations
considered by the County Governor’s

27
T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T

relating to discharge of oil-con- The product information shall include,


taining water”. among other things, the chemical compo-
-Measures for sanitation drainage sition, risks to health and the environ-
are designed according to ment, and preventive measures.
“Regulations on discharge from
Procedures for acquiring of chemicals
separate drainage systems”.
which are a health and environmental haz-
-Run-off from operations and
ard are given in Manual 214, “Health,
drainage from tunnelling. The
environment and safety”.
normal cleansing methods will be
The conditions in the recipient shall be
use of oil separators and sediment
registered with regard to water mass, and
basin. With particularly sensitive
on the basis of this the appropriate dilution
recipients, further cleansing may
shall be calculated. Further, user-interests,
be made by sand filters.
biological circumstances etc. of the recip-
ient shall be registered.
Evaluation of the effluent (consequences
An evaluation of the environmental haz-
for the environment)
ard resulting from the use of these materi-
A summary is to be given of the user
als shall be undertaken by qualified per-
interests for the recipient together
sonnel.
with an evaluation of possible effects
If the environmental hazard is consid-
of the discharge.
ered to be such that there is a danger of
pollution, the client shall ensure that the
Other information:
necessary dispensation is obtained for the
The following shall be referred to in
pollution control authorities.
the application:
- seepage from mass rock waste sites
308 Permanent drainage
- routines for depositing sludge and
An application for permanent drainage of
oil from the oil separators
water is not required.
- safety measures for oil and fuel
deposits. When planning the tunnel consideration
has to be made to those assumptions
306.3 Control and supervision which apply to cleaning as a part of oper-
A programme for supervision of the water ations and maintenance.
quality of drainage water following As a general rule the washing frequency
cleansing is normally required together should be planned such that special meas-
with a follow-up of the water quality in the ures are not required to accumulate wash-
recipient. ing water outside the tunnel.
A proposal should accompany the appli- For tunnels where long intervals
cation for a control and supervision pro- between washing occur, or where the vol-
gramme aimed at ensuring that the cleans- ume of traffic is particularly heavy, con-
ing units function as anticipated. sideration should be made as to whether
the washing water can be so polluted that
a special drainage system outside the tun-
307 Use of chemicals in tunnel con-
nel is required such that water which may
struction
be an environmental hazard can be man-
Use of chemical injection products or
aged.
other chemicals obliges the producer,
importer and/or supplier of such material
to prepare and provide documentation.

28
T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T

309 Emission of gas and particles 309.2 Recommended air quality criteria
The recommended values for air quality
309.1 Impact analysis
determined by the Norwegian Pollution
The ventilation method in road tunnels
Control Authority are given in Table 3.1
can be decisive for the level of emission
and location of the emission points. In
309.3 Emissions through ventilation
connection with the zone plan, an impact
shafts
analysis is required of the tunnel ventila-
Where it is difficult to achieve the recom-
tion including the possible need for and
mended levels of air quality criteria
location of a ventilation tower, cleaning
through emission at the tunnel entrances,
plant, etc.
emission via a ventilation shaft is an alter-
In the impact analysis the level of air pol- native.
lution in the vicinity of housing is calcu- The dispersion of the emission from
lated based on the recommended criteria ventilation shafts is calculated with the aid
determined by the Norwegian Pollution of dispersion models used for chimneys.
Control Authority (SFT). Simultaneously, The ventilated air jet stream is directed
it should be ensured that the levels of vertically upwards. This implies that the
pollution defined in the Pollution Act pollution is lessened before reaching
covering local air pollution and noise are ground level.
not exceeded. The height and the dimensions of the
On the basis of the estimated concentra- shaft are determined by the air volume and
tion of pollution in the emission, the level demands for air quality at ground level. In
of pollution in the immediate vicinity must addition, consideration shall be made for
be evaluated. The term ‘concentration of noise emanating from the ventilation shaft
pollution’ implies a comparison of the (especially with high air speeds).
actual level with that of the recommended
air quality criteria as given by the 310 Cleansing tunnel air
Norwegian Pollution Control Authority. Today, equipment is available which
See Appendix A for an evaluation and enables tunnel air to be cleansed both of
calculation of air pollution for road tun- particles and NO2.
nels. The necessity of cleansing measures is
determined by the permitted concentra-
tion in the tunnel or the recommended air
quality criteria outside the tunnel.

Table 3.1 Recommended air quality criteria for air outside the tunnel

Marginal values Unit of measurement Period of measurement*


C 15 min. 1 hour 8 hours 24 hours 6 months

CO mg/m3 80 25 10
NO2 µg/m3 500 100 75 50
Airborne articles PM10 µg/m3 35
Airborne articles PM2,5 µg/m3 20

* The period of measurement is that for which the mean level of pollution shall be calculated.
From SFT-report no. 92:16 “Effects of air pollution on health and the environment. Recommended air quality criteria”.

29
R O A D T U N N E L S C O N S I D E R AT I O N O F T H E L O C A L E N V I R O N M E N T

If a ventilation solution is planned which account of the reflecting surfaces. In addi-


includes cleansing measures, this has to be tion to the distance, the length of the tun-
approved by the Norwegian Public Roads nel and the gradient of the roadway in the
Administration. tunnel entrance will also be factors in
determining the noise level. A higher gra-
Cleansing particles dient will result in a higher noise level on
On order to clean the tunnel air of parti- account of acceleration.
cles, an electrostatic filter may be The Ministry of the Environment
employed. This technology enables defines the noise limits for new construc-
80–95% of particles to the removed from tions. The pollution limits prescribed in
tunnel air which goes through the filter the provisions of the Pollution Act con-
and which is bound to special particle cerning local air pollution are required to
fractions. be complied with for existing roads.
In order to attain the greatest efficiency A simplified method for calculation of
the design and planning shall be adapted noise levels from road tunnels has been
to the actual tunnel. prepared and which is designed to evalu-
Electrostatic filters for cleansing parti- ate the need for counter-measures. This is
cles can be installed in side tunnels as an illustrated in Appendix B. The method
overlying installation, or included in the shows the calculated noise level from the
ventilation shaft. tunnel entrance. When aggregated with the
The risk of an explosion is present in the noise level outside the tunnel, this shows
event of a major leakage of heavy, inflam- the total noise level at any point. When
mable gases/fluids. When mounted in a this is compared to other guidelines, it is
side tunnel a raised skirt at the entrance to then possible to determine whether meas-
the bypass is recommended in order to ures are required for noise reduction.
divert the gases.

Cleansing NO2
In order to clear the tunnel of NO2, a spe-
cial type of active carbon is used resulting
in up to 70% of the NO2 content in the tun-
nel air being removed. On account of the
restricted space, the cleaning equipment is
placed in a side-tunnel.

311 Noise in the proximity of the tunnel


entrances
Two levels of noise exist in proximity to
the tunnel entrances:
• noise from the open road in the tun-
nel approach
• noise emanating from the tunnel itself.
Inside the tunnel, a higher noise level is
generated than that of the open road on

30