DAILY PROGRESS REPORT

Project Name: 66 KV SUBSTATION PROJECTS – ESKAN SANAD PROJECT


Consultant: ESB INTERNATIONAL DR Ref No:
Contractor: AL FANAR CONSTRUCTION Date: 24.09.2020
TO: ESB INTERNATIONAL ATTENTION: Mr. RAJ MOHAN
o
Daily Report (Date / Day): 24.09.2020/Thursday Temperature: 39 - 31 C Temperature: 39 - 31o C

Sub. Qty.
SI. Main M/ T/ Plant & Qty.
Manpower Cont @ Total Remarks
NO. Cont. Hrs Hrs Equipment Used
. Site
M-01 Project Director E-01 JCB
M-02 Construction Director E-02 Roller 25 Ton
M-03 Project Manager 1 10 10 Air Compressor
M-04 QA/QC Manager E-03 Back hoe
M-05 Senior / Safety Officer 1 1 10 20 E-04 Grader
M-06 QA/QC Engineer E-05 Bulldozer
M-07 Project Engineer 1 1 10 20 E-06 Excavator/Vibrio 1
M-08 Planning Engineer E-07 Hand Roller
M-09 Quantity Surveyor E-08 Plate Compactor 1
M-10 MEP Engineer E-09 Loader
M-11 Draftsman E-10 Jumping Compactor 1
Total-11
S-01 General Foreman 1 10 10 A-01 Paver
S-02 Foreman A-02 Pneumatic Roller
S-03 Charge Hand 1 10 20 A-03 Roller 2 Ton
S-04 MEP Inspector A-04 Bobcat
S-05 Safety Foreman A-05 Asphalt Cutter
S-06 Surveyor 1 10 10
Total-3
DL-01 Mason-General / Tiles 1 10 10 M-01 Dump truck
DL-02 Molder / Carpenter 10 M-02 Trailer
DL-03 Carpenter-Finishes M-03 Water Bowser
DL-04 Steel Fixer 10 M-04 Trucks
DL-05 Painter /Abdul Nabi
DL-06 Labor (Skilled / Unskilled) 1 10 10 G-01 Concrete Mixer
Surveyor Helper/Al
DL-07 G-02 Generator
Yousuf
DL-08 Operator 1 10 10 G-03 Pick -up
DL-09 Scaffold G-04 Water Pumps 1
DL-10 Welder/Mechanic G-05 Block Cutter
DL-11 Waterproofing / Bayanco G-06 Tower light
DL-12 Electrician/ Plumber 1 10 10 G-07 Water Tank 3
Total-36 G-08 Dewatering Pump
L-01 Drivers 1 1 10 20
Store Keeper & Time
L-02 1 1 10 20 L-01 Mobile Crane
Keeper
L-03 Office Boy 1 10 10 L-02 Tower Crane
L-04 Watchman 1 10 10 L-03 Hi-Up
L-05 Safety assistant L-04 Boom JCB
L-06 Banks man/Rigger L-05 Forklift
Toatal-1
MEP - SUBCONTRACTORS
Electrical Project Engineer
Electricians
Helper - Electricians
Mechanical AC Duct Work
Plumbers
Total-
Grand Total 7 15 190 Total 7

TOTAL MAN HOURS 620

AL FANAR COMPANY
Controlled Document Rev 1
Page 1 of 3
DAILY PROGRESS REPORT

Daily Report (Date / Day: 24.09.2020 /Thursday


Weather: Sunny / Drizzling / Rain / Wind Temperature:39 - 31o C Time Elapsed: 10.00 Hrs.

LOCATION PLANNED ACTIVITY TODAY ACTIVITY


Main building-Basement
Excavation works Backfilling started in main building
Floor
200mm boulder filled and compacted, prior
Transformer bay Excavation works
to fill type B filling

TOMORROW PLANNED ACTIVITY

Main building-Basement Floor Backfilling continue


Transformer bay Backfilling continue

Contractor’s Authorized Signature:

Prepared By:
Name: Sakthi Elangovan Signature: Date: 24.09.2020
For Consultant:
Comments:

Received By:
Name: RAJ MOHAN– ESBI ENGINEER
Signature: Date:

AL FANAR COMPANY
Controlled Document Rev 1
Page 2 of 3
DAILY PROGRESS REPORT

Site progress Photos.

Main building-backfilling works Main building-backfilling works

Transformer bay-boulders filling Transformer bay-boulders filling

AL FANAR COMPANY
Controlled Document Rev 1
Page 3 of 3