CPM
CPM ASSIGNMENT # 06
.
Find the probability that the project will finish
1. by the end of day 26
2. before the start of day 25
3. during the day 24
PERT
4. find the date of completion with at least 93 percent confidence.
Solution
Critical
Submitted To:
Act. Ta tm tb te σte vte
A Sir Liaqat 6Ali Qureshi
6 6 6 0 0
D 2 5 8 5 1 1
Submitted By:
E 2 3 7 3.5 0.83 0.69
F 6 8 10 8 0.67 0.45
MALIK SALMAN AHSAN
I 2 2 5 2.5 0.5 0.25
06-CE-76
Total 25 2.39
TE & σTE
TE = ∑ te = 25
σTE = √ ∑ν = √ 2.39 = 1.55
By the end of day 26
Z-26 = (Ts - TE) /σTE
= 26 - 25 / 1.55
= 0.65
P-26 = 0.75= 75 %
Before the start of day 25
(by the end of day 24)
Z-24 = (Ts - TE) /σTE
= 24 - 25 / 1.55
= -0.65
P-24 = 0.26= 26 % Civil Engineering Department
during the day 24
University of Engineering & Technology
It is equivalent to Taxila
“By the end of day 24 - By the end of day 23”
Z-24 = (Ts - TE) /σTE = 24 - 25 / 1.55 = -.65
P-24 = 0.26= 26 %
Z-23 = (Ts - TE) /σTE = 23 - 25 / 1.55 = -1.29
P-23 = 10%
P24 = P-24 - P-23 =26%-10%=16%
P = 93 %
Z = 1.5 (from table)
Z = (Ts - TE) /σTE
1.5 = (Ts - 25) / 1.55
Ts = 27.325
Therefore, the completion date = end of day 28 with at least 93.5 confidence.
PRACTICE PROBLEM-2
Critical
Act. ta tm tb te σte vte
A 1 3 5 3 0.67 0.45
C. 1 1 4 1.5 0.5 0.25
E 2 4 6 4 1.5 0.45
F 2 3 7 3.5 2.5 0.69
H 3 3 9 4 3.5 1
Total 16 2.8561
TE & σTE
TE = ∑ te = 16
σTE = √ ∑ν = √ 2.86 = 1.69
at least 2 days earlier
(It is equivalent to “By the end of day 14)
Z-14 = (Ts - TE) /σTE = 14 - 16 / 1.69 = -1.18
P-14 = 12 %
no more than 1 day earlier
(It is equivalent to “After the end of day 15)
Z-15 = (Ts - TE) /σTE = 15 - 16 / 1.69 = -0.59
P-15 = 27%
So , P15- = 100-27=73 %
On TE
(It is equivalent to “During day 16”)
It is equivalent to
“By the end of day 15 - By the end of day 13”
P13,14,15 = P-15 - P-12
= 27 - 1
= 9%
before the start of day 18
by the end of day 17
Z-17 = (Ts - TE) /σTE = 17 - 16 / 1.69 = 0.59
P-17 = 73%
Find the date of completion with at least 83 percent confidence.
P = 83 %
Z = 0.95 (from table)
Z = (Ts - TE) /σTE
1.5 = (Ts - 16) / 1.69
Ts = 17.6
PRACTICE PROBLEM-2
Fill in the given tables and answer questions and determine
TE
σTE
Find the probability that the project will finish
1. by the end of day 69
2. on day 66
3. before the start of day 67
4. Find the date of completion with at least 98 % completion
Solution
Critical
Act. ta tm tb te σte vte
B 8 10 12 10 0.67 0.45
D 11 11 15 11.67 0.67 0.45
F 4 9 11 8.5 1.17 1.37
G 5 5 7 5.33 0.33 0.11
I 8 8 8 8 0 0
K 7 9 11 9 0.67 0.45
L 5 8 8 7.5 0.5 0.25
M 7 8 9 8 0.33 0.11
Total 68 3.19
TE & σTE
TE = ∑ te = 68
σTE = √ ∑ν = √ 3.19 = 1.79
on day 66
Duration day 66
P = 98 %
Z = 2 (from table)
Z = (Ts - TE) /σTE
2 = (Ts - 16) / 1.79
Ts = 68.59 or day 69
SUPPLEMENTRY PROBLEM-1
Fill in the given tables and answer questions and determine
TE
σTE
Find the probability that the project will finish
1. By the end of day 33
2. before the start of day 32
3. during day 31
4. Find the date of completion with at least 80 % completion
Solution
Critical
Act. ta tm tb te σte vte
B 6 8 10 8 0.666667 0.81
C 7 7 7 7 0 0
G 5 5 8 5.5 0.5 0.707107
H 3 6 9 6 1 1
J 3 6 6 5.5 0.5 0.707107
Total 32 3.224214
TE & σTE
TE = ∑ te = 32
σTE = √ ∑ν = √ 3.22 = 1.79
By the end of day 33
Z-33 = (Ts - TE) /σTE = 33 - 32 / 1.79 = .56
P-33 = 71 %
before the start of day 32
by the end of day 31
Z-31 = (Ts - TE) /σTE = 31 - 32 / 1.79 = -.56
P-31 = 31 %
during day 31
Z-31 = (Ts - TE) /σTE = 31 - 32 / 1.79 = -.56
P-31 = 31 %
Z-30 = (Ts - TE) /σTE = 30 - 32 / 1.79 = -1.12
P-30 = 14 %
P31 = 31%-14%=17 %
Find the date of completion with at least 80 % completion
P = 80 %
Z = 0.9 (from table)
Z = (Ts - TE) /σTE
.9 = (Ts - 68) / 1.79
Ts = 69.6 or day 70
SUPPLEMENTRY PROBLEM-2
Fill in the given tables and answer questions and determine
TE
σTE
Find the probability that the project will finish
1. at least 2 days early
2. no more than 1 day early
3. on TE
4. on days 23,24 or 25
5. Find the date of completion with at least 93 % completion
Solution
Critical
Act. ta tm tb te σte vte
B 3 6 9 6 1 1
D 2 3 7 3.5 0.833333 0.912871
F 3 3 9 4 1 1
H 6 8 10 8 0.666667 0.816497
J 1 3 8 3.5 1.166667 1.080123
Total 25 4.809491
TE & σTE
TE = ∑ te = 25
σTE = √ ∑ν = √ 4.81 = 2.19
At least 2 days early
(It is equivalent to “By the end of day 23)
SUPPLEMENTRY PROBLEM-3
Fill in the given tables and answer questions and determine
TE
σTE
Find the probability that the project will finish
1. by the end of day 58
2. on day 55
3. before the start of day 56
4. Find the date of completion with at least 98 % completion
Solution
Critical
Act. ta tm tb te σte vte
A 5 6 7 6 0.333333 0.57735
B 3 5 7 5 0.666667 0.816497
E 8 9 13 9.5 0.833333 0.912871
F 1 4 4 3.5 0.5 0.707107
I 6 6 6 6 0 0
J 5 7 9 7 0.666667 0.816497
M 9 10 14 10.5 0.833333 0.912871
N 8 8 11 8.5 0.5 0.707107
Total 56 5.450299
TE & σTE
TE = ∑ te = 56
σTE = √ ∑ν = √ 5.45 = 2.33