You are on page 1of 8

PROBLEM 1:

Limit = 9 Workers/Day

Workdays
Req. Crew size
Normal
Act worker
duration Norma
days Minimum 1 2 3 4 5 6 7 8 9 10 11 12
l
A 3 15 5 3 ( 3 3 3 3 3)
B 6 24 4 4 (4 4 4 4 4 4)
C 4 16 4 1 (2 2 2 2 2 2 2 2 )
D 3 9 3 1 ( 3 3 1 1 1 )
E 6 24 4 4 (4 4 4 4 4 4)
F 2 12 6 4 ( 4 4 4 )
TOTAL = 100 DAILY = 6 9 9 9 9 9 9 9 9 9 4

HISTOGRAM
10

8
WORKERS/DAY

4
Labor Utilization
2

0
1 2 3 4 5 6 7 8 9 10 11 12
WOKDAYS

1
PROBLEM 2:

Limit = 10 Workers/Day

Req. Crew size Workdays


Normal
Act Worker
duration
- days Nom Min 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
A 3 6 2 1 (2 2 2 )
B 4 8 2 2 (2 2 2 2)
C 6 30 5 3 (3 5 5 5 3 3 3 3 )
D 7 28 4 2 ( 4 4 4 4 4 4 4)
E 4 12 3 2 3 3 3 3)
F 10 30 3 3 (3 3 3 3 3 3 3 3 3 3)
G 2 4 2 1 ( 2 2)
H 6 18 3 3 (3 3 3 3 3 3)
I 2 6 3 3 (3 3)
TOTAL = 142 DAILY = 4 4 4 5 8 8 8 10 10 10 10 7 7 7 6 6 6 6 5 5 3 3

HISTOGRAM
12

10
WORKERS/DAY

4
Labor Utilization
2

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
2
WORKDAYS
PROBLEM 3:

Limit = 8 Workers/Day

Req. Crew size Workdays


Normal
Act Worker
duration
days Nom Min 1
HISTOGRAM 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A 3 12 4 2 (4 4 4 )
25
B 5 20 4 2 (4 4 4 4 4)
C20 6 30 5 3 (4 4 5 4 4 3 3 3 )
WORKERS/DAY

D 5 15 3 1 (3 3 3 3 3)
15
E 3 6 2 1 ( 1 1 2 2 )
F10 5 20 4 2 (4 4 4 4 4)
G5 3 9 3 2 ( 3 3 3) Labor Utilization
H 2 6 3 3 (3 3)
0 3 9 3 2 ( 3 3 3)
I
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
TOTAL = 127 DAILY = 8 8 8 8 8 8 8 8 8 8 7 7 7 7 7 6 6
WORKDAYS

PROBLEM 4:

Limit = 6 Workers/Day

Req Crew size Workdays


Normal
worker Norma
Act duration Minimum 1 2 3 4 5 6 7 8 9 10 11 12
days l
A 4 16 4 2 (4 4 4 4)
B 4 12 3 1 (1 1 2 2 3 3 )
C 2 6 3 2 ( 3 3)
D 4 12 3 1 (3 3 3 3)
E 4 8 2 1 (2 2 2 2) 3
F 3 12 4 2 (3 3 3 3)
TOTAL = 66 DAILY = 5 5 6 6 6 6 6 6 5 5 5 5
HISTOGRAM
8

6
WORKERS/DAY

2 Labor Utilization

0
1 2 3 4 5 6 7 8 9 10 11 12
WORK DAYS

PROBLEM 5:

Limit = 7 Workers/Day

4
Req. Crew size Workdays
Normal
Act Worker
duration
days Nom Min 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A 4 12 3 2 (3 3 3 3)
B 2 6 3 2 (3 3 )
C 5 15 3 1 ( 3 3 3 3 3 )
D 5 20 4 2 (4 4 4 4 4)
E 2 12 6 3 (3 3 3 3 )
F 3 9 3 2 ( 3 3 3 )
G 4 16 4 3 (4 4 4 4)
H 2 8 4 2 ( 3 3 2)
I 4 12 3 2 (3 3 3 3)
TOTAL = 110 DAILY = 6 6 6 6 7 7 7 7 7 7 7 7 7 6 6 6 5

HISTOGRAM
8
7
6
WORKERS/DAY

5
4
3 Labor Utilization
2
1
0
PROBLEM 6:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Limit = 9 Workers/Day
WORKDAYS

5
Req. Crew size Workdays
Normal
Act Worker
duration
days Nom Min 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A 3 15 5 3 (3 3 3 3 3)
B 5 15 3 3 (3 3 3 3 3)
C 4 12 3 1 (2 2 2 3 3 )
D 3 9 3 2 ( 3 3 3)
E 5 20 4 3 (4 4 4 4 4)
F 2 16 8 2 ( 5 5 2 2 2 )
G 3 18 6 3 (6 3 3 3 3)
H 5 15 3 2 (3 3 3 3 3)
I 3 9 3 1 ( 3 2 2 2)
TOTAL = 129 DAILY = 8 8 8 9 9 9 9 9 9 9 9 9 8 8 8

HISTOGRAM
10

8
WORKERS/DAY

4 Labor Utilization
2

0
PROBLEM 7:
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Limit = 13 Workers/Day
WORKDAYS

6
Req. Crew size Workdays
Normal
Act Worker
duration
days Nom Min 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
A 3 6 2 1 (2 2 2 )
B 2 4 2 2 (2 2)
C 5 15 3 2 (3 3 3 3 )
D 3 12 4 2 (2 3 3 4 )
E 4 16 4 3 (4 4 4 4)
F 5 10 2 2 (2 2 2 2 2 )
G 5 20 4 3 (4 4 4 4 4)
H 1 5 5 1 ( 2 2 1)
I 4 12 3 3 (3 3 3 3)
J 4 12 3 2 ( 3 3 3 3)
K 2 8 4 3 ( 4 4 )
L 5 20 4 2 (4 4 4 4 4)
M 2 8 4 3 ( 4 4)
N 3 18 6 2 ( 2 4 4 4 2 2)
O 5 10 2 2 (2 2 2 2 2)
TOTAL = 176 DAILY = 7 7 11 11 12 13 13 13 13 13 13 13 13 12 12

7
HISTOGRAM
14
Labor Utilization
12
10
WORKERS/DAY

8
6
4
2 Labor Utilization
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
WORKDAYS

You might also like