Professional Documents
Culture Documents
IFC+Solar+Report Web
IFC+Solar+Report Web
IFC+Solar+Report Web
multi-contract approach.
• Interdependencies between tasks. Interdependencies between tasks will allow the programme
to clearly define the ordering of tasks. A project-
• Parties responsible for tasks.
scheduling package will then indicate the start date of
• Project critical path. dependent tasks and highlight the critical path.
• Actual progress against plan.
Critical path analysis is important to ensure that tasks
All tasks and the expected timescales for completion that can affect the overall delivery date of the project are
should be detailed along with any restrictions on a highlighted and prioritised. A comprehensive programme
particular task. For example, if permits or weather should also take into account resource availability.
constraints are predicted to potentially stop construction This will ensure that tasks are scheduled when required
during particular months, this should be noted. staff or plant components are available. For example,
when exporting to a high voltage transmission line, a
For a solar PV project, it is likely that the programme will large substation facility may need to be designed and
incorporate different levels of detail around each of the built according to the grid company requirements and
following main work areas: interconnect agreement specifications. The outage date
for connecting to the transmission line will be planned
• Final design works.
well in advance. If the developer misses the outage date,
• Procurement and manufacture of equipment. significant delays can be incurred, which can have a major
• Site access. impact on the development. The outage date is thus a
critical path item around which the project development
• Security.
and construction timeline may need to be planned.
• Foundation construction.
Incorporating a procurement schedule that focuses on
• Mounting frame construction.
items with a long manufacturing lead-time (such as
• Module installation. transformers, central inverters and modules) will ensure
that they are ordered and delivered to schedule. It will also
• Substation construction.
highlight any issues with the timing between delivery and
• Electrical site works. construction, and the need for storage onsite.
• Grid interconnection works.
To share this information and to save time and effort, it
• Commissioning and testing. is strongly recommended that an “off-the-shelf” project-
scheduling package is used and that the programme is
A high-level programme should be produced to outline
monitored against site progress regularly.
the timescales of each task, the ordering of the tasks and
any key deadlines. This should be completed as part of the To obtain visibility of the works on a day-to-day basis,
detailed design. and receive early notice of any slippage in programme,
a good management and tracking tool to use is a weekly
The programme will then be built up to detail all the
look-ahead programme. This can be drawn up either
associated tasks and sub-tasks, ensuring that they will
by the EPC contractor or the project management team
be completed within the critical timescale. A thorough
onsite.
programme will keep aside time and resources for any
Milestones are goals that are tied in with contractual • Resource availability (plant, equipment and
obligations, incentives or penalties. Incorporating manpower).
milestones in the programme helps the project team to
• Training and learning curve of manpower, especially if
focus on achieving these goals. In effect, construction must
in a new market or if local resources are being utilised.
be planned around certain milestones or fixed dates (for
example, the grid connection date). • Consenting (or other regulatory) restrictions.
• Safety considerations.
If the contracted milestones are included in the
programme, the impact of slippage on these dates will • Grid availability.
be apparent. Appropriate budgetary and resourcing
10.4.3 RISK MANAGEMENT
decisions can then be made to address those delays. The
milestones can also indicate when payments are due to a The risks associated with the project should be identified,
contractor. Payment of contracted milestones should be assessed and managed throughout the construction
associated with the delivery of all relevant documentation process. The hazards need to be incorporated in the
to ensure the work has been built to specification and planning and scheduling of the project. Each aspect of
quality standards. This will ensure that the contractors the project should be assessed for likelihood and impact
are focused on delivering the paperwork as well as the of potential risks. The next step would be to develop
physical works. It will also help to minimise the potential a suitable action plan to mitigate identified risks. If a
for programme slippage later in the works due to awaiting particular risk could affect the delivery of the whole
documentation. project, alternatives for contingency (in terms of time and
budget) should be included.
10.4.2 PLANNING AND TASK SEQUENCING
Risk items may include timing delays, weather risk,
Appropriate sequencing of tasks is a vital part of the
grid connection delays, staff and equipment availability,
planning process. The tasks must be sequenced logically
transportation, ground conditions and environmental or
and efficiently. The overall sequence of works is
health and safety incidents. Many of these risks will have
generally site access, site clearance, security, foundation
been mitigated during the planning and design stage, for
construction, cable trenches and ducts, substation
example, by completing studies and plant design.
construction, mounting frame construction, module
installation, electrical site works, communications,
Some risks will remain until the equipment is on site:
site grid works and finally, testing and commissioning.
lost equipment or equipment damaged in transport, for
Each of these work areas should be broken down into a
example. This risk is reduced by selecting an experienced
series of sub-tasks. Alongside these, an assessment of the
supplier with suitable transport equipment. Insurance
inputs required for each task (especially when interfaces
will cover the cost associated with sourcing replacement
are involved) will help develop a logical and efficient
equipment, however if a key component such as the grid
sequence.
transformer is lost, then insurance will not compensate
for the time delays and loss of generation associated with
Consideration should also be given to any factors that
the component not being available. Such risks should be
could prevent or limit possible overlap of tasks. These
considered when drafting the EPC contract terms.
factors could include:
• Details of any records to be kept (for example, The World Bank Group General EHS Guidelines cover
photographs or test results). H&S during construction, including:
10.8.5 LOGISTICAL
• Execution plans.
Employees for project installation companies in emerging
markets are often inexperienced. This can lead to incorrect • Risk assessments and method statements.
installation methods or procedures, and may include a • Quality plans.
The construction of a solar PV power plant is a relatively straightforward process. However, there are common mistakes that EPC contractors
can easily avoid with correct planning and training procedures. Examples of such mistakes are itemised below.
PV Module Installation
Mounting Structure
Civil Works
The integrity of the controlled environment within equipment enclosures/housings can be compromised if not installed correctly. Examples of
common issues include:
Unused glands not sealed or replaced with dummies.
Unsealed cable conduits.
Damaged or missing gaskets on entrance doors.
Unsealed cable trenches leading into inverter housings.
Water ingress due to any/all of the above, leading to a humid atmosphere causing corrosion damage to electrical components.
Environmental Monitoring
Incorrect positioning of the environmental monitoring equipment can lead to inaccuracies during performance assessment. The most common
reasons for these inaccuracies include:
Pyranometers not positioned at the same tilt angle as the modules.
Pyranometers subject to shading, causing reporting of elevated performance ratio (PR) calculations.
(continued)
Cable Management
Signage
Spare Parts
The permanent storage area for spare components is often not available when such components are delivered to the site, leading to
damage from poor temporary storage conditions.
Required
Recommended
• Environmental and human factors (for instance, • Dust caused by vehicular traffic.
autumn fall debris and soiling from local agricultural
• Site accessibility based upon weather predictions.
and industrial activities).
• Availability of water and cleaning materials.52
• Weather patterns: cleaning during rainy periods is less
likely to be required. If the system efficiency is found to be below the expected
level, then the cleanliness of the modules should be
checked and cleaning conducted as necessary.
Figure 25: Module Cleaning Using Brush Trolley The optimum frequency of module cleaning can be
determined by assessing the costs and benefits of
conducting the procedure. The benefit of cleaning should
be seen in an improved system performance ratio (PR)
due to the lower soiling loss and resultant increase in
revenue. A cost estimate to clean the PV modules should
be obtained from the O&M contractor and compared
with the potential increase in revenue. The agreed O&M
contract should detail an agreed number of cleans per
annum and their frequency. It should also outline the
labour rate or unit price at which the owner may request
an additional plant-wide clean of modules to allow this
cost-benefit analysis to be conducted.
Image courtesy of First Solar
All junction boxes or string combiner boxes should • Removal of dust from electronic components.
be checked periodically for water ingress, dirt or dust
• Tightening of any loose connections.
accumulation and integrity of the connections within
the boxes. Loose connections could affect the overall • Any additional analysis and diagnostics recommended
performance of the PV plant. Any accumulation of water, by the manufacturer.
dirt or dust could cause corrosion or short circuit within
11.3.6 STRUCTURAL INTEGRITY
the junction box.
The module mounting assembly, cable conduits and any
Where string level monitoring is not used, the O&M other structures built for the solar PV power plant should
contractor should conduct periodic checks, at least on an be checked periodically for mechanical integrity and signs
annual basis, of the integrity of the fuses in the junction of corrosion. This will include an inspection of support
boxes, combiner boxes and, in some cases, the module structure foundations for evidence of erosion from water
connection box. run-off.
A trained specialist should conduct thermography using a The alignment and positioning of the tracking system
thermographic camera at least on an annual basis. should also be checked to ensure that it is functioning
optimally. Sensors and controllers should be checked
11.3.5 INVERTER SERVICING
periodically for calibration and alignment.
Generally, inverter faults are the most common cause
of system downtime in PV power plants. Therefore, the 11.3.8 BALANCE OF PLANT
scheduled maintenance of inverters should be treated as a The remaining systems within a solar PV power plant,
centrally important part of the O&M strategy. including the monitoring and security systems, auxiliary
power supplies, and communication systems, should be
The maintenance requirements of inverters vary with
checked and serviced regularly. Communications systems
size, type and manufacturer. The specific requirements
within and externally connected to the PV plant should be
of any particular inverter should be confirmed by the
checked for signal strength and connection.
manufacturer and used as the basis for planning the
maintenance schedule. 11.3.9 VEGETATION CONTROL
Regular preventative maintenance for an inverter should, Vegetation control and grounds keeping are important
as a minimum, include: scheduled tasks for solar PV power plants. Vegetation
(for example, long grass, trees or shrubs) has the potential
• Visual inspections.
• Provide, at intervals, a visual check of the system 11.7.4 STANDARDS, LEGISLATION AND GUIDELINES
components for visible damage and defects.
This section of the contract outlines the various conditions
• Provide, at intervals, a functional test of the system with which the O&M contractor must comply while
components. carrying out the O&M of the plant. These conditions
• Ensure that the required maintenance will be should be drawn from the following documentation:
conducted on all components of the system. As a • Building or construction permits.
minimum, these activities should be in line with
• Planning consents and licences.
manufacturer recommendations and the conditions of
the equipment warranties. • Grid connection statement, the grid connection
agreement and power purchase agreement.
• Provide appropriate cleaning of the modules and the
removal of snow (site-specific). • Operating manuals for system components.
• Make sure that the natural environment of the system • Applicable legislation.
is maintained to avoid shading and aid maintenance
• Local engineering practices (unless the documents and
activities.
conditions listed above require a higher standard).
• Replace defective system components and system
components whose failure is deemed imminent. 11.7.5 PAYMENT
• Provide daily (typically during business hours) remote The cost and remuneration of the O&M contract are
monitoring of the performance of the PV plant to generally broken down into:
identify when performance drops below set trigger • Fixed remuneration and payment dates.
levels.
• Other services remuneration and expenditure
A schedule of preventative maintenance activities should reimbursement.
be prepared and appended to the O&M contract to easily
• Payment indexation over the duration of the contract. The contract will have a section outlining the governing
law and jurisdiction of the O&M contract. The governing
Remuneration for other services includes payment for any law is normally the law of the country in which the
services beyond the scope of the contract. This should project is located. A legal succession or a transfer of rights
include: condition is required for the developer to reserve the right
• Method for determining level of other services carried to assign the O&M contract to a third party.
out.
It is also recommended that every contract have a non-
• Agreed rates for conducting these services. disclosure agreement. This agreement between the O&M
• Agreed method for approving additional expenses or contractor and the developer will outline the information
services with the owner. that is to be treated as confidential, as well as that
information which can be disclosed to third parties.
• Any required spare parts and other components not
covered by individual warranties or held in the owner’s 11.7.8 INSURANCE
inventory.
The contract should have a section outlining the insurance
11.7.6 WARRANTIES/PERFORMANCE GUARANTEES responsibilities of the contractor for the O&M activities.
This insurance should cover damage to the plant, as well
The contract should include a plant-wide performance
as provide cover for employees conducting maintenance.
guarantee to be calculated on a regular basis. On large-
scale solar PV power plants this typically takes the form It is normal for the O&M contractor to arrange and pay
of an availability or performance ratio (PR) warranty. An for the full site insurance.
availability warranty provides a measure of plant ‘uptime’
and how successful the contractor is in keeping the plant 11.7.9 TERM OF AGREEMENT
functional and capable of exporting electrical energy
Every O&M contract needs to have a section that outlines
to the grid. A PR warranty provides a measure of plant
when the contract shall become effective and the duration
efficiency at converting solar irradiation into electrical
of the contract from the effective date. This section should
energy. While a PR warranty may be preferable because it
also include provisions to renew or extend the contract
incentivizes the contractor to optimise plant performance
upon conclusion of the originally agreed term.
rather than just ensure its operational readiness, some
third-party O&M providers are reluctant to provide such It is also recommended that this section include the
a warranty on systems they did not design or construct. circumstances in which either the maintenance contractor
or the developer would be entitled to terminate the
A PR guarantee is an industry standard and is considered
contract.
a pre-requisite to a suitable long-term O&M strategy.
The guarantee makes it the responsibility of the O&M
contractor to ensure that the plant achieves a PR level
The time of year coupled with the accessibility to the site • Location of the contractor’s premises.
can have a bearing on the actual response time for any • Number and competency of staff.
unscheduled maintenance event. Restrictions to access
• Experience and track record.
roads at certain times of the year can delay response.
Adverse conditions can also reduce the size of the payload • Financial strength and ability to honour warranty
that can be transported to the site, thus extending the obligations.
duration of the maintenance work.
The intention should be to select a suitably experienced
The presence of a strong PR guarantee also ensures that contractor able to meet the requirements of the contract
the contractor is motivated to undertake an efficient for the duration of the project.
response and restore system performance when alerted
The checklist below sets out the basic requirements for the
drafting of a strong solar PV power plant O&M contract.
Developers should consider While the cost per kWh of solar PV power has come down
how policy provisions are dramatically and continues to fall, in most cases direct or indirect
financial incentives are still required in order to increase the
designed and what specific
commercial attractiveness of solar PV projects so that there is
support mechanisms for solar PV
sufficient investment in new projects to meet national goals for
projects are available to bridge renewable energy production.
the gap between the costs of
Price-based incentives such as FiTs remain among the most
conventional power sources and
common instruments to boost the commercial case for solar.
solar PV.
In place of price-based incentives, quantity-based mechanisms
use binding policy provisions to establish quotas that require
power utilities to purchase a specific percentage of their power
from a renewable source. Quotas translate into investment
opportunities for developers, who are able to supply utilities with
the required electricity generated by renewable energy facilities.
Complementing the arsenal of policy instruments available to
governments are fiscal incentives—e.g., investment or production
tax credits, and direct public support schemes, such as soft
loans or an equity participation by a public entity. Policies that
guarantee and facilitate connection and access of PV plants to
the grid are also important for the viability of PV projects by
removing common barriers.
• Determine whether the project will be able to meet • Market-based Instruments: These accompany quantity-
the criteria for securing support and understand the based mechanisms, such as renewable portfolio
historical reliability of the delivery of these supports. standards or quota obligations. Certificates associated
with renewable energy production are traded on a
• Factor all this information into the business plan and
market and result in additional revenue for renewable
demonstrate to investors that the discounted cash flows
energy producers. Examples include tradable
are appealing.
renewable certificates or carbon certificates.
• Follow through meeting the requirements to secure the
• Tax Incentives: Tax incentives can be used by a
support available.
project owner to offset capital costs or profits, or to
reduce specific taxes such as VAT or import duties.
Refer also to the checklist at the end of the chapter for key
Accelerated depreciation is another option intended
considerations in accessing support mechanisms in any
to attenuate the high capital costs of renewable energy
market.
projects.
12.2 POLICIES AND SUPPORT MECHANISMS • Soft Loans: Soft loans—i.e. those with a below-market
OVERVIEW interest rate or extended tenor—are sometimes made
12.2.1 TYPES OF SUPPORT MECHANISMS available, especially in the early stage of technology
deployment by government-backed institutions.
This sub-section provides an overview of the six common
types of renewable energy support mechanisms used • Capital Grants: Capital grants from public sources
by governments, including both mechanisms that help reduce the upfront financing burden and can stimulate
developers to improve cash flow and those that offer interest in a new market. This option was used in the
opportunities to competitively enter the market: early stages of PV development. As the technology has
matured, it is not necessary and now very rare.
• Feed-in Tariffs (FiTs): A FiT is a predetermined price
for every unit of electricity generated by a solar PV The above provide direct and indirect financial supports
power plant, paid through a long-term contract. designed to cover the incremental costs of solar PV
Typically, projects must meet certain eligibility criteria power against conventional power supply options. The
and receive authorization from a government body to relative merits and conditions of different energy policy
receive the FiT (and usually preferential grid access as frameworks vary widely between countries and regions.
well); smaller projects may automatically receive the Hence, it is crucial for developers to consider the effect
FiT up to a certain maximum level of MWs (maximum on the commercial viability of their project, including
capacity). the private investment risk of policies within a specific
• Reverse Auctions and Tenders: Reverse auctions political and economic context.53 The International
for independent power producers (IPPs) involve the
competitive procurement of energy, whether at a 53 For more on this topic, see IEA, IRENA, the US National Laboratories (including
specific site or without specifying where a new plant Lawrence Berkeley, Sandia, and the National Renewable Energy Laboratory)
and the World Bank’s Energy Management Assistance Program. See also,
must be built. Renewable energy auctions can be IRENA’s “Evaluating Policies in Support of the Deployment of Renewable
Power” (2012), and the World Bank’s Renewable Energy Financial Instrument
technology-neutral where solar competes with other Tool (REFINe).
54 http://www.iea.org/policiesandmeasures/renewableenergy/
55 There are many publications analyzing feed-in tariffs. Among them, see 56 Legislation: Royal Decree 1565/2010 adopted on 19 November 2010 by the
“Feed-in Tariffs as a Policy Instrument for Promoting Renewable Energy and Council of Ministers. For more details, see the European Photovoltaic Industry
Green Economies in Developing Countries,” United Nations Environment Association’s “Retrospective Measures at the National Level and their impact
Programme (UNEP), 2012. on the photovoltaic sector.” 10 December 2013. Available at www.epia.org.
The solar market in Thailand is currently driven by two key Feed-in Tariff (FiT) policies designed to help the country meet its ambitious
targets for solar development by 2021.a
1. Rooftop solar projects policy.b
2. Ground-mounted solar projects policy.
The rooftop FiT policy provides an incentive for developing rooftop and community ground-mounted solar systems, and is capped at an
installed capacity of 200 MW. The FiT rate is scaled dependent on the project size. The FiT rates below are granted to projects that were
fully commissioned before December 2013 and are valid for a 25-year operational period.
The ground-mounted FiT policy provides an incentive for up to 800 MW of projects to be commissioned by the end of 2014. The FiT rate
varies throughout the lifetime of a developed project and is presented below.
For both the rooftop and ground-mounted FiT policies, the FiT rate can be considered relatively generous and project IRRs should be
attractive to investors. The Thai government has periodically revised the FiT rates and current information on incentives for projects
developed beyond 2014 can be found online.c
a http://thaisolarpvroadmap.org/wordpress/?p=940
b http://www.eppo.go.th/nepc/kpc/kpc-145.html
c http://www.iea.org/policiesandmeasures/renewableenergy/?country=Thailand
South Africa has in place policies and initiatives that are aimed at accelerating growth in the solar PV power sector, including REIPPP and
the Eskom Standard Offer.
REIPPP
South Africa’s REIPPP is split into different bidding rounds. The allocated resources are shown below for Rounds 1 to 3. The decreasing trend
in average PV bid price and the increase in local content is indicative of the policy’s success in incentivizing solar development, although it
remains to be seen whether developers can truly sustain operation at such low prices.a
Under Round 1 of the REIPPP, construction has commenced on 18 large-scale solar PV projects with a combined installed capacity of 630
MW. In Round 2, a total of nine projects with a combined capacity of 417 MW were awarded preferred bidder status and are currently under
construction. An additional six projects with a capacity of 435 MW have achieved preferred bidder status in Round 3 and are approaching
financial close. In 2013, nearly all of South Africa’s solar PV power market consisted of large ground-mounted systems and it is expected
that this market will remain strong.
However, historically there have been a number of delays with the bidding process. In September 2012, the Department of Energy
announced delays to Round 3 of the REIPPP due mainly to difficulty in progressing the first round projects to financial close. The need to
focus on financial closure for projects selected during the first two bidding rounds had a knock-on effect.b
In 2013, the government delayed an announcement on a final list of preferred bidders in the third round of its national renewable energy
programme. This was finally completed in November 2013, more than 12 mosnths later than expected.
The Department of Energy is now in the process of finalising the financial close protocol for the Round 3 preferred bidders.
a http://www.esi-africa.com/sas-third-round-bidding-sees-prices-drop-dramatically/
b http://irp2.files.wordpress.com/2011/10/pvsouthafricamap-2013-04-17.pdf
c www.esi-africa.com/sas-third-round-bidding-sees-prices-drop-dramatically/
d www.ey.com/UK/en/Industries/Cleantech/Renewable-Energy-Country-Attractiveness-Index---country-focus---South-Africa
Competitive bidding processes have been successfully While involving higher preparation costs for the entity
implemented recently in several emerging markets, running the tender, and higher risks for the parties
including India and South Africa. In South Africa, bidding, the competitive bidding process does offer
the Renewable Energy Independent Power Producer a greater level of assurance that projects are being
Procurement (REIPPP) scheme (see Box 9) is a bidding incentivized at the minimum levels required (“revealed
process in which proponents bid to be awarded a power prices”). As such, it can be a good strategy for larger
sale agreement until a certain MW quota (announced for markets that have established interest and are looking to
each round) is reached. Similarly, India operated a reverse scale up installed capacity.
auction to award successful proponents a PPA as part of
the Jawaharlal Nehru National Solar Mission (JNNSM). Box 10 summarises key elements of India’s regulatory
support framework, which has evolved over time and used
multiple options, including FiTs, tenders and renewable
India has implemented a number of different regulatory support schemes including FiTs, renewable obligations and reverse auctions.
The National Action Plan on Climate Change (NAPCC) of India sets Renewable Purchase Obligation (RPO) targets for each state in India.
This provides a minimum level of the total power that electricity distribution companies need to purchase from renewable energy sources.
Although this is not directly related to solar projects, it requires the states to incentivise the development of renewable energy projects.
Among the states, Gujarat has offered the highest FiT, at 12 Rupees ($0.20), resulting in an installed capacity of 916.4 MW as of 31 March
2014. Below is a short summary of the FiT rates by state awarded by individual state-based solar energy policies.a
The national Jawaharlal Nehru National Solar Mission (JNNSM),c also referred to as the National Solar Mission, was launched in January 2010
to specifically incentivise the development of solar power as part of the broader national renewable energy targets. JNNSM set a target of
20GW of grid-connected solar power by 2022. It aims to reduce the cost of solar energy-to-grid parity by supporting large-scale deployment
(through a reverse auction scheme in Phases 1 and 2), long-term policy, research and development and domestic production. The develop-
ment road map of JNNSM is divided into three phases, presented below.
In the first phase, selected developers were awarded a PPA with the Central Electricity Regulatory Commission (CERC) through a reverse
auction scheme. The average tariff was approximately US$0.15/kWh, representing a 43 percent decrease on the benchmark tariff approved
by the CERC. It is noted that only 67 percent of Phase 1 projects were commissioned as of March 2014. There are a variety of reasons for this,
including delays to financial close, land acquisition and grid connection issues. Reverse auction was used in Phase 2d through which 10,000
MW are expected to be awarded.
a http://mnre.gov.in/file-manager/UserFiles/guidelines_sbd_tariff_gridconnected_res/salient_features_for_State-wise_solar_policies.pdf
b http://geda.gujarat.gov.in/policy_files/Solar%20Power%20policy%202009.pdf
c Ministry of New and Renewable Energy, Towards Building SOLAR INDIA Available at: http://mnre.gov.in/pdf/mission-document-JNNSM.pdf
d http://seci.gov.in/content/innerpage/phase-ii--batch-i-log-of-documents-releasednotifications-issued.php
64 For more, see B. Shen et al., “China’s Approaches to Financing Sustainable 66 The Green Climate Fund’s stated intention to work directly with the private
Development: Policies, Practices, and Issues,” Lawrence Berkeley National Lab sector raises the interesting possibility of combining multilateral donor funding
paper LBNL-5579E. June 2012. with local implementation, but is still in early stages.
65 For one assessment of policies in India, see G. Shrimali, et al., “Solving India’s 67 “1603 Treasury Program,” section of the Solar Energy Industry Associations
Renewable Energy Financing Challenge: Which Federal Policies can be Most website, available online at http://www.seia.org/policy/finance-tax/1603-
Effective?,” Climate Policy Initiative. March 2014. treasury-program
12.4 FURTHER GUIDANCE TO DEVELOPERS ON Given how rapidly solar PV power costs have dropped in
REGULATORY SUPPORT FRAMEWORKS the last five years (2009–2014), it is especially important
for solar energy developers to consider the possibility
Developers need to be aware of secondary regulations
that solar energy incentives will evolve as well, either
that may influence project transaction costs. For example,
through anticipated policy expirations and adjustments or
a lengthy waiting period for generation permits could
unexpected policy changes. By the end of 2014, most FiTs
significantly delay the start-up of the new plant, and
in Europe were reduced substantially from the peak levels
thus create financial losses for the developer. Another
observed in 2008, reflecting the reduction in capital cost
example is power quality regulations, which may include
of a solar PV power installation. Interestingly, thus far,
frequency regulation (defined by a grid code) that
it is governments in developed economies (such as Spain,
applies to all electricity producers. While power quality
Italy, and Greece) that have made retroactive changes to
requirements are not solar specific, they can make it more
pre-existing support mechanisms in order to reduce levels
difficult for sources of intermittent power, such as solar,
of support provided to existing solar PV projects. While
to meet criteria for grid integration.68 Further examples
retroactive changes of this kind are not common (and, in
of regulations that are secondary to solar, including
the case of the countries cited above, were influenced by
important aspects of the grid connection process, are
the strained financial situation of a number of European
covered in Section 8 on Permits and Licenses.
countries in the global recession after 2008), it is wise to
Renewable energy policies need to be considered in the consider the risk that policies may change.
context of the broader power market in which the project
If the share of renewable energy in a market coming
is being developed. Is the market fully de-regulated with
from variable output power plants is high or expected
generation, transmission, and distribution each operated
to become high (over 5–10 percent), it is important to
independently? Or is the project being developed for a
understand not only the support policies for solar power
vertically-integrated, state-owned utility through a Public
per se, but also the policies that have an impact on the
Private Partnership?
overall power system, including the grid development,
In markets where a state-owned entity controls generation, investment in storage and flexible power generation,
the major opportunity for a developer is likely to be in and demand-side management. In other words, support
response to a public tender or a Public Private Partnership, mechanisms for solar PV power cannot be considered
such as a Build-Operate-Transfer (BOT) or a Build- in isolation because integration of solar and other types
Own-Operate (BOO) with a PPA. The structure of the of renewables into a given power system and electricity
power market defines the types of project development market creates additional challenges that may affect
opportunities available. However, while having this a developer, if the level of penetration of intermittent
broader context on the structure of the relevant power renewable power grows to high levels.
market is critical, this topic will not be discussed further
69 While not the focus of this publication, electricity market structure and reform
68 In many emerging markets, where maintaining the power supply is the is a priority topic for the World Bank Group. World Bank’s Energy Sector
predominate concern and the penetration of intermittent renewables such Management Assistance Program (ESMAP) and the World Bank Energy
as solar is low, power quality and variable energy integration may not be top Practice Group have many publications and activities covering this important
concerns. However, as the share of renewables grows in global markets, power issue from the perspective of the government/regulator. Many have a specific
quality may become more of a priority. country or regional focus.
The PPA is the most important Solar PV power plant projects generate revenue by selling power.
agreement for financing a How power is sold to the end users or an intermediary depends
mainly on the power sector structure (vertically integrated or
solar PV project. All other
deregulated) and the regulatory framework that governs PV
related agreements—the loan
projects. Power can be sold either through a long-term PPA or
agreement, grid connection through participation in an open market (“merchant” plant).
agreement, and EPC contract—
At the writing of this guide (early 2015), there were only a few
should be aligned with the PPA.
merchant solar projects in the world; the vast majority of PV
power plants are developed using longer-term PPAs. Merchant
PV power plants are rare because PV costs typically result
in power that is more expensive than other energy sources
and excessively risky to financiers. Also, regulations (support
mechanisms) promoting PV technology and other renewables
are usually based on some form of long-term PPA. However, as
PV costs continue to decline, merchant PV plants may become
more common. For example, in 2014, IFC and other partners
financed the first merchant solar PV project in Chile, the La
Huayca II project, with no subsidy and no PPA. Merchant plants,
depending on how the power sector is structured, may be able to
sell both energy and capacity (the latter in a day-ahead market).
Including La Huayca, as of early 2015, IFC had financed four
large-scale PV projects in Chile, of which three were merchant
projects and only one had a PPA. These projects are described
briefly in Table 19.
This section looks at the key elements of the typical PPA for
large-scale PV projects, and describes how small solar power
plants (distributed generation) can utilize similar contractual
arrangements.
of the power market. For renewables (including PV) that and creating greater certainty around the revenue stream.
are supported by regulatory mechanisms (see Section 12), Off-taker credit-worthiness is a factor whose importance
the most common option is to sell all electricity generated cannot be overemphasized. It is one of the most critical
to a power company (vertically integrated, transmission elements considered when developing a PPA and the focus
or distribution), often wholly or partially government- of thorough due diligence.
owned. However, a solar PV plant may also sell electricity
to a trading company or a consumer, provided that this PPAs may be standardized and non-negotiable (except
is allowed by market rules. In the latter case, wheeling possibly for the tariff); standardized to provide an
charges may have to be paid by one of the two parties of initial framework for negotiations; or open to bilateral
the PPA. negotiations. PPAs for solar PV projects have historically
been shaped by the supporting regulatory framework, as
The PPA is the most important agreement for financing described in Section 12. For example, it has been common
a solar PV project. All other related agreements—the for the tariff, off-take terms (take or pay), and contract
loan agreement, grid connection agreement, and EPC duration to be pre-defined by a national or regional policy
contract—should be aligned with the PPA. The PPA should (see sub-section 12.3).
define all of the commercial terms affecting the sale of
electricity between the two parties, including the date the While the classic PPA model of a utility off-taker paying
project will begin commercial operation, the schedule a fixed price to the producer is likely to remain common
for delivery of electricity, the tariff, the volume of energy in the coming years, developers and financers should stay
expected to be delivered, payment terms, penalties for abreast of market developments, and consider both the
underperformance on either side, and provisions for risks and opportunities introduced by changes in pricing
termination. and business models. Box 11, at the end of this section,
considers the recent rise in opportunities for distributed
As such, the PPA is the principal agreement that defines generation projects, sometimes referred to as “Commercial
the revenue stream, and thus the credit quality of an PPAs.”
electricity-generating project, and is therefore a key
instrument of project financing. A robust PPA helps de-risk Refer also to the checklist at the end of this section for
projects by clearly specifying rights and responsibilities, basic requirements specific to PPAs for solar PV projects.
The tariff may be adjusted based on an index that reflects The predicted annual energy production is estimated
annual inflation and foreign exchange fluctuations. If based on the project’s installed capacity, solar irradiation,
indexation is not included, the developer should assess and the resulting capacity factor or performance ratio,
the risks associated with inflation and changes in foreign as described in detail in Section 5 on Energy Yield. The
exchange rates. Long-term operating costs for solar predicted annual production should take into account
projects are very low, making inflation less of a concern seasonal variations in solar irradiation and system losses
than for other technologies, but should still be considered. to the point of metering. Also, panel degradation loss
In markets where it is difficult to obtain long-term should be taken into account reflecting how efficiency and
financing in local currency, foreign exchange rates reflect annual energy production may be reduced year-on-year
substantial risk exposure. Foreign exchange is also a over the life of the plant.
substantial risk linked to repatriation of profits.
An accurate annual production prediction gives the off-
Tariffs for solar power projects may continue to be taker comfort in knowing how much energy it will receive
determined through regulations, but as the cost of and the seller comfort knowing how much it can sell. The
70 The World Bank Group has publicly available PPA resources at http://ppp. 72 Ebehard, A., Kolker, J. and Leigland, J. “South Africa’s Renewable Energy
worldbank.org/public-private-partnership/solar-power-energy IPP Procurement Program: Success Factors and Lessons.” Public-Private
71 For example, see “Understanding Power Purchase Agreements,” funded by the Infrastructure Advisory Facility (PPIAF) of the World Bank. May 2014.
U.S. government’s Power Africa initiative, available at no cost online at http:// 73 Upadhyay, A. “Dubai Shatters Solar Price Records Worldwide — Lowest Ever!”
go.usa.gov/FBzH Cleantechnica Website, November 29th, 2014.
Most solar and other renewable energy, as non- “Conditions to commencement” or “conditions
dispatchable forms of power, are sold on an “obligation precedent” define conditions that must be satisfied by the
to take” or “take or pay” basis, whereby all power they developer prior to commencement of the PPA term.
generate must be accepted by the grid. If this is not the
These conditions generally include securing the required
case, then the volume of power being transacted should
project permits/approvals, the execution of an O&M
also be specified, with clarity on any penalties due should
agreement (covering civil works for land maintenance,
that volume of power not be delivered.
module and balance of system routine inspections),
13.2.2 PPA DURATION a secure grid connection, and issuance of a takeover
certificate.
The PPA specifies the expected start and termination dates
of the agreement. The duration of the PPA should be equal The conditions to commencement set out a common
to and ideally longer than the period of time required to understanding of the requirements of the project before
repay the project’s lenders and to meet expected equity commissioning. If the project developer does not satisfy all
returns. In some cases, the duration will be determined by conditions, the off-taker may have the right to terminate
the regulatory support mechanism under which the solar the PPA. However, conditions to commencement often
PV project is developed; in other cases, the PPA duration define requirements for the developer that, if not met,
can be negotiated. PPAs covering a 15- to 25-year period might leave the project legally exposed. Therefore, it is in
are desirable for PV plants and are relatively common. The all parties’ interest for the conditions to commencement to
longer the term of the PPA, the less exposure the project be met.
has to future changes in power prices, and the more secure
its revenue stream. A sufficiently long PPA duration is 13.2.5 GRID CONNECTION AGREEMENT
especially critical for solar PV plants because the vast
The PPA will typically reference and summarise the terms
majority of costs are incurred up front and must be repaid
of the Grid Connection Agreement, often in an annex.
over the project’s life. PV power plants are expected to
It is very common for grid connection to be delayed,
operate with fairly predictable degradation rates for 20
and where the off-taker or grid company is responsible,