WEEKLY 

PROGRESS REPORT Date : 24/01/2021 ‐ 30/01/2021
Rehabilitation of Port # 1 Section 2 of Muneshwers wharf
Client: Muneshwers Ltd.
Supervising Consultant: SRKN'gineering and Associates
Contractor: Kares Engineering Inc.

Accidents on site: None

S. No. Description of work in Progress Remarks Status (Days behind schedule)


1 Piles driven All piles for span 3 driven On schedule

2 Rebars bent
3 main bars  Completed On schedule
4 L shape bars for shear connector Completed On schedule
5 ties for shear conector Completed On schedule
6 Formwork completed Completed On schedule

7 Pouring of concrete for span 3 Completed On schedule


8 Removal of Deck slabs from gridline 12‐14 67% completed behind schedule
9 Breaking of pile caps 12‐13 completed on schedlue
10 clearing area 
clearing area of obstacles/debris from gridline 12‐14 30% completed 4 days behind schedule

11 Swamping 15 piles 0% completed 6 days behind schedule 


12 splicing 6 piles 0% completed 7 days behind schedule

S. No. Delayed Activities Remarks


Delyed by 2 days. Work was done on a  22 hrs shift on the 23rd‐24th Jan to 
1 swamping/Splicing/driving piles on line 11 (48 hr)
make up back this time.
Presence of a vast amount of obstacles (existing piles and concrete pile cap to 
be broken) resulted in much more effort needed than anticipated. Also, time 
2 clearing area of obstacles/debris from gridline 12‐14
was lost to facilitate the setting up of formwork and placement of rebar cages 
(in close proximity) in a safe manner.
Due to the existing obstacles present, no piles can be swamped/spliced until 
3 Swamping/splicing of piles
obstacles are removed.
4
5

General Remarks
‐ American Crawler crane down time 25th Jan 2021‐present. However, no major delay resulted from this.

Consultant's Representative :  Varun Ramkawal