You are on page 1of 6

National Drainage and Irrigation Authority

#REF!

Bill No. xx. Concrete Drain


Item Description Qty Unit Rate (G$) Amount (G$)
Earth Works
Allow for all temporary works and drainage diversions including sum -
cofferdams, de-watering of excavated areas, etc for the duration of the
project and removal of all temporary works upon completion of the
works.

Excavate to construction level for drain and store selected material for cu.m -
re-use. Rate to include for cutting and shaping of the channel to the
required slope as shown in the drawings and disposal of unacceptable
material at the closest public disposal site designated by the Local
Regulatory Body or Supervisory Consultant.

Allow for the sand filling and compaction of areas below the blinding cu.m -
and structural concrete.

Concrete Works
Blinding
Supply, place and compact 50 mm cement/sand blinding. Compressive
sq m -
strength in accordance with drawings and specifications.

Formwork
Provide and fix fair-faced formwork for structure inclusive of all struts, -
ties and props as maybe required for drain walls

Reinforcement
Supply, cut, bend and fix reinforcement. Rate to include for
anchorage and end laps to reinforcement.
20mm diameter H.T.S. tonne -
16mm diameter H.T.S. tonne -
12mm diameter H.T.S. tonne -
10mm diameter H.T.S. tonne -

Concrete
Supply, place and compact Grade 30 structural concrete -

TOTAL CARRIED TO SUMMARY #REF!


dia 10 12 16 20 25
kg/m 0.617 0.888 1.578 2.466 3.853

TOP SECTION
main bars
outer face T 16 inner face

length of drain 282 m length of drain 282

height of wall 4m height of wall 4


spacing of bars 0.2 m spacing of bars 0.2
no of bars. 1411 no. no of bars. 1411
length of 1 bar 4m length of 1 bar 4
total length 5,644 m total length 5,644
weight of bars 8,908 kg weight of bars 5,011
both sides of drain (x2) 17,816.26 kg both sides of drain (x2) 10,021.65
+5% 18,707.07 kg +5% 10,522.73

distribution bars
both face T 10
length of drain 282 m
height of wall 4m
spacing of bars 0.2 m
no of bars. 21 no.
length of 1 bar 301.7142857 m accounts for laps
total length 6,336 m
weight of bars 3,906 kg
both sides of drain (x4) 15,625.53 kg 15625.5279
+5% 16,406.80 kg

BOTTOM SECTION
main bars
outer face T 20 inner face
length of drain 282 m length of drain 282
spacing of bars 0.2 m spacing of bars 0.2
no of bars. 1411 no. no of bars. 1411
length of 1 bar 7.4 m length of 1 bar 6.38
total length 10,441 m total length 9,002
weight of bars 25,750 kg weight of bars 14,208
+5% 27,037.56 kg +5% 14,918.89

distribution bars
both face T 12
length of drain 282 m
height of wall 5.8 m
spacing of bars 0.15 m
no of bars. 39.66666667 no.
length of 1 bar 306 m accounts for laps
total length 12,138 m
weight of bars 10,776 kg
both faces of drain (x2) 21,552.57 kg
+5% 22,630.20 kg

REINFORCEMENT
T10 16,406.80 kg
T12 33,152.93 kg
T16 33,625.96 kg
T20 27,037.56 kg

SANDFILLING
length 282 m
width 1 4.2 m
width 2 2.2 m
depth 1 0.25 m
depth 2 0.15 m
volume 389.16 m
+5% 408.62 m3

BLINDING
length 282 m
width 5.6 m
area 1579.2 m2
+5% 1,658.16 m2

FORMWORK
length 282 m
width 4.2 m
area 1184.4 m2
+5% 1,243.62 m2

CONCRETE
area(CSA) 3.4429 m2
length 282 m
volume 970.8978 m3
+5% 1019.44269 m3
EXCAVATION
area(CSA) 3.4429 m2
length 282 m
volume 970.8978 m3
+5% 1019.44269 m3
T 12

m
m
no.
m
m
kg
kg
kg

T 16
m
m
no.
m
m
kg
kg
Top section of draini (sloping at 1:1)
Thickness = 200mm
Rebar = T16 @ 200mm in the outer face, T12 @ 200mm inner face (bars
running from bottom to top of wall
= distribution bars to be T10 @ 200mm both faces (bars running parallel to
flow channel)

1m wide flat section of wall


Thickness = 250mm
Rebar = T16@200mm in outer face, T12@ 200mm inner face
= distribution bars to be T10 @ 200mm both faces

1.0m high wall (bottom section of drain)


Thickness = 300mm
Rebar = T20@200mm in outer face, T16@ 200mm inner face
= distribution bars to be T12 @ 150mm both faces

3m wide base
Thickness = 350mm
Rebar = T20@200mm in bottom face, T16@ 200mm top face
= distribution bars to be T12 @ 150mm both faces