Clear Size of room = Length 25 ft

Width 20 ft
Thickness of wall = 0.75 ft
No of beam = 2 nos
width of beam = 1 ft
No of bay in slab = 3 nos
Width of three bay
Bay 1 = 8 ft
Bay 2 = 7 ft
Bay 3 = 8 ft
Clear Width of verandha = 8 ft
Thickness of Slab = 150 mm
Size of beam = width 1.166667 ft
Height 1.666667 ft
R/f in one beam = 2 nos 20 mm bar
6 nos 16 mm bar
0 nos 12 mm bar
stirrup nos 8 mm bar
Dia of Main R/f in slab = 10 mm bar
Dia of D/s R/f in Slab = 8 mm bar
Spacing of main bar = 150 mm
Spacing of D/s bar = 200 mm
Beam
Main Bar
length of one 20 mm bar = Clear span+Inclined length-Elongated length+bend length of bar
= 7.311138 mtr
Weight of one 20 mm bar = d^2*length of bar/162
= 18.05219 kg
Weight of 20 mm bar in one beam = 36.10439 kg
Wieght of 20 mm bar in one room = no. of beam*weight of 20 mm bar in one beam
= 72.20877 kg

Length of one 16 mm bar = Clear Span


= 6.32622 mtr
Weight of one 16 mm bar = d^2*length of bar/162
= 9.996989 kg
Weight of 16 mm bar in one beam = 59.98193 kg
Wieght of 16 mm bar in one room = no. of beam*weight of 20 mm bar in one beam
= 119.9639 kg

So weight of 20 mm bar in room = 0.722088 Quintal


So weight of 16 mm bar in one room = 1.199639 Quintal
Stirrups
Up to 2d length
d/4 =
Spacing of stirrup up to 2d length
= min. 8dᵇ dᵇ= bar dia
100 mm
d= effective depth of beam = total depth of beam-2*clear cover-stirrup di
= 434 mm

Spacing of stirrup up to 2d length = 100 mm

Stirrups spacing in rest of length = <d/2 or 200 mm


= 217 mm
Actual spacing of stirrups = 200 mm
Cut length of one stirrups =
length of stirrup+length of hooks+length of 90 & 135deg bend
1740 mm

No of stirrrups in 2d length = 10 nos


No of stirrups for both side of beam = 20 nos
no of stirrups in rest of length = 24 nos

Total no of stirrups = 44 nos


Cut length of all stirrups in one beam = 76.56 mtr
Cut length of all stirrups in one room = 153.12 mtr

Weight of 8mm bar = 60.49185 kg

So weight of 20 mm bar in room = 0.722088 Quintal


So weight of 16 mm bar in one room = 1.199639 Quintal
So weight of 8 mm bar in one room = 0.604919 Quintal

Main R/f and D/s R/f in Slab


Main R/f
IN Bay 1
Cut length of main R/f in slab = Clear span+Inclined Length -Elongation Length
= 2914.141 mm
Cut length of alternate main R/f in slab = 3645.849 mm

No of Main R/f in Bay 1 = Width of Room/main bar Spacing


= 20 nos
No of Alternate bar in Bay 1 = Width of Room/main bar Spacing
= 20 nos
Total Length of main bar in Bay 1 = 58.28283 mtr
Total length of alternate bar in Bay 1 = 72.91698 mtr

Weight of main bar = 0.617284 kg/m


Total length of main bar in bay 1 = 131.1998 mtr
Total weight of main bar in bay 1 = 80.98753 kg

IN Bay 3
Cut length of main R/f in slab = Clear span+Inclined Length -Elongation Length
= 2914.141 mm
Cut length of alternate main R/f in slab = 3645.849 mm
No of Main R/f in Bay 3 = Width of Room/main bar Spacing
= 20 nos
No of Alternate bar in Bay 3 = Width of Room/main bar Spacing
= 20 nos
Total Length of main bar in Bay 3 = 58.28283 mtr
Total length of alternate bar in Bay 3 = 72.91698 mtr

Weight of main bar = 0.617284 kg/m


Total length of main bar in bay 3 = 131.1998 mtr
Total weight of main bar in bay 3 = 80.98753 kg

IN Bay 2
Cut length of main R/f in slab = Clear span+Inclined Length -Elongation Length

Cut length of alternate main R/f in slab = 3249.507 mm

No of Main R/f in Bay 2 = Width of Room/main bar Spacing


= 41 nos

Total Length of main bar in Bay 2 = 133.2298 mtr

Weight of main bar = 0.617284 kg/m


Total length of main bar in bay 2 = 133.2298 mtr
Total weight of main bar in bay 2 = 82.24062 kg

IN Verandha
Cut length of main R/f in slab = Clear span+Inclined Length -Elongation Length
= 2914.141 mm
Cut length of alternate main R/f in slab = 3645.849 mm

No of Main R/f in verandha = Width of Room/main bar Spacing


= 25 nos
No of Alternate bar in verandha = Width of Room/main bar Spacing
= 25 nos
Total Length of main bar in verandha = 72.85354 mtr
Total length of alternate bar in verandha = 91.14622 mtr

Weight of main bar = 0.617284 kg/m


Total length of main bar in verandha = 163.9998 mtr
Total weight of main bar in verandha = 101.2344 kg
So weight of 10 mm bar in one room = 3.454501 Quintal
Extra Bar
In Bay 1
Length of bar 1 = 0.15L+half of wall thickness
= 480.1829 mm
Length of bar 2 = 0.25L+half of wall thickness+0.3L
= 1455.793 mm
no of bar 1 in block 1 = 20 nos
No of bar 2 = 20 nos
total length of bar 1 = 9.603659 mtr
Total length of bar 2 = 29.11585 mtr

wt of main bar = 0.617284 kg/m


total wt of main bar = 23.90093 kg
In Bay 3
Length of bar 1 = 0.15L+half of wall thickness
= 480.1829 mm
Length of bar 2 = 0.25L+half of wall thickness+0.3L
= 1455.793 mm
no of bar 1 in block 1 = 20 nos
No of bar 2 = 20 nos
total length of bar 1 = 9.603659 mtr
Total length of bar 2 = 29.11585 mtr

wt of main bar = 0.617284 kg/m


total wt of main bar = 23.90093 kg
Verandha
Length of bar 1 = 0.15L+half of wall thickness
= 480.1829 mm
Length of bar 2 = 0.25L+half of wall thickness+0.3L
= 1455.793 mm
no of bar 1 in block 1 = 25 nos
No of bar 2 = 25 nos
total length of bar 1 = 12.00457 mtr
Total length of bar 2 = 36.39482 mtr

wt of main bar = 0.617284 kg/m


total wt of main bar = 29.87617 kg
So weight of 10 mm extra bar in room = 77.67803 kg
Distribution R/f
IN Bay 1
Cut length of D/S R/f in slab = Clear span+Inclined Length -Elongation Length
= 6576.678 mm
Cut length of alternate D/S R/f in slab = 8405.946 mm

No of D/S R/f in Bay 1 = space for D/s bar placing/D/s bar Spacing
= 8 nos
No of Alternate bar in Bay 1 = space for D/s bar placing/D/s bar Spacing
= 8 nos
Total Length of D/S bar in Bay 1 = 52.61342 mtr
Total length of alternate bar in Bay 1 = 67.24757 mtr

Weight of D/S bar = 0.395062 kg/m


Total length of D/S bar in bay 1 = 119.861 mtr
Total weight of D/S bar in bay 1 = 47.35249 kg
IN Bay 3
Cut length of D/s R/f in slab = Clear span+Inclined Length -Elongation Length
= 6576.678 mm
Cut length of alternate D/s R/f in slab = 8405.946 mm

No of D/s R/f in Bay 3 = space for D/s bar placing/D/s bar Spacing
= 8 nos
No of Alternate bar in Bay 3 = space for D/s bar placing/D/s bar Spacing
= 8 nos
Total Length of D/s bar in Bay 3 = 52.61342 mtr
Total length of alternate bar in Bay 3 = 67.24757 mtr

Weight of D/sbar = 0.395062 kg/m


Total length of D/s bar in bay 3 = 119.861 mtr
Total weight of D/s bar in bay 3 = 47.35249 kg

IN Bay 2
Cut length of D/sR/f in slab = Clear span+Inclined Length -Elongation Length
= 6576.678
Cut length of alternate main R/f in slab = 8405.946 mm

No of D/s R/f in Bay 2 = space for D/s bar placing/D/s bar Spacing
= 5 nos
No of Alternate bar in Bay 2 = space for D/s bar placing/D/s bar Spacing
= 5 nos
Total Length of D/s bar in Bay 2 = 32.88339 mtr
Total Length of alternate D/s bar in Bay 2 = 42.02973 mtr

Weight of D/s bar = 0.395062 kg/m


Total length of D/s bar in bay 2 = 74.91312 mtr
Total weight of D/s bar in bay 2 = 29.59531 kg

IN Verandha
Cut length of D/s R/f in slab = Clear span+Inclined Length -Elongation Length
= 8101.068 mm

No of D/s R/f in verandha = Width of Room/D/sbar Spacing


= 16 nos

Total Length of D/s bar in verandha = 129.6171 mtr

Weight of D/s bar = 0.395062 kg/m


Total length of D/s bar in verandha = 129.6171 mtr
Total weight of D/s bar in verandha = 51.20675 kg

So weight of 8 mm bar in one room = 1.75507 Quintal


Extra Bar
In Bay 1
Length of bar 1 = 0.15L+half of wall thickness
= 1028.963 mm
Length of bar 2 = 0.25L+half of wall thickness+0.3L
= 3467.988 mm
no of bar 1 = 6 nos
No of bar 2 = 6 nos
total length of bar 1 = 6.17378 mtr
Total length of bar 2 = 20.80793 mtr

wt of main bar = 0.395062 kg/m


total wt of main bar = 10.65944 kg
In Bay 3
Length of bar 1 = 0.15L+half of wall thickness
= 1028.963 mm
Length of bar 2 = 0.25L+half of wall thickness+0.3L
= 3467.988 mm
no of bar 1 = 6 nos
No of bar 2 = 6 nos
total length of bar 1 = 6.17378 mtr
Total length of bar 2 = 20.80793 mtr

wt of main bar = 0.395062 kg/m


total wt of main bar = 10.65944 kg
Verandha
Length of bar 1 = 0.15L+half of wall thickness
= 1257.622 mm
no of bar 1 in both side = 12 nos

total length of bar 1 = 15.09146 mtr

wt of extra D/s bar = 0.395062 kg/m


total wt of main bar = 5.96206 kg
In Bay 2
Length of bar 1 = 0.15L+half of wall thickness
= 434.4512 mm
Length of bar 2 = 0.25L+half of wall thickness+0.3L
= 3467.988 mm
no of bar 1 = 5 nos
No of bar 2 = 5 nos
total length of bar 1 = 2.172256 mtr
Total length of bar 2 = 17.33994 mtr

wt of main bar = 0.395062 kg/m


total wt of main bar = 7.708522 kg
So weight of 8 mm extra bar in one room = 0.349895 Quintal

Weight of 20 mm bar in one room = 0.722088 Quintal


Weight of 16 mm bar in one room = 1.199639 Quintal
Weight of 10 mm bar in one room = 4.231281 Quintal
Weight of 8 mm bar in one room = 2.709884 Quintal

Total Wt of R/f in one room = 8.862891 Quintal


886.2891 kg

WEIGHT of r/f in beam = 2.526645 Quintal


weight of r/f in slab = 6.336246 quintal
volume of slab = 8.079268 mtr
= 9.222561 mtr
Thickness of slab = 0.15 mtr
volume of slab = 11.17673 m3
total R/f in slab = 633.6246 kg
r/f in slab per m3 = 56.69141 kg/m3

Clear Span = 6554.878 mm

ed length+bend length of bar Inclined length = 0.42D D=effetive ht of beam


D = 458.1301 mm Clear Cover in beam/slab
Elongated Length = 2d for every 45 degree bend
= 2*2d d=dia. Of bar
= 80 mm
in one beam for 90 degree bend = 4d
= 80 mm
bend lenth of bar = 458.1301 mm

in one beam

108.5 mm

= 128 mm
2d length Rest length
868 mm
f beam-2*clear cover-stirrup dia-half of bar dia 4818.87804878049

Length of 2 hooks = 9dᵇ 144 mm


length of 90 deg bend = 2dᵇ 16 mm
no of 90deg bend = 3
0 & 135deg bend total length of 90deg bend = 48 mm
length due135 deg bend = 3dᵇ 24 mm
no of bend = 2
total length due to 135 deg bend 48 mm

ation Length Alternate bar


0.3L
0.15L

ation Length Alternate bar


0.3L
0.15L
ation Length Alternate bar
0.3L
0.15L

ation Length Alternate bar


0.3L
0.25L

bar 1
bar 2
0.15L
0.3L
0.25L

Spacing for d/s bar placement

ation Length Alternate bar


0.3L
0.15L

Spacing for D/s bar placing = clear span-(0.15l-half wall thickness)-0.25l


= 1577.744

Extra bar for one side = 4


Extra bar for other side = 4
ation Length Alternate bar
0.3L
0.15L

Spacing for D/s bar placing = clear span-(0.15l-half wall thickness)-0.25l


= 1577.744

Extra bar for one side = 4


Extra bar for other side = 4

ation Length Alternate bar


0.3L
0.15L

Spacing for D/s bar placing = clear span-(0.15l-half wall thickness)-0.25l


= 1394.817
Extra bar for one side = 2
Extra bar for other side = 2

ation Length Alternate bar


0.3L
0.15L

Spacing for D/s bar placing = clear span-(0.15l-half wall thickness)-0.25l


= 1577.744
Extra bar for both side = 8
bar 1
bar 2

0.15L
0.3L
0.25L
e ht of beam
Clear Cover in beam/slab = 25 mm

d=dia. Of bar

20 mm bar

16 mm bar

gth 2d length
878049 mm

db= bar dia.

Elongation Length for 45 deg bend = 1db 10 mm


90 deg bend = 2db 20 mm
Inclined Length = 0.42d
d=effective depth of slab
d= 90 mm
0.42d= 37.8 mm
Alternate bar overhang length=0.3L
731.707317 mm

Elongation Length for 45 deg bend = 1db 10 mm


90 deg bend = 2db 20 mm
Inclined Length = 0.42d
d=effective depth of slab
d= 90 mm
0.42d= 37.8 mm
Alternate bar overhang length=0.3L
731.707317 mm

Elongation Length for 45 deg bend = 1db 10 mm


90 deg bend = 2db 20 mm
Inclined Length = 0.42d
d=effective depth of slab
d= 90 mm
0.42d= 37.8 mm
Alternate bar overhang length=0.3L
640.243902 mm

Elongation Length for 45 deg bend = 1db 10 mm


90 deg bend = 2db 20 mm
Inclined Length = 0.42d
d=effective depth of slab
d= 90 mm
0.42d= 37.8 mm
Alternate bar overhang length=0.3L
731.707317 mm
Elongation Length for 45 deg bend = 1db 8 mm
90 deg bend = 2db 16 mm
Inclined Length = 0.42d
d=effective depth of slab
d= 90 mm
0.42d= 37.8 mm
Alternate bar overhang length=0.3L
f wall thickness)-0.25l 1829.26829 mm

Elongation Length for 45 deg bend = 1db 8 mm


90 deg bend = 2db 16 mm
Inclined Length = 0.42d
d=effective depth of slab
d= 90 mm
0.42d= 37.8 mm
Alternate bar overhang length=0.3L
f wall thickness)-0.25l 1829.26829 mm

Elongation Length for 45 deg bend = 1db 8 mm


90 deg bend = 2db 16 mm
Inclined Length = 0.42d
d=effective depth of slab
d= 90 mm
0.42d= 37.8 mm
Alternate bar overhang length=0.3L
f wall thickness)-0.25l 1829.26829 mm

Elongation Length for 45 deg bend = 1db 8 mm


90 deg bend = 2db 16 mm
Inclined Length = 0.42d
d=effective depth of slab
d= 90 mm
0.42d= 37.8 mm
Alternate bar overhang length=0.3L
f wall thickness)-0.25l 2286.58537 mm