You are on page 1of 10

PILE CAP DESIGN(1 PILE): P600

Grade of concrete = 25 N/mm2


Grade of steel = 500 N/mm2
Diameter of pile = 500 mm
Length of beam = 0.8 m
Breadth of beam = 0.8 m
Load from column(W) = 800 kN
Selfweight of pile cap = 40 kN
Total load = 840 kN
B.M. on beam(M) = 336 kNm
d = 348.91 mm
Clear Cover = 60 mm
Dia of bar used 16 mm
Overall depth = 432.91 mm
Min. required depth of pile cap = 750.00 mm
Overall depth provided (D) = 800 mm *NOTE: Depth should b
Actual effective depth(d) = 716 mm
Mu/bd2 = 0.82
pt(from table 4 of SP16) = 0.12 %
Ast = 1145.6 mm2
No. of bars = 5.70
No. of bars provided = 10.00 spacing
Distribution R/F = 401.92 mm2
No. of bars provided = 10.00 spacing
Actual pt = 0.35 %
Check for punching shear:
Load/m = 1050.00 kN/m
Shear Force(Vu) = 630.000 kN
Tv = 1.10 N/mm2
Tc(from table 19 of IS456) = 0.365 N/mm2
Shear R/F required
Shear resistance of concrete = 209072.000 N
Net shear force for which shear R/F is necessary = 420928.000 N
Let stirrup bar dia = 16 mm
No. of legs of stirrup = 2
Area of 1 bar = 401.920 mm2
Spacing of stirrups = 297.395 mm
900x900x950
8-#20

*NOTE: Depth should be sufficient to accommodate 50xdia of col. bars


Min. depth to be 1.5 x pile dia

57.77778

57.77778
PILE CAP DESIGN(2 PILES): 2- P50

Grade of concrete = 25 N/mm2


Grade of steel = 500 N/mm2
Diameter of pile = 500 mm
Length of beam = 2.3 m
Breadth of beam = 0.8 m
Load from column(W) = 3000 kN
Selfweight of pile cap = 150 kN
Total load = 3150 kN
Distance between 2 piles = 1500 mm
B.M. on beam(M) = 1125 kNm
d req = 638.44 mm
Clear Cover = 60 mm
Dia of bar used 25 mm
Overall depth = 735.94 mm
Min. required depth of pile cap = 750.00 mm
Overall depth provided (D) = 1000.00 mm *NOTE: Depth should b
Actual effective depth(d) = 902.5 mm
Mu/bd2 = 1.73
pt(from table 4 of SP16) = 0.532 %
Ast = 3841.04 mm2
No. of bars = 7.83
No. of bars provided = 8.00 spacing
Distribution R/F = 785.00 mm2
No. of bars = 16.00 spacing
Actual pt = 0.54 %
Check for punching shear:
Load/m = 1369.57 kN/m
Shear Force(Vu) = 2362.500 kN
Tv = 3.27 N/mm2
Tc(from table 19 of IS456) = 0.370 N/mm2
Shear R/F required
Shear resistance of concrete = 267140.000 N
Net shear force for which shear R/F is necessary = 2095360.000 N
Let stirrup bar dia = 20 mm
No. of legs of stirrup = 2
Area of 1 bar = 628.000 mm2
Spacing of stirrups = 117.662 mm
-Values to be entered

2300x800x1000
8-#25
16-#25

*NOTE: Depth should be sufficient to accommodate 50xdia of col. bars


Min. depth to be 1.5 x pile dia

70.916289474588 mm

118.66666666667 mm
PILE CAP DESIGN(2 PILES): 2- P70

Grade of concrete = 25 N/mm2


Grade of steel = 415 N/mm2
Diameter of pile = 700 mm
Length of beam = 3.1 m
Breadth of beam = 1 m
Load from column(W) = 5000 kN
Selfweight of pile cap = 250 kN
Total load = 5250 kN
Distance between 2 piles = 2100 mm
B.M. on beam(M) = 2625 kNm
d req = 872.28 mm
Clear Cover = 60 mm
Dia of bar used 32 mm
Overall depth = 980.28 mm
Min. required depth of pile cap = 1050.00 mm
Overall depth provided (D) = 1400.00 mm *NOTE: Depth should b
Actual effective depth(d) = 1292 mm
Mu/bd2 = 1.57
pt(from table 4 of SP16) = 0.467 %
Ast = 6033.64 mm2
No. of bars = 7.51
No. of bars provided = 8.00 spacing
Distribution R/F = 1286.14 mm2
No. of bars = 16.00 spacing
Actual pt = 0.50 %
Check for punching shear:
Load/m = 1693.55 kN/m
Shear Force(Vu) = 3937.500 kN
Tv = 3.05 N/mm2
Tc(from table 19 of IS456) = 0.370 N/mm2
Shear R/F required
Shear resistance of concrete = 478040.000 N
Net shear force for which shear R/F is necessary = 3459460.000 N
Let stirrup bar dia = 12 mm
No. of legs of stirrup = 2
Area of 1 bar = 226.080 mm2
Spacing of stirrups = 30.485 mm
-Values to be entered

3100x1000x950
8-#32
16-#32

*NOTE: Depth should be sufficient to accommodate 50xdia of col. bars


Min. depth to be 1.5 x pile dia

98.340800795442 mm

164.53333333333 mm
PILE CAP DESIGN(3-PILES): 3-p60

Grade of steel = 415.000 N/mm2


Load on pile = 670.000 kN
Reaction at A, B & C = 223.333 kN
Reaction at D = 446.667 kN
Dia of pile = 500.000 mm
c/c distance between piles = 1500.000 mm
Length of beam DC = 2099.038 mm
Length of beamAB = 1500.000
Width of beam DC = 800.000 mm
Min. required depth of pile cap = 750.000 mm
Let depth of beam DC = 1300.000 mm *NOTE: Depth should be su
Selfweight of beam DC = 54.57 kN/m
BM at G due to selfweight = 60.114 kNm
BM due to col. Load on beam DC = 193.412 kNm
Total BM = 253.526 kNm
BM due to col. Load on beam AB = 335.000 kNm
BM due to selfweight = 15.349 kNm
BM due to self weight transferred by beam DC to beam AB = 60.114 kNm
Total BM on beam AB = 410.463 kNm
Factored BM = 615.695 kNm
Clear cover = 60.000 mm
Dia of bar used = 16.000 mm
Effective depth = 1232.000 mm
Design of beam DC:
Mu/bd2 = 0.209
pt from table 4 of SP16 = 0.084 %
Ast = 827.90 mm2
No. of bars = 4.12
No. of bars provided = 5.00 spacing
Distribution Reinforcement = 200.96 mm2
No. of bars provided = 7.00 mm2 spacing
Actual pt = 0.102 %
Design of beam AB:
Mu/bd2 = 0.338
pt from table 4 of SP16 = 0.099 %
Ast = 975.744
No. of bars = 4.86
No. of bars provided = 5.00 mm2
Distribution Reinforcement = 1.000 mm2
Check for punching shear:
Load/m = 54.89 kN/m
Shear Force(Vu) = 86.419 kN
Tv = 0.09 N/mm2
Tc(from table 19 of IS456) = 0.400 N/mm2
Provide min. shear R/F
Shear resistance of concrete = 394240.000 N
Let stirrup bar dia = 16 mm
No. of legs of stirrup = 2
Area of 1 bar = 401.920 mm2
Spacing of stirrup = 453.479 mm
Provide Ф12@200mm c/c
A D
*NOTE: Depth should be sufficient to accommodate 50xdia of col. bars
Min. depth to be 1.5 x pile dia

150 mm

325.8397 mm
D B

You might also like