You are on page 1of 27

Part 6

Superstructure (excluding roofs)

6.1 External masonry walls

6.2 External timber framed walls

6.3 Internal walls

6.4 Timber and concrete upper floors

6.5 Steelwork

6.6 Staircases

6.7 Doors, windows and glazing

6.8 Fireplaces, chimneys and flues

6.9 Curtain walling and cladding

6.10 Light steel framed walls and floors


Part 6 Superstructure (excluding roofs)

Chapter 6.1
External masonry walls
6.1 External masonry walls

CONTENTS

DESIGN Clause Page APPENDIX 6.1-A


Design standards D1 1 Suitable wall constructions 16
Statutory requirements D2 1 APPENDIX 6.1-B
Structural design D3 1 Areas of severe exposure to frost attack 18
Exposure D4 2 APPENDIX 6.1-C
Mortar D5 3 Mortar mixes 20
Damp-proof courses and cavity trays D6 3 APPENDIX 6.1-D
Wall ties D7 4 Dpcs and cavity trays 21
Stone masonry D8 4 APPENDIX 6.1-E
Lintels D9 4 Durability classification of bricks 22
Thermal insulation D10-D11 5 APPENDIX 6.1-F
Fire safety D12 5 Protection of ancilliary components 22
Sound insulation D13 5
Claddings D14 5 INDEX 22
Rendering D15 5
Provision of information D16-D17 6
Scope
MATERIALS
Materials standards M1 7
This Chapter gives guidance on meeting the Technical
Bricks M2 7 Requirements and recommendations for external masonry
Blocks M3 7 walls.
Stone masonry M4 8
Mortar and rendering M5 8
Dpc materials M6 8
Wall ties M7 8
Lintels M8 8
6.1

Thermal insulation M9 8
Cladding materials M10 8
Movement joints M11 9

SITEWORK
Sitework standards S1 9
Construction S2 9
Stone masonry S3 11
Damp-proof courses and cavity trays S4 11
Wall ties S5 12
Lintels S6 13
Thermal insulation S7 14
Rendering S8 14
Cold weather working S9 15
Handling and protection S10 15
External masonry walls 6.1
(d) point loads The spacing of the first movement joint
DESIGN STANDARDS Padstones and spreaders may be from a return should not be more than half
necessary and, where required, should be of the above dimension.
6.1 - D1 Design shall meet the Technical located beneath areas of concentrated
Requirements When different materials are used
loads.
together, consideration should be given to
Design that follows the guidance below will
(e) chases potential differential movement. Wall ties
be acceptable for external masonry walls.
The position and depth of chases for are needed on either side of movement
services should be considered. Horizontal joints (reference should be made to Clause
STATUTORY chases should be limited to one-sixth the D7 and Sitework clause 6.1 - S5).
REQUIREMENTS thickness of a single leaf, and vertical
Movement joints should run the full height
chases to one-third the thickness of a
6.1 - D2 Design shall comply with all of the masonry wall. Any movement
single leaf.
relevant statutory requirements joints provided in the substructure must
Particular care is needed where hollow be carried up into the superstructure.
Design should be in accordance with
blocks are specified. Hollow blocks Movement joints may be needed in the
relevant Building Regulations and other
should not be chased, unless specifically superstructure where none are required
statutory requirements.
permitted by the manufacturer. in the substructure - however suitable
allowance should be made for relative
STRUCTURAL DESIGN (f) bonding movement.
When partition walls abut the external
6.1 - D3 External cavity and solid Where masonry walls form panels in a
wall and are of similar materials, they may
walls shall be designed to support and framed structure, movement joints should
be either fully bonded or tied together.
transfer loads to foundations safely and be provided in accordance with BS EN
Where materials have dissimilar shrinkage
without undue movement 1996-2.
or expansion characteristics, eg dense
Items to be taken into account include: concrete and aerated concrete, a tied joint Details of suitable materials to form
(a) standards is preferable as this will reduce the risk of movement joints are given in the Materials
Structural design should be in accordance random cracking. section of this chapter.
with BS EN 1996-1-1.
In the case of a connection between a Where movement joints are provided to
Intermediate floors and roofs should be loadbearing wall on foundations and a control shrinkage in concrete blockwork,
designed to provide lateral restraint to non-loadbearing wall supported on a they may be simple vertical joints filled
external walls, in accordance with BS 8103 ground bearing slab, it is preferable to tie, with mortar and sealed.
and ancillary components to BS EN 845-1. not bond, the walls. This will reduce the
risk of cracking due to differential vertical To ensure the sealant is effective, there
Walls of dwellings or buildings containing movement. should be a good bond with the masonry.
dwellings over three storeys high should The sealant should be at least 10mm deep
be designed in accordance with Technical Tied joints should be formed using or in accordance with manufacturers’
Requirement R5. expanded metal, wire wall ties or a instructions.

6.1
proprietary equivalent, at maximum
(b) lateral restraint provided by concrete 300mm intervals. Movement joints are not normally
floors necessary to the inner leaf of cavity walls
Concrete floors, with a minimum 90mm (g) movement joints but consideration should be given to
bearing onto the wall, provide adequate Movement joints should be provided, providing:
restraint. where necessary, and in such a way that • movement joints in rooms with straight
stability is maintained. If no provision unbroken lengths of wall over 6m. This is
Concrete floors running parallel to and is made for both initial and long term unnecessary for fired clay bricks
not built into walls require restraint straps movements, masonry walls may crack. • bed joint reinforcement as an alternative
to provide restraint to the wall (reference to movement joints in areas of risk, eg
should also be made to Chapter 6.4 Vertical movement joints should be
under window openings.
‘Timber and concrete upper floors’ (each provided in the outer leaf to minimise the
section)). risk of major cracking, as shown in the To reduce cracking and to maintain the
following table: level of thermal resistance:
(c) lateral restraint provided by timber • bricks and blocks, or blocks of different
floors Material Joint Normal spacing densities, in a wall should not be mixed
Timber joisted floors can provide adequate width • a joint should be formed where
restraint when joists are carried by (mm) dissimilar materials abut
ordinary hangers to BS EN 845 and Clay brick 16 12m (15m maximum) • the joint should be tied (eg with
connected to the wall with restraint straps. expanded metal in the bed joint) unless
Calcium 10 7.5 to 9m
In buildings of not more than two storeys, silicate the joint is to act as a movement joint.
timber joisted floors can provide adequate brick
Where cracking is likely, walls should be
restraint without strapping when: Concrete 10 6m dry lined or clad (reference should also be
• the minimum bearing onto masonry block and made to Sitework clause 6.1 - S2(g)).
is 90mm (or 75mm onto a timber wall brick
plate), or Any 10 half the above (h) calcium silicate brickwork
• joists are carried by restraint type masonry in spacings and 1.5m Design of calcium silicate brickwork
hangers, as described in BS EN 845-1 a parapet from corners (double should follow the the brick manufacturer’s
with performance equivalent to a wall the frequency) recommendations.
restraint strap at not more than 2m
centres. (i) cladding to framed structures
Allowance should be made for differential
movement between cladding and frame.

2013 Chapter 6.1 Page 1


6.1 External masonry walls

The following precautions should be taken • below dpc where there is a high risk of In Scotland, Northern Ireland, the Isle of
to prevent buckling and fracturing of saturation Man and in other places where the
masonry panels: • retaining walls exposure to driving rain is Very Severe,
• flexible movement joints should be • parapets masonry should form a rebate at the
provided at the underside of each • freestanding walls reveals of openings to avoid a straight
horizontal support member • rendered walls through joint where the frame abuts the
• the masonry outer leaf should have at • areas of Severe or Very Severe exposure masonry.
least two-thirds of its width supported to driving rain. Minimum 12mm overlap of
masonry (or render) to frame
securely by the concrete frame or a
Reclaimed bricks should be used only in
metal angle sealant ‘rebated‘ or
accordance with Technical Requirement R3. ‘check‘ reveal
• the inner leaf should be adequately tied 25mm
in areas of Very
severe exposure
to the structural frame. Forked plate (b) rain penetration
ties held in dovetail slots, cast into the Rainwater will penetrate the outer leaf of
sealant

column or an equivalent are acceptable a masonry wall in prolonged periods of


• vertical movement joints should be driving rain. Resistance to rain penetration
provided at corners. of masonry walls can be improved by Proprietary cavity closers may be an
cladding the wall. Total resistance can only acceptable alternative provided they have
For timber framed construction, reference
be achieved with an impervious cladding. been assessed in accordance with
should be made to Chapter 6.2 ‘External
Technical Requirement R3. For information
timber framed walls’ (Design). The following should be taken into account on doors and windows, reference should be
to minimise the risk of rain penetration: made to Chapter 6.7 ‘Doors, windows and
(j) corbelling
• determination of the exposure to wind glazing’ (each section).
The size of corbels should not exceed the
driven rain
dimensions given in Sitework clause In Scotland and areas of Severe or Very
• a suitable wall construction and
6.1 - S2(j). Severe exposure to driving rain, cavities
insulation method
• design detailing for the local exposure, should be continuous around enclosed
EXPOSURE taking into account the likely quality of porches and habitable areas.
6.1 - D4 External walls shall be suitable workmanship on site. Cavity trays should be used at junctions
for their exposure and resist the A very high standard of workmanship with roof (reference should also be made
passage of moisture to the inside of the is required to ensure that cavities are to Clause D6).
dwelling not bridged. Where full or partial cavity Sills, copings and the like should be
In this Chapter, reference is made to insulation is proposed, the installation weathered and throated unless adequate
exposure to: should follow the recommendations of any alternative provision is made to protect the
• wind driven rain assessment and the manufacturer. brickwork from saturation, frost damage
• frost attack. and staining.
The most exposed part of the building
Details of how these are defined are should be given particular attention when
(c) frost attack
6.1

contained in Appendices 6.1-A and 6.1-B. selecting a suitable construction method


The main factors affecting frost attack are:
as this may affect the choice for the whole
Items to be taken into account include: • degree of exposure (incidence of frost)
building.
(a) general aspects affecting durability • saturation of the masonry
Masonry in the following locations is The following aspects of design can reduce • frost resistance of the masonry
particularly likely to become saturated and the risk of rain penetration: • localised protection of the masonry
may remain so for long periods. Precautions • providing cladding (other than render) by roof overhangs, trees and other
as necessary should be taken to resist frost to the wall. Even if cladding is only buildings.
damage and sulfate attack in: added to gable walls and upper floors, it
Areas of severe frost exposure are shown
• parapet walls and copings reduces rain penetration
on the map in Appendix 6.1-B.
• sills and projections • increasing the clear cavity width or the
• masonry below dpc at ground level width of full cavity insulation. Increasing In areas of exceptionally severe frost
• freestanding walls. the cavity width for full cavity insulation exposure, which is defined as a location
from 50mm to 75mm or more greatly which is in a severe frost exposure area
The selection of bricks and mortar should reduces the risk of rain passing through and, in addition, faces long stretches of
follow the recommendations given the cavity. A nominal cavity of 50mm is open countryside, only frost-resistant
in BS EN 1996-1-1 and manufacturers’ always required on the outside of partial bricks (F2,S2 or F2,S1 to BS EN 771) are
recommendations. cavity insulation acceptable for the superstructure.
• rendering the wall (reference should also
In addition to the mortar designations In areas of severe frost exposure, the
be made to Clause D15). Specify backing
given in BS EN 1996-1-1, the following following are acceptable:
material carefully to avoid cracking
mortar mixes can be used with ordinary • clay facing bricks which are frost-
which can reduce the effectiveness of
Portland cement or sulfate-resisting resistant (F2,S2 or F2,S1 to BS EN 771).
render against rain penetration
cement: Reference should be made to Appendix
• designing protective features to keep
• air-entrained 1 : 1 : 5½ cement : lime : 6.1-E for the freeze/thaw resistance
sand, or
the wall dry, eg projecting sills and deep
overhanging eaves and verges classification of bricks to BS EN 771
• air-entrained 1 :½ : 4½ cement : lime : • clay bricks which are classified
• mortar joints. All joints should be fully
sand. in manufacturers’ published
filled. Where full cavity insulation is
Sulfate-resisting cement should be used proposed, recessed joints should not be recommendations as satisfactory for the
where clay bricks with S1 designation are used. Reference should also be made to exposure
used as follows: Clause D5(c). • calcium silicate bricks (in accordance
In areas of Very Severe exposure to driving with BS EN 771)
• below dpc where there are sulfates • concrete bricks with a strength not less
rain and in Scotland the cavity should not
present in the ground than 20N/mm2
contain full fill insulation.

Page 2 Chapter 6.1 2013


External masonry walls 6.1
• concrete blocks with a density not less bricks without the brick manufacturer’s (d) admixtures and additives
than 1500kg/m3 or of strength not less written agreement. Calcium chloride should not be used as
than 7.3N/mm2 an admixture to mortar. The contents of
• most types of aerated concrete blocks MORTAR admixtures should be checked to ensure
with render. that they do not contain calcium chloride.
6.1 - D5 Mortar shall be of the mix
In Scotland, all clay bricks used as facings proportions necessary to achieve Admixtures should only be used in
should be frost-resistant (F2,S2 or F2,S1 to adequate strength and durability and be accordance with manufacturers’
BS EN 771). suitable for the type of masonry recommendations/instructions.
If there are doubts about the suitability Items to be taken into account include: Mortars containing an air-entraining
of a facing brick for sites in areas of plasticiser are more resistant to freeze/
exceptionally severe frost exposure (a) geographical location and position thaw damage when set.
classification, written confirmation should within the structure
Recommended mortar mixes for different White cement to BS EN 197 and pigments
be obtained from the brick manufacturer
locations are given in Appendix 6.1-C. to BS 1014 may be used, but pigments
that the brick is suitable for:
should not exceed 10% of the cement
• its geographical location, and
(b) sources of sulfate weight or 3% if carbon black is used.
• its location in the structure.
Ordinary Portland cement mortar can
Further advice concerning admixtures is
This applies particularly to bricks such expand, crumble and deteriorate badly
given in Appendix 6.1-C.
as fletton facings which are moderately if attacked by sulfates. Sufficient soluble
freeze/thaw resistant (F1,S2 or F1,S1). sulfate to cause this problem may be
In addition, follow manufacturers’ contained in clay bricks. Clay bricks with DAMP-PROOF COURSES
recommendations on suitability, including an S1 designation have no limit on their AND CAVITY TRAYS
the choice and use of mortar and the type sulfate content. The problem is most acute
of pointing. when brickwork is saturated for long 6.1 - D6 Damp-proof courses and related
periods; mortar is vulnerable to attack by components shall be provided to prevent
Recessed joints should only be used in moisture rising or entering the building
any soluble sulfates present.
compliance with Clause D5(c).
To reduce the risk, sulfate-resisting Items to be taken into account include:
Bricks that are not frost-resistant (F0,S2 or
Portland cement to BS 4027 should be (a) dpcs
F0,S1 to BS EN 771) may not be acceptable
used: Damp-proof courses should be provided
for use externally, unless completely
• below dpc level when sulfates are in accordance with the Table in Appendix
protected by a cladding which can
present in the ground 6.1-D.
adequately resist the passage of water.
• when clay bricks (F2,S1 and F1,S1 to BS
Good brickwork detailing can limit EN 771) are used, and there is a high At complicated junctions, clear drawings
persistent wetting of brickwork and reduce saturation risk, for example in the should be provided and preformed
the risk of frost attack. following situations: profiles specified. Isometric drawings
-- parapets can sometimes be clearer than the

6.1
For example: -- chimney stacks combination of plan and section/elevation
• paths should drain away from walls to -- retaining walls drawings.
avoid saturating bricks near the ground -- freestanding walls
• sills, copings and the like should have a -- rendered walls (b) cavity trays
weathered upper surface -- areas of Severe or Very Severe Cavity trays should be provided at all
• a coping should be provided for exposure to driving rain. interruptions to the cavity, eg window
all parapet walls, chimneys and and door openings, air bricks, etc, unless
freestanding walls unless clay bricks of (c) joints otherwise protected, eg by overhanging
F2,S1 or F2,S2 classification to BS EN Struck (or weathered) and bucket handle eaves.
771 have been used. Copings should joints are preferable.
A cavity tray should:
have a generous overhang, throatings
Recessed joints should not be used where: • provide an impervious barrier and
at least 40mm clear of the wall and a
• bricks are perforated nearer than 15mm ensure that water drains outwards
continuous, supported dpc underneath
to the face • project at least 25mm beyond the outer
which projects beyond the line of the
• bricks are not frost resistant (if clay F1,S1 face of the cavity closure or, where
wall. Single leaf parapet walls should not
or F1,S2 to BS EN 771), unless the brick a combined cavity tray and lintel is
be rendered on both sides.
manufacturer has agreed in writing for acceptable, give complete protection to
Where there is a risk that brickwork may their use in a particular location the top of the reveal and vertical dpc
be persistently wet, bricks should be • there is no reasonable shelter from where provided
specified that are low in soluble salts (if driving rain (reasonable shelter could • provide drip protection to door and
clay, F2,S2 or F1,S2 to BS EN 771). be from buildings or groups of trees window heads
if these are within 50m and of similar • have an overall minimum upstand from
Note height to the dwelling) the inside face of the outer leaf to the
Only clay bricks designated L by BS EN • the dwelling is built on steep sloping outside of the inner leaf of 140mm
771 have a low limit on their soluble salt ground, facing open countryside or • be shaped to provide at least a 100mm
content. In persistently wet conditions, clay within 8km of a coast or large estuary vertical protection above a point where
bricks of S1 designation may create sulfate • the cavity is to be fully filled with cavity mortar droppings could collect.
attack on the mortar. insulation.
Painted or decorated finishes can trap Jointing is preferable to pointing because
moisture in external brickwork and it leaves the mortar undisturbed.
increase the risk of frost damage, sulfate
attack or other detrimental effects. They
should not be applied to S1 designation

2013 Chapter 6.1 Page 3


6.1 External masonry walls

throating Minimum bearing length (mm)


clear of
brickwork Span (m) Simple Lintel combined
lintel with cavity tray
dpc supported Up to 1.2 100 150
at least at least over cavity
140mm 100mm Over 1.2 150 150

To avoid overstressing, composite lintels


open perpend
weep holes at
should have the required depth of fully
maximum 1m
spacing at least bedded brickwork stipulated by the
150mm
shape of an
effective
manufacturer above the lintel, before
cavity tray point loads are applied. Where necessary,
padstones and spreaders should be
In Scotland, Northern Ireland, the Isle of provided under the bearings of lintels.
Man and areas of Very Severe exposure to Reference should be made to Chapter
driving rain, the upstand part of the damp- 6.5 ‘Steelwork support to upper floors
proof protection should be returned into and partitions’ (Design) for details of
(e) materials padstones.
the inner leaf of masonry except at sloping
Materials that are suitable for use as dpcs
abutments. In all other areas, the upstand (b) adequate durability against corrosion
are given in Materials clause 6.1 - M6.
should be returned into the inner leaf and resistance to water entering the
unless it is stiff enough to stand against
the inner leaf without support. WALL TIES dwelling
Cavity tray/damp-proof protection should
Where fairfaced masonry is supported by 6.1 - D7 Wall ties shall be provided, be provided over all openings, either as a
lintels: where required, to tie together the combined part of the lintel or separately.
• weep holes should be provided at leaves of cavity walls Reference should be made to Clause D6(b).
450mm (maximum) centres with at least The spacing of wall ties in masonry walls Steel and concrete lintels should comply
two weep holes per opening should be in accordance with Sitework with BS EN 845-2.
• cavity trays or combined lintels should clause 6.1 - S5.
have stop ends. Separate cavity tray protection should be
Details of suitable wall ties are given in the provided when:
Where full fill insulation is placed in the Materials section of this Chapter. • the profile of the lintel is not as shown in
cavity, a cavity tray should be used above
Clause D6(b), or
the highest insulation level, unless the STONE MASONRY • steel lintels have materials coatings
insulation is taken to the top of the wall.
references L11, L14 and L16.1 and are
(Manufacturers’ recommendations should 6.1 - D8 Elements constructed of
used in external walls
be followed.) natural or cast stone masonry shall
comply with the performance standards Lintels used in aggressive environments
6.1

(c) abutment details for brick and block masonry, where (e.g. coastal sites) should be austenitic
Cavity trays should be provided at applicable stainless steel.
abutments of roofs and cavity walls. This
will ensure that any water penetrating into Stone masonry (natural or cast stone) In Scotland, Northern Ireland, the Isle of
the cavity does not enter the enclosed should be designed to meet the Man and areas of Severe or Very Severe
area. This only applies where the roof requirements of BS EN 1996 ‘Design of exposure to driving rain, separate damp-
is over an enclosed area, including an masonry structures’. proof protection should be provided over
attached garage, but does not apply to all lintels in accordance with the guidance
open car ports and open porches. LINTELS for cavity trays given in Clause D6(b).

Where the roof abuts at an angle with 6.1 - D9 Lintels shall safely support the Lintels should be of such a size and be
the wall, preformed stepped cavity trays applied loads located so that the external edge of the
should be provided. Items to be taken into account include: lintel projects beyond, and therefore offers
protection to, the window head.
(a) structural support
preformed
stepped Concrete, steel and reinforced brickwork (c) cold bridging and condensation
cavity trays
are acceptable materials for use as lintels. The BRE Report ‘Thermal insulation:
Timber lintels should not be used, unless: avoiding risks’ discusses aspects of
• they are protected from the weather, insulation relevant to external masonry
and walls. In England and Wales account should
• they do not support masonry or other be taken of Accredited Details.
at least
85mm rigid or brittle materials. The risk of condensation at reveals and
Lintels should be designed in accordance soffits becomes more likely as the wall
either with Technical Requirement R5 or insulation increases. Cold bridge paths
manufacturers’ published data. A lintel should be avoided.
should be provided where frames are not To avoid a cold bridge, the wall insulation
designed to support superimposed loads. should ideally abut the head of the window
(d) parapet details
Lintels should be wide enough to provide frame.
Dpcs below the coping should be
supported over the cavity to prevent adequate support to walling above. Clause D4(b) details methods of preventing
sagging. A dpc should be specified that can Masonry should not overhang the lintel rain penetration which may also be
achieve a good key with the mortar. support by more than 25mm. A lintel required.
should extend beyond the opening at each
end by at least the following lengths:

Page 4 Chapter 6.1 2013


External masonry walls 6.1
(d) adequate fire resistance (c) partial cavity insulation SOUND INSULATION
Where steel lintels are used, Partial cavity insulation should be fixed
manufacturers’ recommendations for only against the cavity face of the inner 6.1 - D13 External walls adjacent to
providing adequate fire resistance, leaf. The clear cavity width between partial sound-resisting walls shall be designed
particularly to the lower steel flange, cavity insulation and the outer leaf should to adequately resist flanking sound
should be followed. be at least 50mm nominal. In areas of Very transmission
Severe exposure in England and Wales, a Acceptable levels of sound reduction
THERMAL INSULATION residual cavity of 75mm is required where between dwellings may be achieved by:
the outer leaf is fair faced masonry. • the inner leaf of an external cavity wall
6.1 - D10 External walls shall be
Wall ties should be long enough to allow a having sufficient weight, and
designed to provide the required
50mm embedment in each masonry leaf. • sealing of air paths
standard of thermal insulation
• allowing appropriate spacings between
The insulation value of the wall must meet (d) inner leaf of insulated blockwork openings in external walls.
the requirements of the relevant Building Types of blockwork include:
Regulations. The density of external walls and the
• lightweight aerated concrete
position of openings adjacent to sound-
• lightweight aggregate blocks
Design should avoid cold bridging at resisting walls should be in accordance
• voided blocks with insulation infill
openings and at junctions of external walls with statutory requirements and, where
• blocks faced with insulation material.
with roofs, floors and internal walls. relevant, an assessment which complies
Manufacturers’ recommendations should with Technical Requirement R3.
6.1 - D11 External walls shall be designed be followed and particular note taken of
to ensure the correct use of insulation
materials
the following: CLADDINGS
• a clear 50mm wide cavity should always
be maintained 6.1 - D14 Cladding shall satisfactorily
Items to be taken into account include:
• the blocks should be capable of resist the passage of moisture
(a) acceptable insulation materials
Insulation, or lightweight aerated concrete supporting concentrated loads Items to be taken into account include:
blocks, or blocks with face bonded • the correct type of joist hanger for the (a) battens
insulation, or voided blocks with insulation type and size of block and size of joist Where battens are required, they must be
infill should be used in accordance with: should be used pre-treated with preservative, as described
• an assessment which complies with • long unbroken lengths of blockwork in Chapter 2.3 ‘Timber preservation
Technical Requirement R3, or should be avoided (natural solid timber)’ (each section).
• a British Standard and the relevant Code • precautions should be taken to reduce
of Practice. risk of shrinkage cracking (b) joints
• dry lining should be used where Joints between claddings and adjacent
(b) full cavity insulation shrinkage cracking might be unsightly materials should be detailed to be
In Northern Ireland and the Isle of Man, and to avoid long term pattern staining watertight under the particular exposure
it is not permissible to fill cavities with at mortar joints conditions of the site. Where necessary,

6.1
pumped thermal insulants at the time of • restrictions on chasing for services provision should be made for differential
construction. when using voided blocks should be movement.
noted (reference should be made to
In Scotland, it is not permissible to fill the (c) moisture barriers
Clause D3(e)).
full width of the cavity with any thermal Unless specifically not required for a
insulants at the time of construction. (e) dual insulation proprietary cladding, moisture barriers
Where partial cavity insulation is used should be provided between walls of solid
The type of insulation, its thickness and
in addition to an insulated block inner masonry and any boarding, slating, tiling
the wall construction should be suitable for
leaf (reference should be made to Clause or other similar claddings. The moisture
the exposure of the dwelling in accordance
D11(c)), the whole composite construction barrier may be roofing underfelt or
with Appendix 6.1-A.
should have been assessed in accordance equivalent.
Materials clause 6.1 - M9 sets out the range with Technical Requirement R3.
of acceptable insulation materials and the Vapour barriers such as polyethylene
relevant British Standards. (f) insulated dry linings sheet are not an acceptable moisture
Where an insulated dry lining contains a barrier as they can trap moisture in the
Render on an external leaf of clay bricks combustible insulant, the plasterboard structure.
(F2,S1 or F1,S1 designation bricks to BS EN should be at least 12.5mm thick and
771) in Severe or Very Severe exposures mechanically fixed to the masonry inner For timber framed walls clad with masonry,
is not permitted where the cavity is to be leaf. This is to prevent early collapse of the reference should be made to Chapter 6.2
fully filled with insulation. lining in a fire. ‘External timber framed walls’ for details.

The following design points should be (d) vertical tile or slate cladding
noted: FIRE SAFETY Every tile or slate should be nailed with
• stop ends should be provided to cavity 6.1 - D12 Cavity walls shall adequately two nails. Nails should be aluminium,
trays or combined lintels resist the passage of fire copper or silicon bronze.
• weepholes should be provided at
Cavities should be closed with cavity Bottom edges should be finished with an
450mm (maximum) centres with at least
closers in accordance with statutory under-course and tilting batten.
two per opening
• mortar joints should not be recessed requirements.
(e) timber cladding
• painted finishes on bricks or render are Timber claddings should be pre-treated
not acceptable if they are likely to cause with preservative in accordance with
frost damage or sulfate attack or other Chapter 2.3 ‘Timber preservation (natural
damage. solid timber)’ (each section).

2013 Chapter 6.1 Page 5


6.1 External masonry walls

RENDERING • cement for brickwork mortar is sulfate- Undercoats should be allowed to shrink
resisting to BS 4027 and dry out before applying following
6.1 - D15 Rendering, in conjunction • the brick manufacturer has confirmed, coats. When rendering onto dense
with the surface to which it is applied, in writing, that the brick is suitable, concrete blocks, adhesion can be improved
shall satisfactorily resist the passage of taking account of the brickwork detailing by use of proprietary bonding agents or a
moisture and the particular exposure of each spatterdash coat.
Items to be taken into account include: rendered element. If sulfate-resisting
cement is used in the mortar, it should (g) detailing of timber/brick/render
(a) rain penetration Dwellings which incorporate rendered
also be used in spatterdash coats and
External rendered finishes should comply panels between timber boards should have
base coats of the render.
with BS EN 13914 ‘Design, preparation at least one coat of render applied over
and application of external rendering and Care should be taken when specifying the whole wall face before the boards are
internal plastering’ and the guidance given render to walls with full cavity fill. The lack fixed. The second coat may be applied
below. of a ventilated cavity can slow down the between the boards.
rate at which the wall dries out.
It is important to prevent rainwater Rendering and timber can shrink causing
penetrating behind the rendering. Design Rendered finishes should not be used over gaps. Precautions should be taken to
features around openings and at the head fully filled cavity walls if: prevent rain from penetrating the junction
of the rendering should provide shelter, • the outer leaf is built in bricks with S1 as this might cause the render to fail as a
where possible, and help to shed water designation (F2,S1 and F1,S1 to BS EN result of frost damage.
away from the surface below. 771), and
• the site is in an area classed as Severe All exposed timber, except naturally durable
(b) exposed elements or Very Severe exposure to driving rain species, should be treated in accordance with
It is not advisable to render exposed (see Appendix 6.1-A). Chapter 2.3 ‘Timber preservation (natural
parts of a building, such as parapets and solid timber)’ (each section).
chimneys constructed of clay bricks of S1 Rendering may be used on brickwork
designation, without the use of sulfate- with partial cavity insulation provided a Where timber is used on brick or render,
resisting cement. clear cavity width between insulation and it is essential that all cut ends, mortices,
outer leaf of at least 50mm nominal is etc made after treatment are flood coated
(c) movement maintained. with preservative.
Movements can occur at a change in
Large section timbers should be fitted
material. In such cases, the render should (e) mixes
with suitable weather bars, flashings, etc
be either stopped at specially formed The rendering mix should be appropriate
to prevent moisture penetration through
movement joints or, if the expected to the strength of the background. No
joints with adjacent materials.
movement is small, be reinforced by metal render coat should be stronger than the
lathing carried across the joint. If metal background or richer than the preceding Non-ferrous fixings should be used.
lathing is used, three rendering coats coat. The render should be of adequate Aluminium is not suitable when the
should be applied. strength to achieve durability. preservative is Copper/Chromium/Arsenic.
6.1

(d) background Mixes should comply with the (h) proprietary and local rendering
To achieve a good bond, the masonry recommendations of BS EN 13914 ‘Design, systems
backing should be moderately strong preparation and application of external Proprietary rendering finishes should be
and porous to give some suction and a rendering and internal plastering’. When applied in accordance with manufacturers’
mechanical key. Dense masonry with a rendering on bricks that are F1,S1 or recommendations.
smooth surface should not be rendered. F1,S2 to BS EN 771, the Table to Sitework
clause 6.1 - S8(b) should be followed. The Traditional local rendering should comply
Aerated or lightweight aggregate concrete manufacturer of the background masonry with the above guidance, as appropriate,
blocks can be used, as a background, should be consulted regarding particular and with established local practice.
but more care is needed when selecting requirements for the mix or its application.
a rendering mix and surface treatment.
Strong render mixes should not be used. Pigments complying with the requirements PROVISION OF
Roughcast and dry dash finishes that of BS 1014 may be added to the finishing INFORMATION
require a strong mix are not recommended coat up to a limit of 10% of the cement
6.1 - D16 Designs and specifications
for use on aerated or lightweight weight or 3% in the case of carbon black.
shall be produced in a clearly
aggregate blocks. Block manufacturers’ White Portland cement may be used.
understandable format and include all
recommendations should be followed. relevant information
(f) number and thickness of coats
In Scotland, render should be applied only The number of coats should be chosen For external masonry walls, the drawings
to bricks: with regard to the background and the should show:
• which are keyed, or exposure conditions of the site. • wall layout with all dimensions shown
• where a spatterdash coat has been • position and size of openings
For rendering on masonry cavity walls,
applied before the first render • coursing of the bricks and blocks in
one undercoat and one finishing coat is
undercoat. relation to storey heights and opening
acceptable. On metal lathing or on solid
In other areas, render should be applied wall construction, two undercoats and one positions
only to bricks where either: finishing coat are required. • details at all junctions, indicating
• keyed bricks are used, or position of dpcs and cavity trays.
Initial undercoats should not be less than Isometric sketches are recommended
• the joints are raked out at least 15mm
10mm and not more than 15mm thick. Any for complicated junctions
deep.
further undercoat should be thinner than • position and type of lintels
Render may be applied to bricks (if clay
the preceding coat. Finishing coats should • position of restraint straps
F2,S1 or F1,S1 to BS EN 771) only if the
be generally between 6mm and 10mm • details of cavity closers
following conditions are met:
thick. • details at reveals

Page 6 Chapter 6.1 2013


External masonry walls 6.1
• details of how support is given to other CLAY BRICKS RECLAIMED BRICKS
elements, eg padstones and wall plates BS EN 771 classifies clay bricks according Reclaimed bricks could be unsuitable
• position and detail of movement joints to their freeze/thaw resistance and soluble for external work because of a high salt
• acceptable methods of pointing or salt content (see Appendix 6.1-E). content or a lack of freeze/thaw resistance.
mortar joint finish Their use is permitted only in accordance
Only bricks that are freeze/thaw resistant
• type of insulant to be used with Technical Requirement R3. It is
(F2,S2 or F2,S1 to BS EN 771) should
• type and location of wall ties. advisable to know where they come
be used where there is a high risk of
from, both geographically and within the
6.1 - D17 All relevant information shall prolonged wetting and freezing. Such
previous building. Bricks used internally
be distributed to appropriate personnel areas include:
or fully protected may be unsuitable in
• all external facing work in Scotland
Ensure that design and specification external situations.
• exposed parts including copings, sills
information is issued to site supervisors and parapets and chimneys which have Reclaimed bricks should be considered
and relevant specialist subcontractors and/ no overhang to provide protection. as F1,S1 or F1,S2 to BS EN 771 and used
or suppliers. Reference should be made to Design accordingly. Independent certification of
Where proprietary products are to be clause 6.1 - D4(c) suitability may be required.
used, manufacturers usually have specific • areas of the country subject to
requirements for fixing and/or assembly exceptionally severe freeze/thaw SPECIAL SHAPED BRICKS
of their products. This information should exposure (see map in Appendix 6.1-B). Special shaped bricks should conform to
also be made available for reference BS 4729.
In areas of severe freeze/thaw exposure
on site so that work can be carried out outside Scotland, bricks that are
satisfactorily in accordance with the design moderately freeze/thaw resistant (F1,S1 BLOCKS
and specification. or F1,S2 to BS EN 771) may be used for 6.1 - M3 Concrete blocks shall:
general wall areas, provided they are (a) be capable of supporting intended
MATERIALS STANDARDS classified in manufacturers’ published loads
recommendations as satisfactory for the
Blocks should comply with BS EN 771 and
6.1 - M1 All materials shall: exposure.
be used in accordance with BS EN 1996-2.
(a) meet the Technical Requirements Bricks that are not freeze/thaw resistant
(b) take account of the design In general, 2.9N/mm2 blocks are suitable
(F0,S2 or F0,S1 to BS EN 771) are not
for one and two storey dwellings.
Materials that comply with the design and acceptable for use externally, unless
the guidance below will be acceptable for completely protected by a cladding which For three storey dwellings or dwellings
external masonry walls. can resist satisfactorily the passage of with storey heights over 2.7m, 7.3N/mm2
water. blocks are required for certain parts of the
Materials for external masonry walls structure.
shall comply with all relevant standards, Where brickwork may become saturated,
including those listed below. Where no moderately freeze/thaw resistant bricks Structural design may show that strengths
standard exists, Technical Requirement R3 (F1,S1 or F1,S2 to BS EN 771) are not lower than 7.3N/mm2 are adequate.

6.1
applies (see Chapter 1.1 ‘Introduction to the appropriate if there is a risk of vulnerability
to frost. In saturated conditions, sulfate- Other factors may dictate the strength of
Standards and Technical Requirements’).
resisting cement mortar is required for S1 blocks required in certain circumstances,
References to British Standards and Codes designation bricks. eg sulfate-resistance may require blocks of
of Practice include those made under the greater strength.
Construction Products Directive (89/106/ CALCIUM SILICATE BRICKS The maximum loadbearing capacity of the
EEC) and, in particular, appropriate Bricks of compressive strength Class 20 wall should not exceed manufacturers’
European Technical Specifications (to BS EN 771-2) are suitable for most recommendations.
approved by a European Committee for applications. Bricks of strength Class 30
Standardisation (CEN). and declared as freeze/thaw resistant (to (b) have appropriate resistance to
BS EN 771-2) are recommended in areas adverse effects of freeze/thaw and
BRICKS of severe freeze/thaw exposure (see map sulfate attack
in Appendix 6.1-B) or for use where bricks Concrete blocks used in the outer leaf
6.1 - M2 Bricks shall:
may be persistently wet (eg parapets, without protective cladding or render,
(a) be capable of supporting intended chimneys, sills and below dpc). should:
loads
Calcium silicate bricks do not contain • have a compressive strength exceeding
Requirements for the design strength of
significant amounts of soluble sulfates 7.3N/mm2, or
bricks are given in BS EN 1996-1-1. The
and may be suitable where sulfate bearing • have a density exceeding 1500kg/m3, or
brick specified in the design should be
soil and ground water conditions exist. • be made with dense aggregate to BS EN
used. Clay bricks to BS EN 771 with a
Manufacturers’ recommendations should 12620, or
minimum compressive strength of 9N/mm2
be followed. • be lightweight aerated concrete blocks
should be adequate for one and two storey
dwellings and 13N/mm2 for three storey having had their suitability confirmed by
CONCRETE BRICKS the manufacturer.
dwellings.
In concrete bricks there is a direct
relationship between strength and Concrete blocks should not be used below
(b) have appropriate resistance to the
durability, including freeze/thaw resistance. dpc where there are sulfates in the ground,
adverse effects of freeze/thaw and
Most concrete bricks in production have unless suitability is confirmed by the block
sulfate attack
a strength of 20N/mm2 and are durable manufacturer. Sulfates may attack the
in most situations. For copings and sills, cement used in the block. Sulfate-resisting
bricks with a compressive strength of 36N/ cement will be required in the mortar. The
mm2 should be used. proportions will depend on the level of
sulfates in the ground.

2013 Chapter 6.1 Page 7


6.1 External masonry walls

(c) have an adequate thermal resistance, DPC MATERIALS Lintels up to 1.2m length which do not
where required need a separate dpc tray should have a
The designer may have specified a 6.1 - M6 Materials for damp-proofing minimum 100mm end bearing and project
particular type and thickness of concrete shall resist adequately the passage of beyond the cavity closer by at least 25mm.
block because of its thermal insulation moisture Normally, other lintels should be long
performance in addition to its strength. Items to be taken into account include: enough to have a minimum 150mm end
Alternative concrete blocks should not be bearing each side of the opening.
(a) dpcs
used without the designer’s acceptance. The following materials are acceptable for Cavity trays may be required over the
use as dpcs: lintels. This should be specified in the
STONE MASONRY • bitumen to BS 6398 design. Reference should be made to
6.1 - M4 Stone masonry shall be capable • polyethylene to BS 6515 (except below Design clause 6.1 - D9(b).
of supporting the intended loads and copings and in parapets)
• proprietary materials assessed in
have appropriate resistance to the
accordance with Technical Requirement
THERMAL INSULATION
adverse effects of freeze/thaw
R3. 6.1 - M9 Insulation materials shall
Stone for masonry should conform to the Dpcs and flexible cavity trays should be of provide the degree of insulation to
requirements of BS EN 771-6. the correct dimensions to suit the detailed comply with the design
design. All retro-fill insulation materials (UF
Cast stone masonry units should comply
with BS EN 771-5 or BS 1217 as appropriate. For complicated junctions, preformed foam, blown mineral fibre and expanded
cavity trays are recommended. Care should polystyrene beads) should be installed by
MORTAR AND RENDERING be taken to order the correct type and installers trained by the assessment holder
shape. and approved jointly by the assessment
6.1 - M5 Mortar and rendering materials holder and the assessing organisation.
shall be of the mix proportions to (b) flashings
achieve adequate strength and durability The following are acceptable as flashings: The installer should be a member of a
to comply with the design • rolled lead sheet (at least Code 4) surveillance scheme acceptable to NHBC.

Items to be taken into account include: complying with BS EN 12588 Insulation materials should be installed in
• aluminium and aluminium alloys accordance with the following:
(a) cement and lime
complying with BS 1470 (0.6mm to • UF foam to BS 5617 installed in
Ordinary Portland cement should be to BS
0.9mm thick) accordance with BS 5618
EN 197. Sulfate-resisting Portland cement
• zinc alloy complying with BS 6561 and • all other insulation materials, whether
should be to BS 4027. Masonry cement
0.6mm thick. for full or partial cavity insulation,
should be to either BS EN 197 or BS EN
insulated blockwork or internal
413. WALL TIES insulation may only be used if
Limes should conform to BS EN 459. 6.1 - M7 Wall ties shall be appropriate assessed in accordance with Technical
for their location and intended use Requirement R3.
(b) sand type
6.1

Sand and aggregate from natural sources Wall ties shall be in accordance with either: The thickness of materials required by the
should conform to BS EN 13139. • BS EN 845, or design and Appendix 6.1-A should be used.
• an assessment in accordance with
(c) mortar type Technical Requirement R3.
Ready-mixed mortars should comply with
CLADDING MATERIALS
BS EN 998. For recommended mortar Ties should be long enough to be 6.1 - M10 Cladding materials shall be
mixes, see Appendix 6.1-C. embedded at least 50mm into each leaf. of the quality, type and dimensions
In England and Wales, wall ties should be required by the design
(d) additives
stainless steel or non-ferrous. In Northern Items to be taken into account include:
Air entraining and set retarding admixtures
Ireland, stainless steel or non-ferrous ties (a) tiles and slates
should comply with BS EN 934.
should be used where the cavity is fully Clay tiles for tile hanging should be to BS
Pigments for colouring mortars should filled with insulation and 75mm wide or 402.
conform to BS EN 12878. more. In Scotland, galvanised ties may be
used. Concrete tiles for tile hanging should be to
(e) render BS 473.
Sand for render should be sharp sand to Where partial cavity insulation is used,
BS EN 13139, preferably from the coarse it should be held in place by retaining Slates for vertical slating should be to BS
end of the grading scale. Sand with devices which may be clipped to the wall 680.
excessive fine material will shrink and ties. These devices should be assessed in
accordance with Technical Requirement R3 (b) timber boarding
crack.
and used only with compatible wall ties. Timber should comply with BS 1186 and be
Reinforcement for render, including angle Class 3 or better.
beads, corner beads, stop beads and
render stops, should be stainless steel or
LINTELS Timber should be a naturally durable
species or pre-treated with preservative.
PVC. 6.1 - M8 Lintels shall be of the type and
Reference should be made to Chapter 2.3
dimensions appropriate to their position
Decorative finishes that contain asbestos ‘Timber preservation (natural solid timber)’
within the structure
are not acceptable. (each section) for guidance on preservative
Steel and concrete lintels should comply treatments.
with BS EN 845-2, ‘Specification for
ancillary components for masonry’. (c) underfelt behind cladding
Type 1F felt to BS 747 is acceptable as an
underfelt behind cladding.

Page 8 Chapter 6.1 2013


External masonry walls 6.1
(d) battens (b) setting out
Battens should be of the size specified When setting out masonry, avoid cutting
in the design and pre-treated with bricks or blocks except when it is essential
preservative treatments. Reference and avoid irregular or broken bonds,
should be made to Chapter 2.3 ‘Timber particularly at openings.
preservation (natural solid timber)’ (each properly
Where a number of openings of similar filled joints
section) for guidance on preservative reduce risk
width are being formed, use a rod cut to of rain
treatments. penetration
the required size to check the width of
(e) proprietary cladding systems openings as the work rises.
Proprietary systems should be assessed
in accordance with Technical Requirement
R3.

MOVEMENT JOINTS Unless the design states otherwise, only


6.1 - M11 Materials for movement joints bucket handle or weathered joints should
shall be suitable for their intended be used. Recessed joints should not be
purpose used where the cavity is to be fully filled
with insulation.
When choosing materials, account should
be taken of the following: Where pigments (to BS 1014) are used
• joint width they should not exceed 10% of the cement
• joint depth weight or 3% if carbon black is used.
• anticipated movement
• movement capability of material For precautions to take in cold weather,
• surface preparation reference should be made to Chapter 1.4
• backing materials ‘Cold weather working’.
• projected life span of joint. To keep courses to the correct height, use (d) cavity walls
a gauge rod. The rod should be marked Cavities should be uniform and of the
Acceptable materials for movement joints
with the height of windows, doors and width specified in the design. All cavities
in clay brick walls are:
floors. should be at least 50mm nominal clear
• flexible cellular polyethylene
• cellular polyurethane All work should be reasonably level and width. Partial cavity insulation should be
• foam rubber. true. The bond detailed in the design fixed against the inner leaf of the cavity.
should be used. Perpendicular joints Check that the correct wall tie is being
Materials which are acceptable for use used (reference should be made to Clause
should be kept in line and plumb. Courses
in contraction joints with concrete bricks S5).
should be kept level by using lines and
or blocks, but not acceptable for use as

6.1
spirit levels. To keep the wall plumb, do not over-reach
expansion joints in fired clay bricks, are:
• hemp at changes of lift. It is better to wait for the
(c) mortar
• fibreboard next scaffolding lift.
Different types of bricks and blocks need
• cork. different strength mortar mixes. Some
In concrete blockwork, the construction parts of the building, such as below
joint may be a simple vertical joint filled dpc, chimneys and copings, may need a
with mortar and sealed. different mix to the main walling. Make
sure the mix is right for the job.

SITEWORK STANDARDS Recommended mortar mixes are given in


Appendix 6.1-C.
6.1 - S1 All sitework shall: Plant and banker boards should be kept
(a) meet the Technical Requirements clean. Mixers should be kept clean to
(b) take account of the design operate efficiently. The mortar colour
(c) follow established good practice and should be consistent.
workmanship
Mortar which has started to set should not The difference in heights between the two
Sitework that complies with the design and be re-tempered.
the guidance below will be acceptable for leaves of a cavity wall under construction
external masonry walls. All bricks and blocks should be laid on a can be up to 6 block courses, provided
full bed of mortar and all perpends should the ties are sufficiently flexible to ensure
be solidly filled. coursing is achieved without breaking the
CONSTRUCTION bond.
6.1 - S2 Construction shall ensure a Joints should be filled to reduce the risk
of rain penetration and dampness in the Cavities should be constructed so that:
satisfactory standard of brickwork and
wall. Solid mortar bedding and fully filled • mortar is struck off from all joints as
blockwork
perpends are particularly important in work proceeds
Items to be taken into account include: exposed areas and where the cavity is to • wall ties are kept free of droppings and
(a) appearance be fully filled with insulation. debris
The appearance of a masonry wall depends • cavity trays are clear of droppings and
upon the materials used, the setting out debris.
and the workmanship. Further details are
given in Clauses S2 to S10.

2013 Chapter 6.1 Page 9


6.1 External masonry walls

• frame cramps, or flat roof joists


• proprietary cavity closers, or
• plugs and fixings.
board keeps 12mm
cavity clear of
mortar droppings Timber plugs should not be used in
vulnerable positions, such as the outer
leaves of walls.

(g) bonding
A regular bonding pattern should be
maintained. External walls should be
bonded to partitions and party walls, as
required by the design. Either: Where a different size of masonry unit is
• • tooth every alternate course, or needed to ensure correct coursing, small
• • tie with wall ties, expanded metal or units of the same material should be used
equivalent at centres not exceeding to reduce cracking and problems due to
300mm vertically. different thermal insulation properties.
different masonry types
bond where blocks used to adjust coursing
are of the same type
Clean cavities with mortar droppings
removed are particularly important in
exposed areas and where partial cavity fill
is used.
Where cavity insulation is used, mortar
droppings should be cleaned off from the
top edge. Mortar left on the top edge may
transmit dampness to the inner leaf. The
use of a cavity batten will prevent this.
incorrect use of different masonry types
Cavity battens should be wrapped with
flexible material to allow easy withdrawal.
Where the inner leaf of a cavity wall is
being used for thermal insulation and
batten keeps tie where blocks are where a different size of masonry unit is
of a different type
cavity clear of
mortar droppings
used to ensure correct coursing, the unit
should have similar thermal insulation
properties to the masonry used for the
rest of the wall. For example aerated
concrete blocks should not be mixed with
6.1

clay bricks.

(h) chasing for services


Chases should be cut with care. Impact
power tools can damage the wall and
should not be used.
(e) movement
Brickwork/blockwork should not be
subjected to vibration until the mortar has
set. horizontal chase no
deeper than one-sixth
block thickness
(f) openings sill
Masonry may be built around either:
• the frame in-situ, or
• a profile or template to enable the frame 1/2 vertical chase no deeper
than one-third block thickness
to be fitted later. 3/4 3/4

Openings should be the correct size and 1/2


square. The brickwork should butt closely
3/4 3/4
against the frame. The frame should not The depth for horizontal chases should be
be distorted by forcing bricks against the brick bond set out at base of wall limited to one-sixth of the thickness of the
so that cut bricks occur below openings
jamb. single leaf. The depth for vertical chases
should be limited to one-third of the
Where joist hangers are not used, joist thickness of the single leaf. Hollow blocks
filling should be brick or blockwork, should not be chased unless specifically
without excessive mortar joints. Clay bricks permitted by the manufacturer.
and concrete blocks should not be mixed.
frames should
Joist filling should be kept 12mm below the (i) movement joints
not be distorted top of flat roof joists to allow for timber Movement joints should be formed where
shrinkage, but check also that cold roof required by the design. Movement joints
ventilation is not blocked (reference should are necessary in long lengths of walling to
be made to Chapter 7.1 ‘Flat roofs and reduce unsightly cracking. Joints are often
Window and door frames, when built-in, balconies’ (Design and Sitework)). hidden in corners, or behind rainwater
should be fixed with: pipes.

Page 10 Chapter 6.1 2013


External masonry walls 6.1
The correct materials should be used DAMP-PROOF COURSES
to form movement joints. Clay bricks
expand and require an easily compressible AND CAVITY TRAYS
material. 6.1 - S4 Dpcs and cavity trays shall be
installed to prevent moisture entering
the building at least
225mm
easily compressible filler
Items to be taken into account include:
12mm (a) horizontal dpcs
Dpcs and cavity trays should be in one
continuous piece, whenever possible.
Joints in horizontal wall dpcs positioned
to prevent rising damp should be
sealant lapped 100mm or sealed or welded. The (b) dpcs in parapet walls
manufacturer’s recommendations should Parapet walls should have:
be checked. Elsewhere, joints in dpcs and • a dpc under the coping, and
cavity trays should be sealed to prevent • a dpc tray starting 150mm minimum
Suitable materials are: water seeping through the joints. above the roof.
• flexible cellular polyethylene At ground level, all parts of the dpc should The coping throating should be clear of the
• cellular polyurethane be at least 150mm above finished ground brickwork. Reference should be made to
• foam rubber. or paving level. Clause S4(d) for guidance on sealing dpcs.
The sealant should be at least 10mm deep All dpcs should be fully bedded in mortar.
to ensure a good bond. If the joint is in
a freestanding wall, the filler will require throating
sealant to both exposed edges and the clear of
brickwork
top (where the joint is carried through the
coping). dpc supported
over cavity
(j) corbelling
Where courses are corbelled out in at least
ordinary masonry, one above another, the 150mm
open perpend
extent of corbelling should not exceed that weep holes at
maximum 1m
shown in the following diagrams. spacing at least
150mm

Where reinforcing is used, corbels should


be designed by an Engineer in accordance
with Technical Requirement R5. Special dpc detailing may be required

6.1
at doorways where the dwelling is to be
T designed to allow access for the disabled.
thickness
not reduced
wall tie
on this side Dpcs should: (c) dpcs to prevent downward flow of
• be laid on a surface, free from water
projections which could puncture or Where dpcs are intended to prevent the
adversely affect the dpc material downward movement of water, joints
• be fully bedded on fresh mortar where should be sealed or welded. Lapped joints,
required by the design, or where the unsealed, are unacceptable.
T
building is over three storeys in height
maximum corbel = T maximum corbel = T • be of correct width Where flashings link with dpcs, rake out
3 3
• not project into the cavity 25mm of mortar below the dpc to allow for
CAVITY WALL SOLID WALL
• not be set back from the edge of the the flashing to be tucked in. It is easiest to
masonry rake out the joints as the work proceeds.
(k) calcium silicate bricks • lap the dpm.
Where calcium silicate bricks are used, the
brick manufacturer’s recommendations dpcs clear of cavity
should be followed.
dpc laps dpm
STONE MASONRY
slight
projection 25mm
6.1 - S3 Stone masonry shall be
mortar raked out flashing wedged in
constructed to an acceptable standard while still green place and pointed up

Stone masonry will be acceptable if it: STAGE 1 STAGE 2

• complies with brickwork/blockwork


clauses (where appropriate) (d) dpcs around openings
• gives an adequate weather-resisting A dpc (either separate or combined as
structure (in conjunction with any brick part of a proprietary cavity closer) should
or block backing and/or vertical damp- The concrete fill in a cavity wall should be provided at jambs of openings and at
proof membranes) stop at least 225mm below the base dpc. heads and sills as required by the design.
• is prepared and laid on its natural bed This may be reduced to 150mm where
(unless local practice is otherwise) special foundations, such as rafts, are
• follows good local recognised practice. used.

2013 Chapter 6.1 Page 11


6.1 External masonry walls

Where a jointed or permeable sill is used protection to the top of the reveal and A dpm should be provided behind meter
(all sills in Northern Ireland and the Isle vertical dpc where provided. boxes in areas of very severe exposure to
of Man), a dpc should be placed between driving rain.
the sill and the outer leaf, turned up at the
back and ends of the sill.

cavity cavity
tray tray

at least at least
dpc turned up 140mm 100mm rise
at back and total rise in cavity tray
ends of sill in cavity from front
tray of cavity

dpc oversails groove in window AIR BRICK


lintel to protect head prevents rain
timber door and penetration
window heads METER BOX

The upstand part of the cavity tray should


Where a separate vertical dpc is used it be returned into the inner leaf masonry (f) stepped cavity trays
should be 150mm wide and be nailed to the unless stiff enough to stand against the At the abutment of pitched roofs to cavity
full height of the frame. The dpc should inner leaf without support. walls, preformed stepped cavity trays
protrude into the cavity by about 25mm should be provided as shown below. The
and extend up to the underside of the lintel In Scotland, all lintels should have a dpc lowest cavity tray should have two stop
where it should be turned back towards built into the inner leaf. ends and a weep hole to allow water to
the inner leaf. drain from the cavity.
In Scotland, Northern Ireland, the Isle of
Man and areas of Very Severe exposure to preformed
sealant stepped
driving rain, the upstand part of the damp- cavity trays
25mm 25mm proof protection should be returned into
sealant the inner leaf of masonry.

NORMAL EXPOSURE VERY SEVERE EXPOSURE


Where fairfaced masonry is supported by
lintels:
• weep holes should be provided spaced at least
at maximum 450mm intervals. Each 85mm

opening should have at least two weep


holes.
• cavity trays or combined lintels should
6.1

have stop ends.

WALL TIES
stop end
6.1 - S5 Wall ties shall be of the correct
type correctly installed
Items to be taken into account include:
at least 2 weep holes (a) type
per opening, not more
than 450mm apart The type of wall tie specified by the
insulation vertical dpc
designer should be used.
combined lintel
projects at least
Where there is a sill dpc, it should be 25mm beyond (b) position
the outer face
lapped with the reveal dpc. of cavity closure If ties slope down to the inner leaf, if
drips are off-centre or if ties have mortar
If there is no sill dpc, the vertical dpc 25mm min droppings on them, water can cross the
should be continued 150mm below the sill cavity.
level.
The two leaves should be coursed so that
A fillet joint of sealant should not be the wall tie is level or slopes outwards.
considered as a substitute for good
combined lintel
workmanship or dpcs. However, a bead of or cavity tray
mastic should be used around openings.

(e) cavity trays


The single brick thick external leaf of a
cavity wall can allow moisture into the
cavity. Cavity trays should be used so that wall tie should be
level or sloping
water drains outwards above openings. A cavity tray should be provided where the to the outside
cavity is bridged by air bricks, etc. The dpc
Cavity trays over lintels should extend at should extend 150mm beyond each side of
outside inside
least 25mm beyond the outer face of the the bridge.
cavity closer and cover the ends of the
lintel. Where the lintel does not require a Where not otherwise protected (eg by a
Ties should be bedded a minimum of
dpc, the lintel itself should have a suitable roof at an appropriate level), a dpc tray
50mm into each leaf of the wall as work
profile and durability and give complete should be provided over meter boxes.

Page 12 Chapter 6.1 2013


External masonry walls 6.1
proceeds. The drip should face downwards. At openings and movement joints, wall ties
Ties should be built-in, not pushed into should be spaced at maximum 300mm
joints. centres vertically even if this means
wall tie built at least
50mm into each leaf cutting cavity insulation to insert the tie. lintel

additional ties additional ties full block for


at movement joint at openings lintel bearing

correct bonding
below supporting
block

225mm
450mm
Lintels and masonry should form openings
of the correct size for the frame of the
window or door.
Concrete floor units or other heavy
900mm
components which bear on lintels should
be positioned carefully to avoid damage or
drip of wall tie placed
centrally in cavity (d) use of partial fill insulation shock load.
Where partial cavity fill insulation is
The lintel toe should:
being used, it should be retained against
• project past the window head
the inner leaf by retaining devices. The
• have a flexible sealing compound
retaining devices should be compatible
between toe and window.
with the wall ties and used in accordance
with an assessment which complies with Brickwork or masonry should not overhang
Technical Requirement R3. the lintel by more than 25mm.
Unless the independent assessment states
otherwise, where partial cavity fill is being
used the wall ties should be spaced more
closely to provide adequate support and
restraint for the 1200mm long boards.
Where one leaf is built in advance of the
Ties should be spaced at 600mm centres
other, the wall ties should project enough
horizontally and in vertical as well as
from the built leaf to bed at least 50mm
horizontal rows, ie not staggered.
into the unbuilt leaf.

LINTELS
overhang overhang

6.1
6.1 - S6 Lintels and beams shall be not more not more
than 25mm than 25mm
installed correctly
flexible sealant
Items to be taken into account include: lintel toe projects between lintel
50mm beyond window head and window
(a) span and placing
wall tie should project Lintels should be the correct size for the STEEL LINTEL
enough to build 50mm
into the unbuilt leaf opening and have the correct bearing at
each end: (b) thermal insulation
Insulation may help to prevent cold bridges
Minimum bearing length (mm) at the heads of openings in external walls.
Span (m) Simple Lintel combined The design should be checked for this
lintel with cavity tray requirement. Insulation should be provided
to the underside of the lintel unless the
Up to 1.2 100 150
manufacturer shows an alternative to
prevent cold bridging.
Over 1.2 150 150

Longer span lintels may require padstones


(c) spacing (the design should be checked).
Wall ties should be spaced above and Setting out should ensure that lintels
below dpc as follows: bear on a full block, where possible, or on
a whole brick, and be installed level on a
Maximum spacing (mm)
solid bed of a mortar. Soft or non-durable
Horizontally Vertically packing should not be used. Small pieces
General wall 900 450 of cut brick or block should not be used
sealant
area around lintel bearings.
At jamb within 225 not more
openings, of opening than 300
movement sealant
joints, etc.

(c) use of dpc cavity trays


A separate cavity tray should be provided
over some lintels if:

2013 Chapter 6.1 Page 13


6.1 External masonry walls

• the corrosion protection to the lintel is • hacking the surface


inadequate, and • applying a bonding agent
• the shape of the lintel is unsuitable. ties in vertical
rows at joints
• applying metal lathing
between • applying a spatterdash coat, or
This should be checked with the designer insulation
boards (partial • other appropriate means.
or buyer. cavity fill)

The surface suction should be checked by


In Scotland, Northern Ireland, the Isle of
splashing water onto the wall. The result
Man and areas of Severe or Very Severe
should be observed and appropriate action
exposure to driving rain, a cavity tray is
taken as follows:
required over all lintels. Reference should
• if too much suction, spraying with water
be made to Clause S4(e) for details of
may be needed - do not use too much
cavity trays.
water
All cavity trays should have stop ends Where wall ties need to be closely spaced, • if too little suction, a spatterdash coat or
where the outer leaf is fairfaced masonry. for example at reveals, it is acceptable to bonding agent may be needed
make a clean cut neatly in the insulation • if the background is too wet, delay
(d) use of steel lintels to accept the extra ties. The insulation rendering until conditions improve.
Where steel lintels are being used, the manufacturer’s instructions should be
inner and outer leaf should be built up followed. The design requirements should be
together to avoid twisting the lintel flange. checked where rendering is continuous
The difference in height between the Insulation should be close butted with no over different materials. Corrosion-
leaves should not exceed 225mm. gaps. Gaps provide routes for dampness, resistant metal lathing should be fixed
and condensation can form on the cold across the joints or, alternatively, provision
spots where insulation is missing. made to accommodate movement.
THERMAL INSULATION
insulation cut to avoid Expanded metal should be fixed with
6.1 - S7 Thermal insulation shall be leaving uninsulated gaps
the correct side towards the wall (see
installed correctly
manufacturers’ literature). If metal lathing
A high standard of workmanship should be is used to bridge changes in background
maintained to minimise the risk of damp material, a separating strip, eg breather
lintel
penetration to the inside of the dwelling paper, should be fixed behind the lathing
where cavity insulation is used. so that the render does not bond at the
background joints. Lathing should be set
In particular:
reveal away from the wall so that rendering can
• mortar joints, including perpends, should blocks
be forced through the mesh to achieve a
be solidly filled with mortar
good bond.
• mortar droppings should be removed
from wall ties and the edges of
insulation materials
6.1

• excess mortar should be struck smooth


from the inside of the outer leaf.
separating strip used behind
Where insulation is built-in, manufacturers’ expanded metal when plastering
across dissimilar backgrounds
instructions should be followed. These fibres in
insulation
are normally printed on the insulation should be
parallel to
packaging and include a recommended the wall to (b) mix
avoid bridging
sequence of construction. the cavity The mix proportions should be checked
(full cavity fill)
against the specification, especially
Recessed joints should not be used where whether sulfate-resisting cement should
the cavity is to be filled with insulation. be used.
In Northern Ireland and the Isle of Man Mixes for rendering on brickwork using
it is not permissible to fill the cavity with Insulation boards for partial fill should be clay bricks with no limit on their soluble
pumped insulants, eg UF foam, at the time stored flat without bearers otherwise they salt content (F2,S1 or F1,S1 to BS EN 771)
of construction. may distort making them difficult to fix should be as follows:
In Scotland, it is not permissible to fill the against the wall. Warped boards should be
Exposure Undercoat mix Finishing coat
full width of the cavity with any thermal rejected.
conditions proportions mix
insulants at the time of construction. (by volume) proportions
RENDERING (by volume)
All retro-fill insulation materials (UF
foam, blown mineral fibre and expanded 6.1 - S8 Rendering shall be to the Parapets, rendering not recommended
correct mix, have a good bond and freestanding
polystyrene beads) should be installed by walls, pillars,
installers trained by the assessment holder be free from significant cracking and retaining
and approved jointly by the assessment crazing walls and
holder and the assessing organisation. Items to be taken into account include: chimneys
The installer should be a member of a All walls 1 : 5, sulfate- 1 : 5, ordinary
(a) preparation of backing surface
surveillance scheme acceptable to NHBC. other than resisting Portland
The surface to be rendered should be free
those above Portland cement : sand,
The first row of insulation boards or batts from dust, loose particles, efflorescence
cement : sand, dry dashing
should be supported on wall ties, two ties and organic growth. plus integral strongly
to each board or batt. waterproofer advised
Where necessary, surfaces should be
Wall ties should coincide with horizontal treated to provide an adequate key by:
For backing brickwork, it should be
joints in the insulation. • raking out joints

Page 14 Chapter 6.1 2013


External masonry walls 6.1
ensured that sulfate-resisting cement Freshly laid mortar and render may fail if it It is cost effective to protect and store
which complies with Appendix 6.1-C is used freezes because the frozen water expands materials properly and maintain good
in the mortar. and forces apart the particles of mortar. quality control during construction.
If water-resisting properties are required, Admixtures which contain calcium chloride (b) handling
Portland cement with a waterproofing should not be used. The unloading of all bricks and blocks,
agent already incorporated may be especially facing bricks, preferably should
The use of air entraining agents in cold
available. Otherwise, a waterproofing be by mechanical means, directly onto a
weather gives better frost resistance to
agent should be used and added to the firm level surface. Bricks that are tipped
set mortar but does not aid the set. The
rendering mix in strict accordance with on delivery or moved about the site in
use of accelerating admixtures and other
manufacturers’ instructions. dumper trucks often have a high degree of
admixtures should not be relied on as an
wastage. Chipped or fractured bricks are
(c) application anti-freeze precaution.
not acceptable for facework.
The number and thickness of coats should
Check what effect additives have on
be in accordance with the design.
setting times. Cold weather slows setting,
as do retarders. If the set is retarded too
much, the next lift might squeeze out the
joints raked out
15mm to give mortar below.
key for 10mm
to 15mm thick
undercoat Brick and blockwork should not be built
nor rendering carried out when the air
temperature is 2°C and falling.

following 2ºC
coats thinner
and weaker
than undercoat 0ºC

render stopped
above dpc

Walls should be protected from frost until


the mortar has set sufficiently to resist

6.1
In Scotland, a spatterdash coat should be frost damage. Covers should be provided
applied before the first render coat if the to form a still air space to insulate the wall.
background is of Scottish common bricks (c) storage
Walling damaged by frost will not regain
and bricks to BS EN 771. Stacks of bricks and blocks should be
strength and should be taken down and
protected from rain, mud splashes, etc by
re-built when conditions improve.
Undercoats should be applied at least 3 covering with waterproof covers. Bricks
days before applying the following coat. and blocks that become excessively wet
cover weighted down
can suffer from:
If coloured pigments are specified,
• staining and efflorescence
batching should be undertaken with care
cover provides • increased drying shrinkage with a
to ensure colour consistency. a still air space
to insulate the greater risk of cracking
wall from frost
(d) cracking and crazing • lack of mortar adhesion to mud stained
Rendering should be free from significant surfaces.
cracking and crazing.
To avoid surface crazing:
• use properly graded sand (fine sand
increases the risk of crazing) Reference should be made to Chapter 1.4
• strong mixes should not be used as the ‘Cold weather working’ for more detailed
finishing coat advice.
• overworking, which causes laitance to be
drawn to the surface, should be avoided
• the finishing coat should be kept damp HANDLING AND
for at least 3 days. In warm dry weather, PROTECTION protection of bricks and blocks
spraying or protection by polyethylene
6.1 - S10 Materials shall be handled, Cement should be stored off the ground
sheet may be needed. Rendering should
stored, used and protected in such a and protected from weather. Sand should
not be carried out during hot weather or
in bright sunshine. way as to ensure that the construction be prevented from spreading and be
shall be neat, clean and undamaged upon protected so that it remains clean.
COLD WEATHER WORKING completion
The work place should be kept clean to
6.1 - S9 Precautions shall be taken to Items to be taken into account include: reduce mortar splashes to a minimum. Any
protect walls and rendering from damage (a) avoidance of damage accidental mortar smears should be lightly
by frost during construction

2013 Chapter 6.1 Page 15


6.1 External masonry walls

brushed off the face after the mortar has


taken its first set. Appendix 6.1-A
(d) workmanship
Materials should be handled with care
during construction to avoid damage and Suitable wall constructions for use with full cavity insulation
staining. Badly chipped bricks should not
Minimum
be used for facework.
insulation thickness (mm)
Exposure Suitable wall construction Built-in Retro-fill UF
category insulation (other foam
than
UF
foam)
Very Any wall with impervious cladding 50 50 50
Severe
Fairfaced masonry with impervious cladding to 100 100 N/A
all walls above ground storey
Any wall fully rendered2 75 75 N/A

Fairfaced masonry 1
N/A N/A N/A

Severe Any wall with impervious cladding or render2 50 50 50

Fairfaced masonry with impervious cladding or 50 75 50


render2 to all walls above ground storey
Unless bricks have been blended by
the manufacturer, bricks from different Fairfaced masonry 75 75 N/A
batches should be mixed to avoid colour Moderate Any wall with impervious cladding or render 50 50 50
patching.
Fairfaced masonry with impervious cladding or 50 50 50
render to all walls above ground storey
Fairfaced masonry 50 75 75

Sheltered Any wall with impervious cladding or render 50 50 50

Fairfaced masonry with impervious cladding or 50 50 50


render to all walls above ground storey
Fairfaced masonry 50 50 50
6.1

N/A - not applicable


bricks from different
batches should be mixed
to avoid colour patching Notes
1 In Very Severe exposure locations fairfaced masonry with full cavity insulation is not
permitted.
To reduce the risk of efflorescence, newly 2 Render on an external leaf of clay bricks (F2,S1 or F1,S1 designation bricks to BS EN 771) in
erected masonry should be covered. This Severe or Very Severe exposures is not permitted where the cavity is to be fully filled with
also prevents the mortar being washed insulation.
out of the joints by rain and stops masonry 3 This table covers walls where the external leaf does not exceed 12m in height.
becoming saturated. 4 The exposure category of the dwelling is determined by its location on the map showing
categories of exposure to wind driven rain.
5 Fairfaced masonry includes clay, calcium silicate and concrete bricks and blocks and
dressed natural stone laid in an appropriate mortar (see Appendix 6.1-C) preferably with
struck or weathered or bucket handle joints. Cavity walls of random rubble or random
natural stone should not be fully filled.
6 Recessed mortar joints should not be used.
7 In Scotland, it is not permissible to fill the full width of the cavity with any thermal
insulation at the time of construction.
8 In Northern Ireland and the Isle of Man it is not permissible to fill the cavity with pumped
thermal insulants (for example, UF foam) at the time of construction.

Page 16 Chapter 6.1 2013


External masonry walls 6.1
MAP SHOWING CATEGORIES OF EXPOSURE TO WIND DRIVEN RAIN

6.1
Exposure zones Exposure to wind driven
rain (litres/m² per spell)

very severe 100 or more

severe 56.5 to less than 100

moderate 33 to less than 56.5

sheltered less than 33

Note:
Variations to the exposure shown on
the map can only be made by site-specific
calculations using BS 8104 “Assessing
exposure of walls to wind driven rain”
and the table above.

Adapted from the map in the


BRE report “Thermal Insulation:
avoiding risks”

2013 Chapter 6.1 Page 17


6.1 External masonry walls

Appendix 6.1-B

Areas of severe exposure to frost attack


The tinted areas have a frost incidence over 60 days a year, rainfall over 1000mm per year and an elevation over 90m above sea level.

KW

IV
PA

AB

PH

DD

PA
FK
KY
G

EH
ML
KA TD

DG NE

CA DH SR

DL TS
6.1

LA
HG YO
BD
Northern Ireland FY PR BB LS
From the available HX
HU
meteorological data, BLOL HD
WF
the three criteria for L WN
M DN
assessing severe WA S
exposure to frost SK
attack, as set out CH
CW LN
above, do not occur LL
simultaneously in any NG
ST DE
part of Northern Ireland
SY TF
WS LE
PE NR
WV
DY B
CV NN
LD WR IP
HR CB
SA MK
GL SG
NP OX LU CO
HP AL CM
CF HA EN
UB G
SN SL TW RM
SS
BS RG DB
SM BR DA
KT CR
BA ME
TA GU CT
SP RH TN
SO
EX
DT BH PO BN

PL
TQ

TR

Map reproduced by permission of Hanson.

Page 18 Chapter 6.1 2013


External masonry walls 6.1
The following list identifies the postal areas within which the three criteria for severe exposure to frost attack are met.
Only in a few instances is the whole of the post code district within the area of severe frost exposure.

54
40
28
27
26
25
24
23 23
22 47 22
20 21 84 19
12 19 48 14 55 20 83 18
11 17 47 13 48 19 82 17
10 16 46 12 47 18 81 16 26
9 13 45 11 46 17 77 15 19
8 12 44 10 45 16 76 14 18
7 24 11 43 8 44 15 75 13 17
6 23 9 10 42 7 43 14 74 12 16
5 22 8 9 41 6 28 13 72 7 6
4 21 7 8 40 4 13 27 12 65 8 7 6 5
3 20 2 7 39 3 12 26 11 64 7 5 6 4 4
5 2 15 1 6 37 9 6 2 11 23 8 63 4 3 4 3 3
3 1 13 0 5 8 7 8 4 1 8 8 14 1 62 3 3 2 2 1 1
AA BB BD BL CA CF CH DD DE DG DH DL EH FK G HD HG HR HX IV KA

6.1
57
55 21
54 20
41 16 19 41
40 15 18 40
33 14 41 17 39
32 13 40 16 38
28 12 38 15 37 48
14 27 11 37 11 36 44 25
13 23 26 12 10 36 10 35 40 24
12 22 25 11 44 9 35 9 34 39 17 23
11 21 8 24 10 8 8 34 8 33 33 16 22
10 20 7 23 9 71 7 7 33 7 32 32 15 21
9 12 6 22 8 66 6 6 32 6 31 20 14 20 71
8 10 5 21 7 49 5 5 27 5 30 19 13 19 11
7 9 4 20 6 48 4 4 26 4 26 30 13 12 18 8 22
6 8 3 16 3 47 3 3 25 3 25 11 11 11 17 5 21
5 6 2 15 2 46 2 2 24 2 23 10 10 10 13 16 2 18
3 13 2 1 11 24 1 19 1 1 23 1 22 6 9 6 10 10 1 9 6
KW KY LA LD LL M ML NE NP OL PA PH S SA SK ST SY TD TS YO

partly within

wholly within

Reproduced by permission of the London Brick Company Ltd.

2013 Chapter 6.1 Page 19


6.1 External masonry walls

Appendix 6.1-C

Mortar mixes
Unless recommended otherwise by the brick manufacturer, the mixes in the table below
should be used for clay bricks.
In the case of concrete or calcium silicate bricks, particular attention should be paid to
manufacturers’ recommendations.
Mortar mixes using ordinary Portland or sulfate-resisting cements where required (see
also Design clauses 6.1- D5(b) and (d)).

Recommended Recommended Recommended Mortar


cement: lime: cement: sand masonry cement: designation
sand mix mix with air- sand mix to BS EN
Location entraining 1996-1-1
plasticiser
General in areas of 1 : ½ : 4½ 1 : 3½ 1:3 (ii)
wall area Severe or
above Very Severe
dpc exposure - high
durability
other exposure 1 : 1 : 5½ 1 : 5½ 1 : 4½ (iii)
categories -
general use
Below - high durability 1 : ½ : 4½ 1 : 3½ 1:3 (ii)
dpc level
and in
chimney
stacks
Cappings, - low 1 : 0 to ¼ : 3 - - (i)
copings permeability
and sills

Air-entraining plasticiser can be incorporated in the following general use and high durability
6.1

mortars:
1 : 1 : 5½, cement : lime : sand, or
1 : 1 : 4½, cement : lime : sand.

Retarded mortar
Retarded mortar and most pre-mixed mortars can be used over a longer period of time than
site mixed, cement : lime : sand mortars. The timescale of use is defined by the manufacturer,
whose advice should be followed:
• protect retarded mortar against freezing prior to use
• do not use retarded mortar beyond the time for which it is effective
• because of delayed setting, temporary bracing of larger walls, for example gable peaks
and long walls, may be necessary.
Admixtures and additives
Where air-entraining plasticisers or other additives are to be used, follow manufacturers’
instructions:
• do not overdose, ‘more is not better’
• an air entraining agent can help reduce frost damage but it is not an anti-freeze
• do not use unauthorised additives.

Page 20 Chapter 6.1 2013


External masonry walls 6.1
Appendix 6.1-D

Dpcs and cavity trays


Some positions where dpcs and cavity trays should be provided:

Location Provision of dpcs and cavity trays


Base of walls, piers, A dpc should be provided a minimum 150mm above adjoining surfaces and
etc linked with the dpm in solid floors.

dpc laps dcm

dpc

at least
150mm

ground

Base of partitions Dpc should be full width of partition.


built off oversite
where there is no
integral dpm
Base of wall built Detail to prevent entry of damp by driving rain.
off beam, slab, etc
Parapet (1) Beneath coping, and
(2) 150mm above adjoining roof surface to link with the roof upstand.
In cavity walls over A cavity tray should be provided to direct to the outside any water that enters
openings, air bricks the cavity. The cavity tray should fully protect the opening.
and the like
At the horizontal A cavity tray should be provided 150mm above the adjoining roof or balcony

6.1
abutment of all surface. The tray should be lapped over any roof upstand or flashing to ensure
roofs over enclosed water penetrating into the cavity does not enter the enclosed area.
areas and balconies
to walls
At sloping A stepped cavity tray should be provided above the roof surface and linked to
abutments of all any roof upstand or flashing to ensure any water penetrating into the cavity
roofs over enclosed does not enter the enclosed area.
areas to cavity
walls
Doorsteps A dpc should be provided behind a doorstep where it is higher than a wall dpc.

dpm behind
doorstep links
with dpc

level of
wall dpc

doorstep

Sills Where precast concrete or similar sills incorporate joints or are of a permeable
material, a dpc should be provided beneath them for the full length and be
turned up at the back and the end of the sill.
Jambs in cavity The reveal should be protected throughout its width by a continuous dpc. The
width of the dpc should be sufficient to be fixed to, or overlap, the frame and
fully protect the reveal.

For Severe and Very Severe exposure conditions: rebated reveal construction,
with or without closed cavity and dpc.

2013 Chapter 6.1 Page 21


6.1 External masonry walls

Appendix 6.1-E

Durability classification of bricks


BS EN 771-1 classifies clay bricks according to their freeze/thaw resistance and active soluble
salts content as follows:

Durability Freeze/thaw resistance Active soluble salts content

F2,S2 Freeze/thaw resistant (F2), durable in Low (S2)


all building situations

F2,S1 Freeze/thaw resistant (F2), durable in Normal (S1)


all building situations

F1,S2 Moderately freeze/thaw resistant Low (S2)


(F1), durable except when saturated
and subject to repeated freezing and
thawing

F1,S1 Moderately freeze/thaw resistant Normal (S1)


(F1), durable except when saturated
and subject to repeated freezing and
thawing

F0,S2 Not freeze/thaw resistant (F0), Low (S2)


liable to be damaged by freezing and
thawing

F0,S1 Not freeze/thaw resistant (F0), Normal (S1)


liable to be damaged by freezing and
thawing

Calcium silicate and concrete bricks contain no significant active soluble salts. Information
on their durability is given in Materials clause 6.1 - M2(b).

Appendix 6.1-F
6.1

Protection of ancilliary components


Selection of ancilliary components in relation to material/coating specification
for use in buildings up to three storeys in a non-aggressive environment
(For the full range of product types, materials and details refer to Table 2 of PD 6697:2010)

Product type EN 845 Material/Coating specification


Ref * (The zinc coating masses are for one surface)

Wall ties 1 Austenitic stainless steel (molybdenum chrome nickel alloys)


conforming to
BS EN 845-1 3 Austenitic stainless steel (chrome nickel alloys)
8 or 9 Zinc coated (940 g/m2) steel wire or component

Tension straps 1 Austenitic stainless steel (molybdenum chrome nickel alloys)


and hangers
conforming to 3 Austenitic stainless steel (chrome nickel alloys)
BS EN 845-1 8 or 9 Zinc coated (940 g/m2) steel wire or component
Tension straps 10 Zinc coated (710 g/m2) steel component
and hangers
conforming to 11 Zinc coated (460 g/m2) steel component
BS EN 845-1 12.1 or Zinc coated (300 g/m2) steel strip or sheet with organic coating
(internal uses 12.2 over all outer surfaces of finished component
**)
13 Zinc coated (265 g/m2) steel wire
14 Zinc coated (300 g/m2) steel strip or sheet with all cut edges
organic coated
15 Zinc pre-coated (300 g/m2) steel strip or sheet
16.1 or Zinc coated (137 g/m2) steel strip or sheet with organic coating
16.2 over all outer surfaces of finished component
17 Zinc pre-coated (137 g/m2) steel strip with zinc coated edges

Page 22 Chapter 6.1 2013


External masonry walls 6.1
Lintels L3 Austenitic stainless steel (chrome and nickel alloys)
conforming to
BS EN 845-2 L10 Zinc coated (710 g/m2) steel component
L11.1 or Zinc coated (460 g/m2) steel component with organic coating
L11.2 over all outer surfaces of finished component
L12.1 or Zinc coated (300 g/m2) steel strip or sheet with organic coating
L12.2 over all outer surfaces of finished component
L16.2 Zinc coated (137 g/m2) steel strip or sheet with organic coating
over all outer surfaces of finished component
Lintels L11 Zinc coated (460 g/m2) steel component
conforming
to BS EN L14 Zinc coated (300 g/m2) steel strip or sheet with all cut edges
845-2, where organic coated
used with a L16.1 Zinc coated (137 g/m2) steel strip or sheet with allorganic coating
separate dpc over all outer surfaces of finished component
Bed joint R1 Austenitic stainless steel (molybdenum chrome nickel alloys)
reinforcement
conforming to R3 Austenitic stainless steel (chrome nickel alloys)
BS EN 845-3

* Material /coating reference in accordance with the relevant part of BS EN 845.


** These products are not suitable for use in contact with the outer leaf of an external cavity
wall or a single leaf cavity wall.
It is an NHBC recommendation that components in contact with, or embedded in, an inner
leaf which is damp or exposed to periodic wettings (eg below dpc) should be protected in the
same way as components in contact with, or embedded in, an outer leaf.

6.1

2013 Chapter 6.1 Page 23


6.1 External masonry walls

INDEX

A F S
Abutment details 4 Fire resistance 4, 5 Setting out 9
Admixtures and additives 3, 8, 20 Flashings 8 Sound insulation 5
Ancilliary components 22 Frost attack 2, 18 Slates 8
B I Stone masonry 4, 7, 11
Background, rendering 6 Insulation, full fill 5, 16 Storage 15
Blockwork 5 Insulation, partial fill 5, 13 Structural support, lintels 4, 13
Bonding 1, 10 J Sulfate 3
Bricks and blocks 7, 22 Joints 3 T
C L Thermal insulation 5, 8, 14
Calcium silicate bricks 1, 7, 11 Lateral restraint 1 W
Cavity trays 3, 11, 12, Lintels 4, 13 Wall ties 4, 8, 12
13, 21 M Workmanship 16
Cavity walls 5, 9 Mortar 3, 8, 9,
Cement 8 20
Cladding 1, 5, 8 Movement joints 1, 8, 10
Cold bridging 4 O
Cold weather working 15 Openings 10
Condensation 4 P
Corbelling 2, 11 Parapet details 4
D Point loads 1
Damp proof courses 3, 8, 11, Protection 1, 15
13, 21 R
Dry linings 5 Rain penetration 2, 5
Durability 4, 22 Reclaimed bricks 7
E Render 5, 8, 14
6.1

Exposure 2, 18

Page 24 Chapter 6.1 2013

You might also like