Professional Documents
Culture Documents
6.5 Steelwork
6.6 Staircases
Chapter 6.1
External masonry walls
6.1 External masonry walls
CONTENTS
Thermal insulation M9 8
Cladding materials M10 8
Movement joints M11 9
SITEWORK
Sitework standards S1 9
Construction S2 9
Stone masonry S3 11
Damp-proof courses and cavity trays S4 11
Wall ties S5 12
Lintels S6 13
Thermal insulation S7 14
Rendering S8 14
Cold weather working S9 15
Handling and protection S10 15
External masonry walls 6.1
(d) point loads The spacing of the first movement joint
DESIGN STANDARDS Padstones and spreaders may be from a return should not be more than half
necessary and, where required, should be of the above dimension.
6.1 - D1 Design shall meet the Technical located beneath areas of concentrated
Requirements When different materials are used
loads.
together, consideration should be given to
Design that follows the guidance below will
(e) chases potential differential movement. Wall ties
be acceptable for external masonry walls.
The position and depth of chases for are needed on either side of movement
services should be considered. Horizontal joints (reference should be made to Clause
STATUTORY chases should be limited to one-sixth the D7 and Sitework clause 6.1 - S5).
REQUIREMENTS thickness of a single leaf, and vertical
Movement joints should run the full height
chases to one-third the thickness of a
6.1 - D2 Design shall comply with all of the masonry wall. Any movement
single leaf.
relevant statutory requirements joints provided in the substructure must
Particular care is needed where hollow be carried up into the superstructure.
Design should be in accordance with
blocks are specified. Hollow blocks Movement joints may be needed in the
relevant Building Regulations and other
should not be chased, unless specifically superstructure where none are required
statutory requirements.
permitted by the manufacturer. in the substructure - however suitable
allowance should be made for relative
STRUCTURAL DESIGN (f) bonding movement.
When partition walls abut the external
6.1 - D3 External cavity and solid Where masonry walls form panels in a
wall and are of similar materials, they may
walls shall be designed to support and framed structure, movement joints should
be either fully bonded or tied together.
transfer loads to foundations safely and be provided in accordance with BS EN
Where materials have dissimilar shrinkage
without undue movement 1996-2.
or expansion characteristics, eg dense
Items to be taken into account include: concrete and aerated concrete, a tied joint Details of suitable materials to form
(a) standards is preferable as this will reduce the risk of movement joints are given in the Materials
Structural design should be in accordance random cracking. section of this chapter.
with BS EN 1996-1-1.
In the case of a connection between a Where movement joints are provided to
Intermediate floors and roofs should be loadbearing wall on foundations and a control shrinkage in concrete blockwork,
designed to provide lateral restraint to non-loadbearing wall supported on a they may be simple vertical joints filled
external walls, in accordance with BS 8103 ground bearing slab, it is preferable to tie, with mortar and sealed.
and ancillary components to BS EN 845-1. not bond, the walls. This will reduce the
risk of cracking due to differential vertical To ensure the sealant is effective, there
Walls of dwellings or buildings containing movement. should be a good bond with the masonry.
dwellings over three storeys high should The sealant should be at least 10mm deep
be designed in accordance with Technical Tied joints should be formed using or in accordance with manufacturers’
Requirement R5. expanded metal, wire wall ties or a instructions.
6.1
proprietary equivalent, at maximum
(b) lateral restraint provided by concrete 300mm intervals. Movement joints are not normally
floors necessary to the inner leaf of cavity walls
Concrete floors, with a minimum 90mm (g) movement joints but consideration should be given to
bearing onto the wall, provide adequate Movement joints should be provided, providing:
restraint. where necessary, and in such a way that • movement joints in rooms with straight
stability is maintained. If no provision unbroken lengths of wall over 6m. This is
Concrete floors running parallel to and is made for both initial and long term unnecessary for fired clay bricks
not built into walls require restraint straps movements, masonry walls may crack. • bed joint reinforcement as an alternative
to provide restraint to the wall (reference to movement joints in areas of risk, eg
should also be made to Chapter 6.4 Vertical movement joints should be
under window openings.
‘Timber and concrete upper floors’ (each provided in the outer leaf to minimise the
section)). risk of major cracking, as shown in the To reduce cracking and to maintain the
following table: level of thermal resistance:
(c) lateral restraint provided by timber • bricks and blocks, or blocks of different
floors Material Joint Normal spacing densities, in a wall should not be mixed
Timber joisted floors can provide adequate width • a joint should be formed where
restraint when joists are carried by (mm) dissimilar materials abut
ordinary hangers to BS EN 845 and Clay brick 16 12m (15m maximum) • the joint should be tied (eg with
connected to the wall with restraint straps. expanded metal in the bed joint) unless
Calcium 10 7.5 to 9m
In buildings of not more than two storeys, silicate the joint is to act as a movement joint.
timber joisted floors can provide adequate brick
Where cracking is likely, walls should be
restraint without strapping when: Concrete 10 6m dry lined or clad (reference should also be
• the minimum bearing onto masonry block and made to Sitework clause 6.1 - S2(g)).
is 90mm (or 75mm onto a timber wall brick
plate), or Any 10 half the above (h) calcium silicate brickwork
• joists are carried by restraint type masonry in spacings and 1.5m Design of calcium silicate brickwork
hangers, as described in BS EN 845-1 a parapet from corners (double should follow the the brick manufacturer’s
with performance equivalent to a wall the frequency) recommendations.
restraint strap at not more than 2m
centres. (i) cladding to framed structures
Allowance should be made for differential
movement between cladding and frame.
The following precautions should be taken • below dpc where there is a high risk of In Scotland, Northern Ireland, the Isle of
to prevent buckling and fracturing of saturation Man and in other places where the
masonry panels: • retaining walls exposure to driving rain is Very Severe,
• flexible movement joints should be • parapets masonry should form a rebate at the
provided at the underside of each • freestanding walls reveals of openings to avoid a straight
horizontal support member • rendered walls through joint where the frame abuts the
• the masonry outer leaf should have at • areas of Severe or Very Severe exposure masonry.
least two-thirds of its width supported to driving rain. Minimum 12mm overlap of
masonry (or render) to frame
securely by the concrete frame or a
Reclaimed bricks should be used only in
metal angle sealant ‘rebated‘ or
accordance with Technical Requirement R3. ‘check‘ reveal
• the inner leaf should be adequately tied 25mm
in areas of Very
severe exposure
to the structural frame. Forked plate (b) rain penetration
ties held in dovetail slots, cast into the Rainwater will penetrate the outer leaf of
sealant
6.1
For example: -- chimney stacks combination of plan and section/elevation
• paths should drain away from walls to -- retaining walls drawings.
avoid saturating bricks near the ground -- freestanding walls
• sills, copings and the like should have a -- rendered walls (b) cavity trays
weathered upper surface -- areas of Severe or Very Severe Cavity trays should be provided at all
• a coping should be provided for exposure to driving rain. interruptions to the cavity, eg window
all parapet walls, chimneys and and door openings, air bricks, etc, unless
freestanding walls unless clay bricks of (c) joints otherwise protected, eg by overhanging
F2,S1 or F2,S2 classification to BS EN Struck (or weathered) and bucket handle eaves.
771 have been used. Copings should joints are preferable.
A cavity tray should:
have a generous overhang, throatings
Recessed joints should not be used where: • provide an impervious barrier and
at least 40mm clear of the wall and a
• bricks are perforated nearer than 15mm ensure that water drains outwards
continuous, supported dpc underneath
to the face • project at least 25mm beyond the outer
which projects beyond the line of the
• bricks are not frost resistant (if clay F1,S1 face of the cavity closure or, where
wall. Single leaf parapet walls should not
or F1,S2 to BS EN 771), unless the brick a combined cavity tray and lintel is
be rendered on both sides.
manufacturer has agreed in writing for acceptable, give complete protection to
Where there is a risk that brickwork may their use in a particular location the top of the reveal and vertical dpc
be persistently wet, bricks should be • there is no reasonable shelter from where provided
specified that are low in soluble salts (if driving rain (reasonable shelter could • provide drip protection to door and
clay, F2,S2 or F1,S2 to BS EN 771). be from buildings or groups of trees window heads
if these are within 50m and of similar • have an overall minimum upstand from
Note height to the dwelling) the inside face of the outer leaf to the
Only clay bricks designated L by BS EN • the dwelling is built on steep sloping outside of the inner leaf of 140mm
771 have a low limit on their soluble salt ground, facing open countryside or • be shaped to provide at least a 100mm
content. In persistently wet conditions, clay within 8km of a coast or large estuary vertical protection above a point where
bricks of S1 designation may create sulfate • the cavity is to be fully filled with cavity mortar droppings could collect.
attack on the mortar. insulation.
Painted or decorated finishes can trap Jointing is preferable to pointing because
moisture in external brickwork and it leaves the mortar undisturbed.
increase the risk of frost damage, sulfate
attack or other detrimental effects. They
should not be applied to S1 designation
(c) abutment details for brick and block masonry, where (e.g. coastal sites) should be austenitic
Cavity trays should be provided at applicable stainless steel.
abutments of roofs and cavity walls. This
will ensure that any water penetrating into Stone masonry (natural or cast stone) In Scotland, Northern Ireland, the Isle of
the cavity does not enter the enclosed should be designed to meet the Man and areas of Severe or Very Severe
area. This only applies where the roof requirements of BS EN 1996 ‘Design of exposure to driving rain, separate damp-
is over an enclosed area, including an masonry structures’. proof protection should be provided over
attached garage, but does not apply to all lintels in accordance with the guidance
open car ports and open porches. LINTELS for cavity trays given in Clause D6(b).
Where the roof abuts at an angle with 6.1 - D9 Lintels shall safely support the Lintels should be of such a size and be
the wall, preformed stepped cavity trays applied loads located so that the external edge of the
should be provided. Items to be taken into account include: lintel projects beyond, and therefore offers
protection to, the window head.
(a) structural support
preformed
stepped Concrete, steel and reinforced brickwork (c) cold bridging and condensation
cavity trays
are acceptable materials for use as lintels. The BRE Report ‘Thermal insulation:
Timber lintels should not be used, unless: avoiding risks’ discusses aspects of
• they are protected from the weather, insulation relevant to external masonry
and walls. In England and Wales account should
• they do not support masonry or other be taken of Accredited Details.
at least
85mm rigid or brittle materials. The risk of condensation at reveals and
Lintels should be designed in accordance soffits becomes more likely as the wall
either with Technical Requirement R5 or insulation increases. Cold bridge paths
manufacturers’ published data. A lintel should be avoided.
should be provided where frames are not To avoid a cold bridge, the wall insulation
designed to support superimposed loads. should ideally abut the head of the window
(d) parapet details
Lintels should be wide enough to provide frame.
Dpcs below the coping should be
supported over the cavity to prevent adequate support to walling above. Clause D4(b) details methods of preventing
sagging. A dpc should be specified that can Masonry should not overhang the lintel rain penetration which may also be
achieve a good key with the mortar. support by more than 25mm. A lintel required.
should extend beyond the opening at each
end by at least the following lengths:
6.1
pumped thermal insulants at the time of • restrictions on chasing for services provision should be made for differential
construction. when using voided blocks should be movement.
noted (reference should be made to
In Scotland, it is not permissible to fill the (c) moisture barriers
Clause D3(e)).
full width of the cavity with any thermal Unless specifically not required for a
insulants at the time of construction. (e) dual insulation proprietary cladding, moisture barriers
Where partial cavity insulation is used should be provided between walls of solid
The type of insulation, its thickness and
in addition to an insulated block inner masonry and any boarding, slating, tiling
the wall construction should be suitable for
leaf (reference should be made to Clause or other similar claddings. The moisture
the exposure of the dwelling in accordance
D11(c)), the whole composite construction barrier may be roofing underfelt or
with Appendix 6.1-A.
should have been assessed in accordance equivalent.
Materials clause 6.1 - M9 sets out the range with Technical Requirement R3.
of acceptable insulation materials and the Vapour barriers such as polyethylene
relevant British Standards. (f) insulated dry linings sheet are not an acceptable moisture
Where an insulated dry lining contains a barrier as they can trap moisture in the
Render on an external leaf of clay bricks combustible insulant, the plasterboard structure.
(F2,S1 or F1,S1 designation bricks to BS EN should be at least 12.5mm thick and
771) in Severe or Very Severe exposures mechanically fixed to the masonry inner For timber framed walls clad with masonry,
is not permitted where the cavity is to be leaf. This is to prevent early collapse of the reference should be made to Chapter 6.2
fully filled with insulation. lining in a fire. ‘External timber framed walls’ for details.
The following design points should be (d) vertical tile or slate cladding
noted: FIRE SAFETY Every tile or slate should be nailed with
• stop ends should be provided to cavity 6.1 - D12 Cavity walls shall adequately two nails. Nails should be aluminium,
trays or combined lintels resist the passage of fire copper or silicon bronze.
• weepholes should be provided at
Cavities should be closed with cavity Bottom edges should be finished with an
450mm (maximum) centres with at least
closers in accordance with statutory under-course and tilting batten.
two per opening
• mortar joints should not be recessed requirements.
(e) timber cladding
• painted finishes on bricks or render are Timber claddings should be pre-treated
not acceptable if they are likely to cause with preservative in accordance with
frost damage or sulfate attack or other Chapter 2.3 ‘Timber preservation (natural
damage. solid timber)’ (each section).
RENDERING • cement for brickwork mortar is sulfate- Undercoats should be allowed to shrink
resisting to BS 4027 and dry out before applying following
6.1 - D15 Rendering, in conjunction • the brick manufacturer has confirmed, coats. When rendering onto dense
with the surface to which it is applied, in writing, that the brick is suitable, concrete blocks, adhesion can be improved
shall satisfactorily resist the passage of taking account of the brickwork detailing by use of proprietary bonding agents or a
moisture and the particular exposure of each spatterdash coat.
Items to be taken into account include: rendered element. If sulfate-resisting
cement is used in the mortar, it should (g) detailing of timber/brick/render
(a) rain penetration Dwellings which incorporate rendered
also be used in spatterdash coats and
External rendered finishes should comply panels between timber boards should have
base coats of the render.
with BS EN 13914 ‘Design, preparation at least one coat of render applied over
and application of external rendering and Care should be taken when specifying the whole wall face before the boards are
internal plastering’ and the guidance given render to walls with full cavity fill. The lack fixed. The second coat may be applied
below. of a ventilated cavity can slow down the between the boards.
rate at which the wall dries out.
It is important to prevent rainwater Rendering and timber can shrink causing
penetrating behind the rendering. Design Rendered finishes should not be used over gaps. Precautions should be taken to
features around openings and at the head fully filled cavity walls if: prevent rain from penetrating the junction
of the rendering should provide shelter, • the outer leaf is built in bricks with S1 as this might cause the render to fail as a
where possible, and help to shed water designation (F2,S1 and F1,S1 to BS EN result of frost damage.
away from the surface below. 771), and
• the site is in an area classed as Severe All exposed timber, except naturally durable
(b) exposed elements or Very Severe exposure to driving rain species, should be treated in accordance with
It is not advisable to render exposed (see Appendix 6.1-A). Chapter 2.3 ‘Timber preservation (natural
parts of a building, such as parapets and solid timber)’ (each section).
chimneys constructed of clay bricks of S1 Rendering may be used on brickwork
designation, without the use of sulfate- with partial cavity insulation provided a Where timber is used on brick or render,
resisting cement. clear cavity width between insulation and it is essential that all cut ends, mortices,
outer leaf of at least 50mm nominal is etc made after treatment are flood coated
(c) movement maintained. with preservative.
Movements can occur at a change in
Large section timbers should be fitted
material. In such cases, the render should (e) mixes
with suitable weather bars, flashings, etc
be either stopped at specially formed The rendering mix should be appropriate
to prevent moisture penetration through
movement joints or, if the expected to the strength of the background. No
joints with adjacent materials.
movement is small, be reinforced by metal render coat should be stronger than the
lathing carried across the joint. If metal background or richer than the preceding Non-ferrous fixings should be used.
lathing is used, three rendering coats coat. The render should be of adequate Aluminium is not suitable when the
should be applied. strength to achieve durability. preservative is Copper/Chromium/Arsenic.
6.1
(d) background Mixes should comply with the (h) proprietary and local rendering
To achieve a good bond, the masonry recommendations of BS EN 13914 ‘Design, systems
backing should be moderately strong preparation and application of external Proprietary rendering finishes should be
and porous to give some suction and a rendering and internal plastering’. When applied in accordance with manufacturers’
mechanical key. Dense masonry with a rendering on bricks that are F1,S1 or recommendations.
smooth surface should not be rendered. F1,S2 to BS EN 771, the Table to Sitework
clause 6.1 - S8(b) should be followed. The Traditional local rendering should comply
Aerated or lightweight aggregate concrete manufacturer of the background masonry with the above guidance, as appropriate,
blocks can be used, as a background, should be consulted regarding particular and with established local practice.
but more care is needed when selecting requirements for the mix or its application.
a rendering mix and surface treatment.
Strong render mixes should not be used. Pigments complying with the requirements PROVISION OF
Roughcast and dry dash finishes that of BS 1014 may be added to the finishing INFORMATION
require a strong mix are not recommended coat up to a limit of 10% of the cement
6.1 - D16 Designs and specifications
for use on aerated or lightweight weight or 3% in the case of carbon black.
shall be produced in a clearly
aggregate blocks. Block manufacturers’ White Portland cement may be used.
understandable format and include all
recommendations should be followed. relevant information
(f) number and thickness of coats
In Scotland, render should be applied only The number of coats should be chosen For external masonry walls, the drawings
to bricks: with regard to the background and the should show:
• which are keyed, or exposure conditions of the site. • wall layout with all dimensions shown
• where a spatterdash coat has been • position and size of openings
For rendering on masonry cavity walls,
applied before the first render • coursing of the bricks and blocks in
one undercoat and one finishing coat is
undercoat. relation to storey heights and opening
acceptable. On metal lathing or on solid
In other areas, render should be applied wall construction, two undercoats and one positions
only to bricks where either: finishing coat are required. • details at all junctions, indicating
• keyed bricks are used, or position of dpcs and cavity trays.
Initial undercoats should not be less than Isometric sketches are recommended
• the joints are raked out at least 15mm
10mm and not more than 15mm thick. Any for complicated junctions
deep.
further undercoat should be thinner than • position and type of lintels
Render may be applied to bricks (if clay
the preceding coat. Finishing coats should • position of restraint straps
F2,S1 or F1,S1 to BS EN 771) only if the
be generally between 6mm and 10mm • details of cavity closers
following conditions are met:
thick. • details at reveals
6.1
applies (see Chapter 1.1 ‘Introduction to the appropriate if there is a risk of vulnerability
to frost. In saturated conditions, sulfate- Other factors may dictate the strength of
Standards and Technical Requirements’).
resisting cement mortar is required for S1 blocks required in certain circumstances,
References to British Standards and Codes designation bricks. eg sulfate-resistance may require blocks of
of Practice include those made under the greater strength.
Construction Products Directive (89/106/ CALCIUM SILICATE BRICKS The maximum loadbearing capacity of the
EEC) and, in particular, appropriate Bricks of compressive strength Class 20 wall should not exceed manufacturers’
European Technical Specifications (to BS EN 771-2) are suitable for most recommendations.
approved by a European Committee for applications. Bricks of strength Class 30
Standardisation (CEN). and declared as freeze/thaw resistant (to (b) have appropriate resistance to
BS EN 771-2) are recommended in areas adverse effects of freeze/thaw and
BRICKS of severe freeze/thaw exposure (see map sulfate attack
in Appendix 6.1-B) or for use where bricks Concrete blocks used in the outer leaf
6.1 - M2 Bricks shall:
may be persistently wet (eg parapets, without protective cladding or render,
(a) be capable of supporting intended chimneys, sills and below dpc). should:
loads
Calcium silicate bricks do not contain • have a compressive strength exceeding
Requirements for the design strength of
significant amounts of soluble sulfates 7.3N/mm2, or
bricks are given in BS EN 1996-1-1. The
and may be suitable where sulfate bearing • have a density exceeding 1500kg/m3, or
brick specified in the design should be
soil and ground water conditions exist. • be made with dense aggregate to BS EN
used. Clay bricks to BS EN 771 with a
Manufacturers’ recommendations should 12620, or
minimum compressive strength of 9N/mm2
be followed. • be lightweight aerated concrete blocks
should be adequate for one and two storey
dwellings and 13N/mm2 for three storey having had their suitability confirmed by
CONCRETE BRICKS the manufacturer.
dwellings.
In concrete bricks there is a direct
relationship between strength and Concrete blocks should not be used below
(b) have appropriate resistance to the
durability, including freeze/thaw resistance. dpc where there are sulfates in the ground,
adverse effects of freeze/thaw and
Most concrete bricks in production have unless suitability is confirmed by the block
sulfate attack
a strength of 20N/mm2 and are durable manufacturer. Sulfates may attack the
in most situations. For copings and sills, cement used in the block. Sulfate-resisting
bricks with a compressive strength of 36N/ cement will be required in the mortar. The
mm2 should be used. proportions will depend on the level of
sulfates in the ground.
(c) have an adequate thermal resistance, DPC MATERIALS Lintels up to 1.2m length which do not
where required need a separate dpc tray should have a
The designer may have specified a 6.1 - M6 Materials for damp-proofing minimum 100mm end bearing and project
particular type and thickness of concrete shall resist adequately the passage of beyond the cavity closer by at least 25mm.
block because of its thermal insulation moisture Normally, other lintels should be long
performance in addition to its strength. Items to be taken into account include: enough to have a minimum 150mm end
Alternative concrete blocks should not be bearing each side of the opening.
(a) dpcs
used without the designer’s acceptance. The following materials are acceptable for Cavity trays may be required over the
use as dpcs: lintels. This should be specified in the
STONE MASONRY • bitumen to BS 6398 design. Reference should be made to
6.1 - M4 Stone masonry shall be capable • polyethylene to BS 6515 (except below Design clause 6.1 - D9(b).
of supporting the intended loads and copings and in parapets)
• proprietary materials assessed in
have appropriate resistance to the
accordance with Technical Requirement
THERMAL INSULATION
adverse effects of freeze/thaw
R3. 6.1 - M9 Insulation materials shall
Stone for masonry should conform to the Dpcs and flexible cavity trays should be of provide the degree of insulation to
requirements of BS EN 771-6. the correct dimensions to suit the detailed comply with the design
design. All retro-fill insulation materials (UF
Cast stone masonry units should comply
with BS EN 771-5 or BS 1217 as appropriate. For complicated junctions, preformed foam, blown mineral fibre and expanded
cavity trays are recommended. Care should polystyrene beads) should be installed by
MORTAR AND RENDERING be taken to order the correct type and installers trained by the assessment holder
shape. and approved jointly by the assessment
6.1 - M5 Mortar and rendering materials holder and the assessing organisation.
shall be of the mix proportions to (b) flashings
achieve adequate strength and durability The following are acceptable as flashings: The installer should be a member of a
to comply with the design • rolled lead sheet (at least Code 4) surveillance scheme acceptable to NHBC.
Items to be taken into account include: complying with BS EN 12588 Insulation materials should be installed in
• aluminium and aluminium alloys accordance with the following:
(a) cement and lime
complying with BS 1470 (0.6mm to • UF foam to BS 5617 installed in
Ordinary Portland cement should be to BS
0.9mm thick) accordance with BS 5618
EN 197. Sulfate-resisting Portland cement
• zinc alloy complying with BS 6561 and • all other insulation materials, whether
should be to BS 4027. Masonry cement
0.6mm thick. for full or partial cavity insulation,
should be to either BS EN 197 or BS EN
insulated blockwork or internal
413. WALL TIES insulation may only be used if
Limes should conform to BS EN 459. 6.1 - M7 Wall ties shall be appropriate assessed in accordance with Technical
for their location and intended use Requirement R3.
(b) sand type
6.1
Sand and aggregate from natural sources Wall ties shall be in accordance with either: The thickness of materials required by the
should conform to BS EN 13139. • BS EN 845, or design and Appendix 6.1-A should be used.
• an assessment in accordance with
(c) mortar type Technical Requirement R3.
Ready-mixed mortars should comply with
CLADDING MATERIALS
BS EN 998. For recommended mortar Ties should be long enough to be 6.1 - M10 Cladding materials shall be
mixes, see Appendix 6.1-C. embedded at least 50mm into each leaf. of the quality, type and dimensions
In England and Wales, wall ties should be required by the design
(d) additives
stainless steel or non-ferrous. In Northern Items to be taken into account include:
Air entraining and set retarding admixtures
Ireland, stainless steel or non-ferrous ties (a) tiles and slates
should comply with BS EN 934.
should be used where the cavity is fully Clay tiles for tile hanging should be to BS
Pigments for colouring mortars should filled with insulation and 75mm wide or 402.
conform to BS EN 12878. more. In Scotland, galvanised ties may be
used. Concrete tiles for tile hanging should be to
(e) render BS 473.
Sand for render should be sharp sand to Where partial cavity insulation is used,
BS EN 13139, preferably from the coarse it should be held in place by retaining Slates for vertical slating should be to BS
end of the grading scale. Sand with devices which may be clipped to the wall 680.
excessive fine material will shrink and ties. These devices should be assessed in
accordance with Technical Requirement R3 (b) timber boarding
crack.
and used only with compatible wall ties. Timber should comply with BS 1186 and be
Reinforcement for render, including angle Class 3 or better.
beads, corner beads, stop beads and
render stops, should be stainless steel or
LINTELS Timber should be a naturally durable
species or pre-treated with preservative.
PVC. 6.1 - M8 Lintels shall be of the type and
Reference should be made to Chapter 2.3
dimensions appropriate to their position
Decorative finishes that contain asbestos ‘Timber preservation (natural solid timber)’
within the structure
are not acceptable. (each section) for guidance on preservative
Steel and concrete lintels should comply treatments.
with BS EN 845-2, ‘Specification for
ancillary components for masonry’. (c) underfelt behind cladding
Type 1F felt to BS 747 is acceptable as an
underfelt behind cladding.
6.1
spirit levels. To keep the wall plumb, do not over-reach
expansion joints in fired clay bricks, are:
• hemp at changes of lift. It is better to wait for the
(c) mortar
• fibreboard next scaffolding lift.
Different types of bricks and blocks need
• cork. different strength mortar mixes. Some
In concrete blockwork, the construction parts of the building, such as below
joint may be a simple vertical joint filled dpc, chimneys and copings, may need a
with mortar and sealed. different mix to the main walling. Make
sure the mix is right for the job.
(g) bonding
A regular bonding pattern should be
maintained. External walls should be
bonded to partitions and party walls, as
required by the design. Either: Where a different size of masonry unit is
• • tooth every alternate course, or needed to ensure correct coursing, small
• • tie with wall ties, expanded metal or units of the same material should be used
equivalent at centres not exceeding to reduce cracking and problems due to
300mm vertically. different thermal insulation properties.
different masonry types
bond where blocks used to adjust coursing
are of the same type
Clean cavities with mortar droppings
removed are particularly important in
exposed areas and where partial cavity fill
is used.
Where cavity insulation is used, mortar
droppings should be cleaned off from the
top edge. Mortar left on the top edge may
transmit dampness to the inner leaf. The
use of a cavity batten will prevent this.
incorrect use of different masonry types
Cavity battens should be wrapped with
flexible material to allow easy withdrawal.
Where the inner leaf of a cavity wall is
being used for thermal insulation and
batten keeps tie where blocks are where a different size of masonry unit is
of a different type
cavity clear of
mortar droppings
used to ensure correct coursing, the unit
should have similar thermal insulation
properties to the masonry used for the
rest of the wall. For example aerated
concrete blocks should not be mixed with
6.1
clay bricks.
6.1
at doorways where the dwelling is to be
T designed to allow access for the disabled.
thickness
not reduced
wall tie
on this side Dpcs should: (c) dpcs to prevent downward flow of
• be laid on a surface, free from water
projections which could puncture or Where dpcs are intended to prevent the
adversely affect the dpc material downward movement of water, joints
• be fully bedded on fresh mortar where should be sealed or welded. Lapped joints,
required by the design, or where the unsealed, are unacceptable.
T
building is over three storeys in height
maximum corbel = T maximum corbel = T • be of correct width Where flashings link with dpcs, rake out
3 3
• not project into the cavity 25mm of mortar below the dpc to allow for
CAVITY WALL SOLID WALL
• not be set back from the edge of the the flashing to be tucked in. It is easiest to
masonry rake out the joints as the work proceeds.
(k) calcium silicate bricks • lap the dpm.
Where calcium silicate bricks are used, the
brick manufacturer’s recommendations dpcs clear of cavity
should be followed.
dpc laps dpm
STONE MASONRY
slight
projection 25mm
6.1 - S3 Stone masonry shall be
mortar raked out flashing wedged in
constructed to an acceptable standard while still green place and pointed up
Where a jointed or permeable sill is used protection to the top of the reveal and A dpm should be provided behind meter
(all sills in Northern Ireland and the Isle vertical dpc where provided. boxes in areas of very severe exposure to
of Man), a dpc should be placed between driving rain.
the sill and the outer leaf, turned up at the
back and ends of the sill.
cavity cavity
tray tray
at least at least
dpc turned up 140mm 100mm rise
at back and total rise in cavity tray
ends of sill in cavity from front
tray of cavity
WALL TIES
stop end
6.1 - S5 Wall ties shall be of the correct
type correctly installed
Items to be taken into account include:
at least 2 weep holes (a) type
per opening, not more
than 450mm apart The type of wall tie specified by the
insulation vertical dpc
designer should be used.
combined lintel
projects at least
Where there is a sill dpc, it should be 25mm beyond (b) position
the outer face
lapped with the reveal dpc. of cavity closure If ties slope down to the inner leaf, if
drips are off-centre or if ties have mortar
If there is no sill dpc, the vertical dpc 25mm min droppings on them, water can cross the
should be continued 150mm below the sill cavity.
level.
The two leaves should be coursed so that
A fillet joint of sealant should not be the wall tie is level or slopes outwards.
considered as a substitute for good
combined lintel
workmanship or dpcs. However, a bead of or cavity tray
mastic should be used around openings.
correct bonding
below supporting
block
225mm
450mm
Lintels and masonry should form openings
of the correct size for the frame of the
window or door.
Concrete floor units or other heavy
900mm
components which bear on lintels should
be positioned carefully to avoid damage or
drip of wall tie placed
centrally in cavity (d) use of partial fill insulation shock load.
Where partial cavity fill insulation is
The lintel toe should:
being used, it should be retained against
• project past the window head
the inner leaf by retaining devices. The
• have a flexible sealing compound
retaining devices should be compatible
between toe and window.
with the wall ties and used in accordance
with an assessment which complies with Brickwork or masonry should not overhang
Technical Requirement R3. the lintel by more than 25mm.
Unless the independent assessment states
otherwise, where partial cavity fill is being
used the wall ties should be spaced more
closely to provide adequate support and
restraint for the 1200mm long boards.
Where one leaf is built in advance of the
Ties should be spaced at 600mm centres
other, the wall ties should project enough
horizontally and in vertical as well as
from the built leaf to bed at least 50mm
horizontal rows, ie not staggered.
into the unbuilt leaf.
LINTELS
overhang overhang
6.1
6.1 - S6 Lintels and beams shall be not more not more
than 25mm than 25mm
installed correctly
flexible sealant
Items to be taken into account include: lintel toe projects between lintel
50mm beyond window head and window
(a) span and placing
wall tie should project Lintels should be the correct size for the STEEL LINTEL
enough to build 50mm
into the unbuilt leaf opening and have the correct bearing at
each end: (b) thermal insulation
Insulation may help to prevent cold bridges
Minimum bearing length (mm) at the heads of openings in external walls.
Span (m) Simple Lintel combined The design should be checked for this
lintel with cavity tray requirement. Insulation should be provided
to the underside of the lintel unless the
Up to 1.2 100 150
manufacturer shows an alternative to
prevent cold bridging.
Over 1.2 150 150
following 2ºC
coats thinner
and weaker
than undercoat 0ºC
render stopped
above dpc
6.1
In Scotland, a spatterdash coat should be frost damage. Covers should be provided
applied before the first render coat if the to form a still air space to insulate the wall.
background is of Scottish common bricks (c) storage
Walling damaged by frost will not regain
and bricks to BS EN 771. Stacks of bricks and blocks should be
strength and should be taken down and
protected from rain, mud splashes, etc by
re-built when conditions improve.
Undercoats should be applied at least 3 covering with waterproof covers. Bricks
days before applying the following coat. and blocks that become excessively wet
cover weighted down
can suffer from:
If coloured pigments are specified,
• staining and efflorescence
batching should be undertaken with care
cover provides • increased drying shrinkage with a
to ensure colour consistency. a still air space
to insulate the greater risk of cracking
wall from frost
(d) cracking and crazing • lack of mortar adhesion to mud stained
Rendering should be free from significant surfaces.
cracking and crazing.
To avoid surface crazing:
• use properly graded sand (fine sand
increases the risk of crazing) Reference should be made to Chapter 1.4
• strong mixes should not be used as the ‘Cold weather working’ for more detailed
finishing coat advice.
• overworking, which causes laitance to be
drawn to the surface, should be avoided
• the finishing coat should be kept damp HANDLING AND
for at least 3 days. In warm dry weather, PROTECTION protection of bricks and blocks
spraying or protection by polyethylene
6.1 - S10 Materials shall be handled, Cement should be stored off the ground
sheet may be needed. Rendering should
stored, used and protected in such a and protected from weather. Sand should
not be carried out during hot weather or
in bright sunshine. way as to ensure that the construction be prevented from spreading and be
shall be neat, clean and undamaged upon protected so that it remains clean.
COLD WEATHER WORKING completion
The work place should be kept clean to
6.1 - S9 Precautions shall be taken to Items to be taken into account include: reduce mortar splashes to a minimum. Any
protect walls and rendering from damage (a) avoidance of damage accidental mortar smears should be lightly
by frost during construction
Fairfaced masonry 1
N/A N/A N/A
6.1
Exposure zones Exposure to wind driven
rain (litres/m² per spell)
Note:
Variations to the exposure shown on
the map can only be made by site-specific
calculations using BS 8104 “Assessing
exposure of walls to wind driven rain”
and the table above.
Appendix 6.1-B
KW
IV
PA
AB
PH
DD
PA
FK
KY
G
EH
ML
KA TD
DG NE
CA DH SR
DL TS
6.1
LA
HG YO
BD
Northern Ireland FY PR BB LS
From the available HX
HU
meteorological data, BLOL HD
WF
the three criteria for L WN
M DN
assessing severe WA S
exposure to frost SK
attack, as set out CH
CW LN
above, do not occur LL
simultaneously in any NG
ST DE
part of Northern Ireland
SY TF
WS LE
PE NR
WV
DY B
CV NN
LD WR IP
HR CB
SA MK
GL SG
NP OX LU CO
HP AL CM
CF HA EN
UB G
SN SL TW RM
SS
BS RG DB
SM BR DA
KT CR
BA ME
TA GU CT
SP RH TN
SO
EX
DT BH PO BN
PL
TQ
TR
54
40
28
27
26
25
24
23 23
22 47 22
20 21 84 19
12 19 48 14 55 20 83 18
11 17 47 13 48 19 82 17
10 16 46 12 47 18 81 16 26
9 13 45 11 46 17 77 15 19
8 12 44 10 45 16 76 14 18
7 24 11 43 8 44 15 75 13 17
6 23 9 10 42 7 43 14 74 12 16
5 22 8 9 41 6 28 13 72 7 6
4 21 7 8 40 4 13 27 12 65 8 7 6 5
3 20 2 7 39 3 12 26 11 64 7 5 6 4 4
5 2 15 1 6 37 9 6 2 11 23 8 63 4 3 4 3 3
3 1 13 0 5 8 7 8 4 1 8 8 14 1 62 3 3 2 2 1 1
AA BB BD BL CA CF CH DD DE DG DH DL EH FK G HD HG HR HX IV KA
6.1
57
55 21
54 20
41 16 19 41
40 15 18 40
33 14 41 17 39
32 13 40 16 38
28 12 38 15 37 48
14 27 11 37 11 36 44 25
13 23 26 12 10 36 10 35 40 24
12 22 25 11 44 9 35 9 34 39 17 23
11 21 8 24 10 8 8 34 8 33 33 16 22
10 20 7 23 9 71 7 7 33 7 32 32 15 21
9 12 6 22 8 66 6 6 32 6 31 20 14 20 71
8 10 5 21 7 49 5 5 27 5 30 19 13 19 11
7 9 4 20 6 48 4 4 26 4 26 30 13 12 18 8 22
6 8 3 16 3 47 3 3 25 3 25 11 11 11 17 5 21
5 6 2 15 2 46 2 2 24 2 23 10 10 10 13 16 2 18
3 13 2 1 11 24 1 19 1 1 23 1 22 6 9 6 10 10 1 9 6
KW KY LA LD LL M ML NE NP OL PA PH S SA SK ST SY TD TS YO
partly within
wholly within
Appendix 6.1-C
Mortar mixes
Unless recommended otherwise by the brick manufacturer, the mixes in the table below
should be used for clay bricks.
In the case of concrete or calcium silicate bricks, particular attention should be paid to
manufacturers’ recommendations.
Mortar mixes using ordinary Portland or sulfate-resisting cements where required (see
also Design clauses 6.1- D5(b) and (d)).
Air-entraining plasticiser can be incorporated in the following general use and high durability
6.1
mortars:
1 : 1 : 5½, cement : lime : sand, or
1 : 1 : 4½, cement : lime : sand.
Retarded mortar
Retarded mortar and most pre-mixed mortars can be used over a longer period of time than
site mixed, cement : lime : sand mortars. The timescale of use is defined by the manufacturer,
whose advice should be followed:
• protect retarded mortar against freezing prior to use
• do not use retarded mortar beyond the time for which it is effective
• because of delayed setting, temporary bracing of larger walls, for example gable peaks
and long walls, may be necessary.
Admixtures and additives
Where air-entraining plasticisers or other additives are to be used, follow manufacturers’
instructions:
• do not overdose, ‘more is not better’
• an air entraining agent can help reduce frost damage but it is not an anti-freeze
• do not use unauthorised additives.
dpc
at least
150mm
ground
6.1
abutment of all surface. The tray should be lapped over any roof upstand or flashing to ensure
roofs over enclosed water penetrating into the cavity does not enter the enclosed area.
areas and balconies
to walls
At sloping A stepped cavity tray should be provided above the roof surface and linked to
abutments of all any roof upstand or flashing to ensure any water penetrating into the cavity
roofs over enclosed does not enter the enclosed area.
areas to cavity
walls
Doorsteps A dpc should be provided behind a doorstep where it is higher than a wall dpc.
dpm behind
doorstep links
with dpc
level of
wall dpc
doorstep
Sills Where precast concrete or similar sills incorporate joints or are of a permeable
material, a dpc should be provided beneath them for the full length and be
turned up at the back and the end of the sill.
Jambs in cavity The reveal should be protected throughout its width by a continuous dpc. The
width of the dpc should be sufficient to be fixed to, or overlap, the frame and
fully protect the reveal.
For Severe and Very Severe exposure conditions: rebated reveal construction,
with or without closed cavity and dpc.
Appendix 6.1-E
Calcium silicate and concrete bricks contain no significant active soluble salts. Information
on their durability is given in Materials clause 6.1 - M2(b).
Appendix 6.1-F
6.1
6.1
INDEX
A F S
Abutment details 4 Fire resistance 4, 5 Setting out 9
Admixtures and additives 3, 8, 20 Flashings 8 Sound insulation 5
Ancilliary components 22 Frost attack 2, 18 Slates 8
B I Stone masonry 4, 7, 11
Background, rendering 6 Insulation, full fill 5, 16 Storage 15
Blockwork 5 Insulation, partial fill 5, 13 Structural support, lintels 4, 13
Bonding 1, 10 J Sulfate 3
Bricks and blocks 7, 22 Joints 3 T
C L Thermal insulation 5, 8, 14
Calcium silicate bricks 1, 7, 11 Lateral restraint 1 W
Cavity trays 3, 11, 12, Lintels 4, 13 Wall ties 4, 8, 12
13, 21 M Workmanship 16
Cavity walls 5, 9 Mortar 3, 8, 9,
Cement 8 20
Cladding 1, 5, 8 Movement joints 1, 8, 10
Cold bridging 4 O
Cold weather working 15 Openings 10
Condensation 4 P
Corbelling 2, 11 Parapet details 4
D Point loads 1
Damp proof courses 3, 8, 11, Protection 1, 15
13, 21 R
Dry linings 5 Rain penetration 2, 5
Durability 4, 22 Reclaimed bricks 7
E Render 5, 8, 14
6.1
Exposure 2, 18