Professional Documents
Culture Documents
DESIGN PHYLOSOPHY
1.0 INTRODUCTION
This document forms the Engineering Design Basis for Structural Works. The
contents of these documents from the guideline for engineering and to provide
information to the other disciplines concerned.
This technical specification summarizes the concept and codes to be followed for
Integrated Building Management System for the Project.
(a) SBC of Soil :10 MT/M2 at a depth of 2.75 M below NGL (as per Geotechnical
Report)
Foundation Engineering
IS: 456 - 2000 Code of practice for plain and reinforced concrete
1
12 MLD ZLD PLANT, PALI
Reinforcement
2
12 MLD ZLD PLANT, PALI
IS-1489 Part 1(1991) -Portland Pozzolana Cement (PPC) fly ash based
Steel design
5.0 LOADS
3
12 MLD ZLD PLANT, PALI
Design Loads: Building Design Loads will be in accordance with the more
stringent of either the following criteria or as set forth by governing local and
national codes. Structural design will be coordinated with architectural,
mechanical and electrical drawings to ensure all loads impacting structural
elements are adequately supported. Wind and seismic loads will be as required
by governing local or national codes.
Material Densities:
Rubble Masonry 26
5.2 Live loads: Considering the functional utilities of this building, imposed loads
are as:
4
12 MLD ZLD PLANT, PALI
Zone II
5
12 MLD ZLD PLANT, PALI
6.1 Load combination for checking of bearing capacity of soil and design of steel
structures
(Working stress).
1.O DL + 1.O LL
1.O DL +/- 1.O WL. (1.0 EQ)
1.O DL + 1.OLL +/- 1.OWL (1.0 EQ)
1.5DL + 1.5LL
1.5DL +/- 1.5WL (1.5 EQ)
(O.9DL + 1.5WL/(EQ) shall be used for stability against overturning is critical)
1.2DL + l.2LL +/- 1.2WL (1.2 EQ)
6.3. Appropriate factor of Live load shall be taken as per IS 1893 for seismic load
calculation.
6.4. The load combinations giving the most critical conditions on foundations,
structures or individual members shall be taken into account.
7.0 JOINTS
6
12 MLD ZLD PLANT, PALI
Expansion joints of suitable gap at suitable interval not more than 30m shall be
provided in all wall, floors and roof slab of eater retaining structures.
Construction joints shall be provided at right angle to the general direction of the
member. The locations of construction joints shall be decided on convenience of
construction. To avoid segregation of concrete in wall, horizontal construction
joints are normally to be provided at every 2m height. PVC water stops of 150
mm width shall be used for wall and 230 mm width for base slab.
Reinforcement shall have cover and the thickness of such cover (exclusive of
plaster or other Decorative finish) shall be as follows or as per instruction of
Engineer-in-Charge. Minimum cover shall be considered as for Extreme condition
as per IS 456-2000
Column 75 mm
retaining structure.
7
12 MLD ZLD PLANT, PALI
Concrete cover blocks of different and necessary sizes and shall use as and
when required for providing the adequate and specified cover to the
reinforcement. Such cover blocks shall be made so in advance and properly
cured to take the load of reinforcement. Cement mortar blocks in C.M. (1:1) shall
be used for making cover blocks.
In case when the cube strengths at seven days are found to be low or in the
cases when other cements are used, stripping time and removal of props may
have to be extended. In normal circumstances,(generally where temperatures are
above 20C) and where Ordinary Portland Cement is used, forms may generally
be removed after expiry of following periods:
Before Striking
Formwork
8
12 MLD ZLD PLANT, PALI
During construction, curing shall be carried out especially from 7.00 AM to 7.00
PM even on holidays with proper manpower, necessary pumps and pipe lines,
connections, etc.
For other items the curing shall be done as follows or as directed by the
Engineer-in-Charge.
Minimum distance between two parallel main reinforcement bars shall usually be
not less than the greatest of the following:
9
12 MLD ZLD PLANT, PALI
Vertical distance (i) Two thirds the nominal size of coarse aggregate
Or (iii) 25 mm.
METHOD OF ANALYSIS
For the structures, it shall be generated as space structure and shall be analyzed
for different combination of load cases as per IS-456-2000.Elastic analysis by
computer or by manual methods.
12.0 METHOD OF DESIGN
RCC. beams and slabs: Limit State Retaining walls: Working Stress/ Limit
State
I. Liquid depth to be considered up to full height of wall and no relief due to soil
pressure from other side to be considered.
10
12 MLD ZLD PLANT, PALI
II. Structure empty condition (i.e. empty of liquid, any material etc.): full earth
pressure with saturation and surcharge pressure whenever applicable to be
considered.
III. Ground water table shall be taken at deeper level from the ground level as the
site has highly pervious river sand bed thus seeping water if any shall be drained
out fast and stagnancy of seeping water has been ruled out and so there shall be
no chances of uplift pressure or flotation.
Thus Bottom slab or raft and vertical walls will be NOT designed for appropriate
net uplift and pressure under empty conditions, as per site condition and
geotechnical reports.
IV. Partition wall between dry sump and wet sump: to be designed for full liquid
depth up to full height of wall.
V. Partition wall between two compartments: to be designed as one compartment
empty and other full for both the direction.
VI. Walls shall be designed under operating conditions to resists earthquake forces
from earth pressure mobilisation and dynamic water loads.
VII. Underground or partially underground structures shall also be checked against
stresses developed due to any combination of full and empty compartments with
appropriate ground pressure from below to base slab. A minimum factor of 1.2
shall be ensured against overturning.
13.2 Foundations:
Foundation shall be designed to carry all the loads from equipment or Super-
structure, which they support in accordance with the relevant codes.
11
12 MLD ZLD PLANT, PALI
Foundation plinth for structural columns and equipment supports shall extend not
less than 50 mm from the edge of base plate.
The clear distance between a standard mild-steel anchor bolt or anchor sleeve
and the face of the foundation shall be not less than 75mm.
Minimum thickness of lean concrete layer shall be 100mm and shall extend
100mm beyond the foundation edge.
The following are the design requirements for the all reinforced or plain concrete
structure:
All Blinding and levelling concrete shall be a minimum 100mm thick in concrete
grade 1:3:6.
12
12 MLD ZLD PLANT, PALI
f) The bridge & bridge supporting structures shall be designed to safety withstand
IRC loading.
g) All pipes & conduits laid below the structural plinth & road works shall be
embedded in reinforced concrete of grade M-15 of minimum thickness 150 mm.
h) Approved quality water proofing compound (chloride free) shall be added during
concreting of all liquid containing structures in the proportions specified by
manufacturer or 2% by weight of cement whichever is higher. All wall and floor
panel shall be poured in sequential order with a minimum time gap of 4 days.
i) Design of water retaining structures shall be as per IS 3370.
The following minimum thickness shall be used for different reinforced concrete
member irrespective of design thickness:
i. Walls for liquid retaining structures 200mm
ii. Channel / Launder 150mm
iii. Roof slab for liquid retaining structures 150mm
(Other than Flat slab)
iv. Bottom slab for liquid retaining structures 150mm
v. Floor slab including roof slab, walkways, canopy slabs 125mm
vi. Walls of cables / pipes trenches, underground pits etc. 125mm
vii. Column footings 300mm
viii. Parapet, Chajja 100mm
ix. Precast trench cover 75mm
13