You are on page 1of 1

JSA FOR Fixing of light fittings

Name of the Site - NISSAN (2ASDU PROJECT)


Date of Preparation – 07/01/2014
JSA Preparation – R.RAMESH BABU
S.NO SCOPE OF ACTIVITY HAZARD CONTROL MEASURES REQUEST BY
1) Take the Light fittings, 1) Striking against object 1) Make sure no person is coming to your path. ELECTRICAL
ladder / Wheeled 2) Tripping hazard 2) Maintain good housekeeping & supervision INCHARGE / EHS
working platform at
work site
2) Placing and 1) Improper placing of ladder 1) Check the condition of ladder / working platform ELECTRICAL
ascending the ladder / 2) Improper Working platform 2) Make sure the ladder is placed on firm ground INCHARGE / EHS
Working platform 3) Falling hazard 3) Make sure the wheels are locked properly in case of
4) Slipping hazard mobile working platform
4) Usage of slip resistance safety shoe
5) Maintain the thumb rule of three point contact while
ascending
3) Fixing the fittings with 1) Fall from height 1) Use Safety belt properly hooked ELECTRICAL
the hand drill and 2) Electrical Shock 2) Ensure good condition of Handrail in the working INCHARGE / EHS
other hand tools 3) Injury due to broken tools platform
4) Inadequate illumination 3) Periodic checking of tools & temporary electrical
connections by using the stipulated check sheet
4) Experienced & trained workmen
5) Proper supervision
6) Arrange proper lighting
4) Electrical cable / wire 1) Injury due to sharp edged tool 1) Use of hand tolls(cotton) ELECTRICAL
connection and joining 2) Injury due to fall from height 2) Use safety belt properly hooked INCHARGE / EHS

5) Descending the 1) Person may fall due to slip 1) Usage of slip resistance safety shoe ELECTRICAL
ladder 2) improper gripping 2) Maintain the thumb rule of three point contact while INCHARGE / EHS
ascending
6) Removal of the ladder 1) Striking against object 1) Make sure no person is coming to your path.
/ Working platform 2) Tripping hazard 2) Maintain good housekeeping & supervision