Professional Documents
Culture Documents
Protection devices are required to safeguard the expensive power equipment and
transmission lines against overloads and damages. Therefore, they have to switch off
short circuits and earth faults very quickly and to isolate the faulty or endangered parts
in the power system very selectively. They are thus a major factor in ensuring the
stability of the power system in the case of faults.
The purpose of power system control in control centers as a subdivision of power
system management is to secure the transmission and distribution of power in
increasingly more complex power systems by providing each control center with a
continually updated and user-friendly overall picture of the entire network. All
727
ABB_12_E_14 30.08.12 14:36 Seite 728
Fig. 14-1
Functions and subsystems of automation in substations and networks
728
ABB_12_E_14 30.08.12 14:36 Seite 729
14.2 Protection
Functions
Various protection devices in power systems with rated voltages > 1kV are available to
protect generators, transformers, cables, busbars and loads. The purpose of these
devices is to detect faults and to switch off and isolate these selectively and quickly
from the network as a whole so that the consequences of the fault are limited as much
as possible. With today’s high fault current levels and highly integrated networks,
faults have far-reaching consequences, both direct (damaged equipment) and indirect
(loss of production, or PC failures in the service sector). Protective devices must
therefore act very fast with the greatest possible reliability and availability.
considered here in connection with power supply. When measurements are performed
in a multiple phase system such as the usual three-phase system, it is important to
note that some measured values apply to one phase only and others to all three
phases. Furthermore, the currents and voltages in the phases are displaced by a
phase angle. In transmission systems, it is usually possible to switch the three phases
independently of each other. A distinction therefore has to be made between single
phase and multiple phase faults. Both phase to earth short-circuits and phase to
phase faults may occur. In addition, a single phase fault may develop into a multiple
phase fault before it is shut down.
729
ABB_12_E_14 30.08.12 14:36 Seite 730
Without faults, the three phases are symmetrical, i.e. the amplitudes are equal and the
phase angle is 120°. In the case of a fault, asymmetries occur, with possible short-
circuiting of phase voltages. For simple detection of faults which result in asymmetry,
the three phases can be transformed mathematically into three “symmetrical
components” (positive-sequence components, negative-sequence component and
zero sequence component). Without a fault, the positive-sequence component is
identical to the original three-phase system, and the other components are zero. With
pure asymmetry, the negative-sequence component is not equal to zero, and with a
pure earth fault the zero-sequence component is not equal to zero. Usually, both
variables appear in combination. These details are not examined further here.
730
ABB_12_E_14 30.08.12 14:36 Seite 731
protection. Such protective devices are preferably used for parallel lines and for the
low voltage sides of transformers operating in parallel.
Fig. 14-2
Characteristics of overcurrent
protection
a) Definite-time relay, two-stage
b) Inverse-time relays with high-
current stage
I > Overcurrent stage
I Ⰷ High-current stage
tE Operating time
Overload protection
The temperature conditions at the protected object are simulated with the same time
constant in the relays. Any load bias is taken into account by this thermal replica in the
relay in accordance with the heating and cooling curves. Alarm signals or trip
commands are issued if a set temperature limit is exceeded. The relays are built as
secondary relays and operate usually in two or more stages. Overload relays are used
for objects that can overheat such as transformers and motors, but less commonly for
cables. The quality of this protection depends strongly on the accuracy of the thermal
replica.
Frequency protection
If the frequency (f) goes above or below set limits or changes at an unacceptable rate
(df/dt), this is detected and results in load shedding or disconnection of network parts
(islanding). The deviation from the rated frequency is a good indication for an
imbalance between produced and consumed active power (P). If e.g. the frequency
decays because of the loss of generating group, a corresponding load has to be shed
as soon as possible.
Voltage protection
Voltage deviations are reported, allowing the system load to be reduced as necessary.
Both overvoltages and undervoltages can occur.
731
ABB_12_E_14 30.08.12 14:36 Seite 732
compared. If a set ratio of difference current to through current is exceeded, the relay
issues a trip command.
In numerical relays, all the classical components of differential protection like matching
transformers, alarm and trip elements and inrush current stabilization are realized by
algorithms in the microprocessor. The inrush stabilization prevents, for example,
tripping of the transformer differential protection by the harmonics of the current
caused by the magnetization behavior of the transformer. Differential relays are
available for both transformer and generator differential protection.
Line differential protection consists of a unit at each end of the line with current
detection, a comparison function and trip output for the local circuit-breaker. The
differential protection function compares either the polled values or phasor values
derived from these. For a.c. applications, this requires time synchronization of the
measured values from both ends within microseconds. This is achieved by suitable
“handshaking” or GPS synchronization. For maximum precision the devices on both
sides are commonly provided in pairs by one manufacturer.
In addition, the differential protection needs a communication link for the transmission
of the data to be compared, i.e. normally the currents. For long lines only serial
connections are used, nowadays mostly installed as fiber optic cables. These are also
increasingly replacing wires with analog values for the short links needed for
transformer or generator differential protection. From edition 2 onwards, the
communication standard IEC 61850 is preferably used not only for communication
inside substations, but also between them.
The differential protection function switches off the faulty object between the
measuring points very rapidly and selectively. For correct protection operation,
however, the communication link has to be supervised properly. To cope with a loss of
communication, the differential protection is complemented by a distance or
overcurrent protection function (see 14.2.4 and 14.2.2).
Busbar protection
The busbar in a substation is a node in the power grid. According to Kirchhoff’s law the
sum of all incoming and outgoing currents has to be zero. The busbar protection
system acquires and sums up all these currents. Therefore, busbar protection
represents a multi-leg differential protection.
The busbar is usually not a simple node but consists of bus sectionalizers and,
depending on the number of parallel busbars, of bus couplers. Double busbars are
common. In such systems, each feeder may be connected alternatively to one of the
busbars or busbar sections by busbar isolators. To identify the actual node
configuration, a dynamic busbar image (topology) is created from the positions of all
the isolators. This allows tripping of only the faulty busbar section in the case of a
busbar fault. Regarding the complexity of data acquisition (e.g. saturation of the
current transformers) and the high speed required to limit damage in the case of high
short-circuit powers, static electronic protection systems have been used. Today, only
numerical busbar protection systems are installed in new systems or retrofitted. This
allows for compensation of the behavior and saturation of different current
transformers. With the computation power available today, other functions like breaker
failure protection, timed-overcurrent protection, undervoltage protection and phase
discrepancy monitoring may be integrated. Busbar protection may consist of one
centralized unit with a number of inputs and outputs corresponding to that of the
connected lines. The decentralized solution comprises a central “decision-making”
unit with distributed field units, in which all line protection functions are often
integrated, at least for back-up protection.
732
ABB_12_E_14 30.08.12 14:36 Seite 733
Comparative protection
The variables measured at beginning and end of the protected object are not
compared individually but as averages in a certain time window (e.g. for a half-wave of
sinusoidal values) checked for coincidence (phase comparison protection) or for equal
signal direction (signal comparison). These protection devices require only low
communication bandwidth and are very insensitive to interference, but . Since not the
raw data but calculated data are used this protection is slower than the differential and
busbar protection.
Distance protection
The distance of a fault from the relay is calculated by comparing the fault impedance
with the known line impedance. Therefore, voltage and current are measured and a
tripping range (protection zone) is assigned. A device for distance protection normally
has several forward zones and one backward zone. The tripping characteristics can be
represented in the impedance plane as complex polygons or circles and the
corresponding protection zones parameterized. In accordance with adjustable
distance-time parameters, the distance protection trips the allocated circuit-breaker
directly or with some delay as back-up protection. Distance protection operates
selectively and very fast in meshed networks with multiple infeed and needs basically
no communication. Since, however, some of the protection zones always extend
beyond the line end and detect more remote faults, releases or blocks are
communicated to increase the selectivity so that only the faulty line is isolated. Known
line and fault impedances also enable the fault location to be determined with
reasonable accuracy, facilitating the maintenance of long and not easily accessible
lines.
The graded tripping zones (distance-time characteristic) of a distance relay are shown
in Fig. 14-3.
Fig. 14-3
Tripping zones (forward) of a distance
relay with graded tripping time delay t(s)
Line length described by impedance Z(Ω)
A, B and C: Switchgear systems between
line segments
A: Relay location for the continuous characteristic line
B: Relay location for the dashed characteristic line
a-B corresponds to approx. 85 – 90 % of line length A-B
14
733
ABB_12_E_14 30.08.12 14:36 Seite 734
binary signals. Tripping circuits are monitored. These interfaces (process interfaces to
breakers and instrument transformers) can however also be implemented as serial
process connections to IEC 61850.
The power supply for these numerical devices and, where appropriate, the signaling
and tripping circuits is provided by batteries, so that the protection system can still
function reliably in the case of mains power failure.
14.2.7 Protection systems
As already indicated above for differential or directional protection, many protection
functions or protective devices do not operate alone, but are integrated in an overall
protection system. The implementation of such systems is greatly facilitated by
standardized serial communications.
In addition to the examples below, such systems also for example provide circuit-
breaker failure protection (when faults cannot be switched off as intended) and
temporary (inverse) blocking of protection and incoming feeders in radial networks.
It should also be mentioned that apart from linking of protective devices there is also a
demand for parallel protective devices such as main and back-up protection for high
voltage lines. Such redundancies must not be jeopardized by modern communication
architecture.
Protection of switchgear, lines and transformers
The basic scheme for protecting switchgear, lines and transformers is shown in
Fig.14-4.
10a
7 8 2 2
4 4
Fig. 14-4
Basic scheme of protection system for switchgear, lines and transformers:
a) Cable, b) Overhead line, c) Transformer, d) Auxiliary line
1 Overcurrent-time protection, 2 Distance protection, 3 3 Autoreclosing function,
4 Differential protection, 5 Directional ground-fault protection, 6 Overload protection,
7 Frequency monitoring, 8 Voltage monitoring, 9 Ground-fault indicator monitoring,
10 Busbar protection (10a Central unit, 10b Bay unit), 11 Buchholz protection,
transformer temperature monitoring
735
ABB_12_E_14 30.08.12 14:36 Seite 736
Q1
Protection group 2 1
Measure Measure
Distance
protection
Start-up
earth fault
Q2
Measure Differential
unit
Overcurrent
III
Measure Buchholz
services
Overcurrent
II
Measure Buchholz
unit
Overcurrent
I
Measure
Measure Earth fault
Differential
services
Overvoltage
Overcurrent
Measure services
Over-
excitation
Measure
Under-
frequency
Emerg. trip (ET)
Reverse
power I Integrator
Measure ET
Reverse
Voltage regulation power II Integrator
Turbine regulation
Count
Regulate
Stator
Measure earth fault
Fig. 14-5
Single-line diagram of generator unit protection system and single line diagram with
generator circuit-breaker
736
ABB_12_E_14 30.08.12 14:36 Seite 737
power for these auxiliary functions is taken from batteries, so that they continue to
work even in the event of network faults.
Substations are normally unmanned. Operation is controlled centrally via modern
network management systems from regional or national control or load distribution
centers. In the case of switchgear with conventional secondary systems, the network
management system is connected via a central telecontrol substation or remote
terminal unit (RTU). If there is a substation automation system, this telecontrol
substation is replaced by a telecontrol interface in the automation system.
737
ABB_12_E_14 30.08.12 14:36 Seite 738
QB1
QB2
QA1
B1
QB9
QC9
B5
Fig. 14-6
gives an overview of the SA functions in HV substations.
738
ABB_12_E_14 30.08.12 14:36 Seite 739
14.3.2 Interlocking
The reliability of the control sequence for switching operations is ensured not only by
the blocking of switches which may not be operated for inherent reasons, but also by
mutual interlocking of the HV switching devices within each bay and at a higher level
within the entire substation. The interlocking conditions depend on the effective switch
positions in the system (single line diagram at any one time). This is achieved most
simply throughout substations nowadays by the bay control units transmitting the
position signals from each bay to all other relevant bay control units, or alternatively to
a central interlocking device via the communication system. The interlocks in
switchgear systems must in particular prevent disconnectors from operating while
under load, or connecting power to earth.
There are a number of fundamental rules for secure interlocking. Rules related to the
14
operational philosophy of the utility may be added. If for example a substation with
bypass bus is to be interlocked, additional rules are needed for the security of the
bypass disconnectors as well as for protection selectivity. Depending on the
substation configuration, these rules can be expressed in substation-specific Boolean
algebra, or be directly applied to a particular single line configuration with its current
switch positions in a topology-oriented implementation. For the following example of
a double busbar with one feeder, one bus coupler and one bus earthing switch (see
Fig. 14-7) the specifically derived safety-related rules are listed for better
understanding.
739
ABB_12_E_14 30.08.12 14:36 Seite 740
Fig. 14-7
QC11 QC21 QB1 QB2 QB1 QB2
Single line diagram of a switchgear
QC1
QA1 QA1 installation with double busbar, bus
QC2
QB9 coupler and line
QC9
14.3.3 Control
The purpose of a control device in a switchgear installation is to change a defined
actual condition into a specified desired condition.
The operating procedures of controlling, interlocking and signaling can be performed
either by simple contact-type electromechanical and electromagnetic devices such as
740
ABB_12_E_14 30.08.12 14:36 Seite 741
Both substation-level and network control systems nowadays have computer based
workplaces consisting of a keyboard, mouse and one or more screens. If necessary
certain control sequences can be predefined. The feedback signals and indications of
switch positions are displayed on the screen.
Double command blocking
Although there may be several operator workstations with equal entitlements within a
system, often only one command is to be executed at any moment in time. This can
be achieved by double command blocking, implemented as close to the process as
741
ABB_12_E_14 30.08.12 14:36 Seite 742
possible so that all control stations from the network control system to local control
devices can be included. If a switch is selected for a command, then a check is first
made to ensure that no other switch is currently selected or even operating. If this is
the case, then the selection is blocked. Such double command blocking functions are
nowadays performed by the bay control units. This is achieved most simply in
switchgear systems by having each bay control unit signal its selection to all the others
through the communication system.
Direct control
In this mode, the switchgear is controlled locally from the on-site central control point,
where each piece of apparatus has its own control switch. It may utilize the
switchgear’s control voltage or light-duty relays. Control from the substation panel
always includes indication of the switchgear’s respective operating positions. Today
this is mostly replaced by a substation level computer-based HMI with serial
connection to the bay or process electronics. Directly wired control systems are
nowadays only used at local level – often as a back-up for the bay control device.
Remote control
In this mode, the substation is controlled from regional and central control centers,
predominantly via telecontrol link or the communication network of the utility. The
interface between station and remote control is the network control gateway.
Control functions include a wide variety of dedicated applications intended to ensure
the security of commands; representative examples are the monitoring of tripping
circuits (Fig. 14-9), and the duplication of tripping circuits (Fig. 14-10).
QA1 T1 T2 QA2
Protection 1 2
– CB auxillary
switches
DCV 1
TCS =
tripping circuit Trip coll DCV 2
TRIP 1 TRIP 2 TRIP 1 TRIP 2
supervision QA1 QA2
1 L–
742
ABB_12_E_14 30.08.12 14:36 Seite 743
14.3.4 Signaling
14.3.5 Measurement
Operating a substation involves measuring or calculating, recording and evaluating
operational quantities such as currents, voltages, powers, etc. For these tasks, the
primary system provides appropriate instrument transformers or sensors both for
voltage and current, which are installed at the busbar and/or in feeders. The kind,
number and position of instrument transformers depends on the operational
requirements as well as on the protection scheme. See sections 10.6.2 to 10.6.5 on
instrument transformer selection.
Voltage transformers in the feeders are useful for measurement and protection.
Voltage transformers at the busbar are convenient for synchronizing and measurement
purposes; there is then no need for calculation of missing values. The lower costs of
non-conventional instrument transformers frequently allow voltage transformers to be
installed on the busbars, but these then require a process bus, for instance to IEC
61850, and corresponding connections to the secondary system devices.
The secondary sides of current and voltage transformers must be earthed to avoid any
risk to equipment and personnel from unacceptably high voltages.
14
Current transformers must not be operated with open secondary windings, as the high
voltages occurring at the secondary terminals are dangerous to personnel and may
destroy the instrument transformer.
Current transformer circuits must be earthed at one point only. In high-voltage
installations this point should be in the feeder control cubicle wherever possible. The
relevant international standards must be fulfilled for export deliveries. It must be
ensured that the instrument transformer power rating is at least equal to the power
consumption of the measuring devices including the connecting lines. The dimensions
of the connecting lines can be determined with the aid of Fig. 14-10.
743
ABB_12_E_14 30.08.12 14:36 Seite 744
lr I
Example:
A = 2.5 mm2,lr = 85 m:
then R ≈ 0.6 Ω
I = 5 A, R ≈ 0.6 Ω:
then S ≈ 15 VA
Fig. 14-10
Current transformer secondary lines; To determine resistance and power consumption,
R = line resistance Ω, lr = resultant line length in m, S = power in VA, A = line cross
section in mm2 for Cu and Al, I = sec. transformer current in A
Voltage and power problems are overcome by thee use of a fiber-optic process bus to
IEC 61850 for the connection to the primary system.
The measured values are displayed on analog or digital instruments in the panel
control cabinets or on the display of a bay unit and the screen at the substation’s
central control station.
Classification of measuring instruments and their principal applications
Electrical measuring instruments have a class coding. The classes are: 0.1; 0.2; 0.5; 1;
1.5; 2.5 and 5. These indicate the measurement or reading error in percent, in both
positive and negative directions. They always relate to the end of scale value.
Instruments of classes 0.1 to 0.5 are precision instruments, those above are industrial
instruments.
The following standards apply to electrical measuring instruments and recorders: IEC
61010-1, IEC 61010-1/A2 and IEC 60051; and also DIN 43781 (for recorders). These
standards contain the most important definitions, classifications, safety and test
requirements and forms of identification.
744
ABB_12_E_14 30.08.12 14:36 Seite 745
Measuring transducers
Modern digital bay level IEDs can acquire currents and voltages directly from the
primary transformers, and therefore do not need transducers for these electrical
variables. They also have an interface to IEC 61850, which easily supplies the
measured values for further processing.
Any additionally needed transducers in the field of power engineering convert input
variables such as current, voltage, power and system frequency into analog electrical
output variables, usually in the form of injected direct current. Preferably these
transducers have also a serial interface according to IEC61850 to easily connect them
to the substation automation communication system. These values are then available
for processing functions and further transmission.
The most important parameters, device properties, designations and tests of
transducers for variables in power engineering can be found in the VDE 0411 Part 1
and VDE 0411 Part 1/A1 standards mentioned above in connection with instruments.
EN 50178 (VDE 0160) and the VDE/VDI Directive 2192 must also be observed.
14.3.6 Synchronizing
Synchronizing is also based on measurement. System components cannot be
connected in parallel unless their voltage curves coincide, otherwise the electrical
stresses on the equipment become too great. While with DC it is sufficient for the
voltage and polarity of the system components to be the same, with AC voltages the
frequency, the voltage and the phase angle must match; with three-phase current this
is also valid for the phase sequence.
Digital technology offers the option of feeding the input signals of the primary voltage
transformers directly to an automatic synchronization device, which independently
releases the closing operation at the right time.
Synchrocheck
An automatic synchronization device is always recommended for parallel switching of
generators with the power grid. This device automatically brings both the rotation
speed (frequency) and voltage of the generator into a preset tolerance range using
higher and lower commands.
Taking account of the voltage, phase angle, frequency and the mechanical delay of the
circuit breaker the command is issued or enabled such that the breaker contacts touch
at precisely the instant of time when the phase coincidence defined by the settings is
achieved.
The SYNCHROTACT® automatic synchronization device in its simplest form is a single
channel which takes care of measurement, voltage and frequency balancing, of
14
monitoring and command issuing with high security against maloperation. Depending
on the system size and safety concept, dual channel solutions are also used.
Measuring, microprocessor and command relays in both channels exist independently
in the SYNCHROTACT® dual-channel synchronization units. This independence
significantly increases security against maloperation in comparison to the single
channel system. Monitoring via the IEC 61850 communications protocol increases
availability.
745
ABB_12_E_14 30.08.12 14:36 Seite 746
Network
N etz SYN C H R O TAC T
Fig. 14-11
Automatic synchronizer device. -
+
The synchronizer device issues higher and
lower commands to turbine controllers and
voltage controllers. When the paralleling G
conditions are met the circuit-breaker is
closed at the exact moment when the phases U N ITR O L f+/f-
are the same. Erregung
Excitation
U +/U - S 97022
Table 14-1
Selection criteria and alternatives for electricity meters (counters)
Criterion Alternatives
Connection direct or to instrument transformer
Type electromechanical or electronic
Mounting surface-mounted housing, live parts fixed
flush-mounted housing, live parts fixed
flush-mounted housing, live parts removable
subrack, live parts on circuit boards
Current alternating current
three-phase in 3- and 4-wire systems loaded
symmetrically and asymmetrically
Power active and reactive consumption, incoming and
outgoing1)
Tariff single or two-rate tariff2)
Accuracy class 0.2, 0.5, 1, 2, 3
Metering system primary system3)
semi-primary system4)
secondary system5)
Special meters maximum-demand meters6)
pulse meters7)
remote meters
1)
Reversal prevention is necessary where the power flow direction changes.
2)
Tariff changed with separate timer or ripple control receiver.
3)
The ratio of preceding transformers is accounted for in the meter reading.
4)
This takes account only of the ratio of preceding voltage or instrument transformers, the readingsmust
be multiplied by a constant.
5)
This does not take account of the ratio of preceding transformers, the readings must be multiplied by a
constant.
6)
The maximum rate is calculated from the price per kilowatt-hour (kWh) and per kilowatt (kW).
7)
These measure the power throughput and according to the units counted, emit pulses to the connected
remote meters, remote summation meters or telecontrol devices.
ASIC measuring chip
746
ABB_12_E_14 30.08.12 14:36 Seite 747
14.3.7 Metering
General
Meters are used to record the amounts of power supplied by the energy provider or
distributor to the consumer. The selection criteria are shown in Table 14-1.
Meters for billing electricity consumption are in a special category.. In the Federal
Republic of Germany, for instance, they have to meet the requirements of the
Physikalisch-Technische Bundesanstalt (PTB) to be certified and approved. Similar
institutions also exist in other countries. The voltage drop on the instrument
transformer line of billing meters must not exceed 0.1 %.
Electronic four-quadrant meters
The measured variables of current and voltage are acquired with the aid of instrument
transformers and digitized using high-precision A/D converters with a sampling
frequency such as 2400 Hz, and forwarded to a downstream digital signal processor
(DSP). This processor calculates the active, reactive and apparent power or the
corresponding energies and sends energy-proportional pulses to the rate module. The
advantages of this process are in the high integration of the measurement functions,
the low fault rate, the high measurement stability and the opportunity to perform a full
4-quadrant measurement.
The metered values can also be transferred via serial communication to IEC 61850
from the data acquisition equipment to the evaluation equipment (e.g. a tariff rate
processing module). If IEC 61850 is already used for a process bus at the instrument
transformer or sensor, there are no limits in voltage losses, distances and location.
Pilot installations of such systems today use separate communication systems.
Institutes like the Physikalisch-Technische Bundesanstalt (PTB) investigate how
securely measured values relevant to revenue metering can be transmitted using the
communication system of the substation automation system.
electrical
instrument module rate module interface
➩
controller
ASIC microprocessor
U1 I1 왘
➩ ➩ logbook
load profile
inputs
controller
➩
U2 I2 왘 measuring outputs
max. demand
module 2
chip
➩
max. demand
module displays
➩
rate mechanism
U3 I3 왘
➩
14
747
ABB_12_E_14 30.08.12 14:36 Seite 748
The instantaneous active power P is derived by multiplying the current and voltage
values:
p(t) = u(t) * i(t)
The reactive power Q can be calculated from the apparent power S and the active
power P applying the vector method as follows:
S = Urms * Irms
Q = √ S2 – P2
Because the harmonics contents is taken into account in the two rms values of current
(Irms) and voltage (Urms), and, therefore, also in the apparent power S and in the active
power P, the harmonic power is also included in the calculation of the reactive energy
Q.
Power quality
The quality of the electrical power supply is increasingly becoming a factor in supply
contracts. In earlier times it was focused nearly exclusively on reactive power. Today,
power quality also includes availability, harmonics and short time voltage dips. This
needs calculation of the energy contents of single harmonics, which means further
measurement processing and higher frequency range of the measurement chain. The
international users group of IEC 61850 recommends 256 samples per period. These
power quality related values can be provided by additional functions in protection,
control and measurement devices at bay level or within dedicated power quality
measurement devices. All of these devices should be connected according to the IEC
61850 communication standard. There are a growing number of standards with
relevance to power quality.
Standards for metering
The following standards must be taken into account in planning and installing AC and
three-phase AC power meters:
– DIN 43850 Watthour meters; technical values
– DIN 43854 Sealing bolts for watthour meters
– DIN 43855 Watthour meters; plates
– DIN 43856 Electricity meters, tariff time switches and ripple control
receivers; connection diagrams, terminal marking, circuit
diagrams
748
ABB_12_E_14 30.08.12 14:36 Seite 749
– IEC 61107 Data exchange for meter reading, tariff and load control. Direct
local data exchange
– IEC 61142 Data exchange for meter reading, tariff and load control. Local
bus data exchange
749
ABB_12_E_14 30.08.12 14:36 Seite 750
750
ABB_12_E_14 30.08.12 14:36 Seite 751
Fault locators
The availability of transmission lines is particularly important in HV and EHV networks:
it can be improved by fast detection of the fault location and clearing the fault. The on-
line determination of fault distance is based on the comparison of impedance
measurements with and without the fault.. Measurements of the fault impedance have
to be done very fast as the time available is only that from the fault’s occurrence until
its isolation. Many numerical protection devices can provide fault location as an
additional function, and it is a standard function in distance protection devices. The
distance of the fault may be read out directly at the device, and is transmitted by the
communication system to station level or even network level.
There are also evaluation programs for disturbance recorder data, which can
subsequently calculate the fault location (offline) from the disturbance record. This
analysis can be more accurate than the location identified by the protection device if
the data is taken from a dedicated disturbance recorder with a higher sampling rate, or
if different disturbance records, e.g. from the two ends of the same line, are combined.
function.
Autoreclosing
In overhead line networks, autoreclosing plays an important part in maintaining the
power supply. Experience shows that faults in these networks are often only transitory
and can be cleared if the breaker opens for a brief interval during which the arc can
extinguish and the insulating distance reseal before it automatically closes again. The
timing of a successful reclosing operation is shown in Fig. 14-13. Generally, rapid
751
ABB_12_E_14 30.08.12 14:36 Seite 752
Fig. 14-13
Simplified time diagram of successful
reclosure:
AB OPEN command, EB CLOSE
command, LS Circuit-breaker, I Close,
O Open, SP Dead interval, F Onset of
fault
752
ABB_12_E_14 30.08.12 14:36 Seite 753
in a total of 2 x 16 stages of 1% each. The tap changer operates while the windings are
under voltage and load. For this operation the tap changer has a drive with power
storage (e.g. spring) which is charged with the aid of an electric motor.
Tap changer control
1. Local control
The tap changer can be operated directly at the transformer with the aid of a crank
handle (emergency operation). Electrical local control by pushbuttons is also
possible. In this case, each switching step from one tap to another requires a
separate command. The tap changer is designed so that a single command cannot
execute more than one step change. Today, the electric local control is mostly
replaced by an automatic voltage controller with additional manual control mode.
2. Remote control
Remote control is possible from the substation level or from the network control
center. The same control authority principles are applied as for controlling a breaker.
If there is an automatic voltage controller, it is controlled by voltage setpoints.
3. Parallel tap changer control
Where several transformers are connected in parallel without automatic voltage
regulation, the taps must have an interlocking system which is active only in parallel
operation. The interlocking has to prevent different tap positions on the paralleled
Fig. 14-14
H -T higher-lower,
Höher-tiefer, ST selected tapping shown,
Stufenstellungsanzeige
M mechanical
mechanisch E electrical
elektrisch
ST Stufenstellungsanzeige
selected tapping shown, V Voltmeter
voltmeter
M mechanical
mechanisch
14
G Kontaktgeber
contact transmittler
Wahlschalter
O-F selector Ort-Fern
switch local-remote
LL Lauflampe
H-T higher-lower, running light
Höher-tiefer,
E electrical
elektrisch MZ Meßzusatz
measurement unit
M drive motor
Antriebsmotor REG/ Autom. Sp.-Regler und
SE automatic voltage regulator and
Sollwerteinsteller
KB contact strip,
Kontaktbahn setpoint adjuster
B active
beschaltet H-A Wahlschalter Hand-Autom.
selector switch,Einzel-Parallel
Wahlschalter manual-auto
KB contact strip,
Kontaktbahn E-P
und Führung
selector switch single
UB inactive
unbeschaltet
Stufenverriegelung
VER parallel and master selector
transformers giving rise to an excessive reactive current which could damage the
transformers. If the tap positions become different in parallel operation (fault), an
alarm is sent to the control room.
Today, parallel transformers are equipped with automatic voltage regulation, see
Fig. 14-14, and the tap interlocking system is not needed anymore. In parallel
operation, however, a function is necessary which individually corrects the taps to
minimize the reactive current circulating between the transformers. This function
permits parallel operation of transformers with design differences such as differently
set taps and different winding impedances. In principle, however, parallel
transformers should be as similar as possible.
Parallel operation of identical transformers can however be implemented more
simply by having the controller of one transformer act as the master and specify the
tap settings, with the other transformers connected in parallel following. Modern
voltage regulators for parallel transformers communicate with each other and can
function in master or slave mode.
4. Voltage regulators
Voltage regulation by means of tap changers is – as already mentioned above –
mostly performed automatically. The numerical device contains all the necessary
functions such as
– voltage regulator,
– setpoint adjuster for load-dependent setpoint adaptation, and
– compensation of the voltage drop for long lines.
The following operating conditions are taken into account:
– parallel busbar operation,
– parallel network operation, and
– networks with widely varying active and reactive power components.
Switching to manual mode is possible.
The equipment in the control room of the substation provides control and supervision
of the complete substation at one point. Besides technical performance, the design
must also take into account ergonomic aspects such as clear arrangement, ease of
access, proper lighting, freedom from glare, acoustic properties, climate and comfort.
In the case of today’s computerized distributed substation automation systems the
control room essentially contains a station computer (single or redundant) with one or
two, and rarely up to four screens with keyboard, mouse, and printer. The industrial PC
and the communication interface can be conveniently installed in a cabinet beside or
even below the operator’s desk. If substations are normally manned, there may be
several operator workstations and large screens with single line diagrams.
Especially in the highly industrialized countries the substations are mostly unmanned,
and, therefore the control room shrinks to a PC based operator’s workplace and a
gateway to the network control center. In order to increase availability, these two
functions can be run on a single computer, with two computers forming a redundant
system. Caution: Redundant systems must be installed at separate locations to
prevent them from being simultaneously damaged or destroyed by physical damage
or fire.
754
ABB_12_E_14 30.08.12 14:36 Seite 755
14.4.1 Overview
Substation automation systems using microprocessors and serial data communication
perform all the functions of the secondary systems in transformer and switching
substations as described above, i.e. open loop control, interlocking, measurement,
closed loop control, indication, signaling, protection (feeders and busbar) and
operational metering etc., however still with the exception of revenue metering (see
section 14.3.7).
These are supplemented by new functions for process diagnostics, functions for the
automation of autonomous substations, and facilitation of the general task of power
system management by distributed preprocessing.
An essential feature of this new technology is its self-diagnostic capability, which has
operational and maintenance benefits for the user, even if he decides against the other
new possibilities available.
Summarizing, the new technology offers
– rapid fault detection,
– a simple physical system structure, and
– high operational reliability,
resulting a significant improvement of substation availability.
the process as possible, on the one hand to reduce the amount of wiring and cabling
work required, and on the other hand to increase availability without duplicating
devices in order to achieve redundancy.
Numerical methods are employed for functions close to the process, using
programmable modules based on microprocessors.
The distinguishing features of the new automation technology are:
– Use of the same microprocessor-based platform for the implementation of all
functions, either singly or in combinations.
755
ABB_12_E_14 30.08.12 14:36 Seite 756
756
central
network control
network fault
centres
Fig. 14-15
analysis
secondary
installations
ABB_12_E_14 30.08.12 14:36 Seite 757
data exchange
switchbay 1 switchbay n
757
14
ABB_12_E_14 30.08.12 14:36 Seite 758
On the process side of the control system, the bay units are assigned to the process
(bays, feeders). The result is that between every bay and the associated bay unit(s)
there is either a parallel connection, i.e. a direct connection between the bay
switchgear and bay unit is established for every data point such as position indicators
and encoders for analog values, or a serial connection, i.e. the data is supplied to the
bay unit by actuators and sensors via a process bus.
The functions performed in the bay units are basically those which require data from
their associated bay only (e.g. line protection, bay interlocking) and for which short and
fast functional loops are preferable.
The functions in the station unit, in contrast, are those which need data from the whole
substation (e.g. busbar protection, priority treatment of alarms, indication of busbar
voltage), or have a central function (connection to network control center, master clock
(DCF77 or GPS), central operator control station).
Serial links are used throughout for transferring data between bay and station units.
These serial links are normally buses, in star, tree or ring topology. The star can be seen
as a shrunken tree, having only the tree roots.
In the case of protocols such as IEC 61850, in which all connected devices have the
same communication rights or roles, the station unit and the gateway to the network
control center are normally connected to different physical points within the LAN, so as
to increase availability. The exact physical architecture of the communication system
depends not only on the required availability, but also on the number of
communicating devices, the distances between the different connected parts of the
switchgear, the communication load between the devices and the physical
environment, inclusive possible electromagnetic interferences.
For large distances and unscreened regions, normally optical fibers are used as
physical connections (see also section 14.4). A simplified rule for design and
implementation of the physical communication system is that connections within
screened cubicles may be electrical; outside cubicles optical fibers have to be used.
The bay and station units are built up from modular components, possibly as
combined bay control and protection units. The number of modules used depends on
the required quantity of functions, the desired structure and specified aspects of
system quality, such as availability.
However, for safety reasons, in the high-voltage area beyond 72 kV the protection
components are generally designed to operate independently of the other
components of that bay unit.
The autonomous protection devices are all realized today in modern digital technology,
even from different manufacturers or different device generations. At transmission
level the line protection has to be doubled, and supplied by different manufacturers to
avoid the impact of hidden systematic failures. IEC 61850 allows protection devices
from different manufacturers to be integrated without problems in a single automation
system. It thus replaces the IEC 60870-5-103 interface, which does not support all
protection functions in a standardized way and is restricted to master-slave
communication with a single master, as the standard for serial integration of protection
devices. Under the former system, the protection devices could not communicate
directly with each other, but only respond to the master. As a pure information interface
this might be sufficient, but it does not permit the implementation of protection
concepts with autonomous communication (see 14.2.7), which need a real time
communication interface as offered by IEC 61850.
758
ABB_12_E_14 30.08.12 14:36 Seite 759
Fig. 14-16
Optical transmission technology with fiber optic cable, 1 Input, 2 Signal conditioning, 3
Electro-optical converter, 4 Connector, 5 Fiber optic cable, 6 Opto-electrical
transducer, 7 Output
the absence of any problems with earthing and equipotential bonding (maximum
galvanic isolation).
Other important advantages are their large transmission bandwidth, low signal
attenuation (regardless of transmission speed) and ease of handling. Fiber optic
cables are thin and flexible, and can be bent to relatively small radii.
Glass fibers fundamentally differ from plastic fibers in that their attenuation is
significantly lower, so the cables can be much longer, normally up to nearly 2000 m
without any additional measures. Further, they have a longer life than plastic fibers.
759
ABB_12_E_14 30.08.12 14:36 Seite 760
Therefore, glass fibers are normally used in substations. Another criterion for optical
fiber selection is the way how the light is distributed internally. Within multimode fibers
the light is distributed in several modes, which then have parallel attenuation. This
allows distances up to 2000 m, which is normally sufficient for communication within
substations. With monomode fibers, however, distances up to 100 km can be bridged
without amplifiers in between. It should be noted that also the wavelength of the light
is important for the achievable range.
760
ABB_12_E_14 30.08.12 14:36 Seite 761
761
ABB_12_E_14 30.08.12 14:36 Seite 762
Initially, all functions were centralized in the control station. However, the increasing
volume of information soon resulted in a shortage of processing capacity. The current
trend is to decentralize most individual tasks at the point where they occur by
implementing intelligent telecontrol stations (RTUs) or, more powerful substation
automation systems, and to forward only the compressed information essential for
centralized control of the overall network.
The exact tasks to be performed by the network control systems depend on the type
and size of the network, on the installed power equipment, and on the operational
strategy adopted by the network operator (utility).
In supraregional networks, the electric energy is transported from the power plants to
the load centers at voltages of 220 kV and 380 kV, or higher (up to 1200 kV in some
countries). This transmission network in turn supplies the distribution systems,
operating at 110 kV, 60 kV, 20 kV, 10 kV and also other voltages, which carry the electric
energy at regional level from the interconnected network grid to the consumers. HVDC
links have also been established, not only between asynchronous networks, but also for
load support. The same applies to submarine cables, for example to connect offshore
wind farms to the grid.
The entire control and supervision of the machinery and equipment in the power plant
itself, such as turbines and generators, is the dedicated task of power plant control and,
therefore, not considered further here.
The application of network control begins with transmission of the electricity. For this, a
load-dispatching center controls the output of the power plants and the flow of power in
the grid to meet the demand at any moment, based on equivalent load curves from
previous periods and according to mutual agreements with other electrical utilities and
large customers, and together with various other parameters, in order to provide the
most economical and secure service.
Network control centers monitor and control the switch position and the loading of
switchgear and lines in the transmission and distribution systems. When faults occur, it
is possible with the help of high-speed data processing to obtain an up-to-date picture
of the network’s general status and the situation at the site of the fault immediately.
Based on this, all the necessary switching operations can be performed in a secure way.
At the lowest distribution level, the supply of all forms of energy, i.e. gas, water, district
heating, etc. as well as electricity, may be controlled from one single multi-purpose
control center if applicable.
The exact performance required from such a control and management system
determines the equipment needed in the control center. Today this consists almost
exclusively of computer systems with distributed functionality, and with color screens
displaying the network and its status. Because of the continuous increase of the
information to be processed in the control centers, it would no longer be possible for the
operators to monitor and control the system without the help of advanced information
technology. Process computers take over routine tasks from operators and quickly and
safely prepare the data for processing. In addition, control rooms may be also equipped
with control panels or large displays with group information for emergency operation or
a geographical overview.
The different internal data processing and information systems in many utilities are
interconnected by company-owned data networks. This provides an opportunity to use
operational information from the network control system for planning tasks, e.g. for
762
ABB_12_E_14 30.08.12 14:36 Seite 763
network and maintenance planning, and for management decisions. Alternatively, this
information can be obtained directly from the substation automation system by means
of the IEC 61850 communication protocol, if optical connections with sufficiently high
data throughput are available.
Practical experience shows that the design of a new network control system requires
close cooperation between the operator and supplier so that the individual functional
parts of the system, such as data acquisition, transmission and processing, can be
ideally matched to each other and to the tasks to be performed.
14.5.2 Telecontrol and telecontrol systems
Along with data processing, telecontrol plays a vital role in central power system
management. Its purpose is the economical and reliable transmission of data (such as
switching and adjustment commands, signals and measurements) between the
decentralized substations and the centralized network control system.
At the transmitting side of a telecontrol system, the relevant information is prepared for
transmission, i.e. it is coded and secured with additional redundancy so that errors due
to disturbances along the transmission path can be detected at immediately and
unwanted outputs are prevented. At the receiving side, the incoming information is
decoded, checked and, if free from errors, handed over as a command, signal or
measured value to the process modules or to the master computer.
The most important telecontrol terms can be found in the “International electrotechnical
vocabulary – Chapter 371: Telecontrol” as IEC publication IEC 60050 (371) (1984),
published in Germany as IEV 371 (1989), and in the associated revision 1 as supplement
IEC 60050 (371) dated 1997. A further interesting document on this subject is “Begriffe
der Fernwirktechnik”, published as ntz-report No. 26 by VDE-Verlag GmbH, Berlin-
Offenbach 1991, containing all definitions in English and German.
The growing size and complexity of power systems and the increased volume of
information has required an appropriate structuring of the telecontrol network. In the case
of small control centers with few substations, all substations can still be connected
directly to the control center by dedicated telecontrol links, either point-to-point (the
control center communicates only with one substation over each link) or according to the
multi-point principle (the control center interrogates a number of substations one after the
other over the same link for new information). For medium or large network management
systems with many or distant substations, however, a hierarchically structured telecontrol
network is unavoidable because of the usually limited number of available
communication channels and also to relieve the load on the control center. In this case,
the information from several substations, for instance, can be collected, combined and
compressed in so-called concentrator stations.
Choosing the most suitable telecontrol system depends on its required functionality and
performance. The main criteria are the volume of information and speed required.
14
Incorporation into the hierarchy of the overall control system is equally important.
The standards from IEC’s TC 57, “Power Systems Control” have up to now been
dominated by the series IEC 60870-5 (international) and EN 60870-5 (European), entitled
“Telecontrol equipment and systems, Part 5 – Transmission protocols”. The individual
parts describe and define the following subjects:
Part -5-1: Transmission frame formats
Part -5-2: Link transmission procedures
763
ABB_12_E_14 30.08.12 14:36 Seite 764
764
ABB_12_E_14 30.08.12 14:36 Seite 765
Direct-current data transmission is also used for short distances (≤ 10 km), in this case
usually with only low transmission speeds.
The communication channels are either owned by the system operator (utility) or
rented from a telecom company. Typical examples of transmission links belonging to
the utility are telecommunication cables in the form of buried or aerial lines running in
parallel with high-voltage cables or overhead power lines. Aerial cables are divided
into autonomous cables, earth-conductor cables and phase cables.
Other examples are multi-channel microwave links, mainly at transmission level and
PLC communication using the owned power lines themselves. If no telecontrol
transmission links are owned by the utility, data links can be leased from a telecom
company. Note that telecom links (especially current paths) should not be
interconnected with utility owned links. Interfaces between both systems should be
carefully designed based on a stringent concept.
With the establishment of communication systems with high bandwidth by the utilities
themselves optical fibers will more and more replace all other technologies.
For Germany, the most important provisions and recommendations for the
transmission paths are presented together in Volume 1, Chap. 1.1 of the VDEW
recommendations. This includes the provisions of VDE 0800 (telecommunications),
VDE 0228 (influence by power systems), VDE 0816 and DIN VDE 0818 (for cables),
VDE 0850 or EN 60495 and VDE 0851 (for TFH (power line telephony) and VDE 0888
or EN 187000 (fiber optics for telecommunications).
– digital outputs,
– analog outputs.
The classes for noise voltage limit values and insulation requirements are shown in
Tables 14-2 and 14-3. The choice of class depends on the characteristics of the
switchgear.
765
ABB_12_E_14 30.08.12 14:36 Seite 766
Table 14-2
Noise voltage limit values and insulation requirements for binary signals
Notes:
(1) N.F. = System frequency (usually 50/60 Hz)
H.F. = Damped high-frequency oscillation, see IEC 60255-4
IMP = High-voltage pulse
(2) The equipment must withstand this voltage for 1 min without damage.
(3) Insulation class (a) is for normal applications. Insulation classes (b) and (c) may be used in special
cases.
766
ABB_12_E_14 30.08.12 14:36 Seite 767
Table 14-3
Noise-voltage limit values and insulation requirements for analog signals
Notes:
(1) N.F. = System frequency (usually 50/60 Hz)
H.F. = Damped high-frequency oscillation, see IEC 60255-4
IMP = High-voltage pulse
(2) The equipment must withstand this voltage for 1 min without damage.
(3) Insulation class (a) is for normal applications. Insulation classes (b) and (c) may be used in special
cases.
(4) The values for class 3 in Table 14-8 apply here if telecontrol equipment is connected direct to
control devices at the switchgear.
With the use of the process bus to IEC 61850, the secondary system/substation
interface is moved closer to the primary equipment. If the local electronic devices are
seen as part of the switchgear, the requirements for noise voltage and insulation can
become a question of primary technology; the secondary system is then isolated by the
fiber-optic cable link.
General conditions for substations
In substations, all the circuit-breakers and disconnectors which are to be remotely
controlled and have no process bus connection must have a power operating
mechanism and a potential-free make and break contact for switch position indication.
Transformers, arc-suppression and charging-current shunt coils must be provided with
additional potential-free contacts to indicate tap position and running status. All
14
signaling relays working together with telecontrol devices must have a potential-free
normally open (NO) contact. To detect new changes of state the signaling contacts
must be closed only while the coil is energized. Relays isolating against external
interference must be mounted close to the telecontrol equipment. For measurement,
these devices are directly connected to current and voltage transformers.
As part of the power equipment, all these interface devices must conform to the
relevant IEC standards, for instance IEC 60364, and all interface electronics to IEC
61010.
767
ABB_12_E_14 30.08.12 14:36 Seite 768
Commands
Commands to switching devices and transformers or step controlled Petersen coils
are transmitted by the appropriate bay units via digital outputs as two-phase pulsed
commands of 110 or 220 V DC lasting 100 to 500 ms. Other voltages may also be
used.
Single-phase and one-and-a-half-phase output arrangements should be fitted with a
switching monitor in the process-side circuit. The operation or running time of all
switching devices (disconnectors and earthing switches) should to be supervised by
the bay control units.
Plunger core earth-fault neutralizer coils are operated by the allocated control units
either continuously or stepwise. A local/remote switch must be provided to block
remote commands for any switching device, for instance for safety during
maintenance. Suitable software functions must be provided for blocking of several
objects (command groups) or the entire telecontrol through the gateway. The same
requirements apply to RTUs.
Signals
Signals are acquired individually via digital inputs to the secondary device. Normally,
these inputs are galvanically separated by means of optocouplers, whereas the
annunciator contacts can be grouped with a common root. For switch position
indication, both positions must be acquired, and are usually obtained from a
changeover contact or a normally closed (NC) and a normally open (NO) contact. For
disconnectors which operate slowly, the detection and transmission of the
intermediate position should not be suppressed. Signals indicating trips should,
wherever possible, be generated locally in each bay.
The signals can be continuous, of short duration or as transient signals with times of
around 1 ms. The signal voltage used should principally be the battery voltage of 110
V or 220 V DC, which is compatible with all bay units. For dedicated telecontrol
equipment like RTUs, other voltages might be needed.
Measured values
The process interfaces in the digital (numerical) units of substation automation systems
take voltages and currents directly from the instrument transformers. Dedicated
telecontrol systems might need additional interposing transformers. Via the
communication system in the substation and the telecontrol gateway, all measured data
may also be used for remote measuring.
The inputs of bay units must be suitably protected properly against overvoltages.
The entire measurement and transmission chain, from switchgear to control center,
should conform at least to accuracy class 1.
Meter values
If the metering is not already integrated into the secondary system, metered values are
fed to the secondary system as counter pulses or coded counter totals. The counting
devices (primary encoders) usually have 6 decades and BCD coding at the output. For
these counters potential-free inputs are required, and this is normally provided by
optocouplers at the binary inputs.
768
ABB_12_E_14 30.08.12 14:36 Seite 769
Connecting conductors
Only insulated wires and cables may be used to connect the devices of the secondary
system with the switchgear components. Cables with conductors whose insulation is
not moisture-proof have to be suitably sealed at the ends if necessary. The wires and
cables are best installed in underfloor gulleys or on trays or racks. If no gulley is
available, the wiring to the apparatus must be protected by cable channels, cable
ducts, or similar. Earthing wires and cable screens must be connected by low-
impedance connectors to bars linked to the protective earth conductor. To avoid
interference from high-frequency noise created for example by switching operations,
all relevant cables have to be screened and grounded properly.
Fig. 14-17
Load pattern between midnight and
3 p.m., shown as quarter-hourly averages
769
ABB_12_E_14 30.08.12 14:36 Seite 770
Electric energy consumption throughout the day can be made more even by
connecting consumers when load is low – in the afternoons and at night – and
disconnecting them at peak times – in the mornings and evenings. In this way, power
plants and transmission/distribution networks are loaded more uniformly. Depending
on the network management policy, the system, comprising the load management
center, ripple-control equipment (transmitter and coupling) and ripple-control receiver
can be operated on either the open or closed loop principle.
In the first case, the loads are switched on and off according to a fixed timetable. In the
second case, the computer also measures the effective network load, calculates the
trend in order to establish, in relation to a set value, the necessity for connections or
disconnections, and chooses the loads to be affected by any correction required. The
system thus functions like a digital feedback circuit.
Although the main objective is load management, the power utilities also use ripple
control for other purposes, e.g. tariff control (peak rate, off-peak, special rates, etc.),
control of street lighting, neon signs or building illumination, and in special cases also
fire and other alarms, and for operating switchgear where there are no telecontrol links.
With the use of public communications networks such as the internet in most
households, and with inexpensive microprocessor-based metering equipment, “smart
metering” can also be used for control. The deregulated energy market allows such
smart meters to switch loads on or off automatically in response to the electricity price
at the time.
not used locally, there is an energy flow from the distribution to the transmission level,
i.e. in the reverse direction to the flow previously assumed for network design. This is
already observable at times in the night when consumption falls but the wind continues
to blow strongly, and requires adaptation of the network structure with its protection and
control systems. Similar effects are encountered in some countries with power
generation from small plants using coastal gas deposits where purchase of the power is
guaranteed.
The volatility of wind and solar energy means that generation and consumption cannot
be brought in line with each other. The result is a demand for sufficiently large storage
capacities to take the surplus energy which is urgently needed at other times. One
familiar solution is pumped storage hydro power plants (which require hills and water).
New solutions can be discerned in the development of large-scale batteries which is
currently taking place (which, apart from inexpensive batteries, require only space).
If the network – as is conceivable for example with the European interconnected network
grid – has hundreds of thousands of distributed, volatile generation facilities, special
attention has to be devoted to ensuring large-area barrier-free exchange of energy and
the stability of the network. In addition, there is the future volatility of the consumers,
which however will be damped by market prices.
Definition of “smart grid”
The intelligent electrical network of the future will guarantee reliable and cost-efficient
energy supply to all users, even with a very large number of distributed generation
facilities and a host of smart options for consumers. It will therefore promote ecological
power supply, and motivate users of energy to be thrifty. This will be achieved by
optimum use of information technology. This “smartness” is required all the way from the
producer to the consumer, as a collective effect of the network as a whole, and not
merely limited to the distribution network.
Effect on primary systems
The network nodes, i.e. the substations, will remain extensively the same. On account of
the problems of infeed on the distribution level as mentioned above, however, they will
be much more tightly meshed than at present. In this way, the structure of the
distribution network will adapt to that of the transmission network. The number of
voltage levels may be reduced, as is already happening in some countries. Generators
will be connected to the network via the power electronics of the converters, which will
also take on the function of generator circuit-breakers. Power electronics will also be
required for DC links in the grid and for the implementation of FACTS (Flexible AC
Transmission Systems), modifying line impedance electronically and thus controlling
and limiting the load flow. All other line compensation systems such as SVC, TCSS,
STATCOM and UPFC can be regarded as FACTS with a special, limited scope of
function. New elements of primary systems will include storage facilities with familiar
and new technologies, such as advanced batteries.
14
771
ABB_12_E_14 30.08.12 14:36 Seite 772
Meshing of the distribution network has an effect on protection; protection systems will
become similar to those in the transmission system. The small, distributed generation
units with converters which do not supply any notable short-circuit current and which
can be disconnected from the network very rapidly present a problem for protection
systems.
As already mentioned, the consumers in the low voltage network require smart meters
with two-way communication with the utility.
With increasing complexity, automation on all levels will become more and more
important.
The role of standardized communication
Consistent communication is a must in the management of such a smart grid. No matter
whether a function is more local or global (throughout the grid), it must receive all the
data required simply and clearly. It is important to have a powerful communications
infrastructure, which may be composed of different media. The decisive factor is
however a consistent data model for the entire electrical power system. This current
challenge is being addressed by IEC TC57, and the most important components in the
work are the data models of IEC 61850 and IEC 61970 (the Common Information Model
for network control technology).
772