14.8
As the Production planner for Gerry Cook Products, Inc., you have been given a bill of materials for a
bracket that is made up of a base, two springs, and four clamps. The base is assembled from one
clamp and two housings. Each clamp has one handle and one casting. Each housing has two bearings
and one shaft. There is no inventory on hand.
(a) Design a product structure noting the quantities for each item and show the low-level coding.
(b) Determine the gross quantities needed of each item if you are to assemble 50 brackets.
(c) Compute the net quantities needed if there are 25 bases and 100 clamps in stock.
14.9
Your boss at Gerry Cook Products, Inc. has just provided you with the schedule and lead times for the
bracket in Problem 14.8. The unit is to be ready in Week 10. The lead times for the components are
bracket (1 week), base (1 week), spring (1 week), clamp (1 week), housing (2 weeks), handle (1 week),
casting (3 weeks), bearing (1 week), and shaft (1 week).
1
14.10
a) Given the product structure and master production schedule (Figure 14.4), develop a gross
requirement plan for all items.
b) Given the preceding product structure, master production schedule, and inventory status
(Figure 14.14), develop a net materials requirements (planned order release) for all items
FIGURE 14.4
2
14.11
Given the following product structure, master production schedule, and inventory status (Figure 14.15)
and assuming the requirements for each BOM is 1.
Gross requirement of a dependent demand is derived from its immediate parent planned order release.
PERIOD 8 9 10 11 12
Gross requirements: A 100 50 150
Gross requirements: H 100 50
14.12
(a) Based on the following data (see Figure 14.15), complete a net material requirements
schedule for all items (10 schedules in all), assuming the requirement for each BOM is 1
(b) All 10 items, assuming the requirement for all items is 1, except B, C, and F, which
require 2 each.
3