Definitions Introduced
Memorandum submitted by the corporate debtor Date of admission of an application for initiating PPIRP by
the Adjudicating Authority
(a) Interim finance and the costs incurred thereof; Period beginning from the pre-packaged insolvency
(b) RP Fees and expenses incurred by RP for conducting the commencement date and ending on the date on which an
PPIRP during the PPIRP Period; order for approval of resolution plan or termination of PPIRP
(c) Costs incurred by the RP in running the business of the or initiation of CIRP, is passed by the Adjudicating Authority
corporate debtor as a going concern - where management is
vested with RP; Base Resolution Plan
(d) Any costs incurred at the expense of the Government to
facilitate the PPIRP; and A resolution plan provided by the corporate debtor
(e) Any other costs as may be specified (by IBBI);
3
www.virtualaw.in
Eligibility & Conditions for Initiation of PPIRP
CD shall be classified as a micro, small or medium - FCs to propose name of RP (IBBI to specify voting
MSME RP number)
enterprise u/s 7(1) of MSME Development Act, 2006
- FCs with 66% voting share to approve such proposal
- CD has not undergone CIRP or PPIRP for 3 years Majority of Directors / Partners to declare:
CIRP preceding initiation date Declare - That, PPIRP shall be initiated within 90 days
- CD is not undergoing CIRP - That, initiation is not to defraud any person
- Name of the RP as proposed and approved by FC
Note: CD must commit a minimum amount of default of higher value (not exceeding
INR 1 Cr.) to be notified by the MCA
www.virtualaw.in
4
Before Initiation of PPIRP
www.virtualaw.in
5
Application for Initiation of PPIRP
Reject, if
1 MCA to prescribe the format & content of the Application Adjudicating application is
Authority incomplete
(after giving 7 days
shall notice to rectify
To be filed by the Corporate Applicant - where the CD meets defect)
2
the eligibility and conditions for initiation of PPIRP
www.virtualaw.in
6
Application for Initiation of PPIRP
S.7, 9 or 10 Application is
Is the PPIRP Application
pending and whether
pending before
PPIRP Application is filed
Adjudicating Authority
within 14 days of filing of
(before a S.7, 9 or 10
such S. 7, 9 or 10
Application is filed)?
Application?
Adjudicating
Authority shall first
Adjudicating
dispose the S.7, 9 or
Authority shall first
10 Application
dispose the PPIRP
Application
Note: - The above shall not apply, if S. 7, 9 or 10 Application is pending as on the date of commencement of the Ordinance
- Where CD is undergoing PPIRP, the FC or OC of such CD cannot initiate CIRP
- No fresh CIRP Application can be filed till 12 months after the resolution plan is approved in PPIRP
www.virtualaw.in
7
Role of Resolution Professional
- Confirm the list of claims submitted by CD File application for avoidance of transactions under
- Inform the Creditors regarding their claims Chapter III or fraudulent or wrongful trading under
- Maintain updated list of claims Chapter VI
Monitor the management of affairs of the Corporate Present the resolution plans (which confirm to
Debtor S.30(2)) to the CoC for its evaluation
www.virtualaw.in
8
Vesting of Management of CD D is
f C
m e nt o righ ts,
an age a ll t he
em R P, RP
Onc th t he w h ic h
ed w i ut ie s ot her
d d
vest rs and
C IR P an
hall
we g s
po s d urin a to rium
xe rcise of m or
y!
e ns p la
isio nto
CoC resolved with 66% voting prov com
e i
share to vest management of
CD with RP?
www.virtualaw.in
9
Approval of Resolution Plan
2 7 14 Within 90 Within 120
PPIRP days days days days days
Commencement Date
(date of admission of PPIRP)
Note: - All the above dates to be computed from the PPIRP Commencement Date
- Ordinance does not provide for any opportunity to extend the PPIRP period beyond 90 days
- Any person who sustained any loss or damage as a consequence of information provided or omitted in the list of claims or
preliminary IM shall be entitled to move a court having jurisdiction for seeking compensation for such loss or damage from the
promoter of director or partner at the time of such submission or from the person who has authorised such submission.
www.virtualaw.in
10
Approval of Resolution Plan
www.virtualaw.in
11
Approval of Resolution Plan
RP
RP shall provide Evaluation
CoC may provide CD may submit the B
jointly
Matrix & IM to prospective
opportunity to the CD to either individually or
and
resolution applicants who
revise the BRP prior to its with any other person
meet the eligibility criteria
approval or invitation of such BRP shall meet
approved by CoC
prospective resolution requirements of
applicants S.30 (1) & (2)
www.virtualaw.in
12
Termination of PPIRP
1 2 3 4 5
No Resolution Plan CoC did not approve CoC, with 66% voting CoC, with 66% voting Adjudicating Authority
approved by CoC the plan selected after share, resolved to share, resolved to rejected the
within 90 days competing with BRP in terminate the PPIRP initiate CIRP against Resolution Plan as it
the manner specified the CD does not conform to
by IBBI requirements u/s 30(2)
6
Where Adjudicating Authority ordered for vesting
of management of CD with RP and the CoC
approved a resolution plan which does not result
in change in management or control of CD
(refer note)
Note: - In ground no. 6, the Adjudicating Authority shall also order for liquidation.
- In the event of termination, CD shall bear the PPIRP costs, if any.
- After termination, the Adjudicating Authority shall provide for the manner in which the proceedings of
Avoidance Transactions shall continue.
www.virtualaw.in
13
Liquidation of Corporate Debtor
Adjudicating Authority is of
the opinion that the affairs Adjudicating Authority shall
nn ot
of the CD during PPIRP: pass an order vesting the oC ca e
P , C e th
e C IR id at
- have been conducted in management with the
Unlik
o liq u u ring
fraudulent manner Resolution Professional id e t
b to rd
dec rate De
- grossly mismanaged p o P
C o r PPIR
CoC approved resolution No Resolution Plan CoC did not approve the
plan which does not result approved by CoC within resolution plan selected after
in change in management 90 days competing with BRP in the
or control of CD manner specified by IBBI
Adjudicating Authority
Where a resolution plan Adjudicating Authority
shall declare that PPIRP
approved under PPIRP is shall pass an order for
costs shall form part of
contravened by the CD liquidation
liquidation costs
www.virtualaw.in
14
Migration into CIRP
1 3 5
www.virtualaw.in
15
Abbreviations Used
www.virtualaw.in
16
FOR ANY FURTHER QUERIES,
PLEASE CONTACT US AT:
INFO@VIRTUALAW.IN
VListen
First podcast channel in India
on
Insolvency Law
Streaming On
FOLLOW US ON
Disclaimer: While all reasonable efforts have been made to ensure that this info-graphic is free of errors and omissions, please consult the officially published Insolvency and Bankruptcy
Code, 2016 and the rules and regulations made there under and the Insolvency and Bankruptcy Code (Amendment) Ordinance, 2021, in case of any doubts.