Professional Documents
Culture Documents
1.2 Purpose
The intent of this Preliminary BIM Execution Plan (BEP) is to provide a framework that
will let OWJ JV, Sub-contractor, and other interfacing parties to deploy building
information modelling technology and best practices on this project faster and more cost-
effectively throughout the design phase.
The intention of this document is to continually evolve and be updated with
technological developments and as required where the project team deem appropriate
through the design phase of the works.
This plan delineates roles and responsibilities of each party, the detail and scope of
information to be shared, relevant business processes and supporting software and shall
be read in conjunction with the International Best Practice BIM Guides.
The objectives of this BIM Execution Plan are:
1.3 Abbreviations
AIM Asset Information Model
BEP BIM Execution Plan
BIM Building Information Modelling/Management CAFM Computer-
Aided Facilities Management EDMS Electronic Document
Management System
EIR Employer’s Information Requirements (document) FM Facilities
Management
GIS Geographical Information System
IFC Industry Foundation Classes
LOD Level of Development
MPDT Model Production Delivery Table PIM Project Information Model
PM Project Manager
TBC To Be Confirmed
WIP Work in Progress
4D
A 3D representation of an asset with the element of time included to enable
simulations.
5D
A 3D representation of an asset with the element of time and cost
included/linked to enable simulations, commercial management and earned
value tracking to take place.
6D
A 3D representation of an asset which includes data which enables the
efficient management, operation and maintenance of the completed asset.
Contribution
The expression, design, data or information that a party in the Project, creates
or prepares, and shares with other parties in the Project for use in or in
connection with a BIM Model.
Data
Information stored but not yet interpreted or analyzed
Document
Information for use in the briefing, design, construction, operation,
maintenance or decommissioning of a construction project, including but not
limited to correspondence, drawings, schedules, specifications, calculations,
spread sheets
Drawing
Static, printed, graphical representation of part or all of a project or asset
EDMS
Single source of information for any given project, used to collect, manage and
disseminate all relevant approved project documents for multi-disciplinary
teams in a managed process. This is commonly a cloud-based SaaS
(Software as a Service) solution synchronized with party servers to host the
PIM.
Graphical data
Data conveyed using shape and arrangement in space
Non-geometric attribute
A specification that defines a property of an object
Principal Agreement
The agreement or contract for services, supply and/or construction which a
party has entered into for the Project
Project BEP
The Project BEP is the document defining standard methods and procedures
adopted during the contract in order to meet the objectives and requirements
set forth
2. PROJECT INFORMATION
Project Owner: PT. Mass Rapid Transit Jakarta
Project Name: Construction of Jakarta Mass Rapid Transit Project (Phase2)
Project Location and Address: Jakarta Raya
Contract Type / Delivery Method: Design and Build
Construction of the Jakarta Mass Rapid Transit Project Phase 2 comprises ±7.8
km of twin track rail, underground and at grade, with eight stations and 1 depot.
The Project alignment key plan and stations layout are as shown below.
Kota Station.
Glodok Station.
Pre-Final Design
Final-Design
Pre-Final Design
Final Design Submission
Final Design
BIM Manager
C&S BIM Coordinator
MEP BIM Coordinator
Architectural BIM Coordinator
The following section details the application of BIM uses in relation to these
overarching goals described above.
The following sections sets out the requirements for the standard workflows for
each key uses of BIM across the project as agreed in section 4.
6.1 Collaboration Strategy
The overall projects BIM collaboration strategy is developed around the
principals as defined in British Standard BS1192 with the goal of developing and
managed PIM.
Figure 6.1 below illustrates the standard BIM collaboration process to be
adopted between disciplines.
Bentley Project wise will form the core element of the Common Data
Environment (CDE).
Frequency of each model exchange is detailed in the Model Exchange
Schedule section of this BEP for each discipline, indicating the Weekly shared
model requirements and scheduled Virtual Design Review (VDR) dates.
Each discipline team shall take ownership of their Working models (WIP) and
information.
Models are to be reviewed and checked against the requirements as set out in
the Quality Control Section of this BEP.
The federated model will be compiled from only the models which have reached
the SHARED State. This will form the basis of all comments will created,
collated and tracked.
Folder Structure
BIM CDE Purpose Type of Discipline
Document
1_SHARED
PDF
IFC
RVT
DGN Arch
Struc
2_PUBLISHED
3_ARCHIVED
4_WIP
A Shared folder is the central repository for all the LATEST design information
and should be used for all other additional BIM uses required on the project as
defined below.
6.2.5 Published
This folder / State is for validated design output issued to the Client for
specific end of stage milestones for example Pre-Final, Tender or
Construction.
6.2.6 Archived
The Federated VDR model will be submitted to MRT via the EDMS as:
Autodesk Navisworks NWD file format and;
Both these models will be compiled on the IFC file exports of the native design
authoring models.
6.4.1. VDR Clash Migration Strategy
Clashes are inevitable. It is our requirement as a project team develop a
Coordinated Services Model for use in the construction phase of the project.to
identify key areas of design that require further coordination in order to work.
Clashes or coordination Issues shall be created using the Arup JIRA system
in the design authoring platforms or via a specific model check as part of a
VDR.
A VDR with appropriate level of Clash mitigation check is required every two
weeks and at least one week prior to an end of stage milestone. Further
VDRs will be incorporated into the design program to align with the CSD
model development and sign off.
All Issues are to be uploaded and assigned appropriately within in the Arup
JIRA.
Our target is for any Assigned Issue to be responded to within 3 working
days.
Each of the above parameters are to be added to ALL authoring platforms and be
included in the IFC export.
9. COLLABORATION PROCEDURES
The following section sets out the key steps or procedures required to meet the
projects overall collaboration strategy and approach as define above.
9.1 Creation of Design Authoring Models
All models should be created using the specific requirements set out in this BEP
and accompanying technical appendices. Particular attention should be paid to the
following:
Project Set Out
Project Parameters
IFC Export Setup
Linking of SHARED BIM information only. (As Shared within the CDE)
VDR Design Review As Set out in the VDR Program below ALL
Meetings
BIM Workgroup Meeting Monthly BIM Leaders
Example: CLS-BIMWIKA-17.08.25-CMP-01
* indicates that the sequence number resets to zero each day
The table below defines the specific types of comment which will be captured.
Type Description Notes
RFI Request For Information EG Usually created via an EDMS RFI Mail type. A BIM
Used to query an aspect of Issue can be attached as part of the RFI
the model
REV Review Comment Used to capture general overview of a model /
discipline review.
DSG Design Comment Used if Issue requires design/engineering solution or
Input
NON Non Compliance Used to notify areas of the model which do not meet
specific project checks/audits.
CLS Clash All general Spatial / coordination conflicts will be given
this type code.
Item
Arch Struc Vs Struc √ √ √ √
Ductwork vs √
Ductwork
Pipework vs √
Pipework
Cable Tray vs Cable √
Tray
Spatial Zones √ √
Defined
Bespoke Clash √ √
Analysis
All elements with √
correct zones
Note: - All of the above checks are in addition to the Tier 1 checks
Discipline Colour
Architecture Blue (80% Transparent)
Structure Grey
Mechanical Cyan
Electrical Yellow
Fire Red
Hydraulics Magenta
MODEL NAMING:
T&C Telecommunication/signal
Code Type
STN Civil and Structural - Station
ENT Civil and Structural - Entrance [No.]
ES Civil and Structural - Escape Shaft
2.. BIM State Code:
Code State
WIP Work in
PUBL Published
SUB Submission
APP Approved
For object created in BIM software which can have a classification code
added as additional metadata, the following conventation is to be used :
Note: All main filed are all separated by the underscore character
This is to be used for object such as Revit Familied
Field Definition
Source Library author or manufacturer.
Even if the object is generic please include this field.
Term Abbreviation
External Ext
Internal Int
Ground Floor GrFlr
Upper Floor UpFlr
Pitched Ptchd
Flat Flat
Suspended Susp
Raised Access RsdAccs
Ground Bearing GrdBrng
Aluminium Alum
Asphalt Asph
Battens Bttns
Bitumen Btumn
Block Blck
Boarding Brd
Bonded Bndd
Brick Brk
Brick Slips BrkSlp
Cavity Cav
Cassette Cass
Cement Cmnt
Cement Particle Board CPBrd
Ceramic Cermc
Cladding Clad
Composite Panel CmpPnl
Concrete Conc
Concrete Pre-Cast ConcPrc
Concrete In-Situ ConcISt
Cross Laminated Timber CLT
Note: All main fields are all separated by the underscore character “_”
Field Definition
Presentation
Code Description Comments
A Annotation Tags, arrows, symbols etc.
D Dimensions
H Hatch/Shadows
IL Invert Levels For services
M Model related graphics For elements exported from
modelling software such as Revit
M2 2D model graphics (elements in 2D) Element drawn in 2D
M3 3D model graphics (elements in 3D) Element modelled in 3D
P Plot/sheet related elements Title blocks/Viewports
T Text Text
Source_Material_SubType_Differentiator
Field Definition
Source Library author or manufacturer.
Even if the object is generic please include this
field
Material Used to identify the material type, e.g. plastic
Source_Type_SubType_Differentiator_ImageType
Field Definition
Source Material manufacturer (for generic
materials this shall be omitted)
Type Material type e.g. Carpet Tile
Sub Type / Product Used to convey additional information
code / Product Range such as product range. Can also be used
to capture the sub type
Differentiator Used to convey additional specialization
(optional) information not captured in attribute data
e.g. Matte
Image Type Used to convey the image type e.g.
bump, cutout, render