Professional Documents
Culture Documents
October 2019
Chennai Metro Rail Limited
BIM Execution Plan Chennai Metro DDC Phase II Corridor 4 Package 5
Prepared for:
Chennai Metro Rail Limited
Admin Building, CMRL Depot,
Poonamallee High Road,
Koyambedu,
Chennai – 600107,
Tamil Nadu, India
Prepared by:
ASPL+AIPL+AARVEE Consortium
VBC Solitaire
No. 47 & 49, 2nd Floor
Bazullah Road, T Nagar
Chennai 600017
Tamilnadu, India
CIN: U74210TN2002PTC049350
Table of Contents
Figures
Tables
2. Project Information
2.1 Project Owner: Chennai Metro Rail Limited
2.2 Project Name: Contract No. DDC/P2C4/05 (Phase-II, Corridor 4,
Package 05)
2.3 Project Location and Address: Chennai, India
2.4 Contract Type: Detailed Design Consultant
2.5 Additional Project Information:
Engagement of Detailed Design Consultant (DDC) for the works and services of the
detailed design and drawings for the Civil, Structural, Architectural, MEP, VAC & Track
works covering the Alignment, and Elevated section from Pier after Meenakshi College
UG Station to Poonamallee bye-pass (CH 10027.102 to 25829.793), including
approach to Depot and Maintenance Depot at Poonamallee, in Corridor 4 of Phase-II
of Chennai Metro Rail Project.
2.6 Project Milestones:
Brief BIM milestones provided below and to be read along with the latest version
Project Implementation Programmed
Table 1. Project Schedule/ Phases/ Milestones
Project Phase/ Milestone Start date Completion Project stakeholders
date involved
Submission of Concept Design and Design 15-08-2019 14-10-2019 Architecture, Structure, Civil,
Alternatives along with Concept Design Report E&M, Alignment
Submission of Preliminary Design based on 14-10-2019 11-02-2020 Architecture, Structure, Civil,
approved Concept Design, including E&M, Alignment
modifications if any
Delivery of Definitive Design 12-01-2020 09-08-2020 Architecture, Structure, Civil,
E&M, Alignment
Delivery of CRD Drawings 11-04-2020 06-01-2021 Architecture, Structure, Civil,
E&M, Alignment
Issue of" "Good For Construction Drawings” 08-09-2020 04-08-2021 Architecture, Structure, Civil,
E&M, Alignment
5.2 Responsibilities
BIM Manager – The BIM Manager is responsible for the following:
• Authoring the post-contract BIM Execution Plan (BEP) for the project on behalf of
DDC
• Coordinating with CMRL BIM representative in creating the Project BIM Standard
• Attending and providing input during BIM meetings on behalf of DDC
• Coordinating with CMRL Project BIM representative
• Coordinating with DDC design lead and DDC BIM Coordinator
• Generation Master Information Delivery Plan
BIM Coordinator – The discipline BIM coordinator are responsible for the following:
• Ensuring BIM Project Execution Plan is followed through the project duration
• Performing model QA/QC checks on a fortnightly basis
• Export NWC files from the project Revit files on a weekly basis
• Leading the Clash Detection Virtual Walkthrough (CDVW) process
• Updating the Project-wide Navisworks NWF on a fortnightly basis and recording the
NWD.
• Coordinating with discipline BIM Coordinator
• Performing design QA/QC checks, including informal intra-disciplinary CDVW
checks on a fortnightly basis using the project NWF
• Coordinating with the discipline Modeller and designers.
Yellow: Architecture
Blue: Structure
Green, Red, Purple – MEPF
Source: ISO 19650-1:2018_Fig A.2
BIM Preliminary Design, Definitive Per Project DDC Conference Room, War
Coordination Design, CRD and GFC Schedule Room, WebEx
Clash Detection Preliminary Design, Definitive Per Project DDC Conference Room, War
Design, CRD and GFC Schedule Room, WebEx
8. Quality Control
8.1 Overall Strategy for Quality Control
Each participating team will be responsible for the integrity of their models / drawings
as well as compliance with the established CMRL BIM Standards.
DDC P2C4 05 Table No.11 Table No.12 Table No.13 Table No.14
ISSUING ENTITY: Issuing entity for all the documents and drawings will be Detailed
Design Consultant (DDC). It is abbreviated as DDC.
PROJECT: The code for the project is a combination of phase 2 and Corridor 4. It is
abbreviated as P2C4.
PACKAGE: This package as per contract is under package no. 05 (Power House at
Damro to Poonamallee Bypass). It is abbreviated as 05.
DISCIPLINE: Refer below Table for full list of codes:
Table 11. DISCIPLINE CODE
Code Discipline
GEN General
ALN Alignment
GEO Geotechnical
TEM Temporary Works
CIV Civil
ARC Architecture
STN Stations (structure)
STR Structure
VIA Viaducts
TRK Track work
MEP Mechanical, Electrical & Plumbing
VAC Ventilation and Air Conditioning
Project BIM Manager may update the code as per required
FILE TYPE: This element is a two (2) alphanumeric character field. Refer below
Table for full list of codes:
LOCATION: The location code has a maximum of three (3) alphabet characters and is
used to associate documents with geographic areas within the design and construction
region. They are in sequence starting from Power House station to Poonamallee Bypass
Stations. The code is derived by discussing among the Project team members.
Refer Table below for the full list of location codes:
Table 13. STATIONS NAME: CORRIDOR 4, PACKAGE 05
Station No. Station Name Station Code
01 POWER HOUSE AT DAMRO SPH
02 VADAPALANI SVP
03 SALIGRAMAM SSG
04 AVICHI SCHOOL SAS
05 ALWARTHIRU NAGAR SAN
06 VALASARAVAKKAM SVV
07 KARABAKKAM SKM
08 ALAPAKKAM JUNCTION SAJ
09 PORUR JUNCTION SPJ
10 CHENNAI BYPASS CROSSING SCB
11 RAMCHANDRA HOSPITAL SRH
12 IYAPPANTHANGAL BUS DEPOT SID
13 KATTUPAKKAM SKP
14 KUMANANCHAVADI SKI
15 KARYANCHAVADI SKC
16 MULLAITHOTTAM SMT
CORRDIDOR CODE
Corridor-4 Elevated C4E
Depots DEP
SEQUENCE NUMBER: For drawings, dedicated range of numbers will be given for
all the following discipline:
Table 14. Model and Drawing series
Drawing No. Discipline
From 10001 to 19999 Alignment
From 20001 to 29999 Architectural
From 30001 to 39999 Geotechnical
From 40001 to 46999 Stations (structure)
From 47001 to 49999 Structure
From 50001 to 59999 Viaducts
From 60001 to 68999 MEPF
From 69001 to 69999 VAC
From 70001 to 79999 Track Works
From 80001 to 89999 Civil (Traffic, Utilities & etc.)
From 90001 to 99999 General
REVISION: Revision filed shall be one alphabetic letter. The first issue of a complete
drawing package to Employer shall be revision 'A’ and shall not be left blank. Any
resubmissions of the same drawing package shall continue will alphabetic B, C, D ...
In term of contractual tender package, Revision shall be one alphabetic letter when
issued to Employer for the first time. Any resubmissions of the same drawing
package shall continue will alphanumeric A1, A2, A3, A4 . . . . . . . .
BIM models Revision will be used based on the BIM 360 model version for WIP,
Shared and Published.
Therefore, the file naming convention of this project is as follows:
(ISSUING ENTITY) - (PROJECT) - (PACKAGE) - (DISCIPLINE) - (FILE TYPE) -
(LOCATION) - (NUMBER)
There are three option available in the process of model linking under BIM 360
design collaboration module. They are mentioned below:
1. High Trust Design Collaboration
2. Medium Trust Design Collaboration
3. Low Trust Design Collaboration
We will follow option No.2 Medium Trust Design Collaboration for this project. That is
linking the discipline shared models from the shared folder and not from the
‘CONSUME’ folder. Also, CONSUME folder is not to be deleted or rename.
“Rename ‘WorkSet 1’ to ‘0’ and relocate model objects to the new/appropriate project
worksets.”
‘WorkSet 1’ is a default WorkSet that Revit generates when worksets are first
enabled. When enabling worksharing in a Revit file, Revit creates a system workset.
This workset can never be deleted, only renamed. If this workset is used to contain
model objects, it will cut down on the flexibility of editing and consolidating worksets.
Consider renaming the workset to ‘0’ so that it appears at the top of the workset list.
Use workset ‘0’ as a temporary storage for model objects when it is uncertain to
which workset it needs to be assigned.
Create Link discipline specific worksets. Do not use default Revit Shared Levels and
Grids.
10.7 Clash Detection
Navisworks clash detection is required at project milestones but should only be used
for this purpose or when trackable clash reports are required as part of the project
requirement.
Each discipline will be responsible for exporting their most recent Revit model into an
NWC (Navisworks Cache) file for Navisworks clash detection. This file will not
contain any linked models or CAD links. The file(s) will be saved in the “CDE –
Folder Structure (TBC)” folder with the same naming convention as the parent Revit
file. The NWC file will be created by each discipline’s lead at the request of the BIM
Coordinator. The BIM Coordinator will append these files to create an NWF
(Navisworks Working File) and will provide an NWD (Navisworks Document File) for
all disciplines’ use. Each discipline design teams will be responsible for uploading
their NWC file (as required) to the CDE at the request of the Project BIM Coordinator.
Clash Grades: Clashes found by the software are to be analysed, reviewed and
approved as hard clashed (or major clashes), soft clashes (or minor clashes) and
acceptable clashes in accordance with following and resolved or approved
appropriately.
Grade One Clashes: Grade One Clashes are reported clashes that are considered
critical to the design and construction process as they impact on major design
(structural) elements. These clashes should be rectified within the model as soon as
possible. Grade 1 clashes must be resolved, not approved. Clashes with the
following few example elements are Grade 1:
STRUCTURAL
• Sub-Structure
o Foundations
• Super-Structure
o Structural Columns & Primary Beams
o Structural Floors ( including slabs on grade)
o Structural stairs
o Roof Construction
o Core & Shear Walls
• Retaining Walls
• Existing Utilities
• Sub-surface utility ducts & pipe
• Utility Manholes
• Sub-Grade enclosures (e.g. Underground pump-rooms)
Grade Two Clashes: Grade Two Clashes are reported clashes that are considered
important to the design and construction process. These clashes should be rectified
during project progress meetings. Grade 2 clashes may be approved but must be
resolved prior to GFC design issue. Clashes with the following example elements are
Grade 2:
STRUCTURAL
• Walls
• Doors, Windows, louvres
• Roofing
• Casework
Grade Three Clashes: Grade Three Clashes are reported clashes that while
considered important to the correctness of the model will generally be able to be
resolved in the field and that therefore do not require resolution in the BIM Model.
Grade 3 clashes may remain at approved status.
Appendix A
Abbreviation & Definition
Attribute Non-graphical information associated with objects or data within a Model,
e.g. Specification References, Tag Codes, and Classification Codes.
BEP BIM Execution Plan
BIM Building Information Modelling / Building Information Management
BIM Model -A digital representation of the physical and functional characteristics of a
facility created using BIM software as an object-based 3D Model
BoQ Bill of Quantities
CAD Computer Aided Design
CAD Model 2D or 3D CAD files that contain full-size geo-referenced discipline
specific designs
CDE [Common Data Environment] The single source of information for the project,
used to collect, manage and disseminate all relevant approved project documents for
multidisciplinary teams in a managed process
IFC Industry Foundation Classes. A non-proprietary data interchange format
LOD Level of Detail
LOIN Level of Information Need
MDP Model Development Plan
MEPF Mechanical, Electrical, Plumbing and Fire Protection discipline specialties
within engineering
MIDP Master Information Delivery Plan
Model Generic reference to both BIM Models and CAD Models.
NWC Navisworks Cache File, a cached copy of geometry from native BIM model files
(e.g. .rvt) created on the fly when native geometry is opened in Navisworks; can only
be opened with Navisworks Simulate, Review, and Manage
NWD Navisworks Data File. An NWD is a snapshot of the models in the NWF at the
time of Publishing. It saves all the geometry, overrides, transforms, viewpoints, clash
data, everything. NWD files are small, as they compress
NWF Navisworks File Set. An NWF file contains links to the original native files (as
listed on the Selection Tree) together with Navisworks-specific data, such as review
mark-ups. No model geometry is saved with this file format
TIDP Task Information Delivery Plan