You are on page 1of 1

Structural 

Drawings Submittals
Items Date Details
24/01/2021 First Submission to eDF
Main Building ‐ Foundation  04/02/2021 Second Submission to eDF
1
Package + Framing Plans 11/03/2021 Third Submission to eDF
06/04/2021 Fourth Submission to eDF
2 Technical Building ‐ Foundation  09/02/2021 First Submission for coordination
Package + Framing Plans
14/02/2021 First Submission to eDF

Pending Items
Item 01 Floors Reinforcement Drawings Pending eDF approval on foundation package
Item 02 Slab on grade Framing Plans Pending on Atrium Planted Area
Item 03 Steel Roof Pending eDF approval on foundation package
Item 04 Tehnical buildoing Pending approval on MEP tank sizes + receve updated Arch. Drawings based on MEP