Area Limits Calculations (Section 302.3.3 Mixed Use/Separated Uses)

TABLE 1
Construction Type: (insert from 602 and table 503) Mixed Use Separation: Separated
Frontage Increase %: 0% (insert from 506.2) Conversion factor:
Sprinkler Increase %: 0% (insert from 506.3) Conversion factor:
Total Increase %: 0% (frontage increase + sprinkler increase) Total Conversion factor (1.00 + the above): 1.00
Base Allowable Areas: (from table 503 - insert a general list here for reference only)

TABLE 2
Tenant Use Base Allowable sf Conv. Factor Total Allowable sf Actual SF % of Allowable
(from 303) (from Table 503) (total increase %) (base x conv. factor) (from plans) (actual / allowable)
1 1.00 1 0.0000%
2 1.00 1 0.0000%
3 1.00 1 0.0000%
4 1.00 1 0.0000%
5 1.00 1 0.0000%
6 1.00 1 0.0000%
7 1.00 1 0.0000%
8 1.00 1 0.0000%
9 1.00 1 0.0000%
10 1.00 1 0.0000%
TOTAL PERCENTAGE OF ALLOWABLE AREA (Must be less than 100% - sum of ratios less than one) 0 0.0000%
BUILDING CONFORMS TO HEIGHT AND AREA LIMITS OF MIXED USE/SEPARATED REQUIREMENTS (Yes or No): (Y/N)
Note: the sum of the ratios of the floor area of each use divided by the allowable area for each use shall not exceed 1 (100% of the allowable ratio).
Note: Separated uses must have fire separation ratings as shown in Table 302.3.3.

Step 1 Determine the Construction Type. Enter it into table 1.


Step 2 Determine Use Groups applicable to this project and lsit their Base Allowable Areas in Table 1.
Step 3 List the tenants and their respective Use Groups in Table 2. Also enter their actual Square Footages.
Step 4 List Base Allowable Areas for each Use Group in Table 2.
Step 5 Determine the Frontage Increase and the Conversion Factor. Enter them into Table 1.
Step 6 Determine the Sprinkler Increase and the Conversion Factor. Enter them into Table 1.
Step 7 Add the % Total Area Increase and the Total Conversion Factor in Table 1.
Step 8 Enter the Total Conversion Factor from Table 1 into the Conversion Factor column of cells in Table 2.
Step 9 Check the TOTAL Percentage of Allowable Area - it must be less than 1.00 to pass.
Step 10 If the building passes - congratulations! Print the table out or save it for inclusion with your plan submission.
If the building fails - double check your numbers and consider a different strategy.