CONSTRUCTION MANAGEMENT

Submitted By: Muhammad Saad Ameer (2017-TE-11)

Submitted To: Sir Muhammad Touseef Anjum

DEPARTMENT OF TRANSPORTATION ENGINEERING AND MANAGEMENT


UNIVERSITY OF ENGINEERING AND TECHNOLOGY
CONSTRUCTION MANAGEMENT LAB REPORT

The Islamabad–Dera Ismail Khan Motorway (M-14)

1 Project Description

1.1 Project Name

 The Islamabad–Dera Ismail Khan Motorway (M-14)

1.2 Cost of Project

 $1,234,148.38

1.3 Duration of Project

1.4 Length of Road

 285 km

2017-TE-11 1
CONSTRUCTION MANAGEMENT LAB REPORT

1.5 South End

 Dera Ismail Khan

1.6 North End

 Islamabad

1.7 Status

 Under Construction

1.8 Contractors

 Frontier Works Organization (FWO)


 Khalid Rauf & Company Pvt Ltd
 Limak Holding A.S.
 National Logistics Cell
 Zahir Khan & Brothers (ZKB)

1.9 Implementers

 Pakistan National Highway Authority (NHA)

2017-TE-11 2
CONSTRUCTION MANAGEMENT LAB REPORT

1.10 Funders

 Pakistan
 China

This Project consists of five sections, which are as follows: Yarik /DI Khan (on N-55) to Rehamani Khel (55-Km), Rehamani Khel via
Kundal to Daud Khel (70-Km), Daud Khel to Tarap (50-Km), Tarap to Pindigheb (50-Km) and Pindigheb to Hakla on M-1 (60-Km).
The Government of Pakistan committed financing to this project in November of 2017, and the groundbreaking ceremony was held in
May 2016. This project is being developed under the Belt and Road Initiative China-Pakistan Economic Corridor (CPEC) framework.
This project is being constructed as part of the Western Alignment of CPEC.

PROJECT OVERVIEW 2017-TE-11 3


CONSTRUCTION MANAGEMENT LAB REPORT

-
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100% 100%
100%
100%
100%
100% 100%
100% 100%
100%
100%
100%
100%
100%
100%

0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
5%

% COMPLETE

62%

2017-TE-11 4
CONSTRUCTION MANAGEMENT LAB REPORT

WORK OVERVIEW

2017-TE-11 5
CONSTRUCTION MANAGEMENT LAB REPORT

70,000 hrs

60,000 hrs

50,000 hrs

40,000 hrs
Work (hrs)

30,000 hrs
Trucks
Road Marking Machine
Earthwork
Pipes
20,000 hrs
FWO
TEPA
HMA
Digger
10,000 hrs Site Engneer
Pavers (Asphalt)
Concrete Mixers and Pumping Equipment
Dumper Truck
0 hrs Tractor Trolley
4/24/16 11/6/16 5/21/17 12/3/17
Asphalt6/17/1812/30/187/14/19
& Cement Plant engineer 1/26/20 8/9/20 2/21/21 9/5/21 3/20/22 10/2/22 4/16/2310/29/23
Site Engineer
Remaining Cumulative Work Remaining Cumulative
Mason Actual Work Baseline Remaining Cumulative Work
Contractor
Labour (Work Force)
0 hrs 5,000 hrs 10,000 hrs 15,000 hrs 20,000 hrs
2017-TE-11 6

Actual Work Remaining Work


CONSTRUCTION MANAGEMENT LAB REPORT

2017-TE-11 7
CONSTRUCTION MANAGEMENT LAB REPORT

120 hrs
100 hrs
80 hrs
60 hrs
40 hrs
20 hrs
0 hrs
4/24/16 9/25/16 2/26/17 7/30/17 12/31/17 6/3/18 11/4/18 4/7/19 9/8/19 2/9/20 7/12/20 12/13/20 5/16/21 10/17/21 3/20/22 8/21/22 1/22/23 6/25/23

Remaining Availability (Labour (Work Force)) Remaining Availability (Project Manager)


Remaining Availability (Contractor) Remaining Availability (Consultant)
Remaining Availability (Mason) Remaining Availability (Machine Man)
Remaining Availability (Site Engineer) Remaining Availability (Surveyor)
Remaining Availability (Asphalt & Cement Plant engineer) Remaining Availability (Asphalt & Cement Plant)
Remaining Availability (Tractor Trolley) Remaining Availability (Cranes)
Remaining Availability (Dumper Truck) Remaining Availability (Compactors)
Remaining Availability (Concrete Mixers and Pumping Equipment) Remaining Availability (Excavators and Earth Moving Machine)
Remaining Availability (Pavers (Asphalt)) Remaining Availability (Supervisor)
Remaining Availability (Site Engneer) Remaining Availability (Assistant Surveyor)
Remaining Availability (Digger) Remaining Availability (LDA)
Remaining Availability (HMA) Remaining Availability (EPD)
Remaining Availability (TEPA) Remaining Availability (NHA)
Remaining Availability (FWO) Remaining Availability (Dresser Earthwork)
Remaining Availability (Pipes) Remaining Availability (Earthwork Dresser)
Remaining Availability (Earthwork) Remaining Availability (Asphalt)
Remaining Availability (Road Marking Machine) Remaining Availability (Distemper)
Remaining Availability (Trucks)

2017-TE-11 8
CONSTRUCTION MANAGEMENT LAB REPORT

10,000 hrs
9,000 hrs
8,000 hrs
7,000 hrs
6,000 hrs
5,000 hrs
4,000 hrs
3,000 hrs
2,000 hrs
Work (hrs)

1,000 hrs
0 hrs
on es ed ce ed nt in
g
in
g ils ity se se ge ers ign on tion oad rse rse igns site ject
ati oriti Mov aran prov me hift tun rdra ctric r B a n B a igna uld des izati a R Cou Cou l o
il i z
th Be le p re h S ne- a l e la g o S ho e il rm the n g c S era Pr
b u C A u t u E u f S p b o o n ffi n he
o
M ed A ust ork t Be Pro Ear
c Fi of G or an in o e ca o fF of ti ri ra g e er t
d n s l n s f n
Gr Pav tio n th nds De er o yer
m
nda ea up T he v
n M W a t l W t
a ce
r
es oad s M ter
u i tio ui na la
a l la r
o La y a u
La se L lt F o halt ttin ning urn
g O
p
tu Con liti R r a a lla ond Fi st u e T
e o t C In h a a p u a
S
Al
l Uti or act ls M In
s an t B ph f As P
Cl
e
ed gs f tr itta Gr ar
e
t he As o
m n p f
ro is h in co m e
Pr ayin ng
g o in
g
Cs f tabl raw Sub S ub L yi Lay
NO Es op D ia
l La
i ng S h ter
a
i ld en
d M
Bu S o v e
in pr
ta
Ob Ap

Actual Work Remaining Work Baseline Work

2017-TE-11 9
CONSTRUCTION MANAGEMENT LAB REPORT

COST OVERVIEW
-

2017-TE-11 10
CONSTRUCTION MANAGEMENT LAB REPORT

Name Actual Cost Remaining Cost Baseline Cost Cost Cost Variance

Setup and Mobilization $0.00 $0.00 $0.00 $0.00 $0.00

Laying Out and Surveying $297.60 $0.00 $0.00 $297.60 $297.60


Work

Obtain Building NOCs from $0.00 $0.00 $0.00 $0.00 $0.00


All Concerned Authorities

Trial Trenches and Location $1,987.20 $0.00 $0.00 $1,987.20 $1,987.20


Check Of Current Facilities

Established Utilities Must Be $262.80 $0.00 $0.00 $262.80 $262.80


Moved

The Installation of New $350.40 $0.00 $0.00 $350.40 $350.40


Utilities

Send Shop Drawings for Road $0.00 $0.00 $0.00 $0.00 $0.00
Work Clearance

Approve the subcontractors $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractors Must Be $0.00 $0.00 $0.00 $0.00 $0.00


Approved

Approve Materials Submittals $0.00 $0.00 $0.00 $0.00 $0.00

Approve Material Submittals $0.00 $0.00 $0.00 $0.00 $0.00


Material Procurement

Clear and Grubbing $350.40 $0.00 $0.00 $350.40 $350.40

2017-TE-11 11
CONSTRUCTION MANAGEMENT LAB REPORT

Earth Shifting $0.00 $0.00 $0.00 $0.00 $0.00

Drainage $5,440.80 $0.00 $0.00 $5,440.80 $5,440.80

Fine-tuning $492.22 $0.00 $0.00 $492.22 $492.22

Noise Reduction Barriers $0.42 $0.00 $0.00 $0.42 $0.42

Installation of Guardrails $0.42 $0.00 $0.00 $0.42 $0.42

Base granular $885.90 $0.00 $0.00 $885.90 $885.90

Conduits for Electricity $0.00 $0.00 $0.00 $0.00 $0.00

Installation of Drains $0.00 $0.00 $0.00 $0.00 $0.00

Final Granular Base $1,245.82 $0.00 $0.00 $1,245.82 $1,245.82

Walls of Protection $0.22 $0.00 $0.00 $0.22 $0.22

Paving on Base $8,251.42 $0.00 $0.00 $8,251.42 $8,251.42

Symbolism (Foundations) $1,051.62 $0.00 $0.00 $1,051.62 $1,051.62

Installation of Signage $0.00 $526.02 $0.00 $526.02 $526.02

Laying bricks (Wearing $262,752.00 $0.00 $0.00 $262,752.00 $262,752.00


Course)

Granular on the Shoulders $263.10 $0.00 $0.00 $263.10 $263.10

Marking of lanes $0.00 $0.00 $0.00 $0.00 $0.00

2017-TE-11 12
CONSTRUCTION MANAGEMENT LAB REPORT

Landscape design $0.00 $876.00 $0.00 $876.00 $876.00

Acceptance and Checkout $0.00 $0.00 $0.00 $0.00 $0.00

Demobilization $0.00 $9,076.80 $0.00 $9,076.80 $9,076.80

Earthworks $2,102.40 $0.00 $0.00 $2,102.40 $2,102.40

Prepare the Layer of Formation $525.60 $0.00 $0.00 $525.60 $525.60

Sub-base Layer Layout $525.60 $0.00 $0.00 $525.60 $525.60

Laying the Base Layer of the $525.60 $0.00 $0.00 $525.60 $525.60
Road

Bituminous Prime Coat $700.80 $0.00 $0.00 $700.80 $700.80

Laying of Asphalt Foundation $330,108.00 $0.00 $0.00 $330,108.00 $330,108.00


Course

Spray Tack Coat $264,086.40 $0.00 $0.00 $264,086.40 $264,086.40

Laying of Asphalt Wearing $16,505.40 $313,602.60 $0.00 $330,108.00 $330,108.00


Course

Roadway Signage $0.00 $1,226.82 $0.00 $1,226.82 $1,226.82

Putting up Traffic Signs $0.00 $700.80 $0.00 $700.80 $700.80

Lane marking $0.00 $0.00 $0.00 $0.00 $0.00

Cleaning the general site $0.00 $9,427.20 $0.00 $9,427.20 $9,427.20

2017-TE-11 13
CONSTRUCTION MANAGEMENT LAB REPORT

Preparing the project for $0.00 $0.00 $0.00 $0.00 $0.00


handover

Turn Over the Project $0.00 $0.00 $0.00 $0.00 $0.00

2017-TE-11 14
CONSTRUCTION MANAGEMENT LAB REPORT

PROGRESS VERSUS COST


70% $1,400,000.00

60% $1,200,000.00

50% $1,000,000.00

Cumulative Cost
40% $800,000.00
% Complete

30% $600,000.00

20% $400,000.00

10% $200,000.00

0% $0.00
4/24/16 11/6/16 5/21/17 12/3/17 6/17/18 12/30/18 7/14/19 1/26/20 8/9/20 2/21/21 9/5/21 3/20/22 10/2/22 4/16/23 10/29/23

Cumulative Percent Complete Cumulative Cost

2017-TE-11 15
CONSTRUCTION MANAGEMENT LAB REPORT

$350,000.00
COST STATUS
$300,000.00

$250,000.00

$200,000.00

$150,000.00

$100,000.00

$50,000.00

$0.00

Remaining Cost Actual Cost Baseline Cost

2017-TE-11 16
CONSTRUCTION MANAGEMENT LAB REPORT

TASK SHEET
Finish
Task Name Duration Start Finish Predecessors Resource Names % Complete Slack Cost Variance CPI SPI
Setup and Mobilization 30 days Mon 5/2/16 Tue 6/7/16 Supervisor, Site Engineer 100% 0 days $0.00 0 0
Laying Out and Surveying
Work 60 days Wed 6/8/16 Wed 8/24/16 1 Surveyor, Assistant Surveyor 100% 0 days $297.60 0 0
Obtain Building NOCs
from All Concerned
Authorities 24 days Thu 8/25/16 Mon 9/26/16 2 NHA,FWO 100% 0 days $0.00 0 0
Trial Trenches and
Location Check Of Current
Facilities 15 days Thu 8/25/16 Thu 9/15/16 2 Dumper Truck, Digger 100% 0 days $1,987.20 0 0
Established Utilities Must
Be Moved 45 days Fri 9/16/16 Thu 11/10/16 4 Labour (Work Force),Supervisor 100% 0 days $262.80 0 0
The Installation of New Labour (Work Force),Site
Utilities 60 days Fri 11/11/16 Mon 1/23/17 5 Engineer, Supervisor 100% 0 days $350.40 0 0
Send Shop Drawings for
Road Work Clearance 30 days Fri 9/16/16 Sat 10/22/16 4 NHA,FWO 100% 0 days $0.00 0 0
Approve the subcontractors 30 days Fri 9/9/16 Wed 10/19/16 3 HMA 100% 0 days $0.00 0 0
Subcontractors Must Be Thu
Approved 7 days 10/20/16 Thu 10/27/16 8 FWO 100% 0 days $0.00 0 0
Approve Materials Mon
Submittals 15 days 10/24/16 Thu 11/10/16 7 NHA,FWO 100% 0 days $0.00 0 0
Approve Material
Submittals Material
Procurement 15 days Fri 11/11/16 Mon 11/28/16 10 Supervisor 100% 0 days $0.00 0 0
Mon
Clear and Grubbing 60 days 10/24/16 Wed 1/4/17 7 Labour (Work Force),Supervisor 100% 0 days $350.40 0 0
Earth Shifting 45 days Thu 1/5/17 Tue 2/28/17 12 Dresser Earthwork, Supervisor, 100% 0 days $0.00 0 0
Labour (Work Force),Excavators
and Earth Moving Machine,

2017-TE-11 17
CONSTRUCTION MANAGEMENT LAB REPORT

Tractor Trolley
Cranes, Labour (Work
Force),Mason, Site Engineer,
Drainage 30 days Wed 3/1/17 Thu 4/6/17 20 Supervisor, Pipes 100% 0 days $5,440.80 0 0
Aggregate[1],Compactors, Labour
Fine-tuning 25 days Fri 9/29/17 Mon 10/30/17 13 (Work Force),Earthwork Dresser 100% 0 days $492.22 0 0
Noise Reduction Barriers 25 days Thu 1/5/17 Sat 2/4/17 12 Steel[1] 100% 0 days $0.42 0 0
Installation of Guardrails 60 days Thu 1/5/17 Sat 3/18/17 12 Steel[1] 100% 0 days $0.42 0 0
Aggregate[1],Compactors,
Earthwork Dresser, Labour (Work
Base granular 45 days Sat 4/8/17 Thu 6/1/17 14 Force),Sand[1],Supervisor 100% 0 days $885.90 0 0
Conduits for Electricity 90 days Mon 6/27/22 Wed 10/12/22 42 0% 225 days $0.00 0 0
Pipes, Labour (Work
Force),Concrete Mixers and
Installation of Drains 45 days Thu 1/5/17 Tue 2/28/17 12 Pumping Equipment 100% 0 days $0.00 0 0
Aggregate[1],Compactors,
Dresser Earthwork, Labour (Work
Final Granular Base 90 days Sat 6/3/17 Thu 9/28/17 18 Force) 100% 0 days $1,245.82 0 0
Walls of Protection 150 days Mon 3/20/17 Thu 9/28/17 17 Aggregate[1] 100% 0 days $0.22 0 0
Paving on Base 45 days Fri 9/29/17 Thu 11/23/17 21 Aggregate[1],Pavers (Asphalt) 100% 0 days $8,251.42 0 0
Earthwork, Labour (Work
Symbolism (Foundations) 180 days Fri 11/24/17 Sat 6/30/18 23 Force),Mason, Steel[1] 100% 0 days $1,051.62 0 0
Installation of Signage 90 days Mon 6/27/22 Wed 10/12/22 39 Labour (Work Force),Steel[1] 0% 330 days $526.02 0 0
Laying bricks (Wearing Mon Asphalt & Cement Plant, Labour
Course) 120 days 12/30/19 Fri 5/22/20 35 (Work Force),Pavers (Asphalt) 100% 0 days $262,752.00 0 0
Aggregate[1],Asphalt,Labour
(Work Force),Earthwork
Granular on the Shoulders 45 days Sat 5/23/20 Thu 7/16/20 26 Dresser,Sand[1],Supervisor 100% 0 days $263.10 0 0
Road Marking
Marking of lanes 180 days Mon 6/27/22 Wed 1/25/23 39 Machine,Distemper 0% 240 days $0.00 0 0
Labour (Work
Landscape design 300 days Fri 10/15/21 Wed 6/14/23 39 Force),Supervisor,Trucks 0% 120 days $876.00 0 0
Acceptance and Checkout 15 days Fri 10/15/21 Mon 11/1/21 39 0% 615 days $0.00 0 0
Demobilization 60 days Mon 6/27/22 Wed 9/7/22 42 Cranes,Supervisor,Trucks 0% 360 days $9,076.80 0 0
Supervisor,Digger,Labour (Work
Earthworks 540 days Mon 7/2/18 Thu 4/16/20 24 Force) 100% 0 days $2,102.40 0 0
Prepare the Layer of
Formation 90 days Wed 2/6/19 Fri 5/24/19 32 Labour (Work Force),Supervisor 100% 0 days $525.60 0 0
Sub-base Layer Layout 90 days Sat 5/25/19 Wed 9/11/19 33 Labour (Work Force),Supervisor 100% 0 days $525.60 0 0
Laying the Base Layer of 90 days Thu 9/12/19 Sat 12/28/19 34 Labour (Work Force),Supervisor 100% 0 days $525.60 0 0

2017-TE-11 18
CONSTRUCTION MANAGEMENT LAB REPORT

the Road
Labour (Work
Force),Supervisor,Asphalt,Asphalt
Mon & Cement Plant,Asphalt &
Bituminous Prime Coat 120 days 12/30/19 Fri 5/22/20 35 Cement Plant engineer 100% 0 days $700.80 0 0
Labour (Work
Force),Supervisor,Asphalt,Asphalt
Laying of Asphalt & Cement Plant,Asphalt &
Foundation Course 150 days Sat 5/23/20 Fri 11/20/20 36 Cement Plant engineer 100% 0 days $330,108.00 0 0
Labour (Work
Force),Supervisor,Asphalt,Asphalt
& Cement Plant,Asphalt &
Spray Tack Coat 120 days Sat 11/21/20 Thu 4/15/21 37 Cement Plant engineer 100% 0 days $264,086.40 0 0
Labour (Work
Force),Supervisor,Asphalt,Asphalt
Laying of Asphalt Wearing & Cement Plant,Asphalt &
Course 150 days Fri 4/16/21 Thu 10/14/21 38 Cement Plant engineer 5% 0 days $330,108.00 0 0
Roadway Signage 210 days Thu 3/10/22 Wed 11/1/23 39 Labour (Work Force),Steel[1] 0% 0 days $1,226.82 0 0
Putting up Traffic Signs 120 days Fri 10/15/21 Wed 3/9/22 39 Labour (Work Force) 0% 510 days $700.80 0 0
Road Marking
Lane marking 210 days Fri 10/15/21 Sat 6/25/22 39 Machine,Distemper 0% 225 days $0.00 0 0
Thu Cranes,Labour (Work
Cleaning the general site 60 days 10/13/22 Wed 12/21/22 19 Force),Trucks 0% 225 days $9,427.20 0 0
Preparing the project for Thu
handover 30 days 12/22/22 Wed 1/25/23 43 FWO,NHA 0% 225 days $0.00 0 0
Turn Over the Project 15 days Thu 1/26/23 Sat 2/11/23 44 0% 225 days $0.00 0 0

2017-TE-11 19
CONSTRUCTION MANAGEMENT LAB REPORT

RESOURCE SHEET
Resource Name Type Material Label Initials Group Max. Units Std. Rate Accrue At Base Calendar
Labour (Work Force) Work L 100% $0.73/hr Prorated Standard
Project Manager Work P 100% $0.00/hr Prorated Standard
Contractor Work C 100% $0.00/hr Prorated Standard
Consultant Work C 100% $0.00/hr Prorated Standard
Mason Work M 100% $1.30/hr Prorated Standard
Machine Man Work M 100% $0.65/hr Prorated Standard
Site Engineer Work S 100% $1.73/hr Prorated Standard
Surveyor Work S 100% $0.62/hr Prorated Standard
Asphalt & Cement
Work A 100% $0.66/hr Prorated Standard
Plant engineer
Asphalt & Cement
Work A 100% $273.70/hr Prorated Standard
Plant
Tractor Trolley Work T 100% $5.08/hr Prorated Standard
Cranes Work C 100% $18.91/hr Prorated Standard
Dumper Truck Work D 100% $16.56/hr Prorated Standard
Compactors Work C 100% $1.73/hr Prorated Standard
Concrete Mixers and
Work C 100% $2.01/hr Prorated Standard
Pumping Equipment
Excavators and Earth
Work E 100% $16.83/hr Prorated Standard
Moving Machine

2017-TE-11 20
CONSTRUCTION MANAGEMENT LAB REPORT

Pavers (Asphalt) Work P 100% $22.92/hr Prorated Standard


Bitumen/Asphalt Material B $0.55 Prorated
Water Material W $6.52 Prorated
Aggregate Material A $0.22 Prorated
Cement Material C $3.42 Prorated
Steel Material S $0.42 Prorated
Sand Material S $0.08 Prorated
Supervisor Work S 100% $0.00/hr Prorated Standard
Site Engneer Work S 100% $0.00/hr Prorated Standard
Assistant Surveyor Work A 100% $0.00/hr Prorated Standard
Digger Work D 100% $0.00/hr Prorated Standard
LDA Work L 100% $0.00/hr Prorated Standard
HMA Work H 100% $0.00/hr Prorated Standard
EPD Work E 100% $0.00/hr Prorated Standard
TEPA Work T 100% $0.00/hr Prorated Standard
NHA Work N 100% $0.00/hr Prorated Standard
FWO Work F 100% $0.00/hr Prorated Standard
Dresser Earthwork Work D 100% $0.00/hr Prorated Standard
Pipes Work P 100% $0.00/hr Prorated Standard
Earthwork Dresser Work E 100% $0.00/hr Prorated Standard
Earthwork Work E 100% $0.00/hr Prorated Standard
Asphalt Work A 100% $0.00/hr Prorated Standard
Road Marking Machine Work R 100% $0.00/hr Prorated Standard
Distemper Work D 100% $0.00/hr Prorated Standard
Trucks Work T 100% $0.00/hr Prorated Standard

2017-TE-11 21
CONSTRUCTION MANAGEMENT LAB REPORT

RESOURCE USAGE
Resource Name Work
Aggregate 18 ft³
Fine Grading 1 ft³
Granular Base 1 ft³
Granular base final 2 ft³
Barrier walls 1 ft³
Paving base 1 ft³
Shoulder granular 1 ft³
Sprinkling water 4 hrs
Compaction 14 hrs
Site Engineer 24 hrs
Setting up site office 8 hrs
Drainage Storm Water Management ponds 8 hrs
Construction of pier 8 hrs
Bitumen 4 kg
Paving (wearing course) 1 kg
Shoulder granular 1 kg
Construction of slab joints 1 kg
laying of asphalt wearing course 1 kg
Cement 12 bags
Shoulder granular 1 bags
Water 14 tank
Shoulder granulars 1 tank
Sprinkling water 1 tank
Compaction 1 tank

2017-TE-11 22
CONSTRUCTION MANAGEMENT LAB REPORT

Steel 17 kg
Noise barriers 2 kg
Guardrails Installation 2 kg
Signage(foundations) 1 kg
Erecting traffic sigs 1 kg
Cranes 164 hrs
Drainage Storm Water Management ponds 1 hr
Demobilization 1 hr
General site cleaning 24 hrs
Dumper 0 hrs
Trial trenches & bore holes 0 hrs
Compactors 140 hrs
Fine Grading 24 hrs
Granular Base 24 hrs
Granular base final 24 hrs
Paving (wearing course) 24 hrs
Compaction 4 hrs
leveling surface 40 hrs
Concrete Mixers 178 hrs
Excavators 51 hrs
Earthmoving 48 hrs
Excavation 1 hr
Bore pile holes 1 hr
Installation of pile 1 hr
Pvt. Marking Macliie 48 hrs
Lane marking 24 hrs
Bridge pavement marking 24 hrs
Pavers 34 hrs
Paving base 8 hrs
Paving (wearing course) 2 hrs
laying of asphalt wearing course 24 hrs

2017-TE-11 23
CONSTRUCTION MANAGEMENT LAB REPORT

Labor 500 hrs


Protection or relocation of existing utilities as required 8 hrs
Laying of new utilities 56 hrs
Subdrains installation 1 hr
Granular base final 1 hr
Signage(foundations) 21 hrs
Signage installation 24 hrs
Landscaping 24 hrs
Demobilization 3 hrs
Excavation 3 hrs
leveling surface 3 hrs
Erecting traffic sigs 24 hrs
General site cleaning 24 hrs
Concrete Pumping Machine 30.67 hrs
Drainage Storm Water Management ponds 8 hrs
Subdrains installation 16 hrs
Construction of pile cap 6.67 hrs
Trucks 98 hrs
Earthmoving 48 hrs
Landscaping 24 hrs
Demobilization 2 hrs
General site cleaning 24 hrs
Mason 123 hrs
Signage(foundations) 2 hrs
Sprinkling water 2 hrs
Compaction 2 hrs
leveling surface 64 hrs
Bore pile holes 2 hrs
Installation of pile 48 hrs
Placement of girders 40 hrs
Installation of bearing pad 56 hrs

2017-TE-11 24
CONSTRUCTION MANAGEMENT LAB REPORT

Placement of deck slab 40 hrs


Bridge pavement marking 24 hrs
Site Engineer 64 hrs
Laying of new utilities 56 hrs
Excavation 4 hrs
Compaction 4 hrs
Supervisor 350 hrs
Setting up site office 48 hrs
Setting out and survey works 56 hrs
Protection or relocation of existing utilities as required 8 hrs
Laying of new utilities 56 hrs
Procurement of the materials 24 hrs
Clear and grubbing (Site clearance) 56 hrs
Earthmoving 48 hrs
Drainage Storm Water Management ponds 3 hrs
Electrical conduits 24 hrs
Landscaping 24 hrs
Demobilization 3 hrs
Surveyor 56 hrs
Setting out and survey works 56 hrs
Testing Equipment 36 hrs
Fine Grading 24 hrs
Checkout and acceptance 12 hrs
Assistant Surveyor 64 hrs
Setting out and survey works 56 hrs
Spray Machine 40 hrs
Sprinkling water 40 hrs
Drainage Storm Water Management ponds 2 meter
Subdrains installation 2 meter
Pumping Machinery Boring 16 hrs
Bore pile holes 8 hrs

2017-TE-11 25
CONSTRUCTION MANAGEMENT LAB REPORT

Installation of pile 8 hrs


Dresser Earthwork 129.08 hrs
Earthmoving 48 hrs
Fine Grading 24 hrs
Granular Base 24 hrs
Granular base final 24 hrs
Bore pile holes 5.08 hrs
Installation of pile 4 hrs
Un skilled labor 104 hrs
Clear and grubbing (Site clearance) 56 hrs
Earthmoving 48 hrs
Digger 50.67 hrs
Trial trenches & bore holes 24 hrs
Excavation 26.67 hrs
Carriage Charges of RCC Pipe 6in 2 Per pipe
Drainage Storm Water Management ponds 1 Per pipe
Subdrains installation 1 Per pipe
Testing Charges of RCC Pipes 6 2 Per pipe
Drainage Storm Water Management ponds 1 Per pipe
Subdrains installation 1 Per pipe
Foreman Asphalt 50 hrs
Paving (wearing course) 2 hrs
Shoulder granulars 24 hrs
laying of asphalt wearing course 24 hrs
Asphalt Plant Engineer 48 hrs
Paving (wearing course) 24 hrs
laying of asphalt wearing course 24 hrs
Concrete Plant Engineer 125 hrs
Drainage Storm Water Management ponds 2 hrs
Subdrains installation 2 hrs
Forman Concrete 178 hrs

2017-TE-11 26
CONSTRUCTION MANAGEMENT LAB REPORT

Drainage Storm Water Management ponds 4 hrs


Subdrains installation 4 hrs
Erecting traffic sigs 24 hrs
Foreman Earthwork 72 hrs
Earthmoving 48 hrs
Fine Grading 2 hrs
Granular Base 3 hrs
Granular base final 3 hrs
Signage(foundations) 2 hrs
Shoulder granulars 2 hrs
Excavation 3 hrs
Drainage Storm Water Management ponds 2 hrs
Demobilization 1 hr
Installation of pile 1 hr
Electrician 24 hrs
Electrical conduits 24 hrs
Nail and Screw (Copper) 1 kg
Electrical conduits 1 kg
Binding wire 1 kg
Electrical conduits 1 kg
Welding electrode 1 Bundle
Electrical conduits 1 Bundle
Special Clamps with bolts and nuts 1 Item
Electrical conduits 1 Item
Prestressing Cable having 12 Nos. wire 1 Ton
Electrical conduits 1 Ton
Road Marking Machine 48 hrs
Lane marking 24 hrs
Bridge pavement marking 24 hrs
Distemper (Vinyl Emulsion) 2 Gallon
Lane marking 1 Gallon

2017-TE-11 27
CONSTRUCTION MANAGEMENT LAB REPORT

2017-TE-11 28
CONSTRUCTION MANAGEMENT LAB REPORT

GANTT CHART

2017-TE-11 29
CONSTRUCTION MANAGEMENT LAB REPORT

2017-TE-11 30
CONSTRUCTION MANAGEMENT LAB REPORT

2017-TE-11 31
CONSTRUCTION MANAGEMENT LAB REPORT

2017-TE-11 32
CONSTRUCTION MANAGEMENT LAB REPORT

2017-TE-11 33