PROJET : TRAVAUX DE REALISATION DE LA STATION DE POMPAGE SPMZ2 ET SA CONDUITE DE REFOULEMENT

AVANCEMENT DES REGARDS


NETTOYAGE ET BETON DE
RADIER VOILES CLOCHE ECHELON / TAMPON
CONDUITE TROP PLEIN N° Regard PROPRETE Avancement
10% 20% 40% 10% 20%
R1 - - - - - 0%
R1BIS - - - - - 0%
R2 100% 100% 100% - - 70%
R3 100% 100% 100% 100% - 80%
R4 100% 100% 100% 100% - 80%
R5 100% 100% 100% - - 70%
R6 100% 100% 100% - - 70%
R7 100% 100% 100% - - 70%
R8 100% 100% 80% - - 62%
R9 100% 100% 100% - - 70%
R10 100% 100% 100% - - 70%
R11 100% 100% 100% - - 70%
R12 100% 100% 100% - - 70%
REGARD
R13 100% 100% 100% - - 70%
R14 100% 100% 100% - - 70%
R15 100% 100% 60% - - 54%
R16 100% 100% 90% - - 66%
R17 100% 100% 0% - - 30%
R18 100% 100% 0% - - 30%
R19 0% 0% 0% - - 0%
R20 0% 0% 0% - - 0%
R21 0% 0% 0% - - 0%
R22 0% 0% 0% - - 0%
R23 0% 0% 0% - - 0%
R24 0% 0% 0% - - 0%
R25 0% 0% 0% - - 0%

Avancement TOTAL 42%