Professional Documents
Culture Documents
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
Contractor : Daelim-Lotte JV
Site : Gulpur
03 07/06/2017 Issued for Approval Naveed Naseem Tanzeel Javed Afzal Lee Jae Chul Cho Sang wan
02 23/04/2017 Issued for Approval Naveed Naseem Tanzeel Javed Afzal Lee Jae Chul Cho Sang wan
01 26/03/2017 Issued for Approval Naveed Naseem Tanzeel Javed Afzal Lee Jae Chul Cho Sang wan
00 18/01/2017 Issued for Approval Naveed Naseem Tanzeel Javed Afzal Lee Jae Chul Cho Sang wan
Contents
1. Purpose……………………………………………………………………………….3
2. Scope of work…………………………………………………………………………3
4. Resources……………………………………………………………………………12
6. Execution procedure………………………………………………………………….16
9. Attachments…………………………………………………………………………..44
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
1. Purpose
This Method Statement covers the construction works of waterway tunnels concrete lining.
To provide a document that managers must read and understand before starting the job.
a) A vertical pressure shaft of 44.5 m height and 6.7m inner diameter (after lining concrete)
b) A horizontal pressure tunnel of 122.5 m length with 6.7 inner diameter after lining.
b) A vertical transition part of 10.5 m height with 6.7m inner diameter(after lining concrete)
a) A lower bend of 19.635 m length with 6.7m inner diameter (after lining concrete).
b) A horizontal pressure tunnel of 50.650 length with 6.7 inner diameter after lining concrete.
c) A Steel penstock tunnel of 55 m length with 6.7 inner diameter after steel lining
Both Headrace tunnels has exactly the same length, diameter and design.
{Figure 4: Vertical pressure Tunnel}
Shape circular
7.6m (Inner
Vertical Shaft tunnel 1 & 2
Diameter
Circular)
Height 24.5 m
Type of
Concrete lining
lining
Thickness
400 mm
of lining
shape Square
7.6×7.6m Inner
Size
After lining
Horizontal Tunnel 1 & 2
height 10.5 m
Type of
Concrete lining
lining
Thickness
of lining 1000 mm
concrete
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
Shape circular
7.6m Inner
Diameter
(after lining)
Lower bend 1 & 2
length 19.635 m
Type of
Concrete lining
lining
Thickness
of lining 1000 mm
concrete
7.6m (Inner
Diameter
Circular)
length 50.650 m
Type of
Concrete lining
lining
Thickness
of lining 400
concrete
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
7.6m
Type of
Steel lining
lining
Thickness
of lining 700~1000 mm
concrete
2.4.2 Specifications(Revision-C)
1. Tunnels.
3. Organization and responsibilities
Site Manager: Cho Sung wan
Summing up the result of management review of each discipline and reporting the results to project
Manager.
Planning and controlling project schedule.
Checking, analyzing and reporting the differences between schedule and actual progress.
Coordination to each section with respect to relevant technical matters.
Supervising the operation of document control system.
Controlling the project's design documents and the change of the design documents at site.
Controlling for expediting the delivery of purchased material and handling materials at site.
Construction Manager: Mr. Lee Jae Chul
Ensuring identification and analysis of the technical requirements of the project.
Assuring that organization is equipped with adequate resources and information to achieve quality.
Assisting the Site manager in any aspect regarding engineering matter.
Practical responsibilities for implementation of work execution
Control of manpower and equipment
Coordination with QA/QC department regarding inspection and testing
Check and review of progress as per schedule
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
4. Resources
4.1. Manpower
{Table 1 Manpower detail for Horizontal tunnels excavation and support)
2 Surveyor 1 1 1 1
3 Surveyor helper 2 1 2 1
4 Foreman 2 2 1 1
Steel fixer
5 10 10 5 5
Carpenter
6 05 05 4 4
Welder
7 05 05 4 4
8 Mason
5 5 4 4
9 Unskilled labor
12 10 5 5
10 Operators 4 4 2 2
47 44
Total 29 28
1
Excavator (jack hammer) 0.6 CUM Scaling, trimming 1
2 Cleaning,
Charging car 2 man basket 1
dismantling, rebar fixing
3
Steel plate form 6 M (High) Rebar fixing 1
4
Concrete pump 120 m3/hour Concrete pouring 1
Horizontal tunnels
5
Water pumps 3” Dewatering, curing 1
6
Gas cutter Cutting works 1
7 Welding machine Welding works 2
5. Flow diagram
5.1 Vertical tunnels lining concrete flow diagram
[Figure 2: Sequence of work for waterway vertical shafts excavation & support]
Removal of Existing
Temporary facilities
Steel fixing
Assembling of liner
Lean/Leveling concrete
Removal of Existing
Temporary facilities
Steel fixing
Assembling of lining form
Side stopper Shifting and Fixing of lining Fixing of plugs for grouting
form
Detachment of form
6. Execution Procedure
6.1 Concrete lining Lower bend
Concrete lining of waterway tunnels will be started from lower bend,
The lining procedure will include following activities
Cleaning and removing and dirt and left overs due to tunneling works by means of
Bottom cleaning with water jets and manpower.
Placement of lean/leveling concrete, lean concrete will be started from lower bend
towards out let.
Placement of 1st stage concretes according to drawing
Remove any over spray which may prevent correct re-bar placing.
Placing re-bars according to drawing
Fixing of concrete spacers to secure required concrete cover.
Placing of liner segments. (For detail refer to attach#1)
This operation will involve a surveyor which will check
Formwork positioning.
{Figure9: lower bend steel form}
Segments of lower bend lining form will be shifted inside the tunnel by using mobile
crane located at intake Elevation 517, Around 5 meter of bend form plates will be
shifted in the location through horizontal tunnel by using dump truck.
Fixing of segments will be started from horizontal tunnel towards the vertical shaft.
Segments will be joined and fixed on the provided sequence numbers by using
holes and nuts. During fixing of plates charging car will be used from the horizontal
tunnel for worker access and support the plates ,mobile crane will be used through
vertical tunnel to handle the form plates
Welding will be carried out to join the segments when required.
Monolithic concrete will be poured in the lower bend section to avoid the
construction joint.
Concrete pouring will be placed from the bottom of the bend in 50 cm layer. Each
layer will be compacted by means of inner vibrator.
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
As the thickness of lining concrete is 1 mete in this section which in enough space
for workers to go in for the positioning of concrete pipes and use of vibrator for
compaction of concrete.
As the poring of lower bend is long job it will take approximately more than 48
hours, so the stripping will be started form initial poured area after 12 hour from the
completion of total pour. During striping of form charging car will be used from the
horizontal tunnel for worker access and support the plates ,mobile crane will be
used through vertical tunnel to handle the form plates. Form will be shifted out
through vertical tunnels by using mobile crane fixed at intake elevation. Plates
which are not accessible by the crane will be loaded on dump truck by using wheel
excavator and will be shifted out through horizontal tunnel.
Lifting plates are provided at the top of 4 stiffing ribs for the lifting purpose.
{Figure 10: Vertical pressure Tunnel}
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
Lifting plate
Working plate form
2000
A temporary steel structure will be erected at the top of shaft for lifting of steel lining
form during lining concrete. Lining form will be lifted with the chain blocks and steel
sling hooked with the provided lifting plates. These plates are provided with form as
well as with steel rib structure.
A A
Reinforcing bars will be supplied by using crane installed on the top of the vertical
tunnels.
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
Steel bars will be lowered by winch on the working platform and will then be placed on a continuous base: in
order to make steel placement operations more comfortable, vertical bars will be provided with
staggered splicing along the shaft perimeter. {Figure 13: Vertical pressure Tunnel view from bottom}
In order to not create unexpected stresses to the form, concrete lifts will be poured
in layers, so that the difference of level in any part of the casting will not exceed the
limit defined by the equipment designer.
Detachment of the formwork will be performed when the concrete has hardened
and developed enough strength to self-sustain.
The minimum time that will have to elapse between the end of each pouring and
the start of the removal of the relevant formwork will minimum 12 hours, in
compliance with the technical specifications and based on the selected concrete
admixture. Refer to
At the end of the cycle, the detached formwork will be lifted with chain blocks and
then positioned upward for next cast.
As the same form will not be used for next pour, it has planned to delay striping few more hours from the
recommended striping time. Striping will be started from the supports, mobile crane will be used to shift form out.
Concrete will be cured continuously by using water pipes and manpower up to 14 days as per project
specifications.
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
‘
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
Cleaning and removing and dirt and left overs due to tunneling works by means of
Bottom cleaning with water jets and manpower.
Placement of lean/leveling concrete, lean concrete will be started from lower bend
towards out let.
Bottom will be fully cleaned and required top level will be marked at fixed rebar.
Concrete will be placed by using concrete pump.
Survey of the shotcrete face and check for minimum concrete thickness allowance
and remove any over spray which may prevent correct re-bar placing.
Placing re-bars using steel plate form.
Fixing of concrete spacers to secure required concrete cover.
Fixing of grouting plugs according to the drawing and specifications.
Placing formwork according to drawings. This operation will involve a surveyor
which will check formwork positioning.
Pour concrete using long pipes. Special care shall be given during concrete
pouring in order to avoid non symmetrical cast.
Allow initial strength development will be checked by QA department.
Detachment of the formwork will be performed when the concrete has hardened
and developed enough strength to self-sustain.
The minimum time that will have to elapse between the end of each pouring and
the start of the removal of the relevant formwork will minimum 12 hours, in
compliance with the technical specifications and based on the selected concrete
admixture.
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
At the end of the cycle, the detached formwork will be shifted by using hydraulic
system and then it will be positioned for next cast.
the top. Pouring will be started from bottom then sides and finally top. Wall plugs will be
connected with one main supply for symmetrical cost in both sides.
Inner vibrator will be used through the windows, however external vibrators will also be used
where internal vibrators is not practicable
4-8 kg wooden hammers will be used for compaction purpose when required. As shown in the
figure above.
7.2 Lower bend
Concrete Lining thickness is one meter in lower bend section, which is enough space for
worker to go to for us of vibrator.
Two inner vibrators will be used on both side for effective concrete compaction.
Each 50 cm layer will be compacted by means of inner vibrator.
5-8 kg wooden hammer will be used when required for better result.
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
Abbreviations Used:
RFI:Request for Inspection
BP: Batching Plant
QC: Quality Control
QA: Quality assurance
RCP: Report of Concrete production
CDN: Concrete Delivery Note
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
In addition to above, concrete cylinder shall be cast at site and bring Laboratory to verify its compressive
strength at required ages as per project specifications.
The following information shall be marked on every concrete cylinder.
RFI #
Concrete strength
Casting date
Concrete cylinder #
Lab #
QC staff would prepare and maintain a set of following documents against each request of Concrete
production:
RFI
RCP
Compressive strength test results
QA department would assure the quality of above stated works at each stage. However, construction team is
required to submit RFI along with requisite documents for inspection of each stage on completion to the
QA staff (Refer to 7.2.1 – Inspection procedure and record). This formal inspection procedure is
mandatory as per international standard/ project contract documents. QA staff would be responsible to
maintain all QA related record of inspections for above stated works.
The quality assurance of under execution works; Rebar cutting bending, formwork, embedded items
installation and concrete placement also assured by QA team during the work.
The quality of produced Concrete shall also be assured at site by the QA staff (i.e. Inspector, Lab Technician,
Lab Assistant/helpers etc.). They would prepare and sign the “QA Report of Concrete Placement”.
QA persons (i.e. Inspector, Lab technician, Lab assistants/helpers) would be present at site to check the
following properties of transported Concrete:
Temperature
Slump
In addition to above, Concrete cylinder would be casted at site as per frequency of project specification to
verify compressive strength of it’s at required ages. The following information should be marked on every
concrete cylinder which mention below
RFI #
Concrete class
Casting date
Concrete cylinder #
Lab #
These concrete cylinders would be carried to laboratory for further necessary testing.
QA staff would prepare and maintain a set of following documents against each request of
shotcrete/Concrete production:
QA report of Concrete placement
Compressive strength test result
Step # 1 Construction team would prepare/complete the sub-activity according to design and drawings
and after their satisfaction would generate and submit an RFI to QA/QC department. The
RFI submitted must accompany the Survey sheet and other necessary relevant
documents.
Step # 2 QA/QC Engineer/Inspector would receive and record the RFI in a register and carried out
inspection.
Step # 3 If RFI is related to works of Reinforcement, etc. then QA Engineer/Inspector shall make
inspection accordingly. He shall sign the RFI and relevant checklist and update the record
of “RFI Register”. Representative of Construction team would be present at site throughout
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
this process so that important instructions may be delivered to him directly without any
confusion and ambiguity.
Step # 4 If RFI is related to concrete placement then QA Engineer/Inspector would inspect and on
satisfactory inspection he would mark the RFI to Lab Engineer/Snr. Lab Technician for
concrete production accordingly. The representative of Construction team would be
responsible to deal with the manpower to ensure the proper placement of concrete.
Step # 5 Lab Engineer/ Snr. Lab Technician would receive the request and enter the relevant data in
the “Lab Test Request Register”. He would depute QA/QC staff at BP for QC of Concrete
production and it’s QA at site respectively. “RCP” and “QA Report of Shotcrete Placement”
shall be prepared and signed by concerned authorities at BP and site respectively.
During above stated process of Concrete production, the BP operator would issue “CDN” for
each transit mixer duly signed by him and QC staff at BP.
Step # 6 On completion of above process, the QA Engineer would forward the RFI to the QA Manager
for review and signature.
The QA/QC team always invites and welcomes the criticism and suggestions that would be
helpful to enhance its capacity and efficiency leading to a better and proud finish. After all,
the successful completion of a Project always demands a good “teamwork”.
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
During construction material transportation proper root shall be designated for heavy equipment
movement to control road traffic incidence,
Proper area shall be designated for tower crane parts unloading and assembling,
Competent operator and rigger shall be appointed for crane operation
Only authorized person shall carry out lifting activity
To carryout safe lifting operation, compliance of permit to works system shall be ensured,
The lifting equipment that includes shackles and slings must be of good quality and third party certified.
Concrete placement boom shall be thoroughly inspected periodically by the heavy equipment department
to ensure good condition of joints and clamps used.
Whip checks shall be used at each joint of air compressor pipes.
All the newly hired workers shall be inducted prior to send them to site
The access way for the workers shall be un-obstructed and proper,
The construction material shall be unloaded at designated area,
Signal men to shall be deployed at different point to control traffic in routine and during concrete placement
in particular.
Ventilation ducts shall be installed for working in confined spaces like DE-watering tanks if required
As per OHS procedures all the workers shall wear proper full body harness while working at and above
1.5 meters height,
Workers designated for concrete placing bucket shall be provided water proof gloves, to avoid workers
exposure to concrete.
In case of workers working inside concrete must be provided gum shoes with steel toe.
All the workforce including engineers shall use mandatory Personal Protective Equipment during concrete
placement activity.
Suitable ear muffs must be provided to workers in noisy areas to protect workers from noise induced
hearing Loss injury (NIHL),
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
All the Un-protected/open rotating parts in general and conveyor belt in particular must be appropriately
guarded whereas the un protected edged must be barricaded properly to control fall hazard.
Lock out/ Tag out procedure to shall be developed when servicing equipment,
All the chutes in general and Transit Truck Mixers in particular must be secured to reduce injuries from
swinging parts,
Right person for the right job shall be followed,
During reinforcement/ steel erection proper rebar caps shall be used to avoid contact with sharp edges,
To avoid environmental contamination (Soil and water) the grout and waste concrete shall not be thrown
onsite.
As per spill contingency plane Geo membrane impermeable liners shall be provided to control spill
(chemical and oil).
The Geo membrane impermeable liners shall be fixed with appropriate bonding underneath power
generators, Compressor etc. onsite.
All the electrical equipment in general and specifically electrical DB and power generators shall
appropriately grounded to avoid electrocution.
Loose material above the work site shall be remove to control falling object hazard if prevails.
Housekeeping of the worksite shall be maintained on daily basis to keep the area clean/tidy
Capacity of the workers shall be built through daily toolbox meeting regarding worksite hazards and
suitable control measures,
Platform material in general and scaffolding components that includes (Pipes, joints, etc.) shall be as per
standard and shall be inspected before construction, after platform completion and after alteration to
ensure safety at all stages,
Personnel working in the area will wear mandatory personal protective Clothing/Equipment,
Dust and noise will be generated during drilling and grouting; so all the workers on site will wear masks &
ear plugs all the time and maintain a minimum distance of 1 m away from the equipment,
Powered equipment will not be left running unattended,
Barricades with warning devices and flashing lights as needs shall be installed alongside of site area
wherever people or vehicles are exposed and warning lights placed at night,
All the electrical appliances shall be certified (CE Marked) and shall be visually inspected by a competent
person prior to start work on daily basis,
Welfare facilities in general and an operational toilet must be ensured at site for workers facilitation,
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
EPC Contractor EHS department will implement all the agreed EHS plans during the execution of works
explained within the scope of work for Power House. The construction works for the Power House will be
undertaken with.
8.2.1Overall Responsibility
The Contractor accepts overall responsibility for all matters including those regarding health, safety and welfare.
The Contractor is responsible for promulgating Contractor’s OSH Policy and ensuring that i t is being
complied with at all levels in the organization.
Bringing to the attention of the Contractor and the Employer any health and safety issues that require
their attention.
Ensuring that all accidents and “near misses” are properly recorded and reported and that an
investigation is carried out to determine the root causes.
Maintaining safe access at the workplace at all times.
Be the Chairman of the Project’s Safety and Health Committee and ensure that all matters relating
to safety and health brought out in the meetings are carried out and enforced appropriately.
Discouraging horseplay and reprimanding those who consistently fail to consider their own well-
being and that of others around them.
Reporting defects in plant or equipment.
Setting good personal example.
8.2.7 Workers
Using the correct tools and equipment for the job; use safety equipment and protective clothing
supplied, e.g. roof ladders, safety helmets, safety harness, goggles etc., according to job
performed and the hazards identified.
Keeping tools in good working conditions.
Reporting to supervisor defects in plant or equipment.
Developing a personal concern for safety– for themselves and for others, particularly newcomers
and young people.
Avoiding improvising which entails unnecessary risk.
Advice and warning new workers of known hazards.
Refraining from horseplay and the abuse of welfare facilities.
Suggesting ways to eliminating hazards.
8.2.8 Safety and Health Officers
Advising site management on the following:
Prevention of injury to personnel and damage to plant and equipment.
Further improvement in existing sound working methods.
Legal requirements affecting safety, health and welfare of the workers.
Provision and use of protective clothing and equipment.
Potential hazards on new contract before work start and on the site safety organization.
Methods of safe working arising from new developments/activity.
Changes in legislation and safe codes of practices.
Other related health and safety issues occurred in the project.
Carrying out hazard identification and assessment, in association with the Construction
Manager, Supervisor to decide on the best safe methods of working are in operation; that
all regulations are being observed.
Determining the cause of any accident or dangerous occurrence and recommends means
of preventing recurrence.
Supervising the recording and analysis of information on injuries, damage and loss, analyze
accident trends and review overall safety performances.
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
8.3.2 Issues
Following are the environmental issues related to curtain grouting.
Use of water for curtain grouting.
Waste water generation.
Solid waste generation.
Soil contamination
Mr. Saboor Khan Sr. Health Safety Officer Cofferdam, Intake and Weir /In charge in absence of HSE
Manager
Mr. Muhammad Anees Health Safety Officer In charge for all site areas on EHS matters and Office
Mr. Usman Iftikhar Health Safety Officer In charge for All Sites
Mr. Rowaid Ullah Health Safety Officer In charge for Cofferdam and Intake Area
Mr. Qadeer Ali Health Safety Officer In charge for Inlet and Cofferdam (Night)
Mr. Salman Ahmed Health Safety Officer In charge for Cofferdam & Powerhouse (Night)
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
Mr. Rohail Asghar Health Safety Officer In charge for Stilling Basin and Cofferdam
Mr. Burooj Hateem Environmental Specialist In charge for all site areas on environmental matters and Office
Night Shift
Project Manager
Mr. Dong Ho Lee
EHS Advisor
Sahibzada Tanzeel/Mr. Saboor
Cofferdam/Weir
8.4.1.1 Purpose
The sole purpose of Job Hazard Analysis is to identify, control or eliminate potential or actual dangers in a
job or task.
Factors that will be considered in assigning a priority for analysis of jobs include:
Accident frequency and severity: jobs where accidents occur frequently or where they occur
infrequently but result in disabling injuries
Method statement of waterway tunnels concrete lining.
Owner’s Engineer
Doc. No DLJV-CONS-MS-WT-02 Rev 03
Newly established jobs: due to lack of experience in these jobs, hazards may not be evident or
anticipated.
Modified jobs: new hazards may be associated with changes in job procedures.
Infrequently performed jobs: workers may be at greater risk when undertaking non-routine
jobs, and a Job Hazard Analysis provides means of reviewing hazards
EPC management and supervision is responsible for ensuring all work is safely planned while the Contractor
in charge will ensure the implementation of safety protocols at project site; the Job Hazard Analysis will
assist in determining firstly, what are the steps in the job; secondly, what are the potential hazards in the job;
and finally, what are the protective measures for the safety of our worker(s) assigned to do the non-routine
work.
Supervisor overseeing the job breaks job into steps (with assistance from crew members, health & safety
rep etc.)
A job step will be defined as a segment of the operation necessary to advance the work
Keeping the steps in the correct sequence
Is lighting a problem?
The Emergency response and contingency plan criterion is fully in harmony with emergency plan agreed for
Gulpur Hydropower Project.
All emergencies will be dealt with ERP and CP.
8.6.3Medevac Plan
All medical emergencies will be dealt with medevac plan for GHPP.
If a serious injury or illness occurs, the following actions will be taken:
9. Attachments
Attachment # 9 ACI-347
3350
1A
..[:::>.
c.D
(J1
17
1~
15
14
13
o
L()
C0
C0
o
!
/ 2
L()
! / C0
/ / C0
!~
R~\ .
28 kill Ferozc pur Road Lahore.
Ncar TCF School Jhulky \illagc ~ht':l
Intc)'(1 Pdl.com.pk
I
I
1 P7
~
i
I
I
I
/
/
/
/: /
/
\ /
\
/
\
~/
/?< /
Y
\ I,
I,
I
~ 6700
~
-90- ------------
0
4 -r
-. ~I
(01
r ,1 , A r
",I
0:)1
TI' 10 l--r I 1
~I
III [I
I I i ",I I L 1lL-.JJL--1lL_lJ.---lJJ----.t
~I
Nil
i
I I N
N
1
I
I ~I
Ni ~,
i 1
~i
~I
'"
N
0 6'51
0:)1
1 i i
~II'I I~ I I~~I L
I I ---1. L ---1.
i I
w-
I
---"'-----"'---'-'"----wI
vii I
'11734
r,1734 l.-d:~ DETAIL - P5
~o..! e:=.L.~ Oty = 02 Nos ..J.i13.
~.j.~
DETAIL - P3 DETAIL - P4
DETAIL - P1 illY = 02 Nos. LlR Oty = 02 Nos. LlR
Oty = 01 No.
I,
I r
1:1
I
I ~!
N 1'-1
~
N
i L~i__U-~L-~__~
n1734
l....---~-aa.....!
~1734 ~.j.~
:"O------------b..-l
~1734
~.J.~ DETAIL
;....a:a---.------.-~~--.-&:!.....!
- - - - --P6
-
~.'.~ DETAIL - P7
DETAIL - P2
BEND CONCRETE LINING "",\\\,-\1',,,-
REINFORCEivlENT
- - -- --- -----
Sh ..,Cl Sl/~.
__~_-;-_4~~i~=~=---=-®;---------""
~ ~
/
'~'" /
" /
•• " "
1--C"T7-~---"- --------
LO
f'.. 75 ! 75 ._.~~.~~~ _~J1.~L.~~~.... _~~~ ..,' '75~J JI.~LJ~d-
...
J
5'5 ~~ tl h 3863 - -- .. . ~-: J 150
,.... 2026 -~. ..
5Q DET AI~~SH.::cg - - ..... ~.~
DETAIL - SH-01
C-Channel.- 200 x 75
C-Ch~nnel.= 300J<..1QQ.
~o rfoo "it
C') Hole 1018 (")
<0 <0
c01 ~,~~~-,~
L{)f
N NI
~,
=1.
i;5. 50
I g
- 7().Q~~~.. ~.
~!
58 100 175
-"'" ~100-'-
Hole 1018 250 -,-100~
~
.~ '~'~-~~'-~""""""""'l-~~I'
I ~ . ~,//t-~r~'
~r"~--~-~""-'-'~'~-"'r
"-'~-I'~I~~"-- 1 1
'--l'~'LOT~'
(")'
<0. <01 28..+.
Hole 1018
~I .
ID ID.,,!::"J. 11 L{)
I (")1-"
,I -j 281
10r
~ "~-~~~~'~5(;;;;\ ~ I, ~51 ~
158bill H~'E'8 ~~[;-m~",cl~ _-~]
DETAIL - SH-06 a 74 1
C-Chann.el = 1252<63
't-.--~~.. ~. ~~_. ..j
-J_'
450
ITEM MARK - @)
69 347 ,lg.i!l.LEI§te = 465x275x10mIJlII11<,. II~IYLMARK - @
J.2ir1t Plate = 333x200x10mm Thk. ITEM MARK - @)
(5)' 25 ,150 25 Joint Plate = 333x200x10mm Thk,
7
<0
N
(").
<Xl
~I
f'.. 0 ~ 10mm Thk,
r-I--~"1>" ~ L{) 0
Q g I 01 ~I' I
(")
I'-
N LO!_ _ ~ '<R 0
f'..
N ~t ~~
L{)
i
Hole 1018 Tjtlc, LOWER BEND CONCRETE LINING NTS
50)
REINFORCEMENT
_;200_.. 1.!L 150 ~ .-l!2.
ITEM MARK - @)
Joint Plate.403.x.264x10.rnrn.IIlL ITEM MARK..:: ® IIEM, MARK - @ 28 km Feroze pur Road Lahore, 00
Jointf'l§le =..200x200x10mm Thl<.,. lClirll, Plate = 275x200",19.rnm.Jhk .. Near TeF School Jhulky village Sheet
Info@PdLcom,pk I, OF 4
900
522
446 ~~~~~~~~_
i2.
!
l()
~
<p
(')
10mm Thk.
0J
m
0J
0J
Z§iZ§i ,75 75
r~i~-
L()
l()
-~~¢ ~qr ~9-qr~~
L()
~
I'-
10mm Thk.
All Hole 018mm
§;z;z_
ITEM MARK - @
J()i"LElilt" ~§45x(;22)(1Qrnm Thk
<p
31
165
1-
.~X\ /r,\)
~
100
ITEf\Ilt\!16BI\~ @
JOlntf'late~= 650x50Qx~f1lrn_Tf1k.
,0 l{)
f'- Hole 018 r-- Hole 018
= !
~:r
¢ <:>
0 0
0 1O ---- -
(0
ttl
1O
r~ 75
50
75 75
~:L+j '_~";'~~iIJ~J~
(0
<0:
d
N'
~,
(3. 50 -
1453
-----~--
.~_ _ 700
lI ~. T~-~
--~~-"--
DETAIL - SH-04
C~h~1 ~ 125 ,~? .. _ •• t92y~~ ~ C-Channel = 125 x 63 C-Chann.El!.=.2_2.!5..J<...§.3_
<:0
<0
A-I
"rJ ~I ~
lOr
~
d
N
~!
NI
,=L l{) /$+- 0 0
5iL~--r~T~-j ~i
,I
C'0;
CD:
>Omm '"".
glL----- ~~----:~~!~Ftgt,-
IJ g~~_~8 -t --'1---'
1 N ~~
10mm Thk. __ -.- ----'"
LO ~,
_t
DETAIL - SH-06
C-Channel=12~ x_63 ~~ :::J~ .2.Z:~ 193_
333
50 51 r
H~le 018
IJEJ\·11Y1_AR~ @)
69 347 .1c>int Plate_=_42~x275x10mm Thk, ITEM fv!t\~I3.t<-----= @
Joint PI.'l1e_=_:l.:3})(_2_00x 1Omm Thk. IT~f\.ILMAR~ @)
m; 25 150 25 ,Lqir:lLf'!a.!S'_=_3_:l.:l.x.?Q.Ox1,Qnlm Thk.
0 -~I------ 1-'-~~ 200
I~l- - 1- __ _ ___ r~----l
'"
<D <:0, ~I tomm
A-, Thk. Oil
0 I ,g,
~ 10mm Thk. H_ole 018
01~ 0---
N' ro
<:0
r--
l{)
I
~l
-
~-o/
~ --<k,
1
~
- ~I
;:,
~ ~
l{)
L=_
--
¥~
$-----
~
<!)
i-
~~.£OO ___ ~ lQ- -~1QQJ _2~
ITEM MARK -@
JointPlate 403x~1x10mrn_Tllb ITEIYLf\i1ARK .__ ® ITEM_ry1613K - @)
JCJinlPlate =_2.QQx.?QOx10mm I_hl<,_ Joint PJ§!..e-"P5x200x10 rnrn_Jilis
Attachment #2
Vertical pressure tunnel lining form
<'I·'
"r
'"
.,
'"
co'
"'«, PlotForm
S~(~Jji:U1==~A' -
:;lg c Ii 0 !1-=J3~~:JL
See . J)~L1.liL==~I3~
Plan _YL(Uy
Attachment #3
Horizontal pressure tunnel lining form
,
//;
I
I
I
__
I
I.
\ -1 -I I
i : i i IJ
,
!, ,
:, : I
I I I
i I
I I I I I
I I
I I I I I I 1
I ! ,
I
I I
I I
I
I I
I
-, i, i i i i I 1 i\
I I
i I I
I I
I
I I I I I I ! I !
I I
I I
-:S~' -I
i i i i i I
, I I
i I I
I I I I ; I I :, I
I I I
I I ! I !
I
! I !
I
II
I i 1
I i
I I I I I I
I I
I
I I I
OA
I I " -,/
I -i-- /1"; 1------TT- -- ---1- j't - ---j --r-, -!------- 1--------
I
I I I
~ I
I I
I
i i I i i I
I I ,I 1
I
I
I
'~ ,I I
I
~ I
I I
1
I, I
I
i -I
I -,,~.- I i I I
I' I
II I
, ,
J I i i I i i i
I , ,
I
I
I I
I
, 1--
J ! I I
! !
I I
I, I !
I
I
I
I I
"
I i i i i 1 i 1
J i i i, i
I ; I I
I
-:).~.: I I
l :-----1
1 I i i I
! I I I i
Attachment #4
Inlet transition part lining form
INLET TRANSITION PART FORM WORK DETAIL
Eurofonn
~---
I
......... I
I
I
I
a
I • III D II II .. II I
I
I
a a a .1 ..
I
I
I
.1. · · .. hI I~ """""- I
llY ______ _
II iii III II
• D D DiD D •• D
( SECTION A )
I a Eurofonn
r----------
D D
~~,~ ~~
,";~",,-l"/~~r ~ 10:~
""" •• • • :. • ....... 1 .........
......... • • • :. • • • • • • I
R_~cl I~
I
: :I I
....... I: Steel Jib/
i 1'1 Me,h plaHom;
I
I
I
I
(·PROFILE )
I
L~ .- ~.Ib
( SECTION C )
Attachment #5
Progress schedule
(Waterway micro plan)
Water Way
IPS Rev 19( 4 week look ahead)
Activity ID Activity Name Original aining ysical Start Finish Total Qty. Unit Resource IDs 2017 2018
Duration % c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
ti
464d 271d l t 11-Oct-16 A 17-Jan-18 4966.00
Water Way
Tunnel 2 398d 205d 11-Oct-16 A 12-Nov-17 2394.00
Horizontal 357d 87d 11-Oct-16 A 02-Oct-17 1900.00
A1000 Excavation Horizontal + Lower Bend 141d 0d 100% 11-Oct-16 A 28-Feb-17 A 122.00 Mtr
A1100 Bottom Cleaning 5d 0d 100% 28-Feb-17 A 04-Mar-17 A Mtr
A1110 Invert Leveling Conc. 20d 0d 100% 02-Mar-17 A 21-Mar-17 A Mtr
A1120 Drilling for Grouting & Drain Holes 30d 0d 100% 24-Mar-17 A 03-Apr-17 A 1778.00 Mtr
A1125 Dewatering And cleaning 28d 0d 100% 08-Apr-17 A 05-May-17 A
A1130 Removal of Temperory Facilities 4d 4d 0% 08-Jul-17* 11-Jul-17 EA
A1220 Rebar Fixing 30d 30d 0% 12-Jul-17 10-Aug-17
A1230 Assembly Of Lining Form & Hydraulic Jack Test 10d 10d 0% 12-Jul-17 21-Jul-17
A1250 Setting Of Lining Form 8d 8d 0% 22-Jul-17 29-Jul-17
A1260 Lining 1st Segment - 10 Mtr 4d 4d 0% 30-Jul-17 02-Aug-17
A1270 Lining 2nd Segment 4d 4d 0% 03-Aug-17 06-Aug-17
A1280 Lining 3rd Segment 4d 4d 0% 07-Aug-17 10-Aug-17
A1290 Lining 4th Segment 4d 4d 0% 11-Aug-17 14-Aug-17
A1300 Lining 5th Segment 4d 4d 0% 15-Aug-17 18-Aug-17
Steel Penstock 45d 45d 19-Aug-17 02-Oct-17 0.00
A1310 Erection of 1st Shell 6 Mtr and Conc Pouring 5d 5d 0% 19-Aug-17 23-Aug-17
A1320 Erection of 2nd Shell 6 Mtr and Conc Pouring 5d 5d 0% 24-Aug-17 28-Aug-17
A1330 Erection of 3rd Shell 6 Mtr and Conc Pouring 5d 5d 0% 29-Aug-17 02-Sep-17
A1340 Erection of 4th Shell 6 Mtr and Conc Pouring 5d 5d 0% 03-Sep-17 07-Sep-17
A1350 Erection of 5th Shell 6 Mtr and Conc Pouring 5d 5d 0% 08-Sep-17 12-Sep-17
A1360 Erection of 6th Shell 6 Mtr and Conc Pouring 5d 5d 0% 13-Sep-17 17-Sep-17
A1370 Erection of 7th Shell 6 Mtr and Conc Pouring 5d 5d 0% 18-Sep-17 22-Sep-17
A1380 Erection of 8th Shell 6 Mtr and Conc Pouring 5d 5d 0% 23-Sep-17 27-Sep-17
A1390 Erection of 9th Shell 6 Mtr and Conc Pouring 5d 5d 0% 28-Sep-17 02-Oct-17
Lower Bend 46d 46d 23-May-17 07-Jul-17 0.00
A1070 First Stage Conc. 10d 10d 0% 23-May-17 01-Jun-17
A1080 Rebar Fixing 5d 5d 0% 02-Jun-17 06-Jun-17
A1090 Setting Of Lining Form 15d 15d 0% 07-Jun-17 21-Jun-17
A1140 Lining Conc. 6d 6d 0% 22-Jun-17 27-Jun-17
A1210 Removal of Form Work 10d 10d 0% 28-Jun-17 07-Jul-17
Vertical 368d 205d 10-Nov-16 A 12-Nov-17 494.00
A1010 Excavation Vertical Shaft + Transition Part 170d 31d 90% 10-Nov-16 A 22-May-17 50.00
A1040 Preperation Of Lifting Structure 6d 6d 0% 23-May-17 28-May-17 444.00
A1050 Drilling for Grouting & Drain Hole 8d 8d 0% 08-Jul-17 15-Jul-17
A1060 Rebar Fixing 6d 6d 0% 16-Jul-17 21-Jul-17
A1400 Setting of Lining Form 10d 10d 0% 22-Jul-17 31-Jul-17
A1410 Lining Conc. 1st lift -1.8 Mtr 4d 4d 0% 01-Aug-17 04-Aug-17
A1420 Lining Conc. 2nd lift 4d 4d 0% 05-Aug-17 08-Aug-17
A1430 Lining Conc. 3rd lift 4d 4d 0% 09-Aug-17 12-Aug-17
A1440 Lining Conc. 4th lift 4d 4d 0% 13-Aug-17 16-Aug-17
A1450 Lining Conc. 5th lift 4d 4d 0% 17-Aug-17 20-Aug-17
A1460 Lining Conc. 6th lift 4d 4d 0% 21-Aug-17 24-Aug-17
A1470 Lining Conc. 7th lift 4d 4d 0% 25-Aug-17 28-Aug-17
A1480 Lining Conc. 8th lift 4d 4d 0% 29-Aug-17 01-Sep-17
A1490 Lining Conc. 9th lift 4d 4d 0% 02-Sep-17 05-Sep-17
A1500 Lining Conc. 10th lift 4d 4d 0% 06-Sep-17 09-Sep-17
A1510 Lining Conc. 11tht lift 4d 4d 0% 10-Sep-17 13-Sep-17
A1520 Lining Conc. 12th lift 4d 4d 0% 14-Sep-17 17-Sep-17
A1530 Lining Conc. 13th lift 4d 4d 0% 18-Sep-17 21-Sep-17
A1540 Lining Conc. 14th lift 4d 4d 0% 22-Sep-17 25-Sep-17
Transition Part 48d 48d 26-Sep-17 12-Nov-17 0.00
A1550 Preparation of Working Plate Form 8d 8d 0% 26-Sep-17 03-Oct-17
A1560 Rebar Fixing 10d 10d 0% 04-Oct-17 13-Oct-17
A1570 Installation of Lining Form- 1st 6d 6d 0% 14-Oct-17 19-Oct-17
A1580 Lining Conc. 1st lift - 3.5 Mtr 4d 4d 0% 20-Oct-17 23-Oct-17
A1590 Installation of Lining Form-2nd 6d 6d 0% 24-Oct-17 29-Oct-17
A1600 Lining Conc. 2st lift - 3.5 Mtr 4d 4d 0% 30-Oct-17 02-Nov-17
A1610 Installation of Lining Form-3rd 6d 6d 0% 03-Nov-17 08-Nov-17
A1620 Lining Conc. 3rd lift - 3.5 Mtr 4d 4d 0% 09-Nov-17 12-Nov-17
Tunnel 1 464d 271d 11-Oct-16 A 17-Jan-18 2572.00
Horizontal 395d 171d 11-Oct-16 A 09-Nov-17 2128.00
A1630 Excavation Horizontal + Lower Bend 141d 0d 100% 11-Oct-16 A 28-Feb-17 A 122.00 Mtr
A1690 Bottom Cleaning 4d 0d 100% 04-Mar-17 A 21-Mar-17 A Mtr
A1700 Invert Leveling Conc. 20d 0d 100% 04-Mar-17 A 23-Mar-17 A Mtr
A1710 Drilling for Grouting & Drain Holes 31d 0d 100% 25-Mar-17 A 02-Apr-17 A 2006.00 Mtr
A1715 Dewatring And Cleaning 43d 1d 100% 08-Apr-17 A 23-May-17*
Actual Level of Effort Remaining Work M. Blue Shaded Portion Showing Monsoon Period Prepared : Zill-e-Huma / T.M.Khan Data Date: 22-Apr-17
Actual Work Critical Remaining Work %. Red Shaded Portion Showing Ramadan Period Checked : J.W.Song / S.H.Han Print Date: 22-Apr-17
Normal Day Working - 7 Day/Week Approved : Bruce Lee / E.M.Moon Page 1 of 2
Water Way
IPS Rev 19( 4 week look ahead)
Activity ID Activity Name Original aining ysical Start Finish Total Qty. Unit Resource IDs 2017 2018
Duration % c Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
A1720 Removal of Temperory Facilities 5d ti5d l0% t 24-May-17 28-May-17 EA
A1820 Rebar Fixing 20d 20d 0% 24-May-17 12-Jun-17
A1830 Shifting Of Lining Form 10d 10d 0% 19-Aug-17 28-Aug-17
A1840 Setting Of Lining Form 8d 8d 0% 29-Aug-17 05-Sep-17
A1850 Lining 1st Segment - 10 Mtr 4d 4d 0% 06-Sep-17 09-Sep-17
A1860 Lining 2nd Segment 4d 4d 0% 10-Sep-17 13-Sep-17
A1870 Lining 3rd Segment 4d 4d 0% 14-Sep-17 17-Sep-17
A1880 Lining 4th Segment 4d 4d 0% 18-Sep-17 21-Sep-17
A1890 Lining 5th Segment 4d 4d 0% 22-Sep-17 25-Sep-17
Steel Penstock 45d 45d 26-Sep-17 09-Nov-17 0.00
A1900 Erection of 1st Shell 6 Mtr and Conc Pouring 5d 5d 0% 26-Sep-17 30-Sep-17
A1910 Erection of 2nd Shell 6 Mtr and Conc Pouring 5d 5d 0% 01-Oct-17 05-Oct-17
A1920 Erection of 3rd Shell 6 Mtr and Conc Pouring 5d 5d 0% 06-Oct-17 10-Oct-17
A1930 Erection of 4th Shell 6 Mtr and Conc Pouring 5d 5d 0% 11-Oct-17 15-Oct-17
A1940 Erection of 5th Shell 6 Mtr and Conc Pouring 5d 5d 0% 16-Oct-17 20-Oct-17
A1950 Erection of 6th Shell 6 Mtr and Conc Pouring 5d 5d 0% 21-Oct-17 25-Oct-17
A1960 Erection of 7th Shell 6 Mtr and Conc Pouring 5d 5d 0% 26-Oct-17 30-Oct-17
A1970 Erection of 8th Shell 6 Mtr and Conc Pouring 5d 5d 0% 31-Oct-17 04-Nov-17
A1980 Erection of 9th Shell 6 Mtr and Conc Pouring 5d 5d 0% 05-Nov-17 09-Nov-17
Lower Bend 77d 77d 23-May-17 07-Aug-17 0.00
A1660 First Stage Conc. 10d 10d 0% 23-May-17 01-Jun-17
A1670 Rebar Fixing 5d 5d 0% 02-Jun-17 06-Jun-17
A1680 Setting Of Lining Form 15d 15d 0% 08-Jul-17 22-Jul-17
A1740 Lining Conc. 6d 6d 0% 23-Jul-17 28-Jul-17
A1810 Removal of Form Work 10d 10d 0% 29-Jul-17 07-Aug-17
Vertical 434d 271d 10-Nov-16 A 17-Jan-18 444.00
A1640 Excavation Vertical Shaft + Transition Part 141d 31d 80% 10-Nov-16 A 22-May-17 444.00
A1650 Preperation Of Lifting Structure 6d 6d 0% 23-May-17 28-May-17
A1730 Drilling for Grouting & Drain Hole 8d 8d 0% 29-May-17 05-Jun-17
A1990 Rebar Fixing 6d 6d 0% 06-Jun-17 11-Jun-17
A2000 Setting of Lining Form 10d 10d 0% 26-Sep-17 05-Oct-17
A2010 Lining Conc. 1st lift -1.8 Mtr 4d 4d 0% 06-Oct-17 09-Oct-17
A2020 Lining Conc. 2nd lift 4d 4d 0% 10-Oct-17 13-Oct-17
A2030 Lining Conc. 3rd lift 4d 4d 0% 14-Oct-17 17-Oct-17
A2040 Lining Conc. 4th lift 4d 4d 0% 18-Oct-17 21-Oct-17
A2050 Lining Conc. 5th lift 4d 4d 0% 22-Oct-17 25-Oct-17
A2060 Lining Conc. 6th lift 4d 4d 0% 26-Oct-17 29-Oct-17
A2070 Lining Conc. 7th lift 4d 4d 0% 30-Oct-17 02-Nov-17
A2080 Lining Conc. 8th lift 4d 4d 0% 03-Nov-17 06-Nov-17
A2090 Lining Conc. 9th lift 4d 4d 0% 07-Nov-17 10-Nov-17
A2100 Lining Conc. 10th lift 4d 4d 0% 11-Nov-17 14-Nov-17
A2110 Lining Conc. 11tht lift 4d 4d 0% 15-Nov-17 18-Nov-17
A2120 Lining Conc. 12th lift 4d 4d 0% 19-Nov-17 22-Nov-17
A2130 Lining Conc. 13th lift 4d 4d 0% 23-Nov-17 26-Nov-17
A2140 Lining Conc. 14th lift 4d 4d 0% 27-Nov-17 30-Nov-17
Transition Part 48d 48d 01-Dec-17 17-Jan-18 0.00
A2150 Preparation of Working Plate Form 10d 10d 0% 01-Dec-17 10-Dec-17
A2160 Rebar Fixing 8d 8d 0% 11-Dec-17 18-Dec-17
A2170 Installation of Lining Form- 1st 6d 6d 0% 19-Dec-17 24-Dec-17
A2180 Lining Conc. 1st lift - 3.5 Mtr 4d 4d 0% 25-Dec-17 28-Dec-17
A2190 Installation of Lining Form-2nd 6d 6d 0% 29-Dec-17 03-Jan-18
A2200 Lining Conc. 2st lift - 3.5 Mtr 4d 4d 0% 04-Jan-18 07-Jan-18
A2210 Installation of Lining Form-3rd 6d 6d 0% 08-Jan-18 13-Jan-18
A2220 Lining Conc. 3rd lift - 3.5 Mtr 4d 4d 0% 14-Jan-18 17-Jan-18
Actual Level of Effort Remaining Work M. Blue Shaded Portion Showing Monsoon Period Prepared : Zill-e-Huma / T.M.Khan Data Date: 22-Apr-17
Actual Work Critical Remaining Work %. Red Shaded Portion Showing Ramadan Period Checked : J.W.Song / S.H.Han Print Date: 22-Apr-17
Normal Day Working - 7 Day/Week Approved : Bruce Lee / E.M.Moon Page 2 of 2
Attachment #6
Waterway tunnels lining concrete sequence
Waterway Tunnel Concrete Pou
Tunnel # 1
1l
~~I ~t--
rf~_
20
(2~
l 0 ---
I- ~
c:0
...J
W
2
2
~
W
0::
::>
cno
cntn
W·
0::"'<1"
a.. N
~
~ ~~~~
l~==~
W
>
00
10.00 10.00 10.00 10.00 10.65 6.00 I 6.00 I 6.00 I 6.00 6.00 I 6.00 I 6.00 I 6.00 I 7.00
1ST POUR 2ND POUR 3RD POUR 4TH POUR 5TH POUR I SHELL
1ST 2ND
SHELL
3RD
SHELL
4TH 15TH
SHELL SHELL
6TH
SHELL
7TH
SHELL
8TH
SHELL
9TH
SHELL
EL:465.800
t
WLD
~F
I
. . ".".,.".
--
~~
I- 0---- I
L()
c..-:i
....I
W
Z
Z
~
W
0::
::>
wo
WLD
W'
0::"'"
aN
<3
....I
I ---
~
~
~[---.
..... \ ---
I g}-~==
~--- 10.00 10.00 10.00 10.00 10.65 6.00 , 6.00" 6.00 , 6.00 , 6.00 , 6.00 , 6.00 ,6.00 7.00_
1ST POUR 2ND POUR 3RD POUR 4TH POUR 5TH POUR I 1ST 2ND 3RD 4TH 5TH 6TH 7TH 8TH 19TH 1
SHELL SHELL SHELL SHELL SHELL SHELL SHELL SHELL SHELL
EL:465.800
(pLANU)
( SECTION A-A-)
Attachm nt #8
Inspection and test plan
IftA 102MW Pakistan Gulpur Hydro Power Project
Inspection and Test Plan
EPCC: Daelim-Lotte )V Owner's Engineer (OE): MWH-Nespak )V-l Structure: Waterway Tunnels Concrete Doc. !ITP-13/WT
No.
Inspection codes:
Ref. Doc./Dwg. No. Method statement
R =Review of documents W =Witness Point H =Hold Point
Inspections
Frequency
Sr.No. Activity Description Acceptance Criteria Verifying Documents
(if applicable) EPCC EPCC
OE
Con"t: OAfOC
1 Drawings
---~-- 1-- - -- ------------- ----- -- --- - --- ----- 1--- ~----------- - - - ----- -------
1.1 Check approved drawings for latest revision, if any. Document control log book Document transmittal Each R R R
-- ------- --"--- ~--.,,------- -------------------- ---"---- .-..-. --._- i- 1------
2 Control of Inspection, Measuring & Test equipment
-- ---------- ~- ---- -
2.1 All the laboratory equipment, related to job Manufacturer's Specifications Calibration report Applicable Standard R H R
------ --------- - - - - - -- -- --- --------~ ---"-------
2.2 Survey equipment Manufacturer's Specifications Calibration report Applicable Standard H II R
-~-- ------ -----------~--"---.-
------ ---- - - - - - _..---- --- ----- - -- - --- -_.. -- - -------
3 Construction Materials
-~- - -------- --- -- - ------ - ---
Material Source Approval Form
i. Source Approval Profile, Test reports, Certificates Each Source H H R
- - - . - - - - - I--~- ------~-- ----- ------
___ ____(QJ1QC -001 L_______ ____ - - --------- -- -------- -- --
Project Specifications / Material Inspection Report (MIR)
3.1 Cement Each Delivery II H R
- - - - - - - - i~- -------------------------- ---- ___ ASTM-.:C15~_ ---- --- -------
Lab: test reports ~----~.~~- "----~~-- ----~---
-- -----------
Material Inspection Report (MIR)
3.2 Aggregates Project Specifications / Standard Each Delivery H H R
-_._.__...
Lab: test reports
---- ---~-'"--- - -_._----. -~---- ----.-"--~--- -------- -------
Project Specifications/
3.3.1 Sampling of reba I' Lab register Each Delivery R II R
- _ . _ - - _.._- _.---------" ---- -------_._- ---- ----_._---
ASTM-A615 . ".~.--.--
._-_._-- -- ------ --- -----------
3.3.2 Testing of rebar ASTM-A615 Third party test report Each Delivery R H R
---"".-~---------
---- - - - - - - --"---- ----
Embedded items (Drain pipe, PVC Waterstop, Material Inspection Report (MIR)
3.4 Project Specifications / Standard Each Delivery H H R
instrumentation and sensor if applicable) ..- ---
Lab: teEJ~~p_o_r!s~ ______ ---
---- ---~
---~ ----~- ---~
3.4.1 Sampling of embedded items Project Specifications Lab register Each Delivery R H R
3.4.2 Testing of embedded items Project Specifications Third party test report Each Delivery R H R
Manufacturer's Specifications Material Inspection Report (MIR) H
3.5 Chemical additives Each Delivery H R
ASTM-C494 Manufacturer's test certificates
3.6 Water to be used for concrete production ASTM-C1602, ASTM-C1603 Test reports Every 3 months H H R
-- --------- '-~-- -- - - ---_.--- _L_ _._- -------- ... _-_.- ---, -- -------- - ---~ ,---
Page 1 of 3
...... ,.:;. 102MW Pakistan Gulpur Hydro Power Project
Inspection and Test Plan
EPCC: Oaelim-Lotte jV Owner's Engineer (OE): MWH-NespakjV-l Structure: Waterway Tunnels Concrete Doc.
No.
I ITP-13 /WT
Inspection codes:
Ref. Doc./Dwg. No. Method statement
=
R Review of documents W =Witness Point H =Hold Point
Inspections
Frequency
Sr. No. Activity Description Acceptance Cl"iteria Verifying Documents
(if applicable) EPCC EPCC
OE
(onst: OAfOC
4 Batch equipment's
-~~-~-
1-- ,.----.~
-- -~--- - ---- .----- ----~ - -- - - -----~-- - --- -- --- --~.--~--- .. ~.-~ ------ --- ---- -----
7.4 Sampling
---~---- 1--- ---_.- - -------- ------------ ----"_._._. ._-- ------~ -------- -------
Both site
Approved Shotcrete Mix Design Concrete placement report
7.4.1 Slump test Batching plant and W H R
ASTM-C143 Form: QA/QC-033
placement site
Page 2 of 3
102MW Paldstan Gulpur Hydro Power Project
Inspection and Test Plan
Doc.
EPce: Daelim-Lotte jV Owner's Engineer (OE): MWH-Nespak jV-l Structure: Waterway Tunnels Concrete ITP-13jWT
No.
Inspection codes:
Ref. Doc.jDwg. No. Method statement
R = Review of documents W =Witness Point H = Hold Point
Inspections
F"equency
Sr.No. Activity Description Acceptance Criteria Verifying Documents
(if applicable) EPCC EPCC
OE
Compressive strength test sheet
7.4.3 Testing of concrete cylinder ASTM-C39 / AASHTO-T22 At required ages R H R
Form: QAQC-015 ~-~~- ... -~~-.---.~. ~~-~------ ------
--~--.--
8 After Concreting
~. - - - - - - _... - -------- ~---.----.~~ --- ---- -------------~~ ..- --- ----------
8.1 Final cross section Construction Drawing Construction Drawing I-I H R
--------~~
--- ---------~--.~-.--.-
NOTES:
R = Review of documents (Properly compiled accompanied with all the data sheets and test results, whichever applicable)
W = Witness point (Should be informed but presence is not mandatory)
H = Hold oint Activit will not commence an further unless ins ected b the en ineer or as he advises otherwise
Page 3 of 3
Attachment #9
(ACI 347-01)
I'
AC1347-01
Objectil1es ofsafety. quality, and economy are given priority in these guide- CONTENTS
Iinesforform1\·ork. A section on contract documents e.'plains the kind and Preface, p. 347-2
amoulll of specification guidance the engineer/architect should providefor
the contractOl: The remainder of the report advises the fonl1lmrk engineer/
Chapter 1-lntroduction, p. 347·2
colllraclOr on the best lrays to meet the specification requiremellls safe/l"
1.I-Scope
and economicall),. Separate chapters deal I";th design. constructiol1. and
materialsforfonl1lmrk. COl1Sideratiol1S peculiar to architectural concrete 1.2-Definitions
are also ollliined in a separate chapte/O Other sections are devoted to form- I .3-Achieving economy in formwork
II'0rk for bridges, shells, mass concrete, and underground 1\·ork. The con- lA-Contract documents
cluding chapter onfoJ'/l/lmrkfor special methods of construction includes
slip/arming. prep/aced aggregate concrete, Iremie concrete, precast, and
prestressed concrete.
Chapter 2-Design, p. 347·5
2 , I-General
2,2-Loads
Keywords: anchors; architectural concrete; coatings; concrete; construc-
tion: fa lsework : forms; formwork; fornl ties; foundations; quality control: 2.3-Unit stresses
reshoring: shoring: slipform construction; specifications; tolerances. 2.4-Safety factors for accessories
2.S-Shores
2,6- Bracing and lacing
ACI Committee Reports, Guides, Standard Practices, 2.7-Foundations for formwork
and Commentaries are intended for guidance in planning, 2.8-Settlement
designing, executing, and inspecting construction. This
document is intended for the use of individuals who are
Chapter 3-Construction, p. 347·9
competent to evaluate the significance and limitations of 3 . I-Safety precautions
its content and recommendations and who will accept re- 3 .2-Constl1lction practices and workmanship
sponsibility for the application of the material it contains. 3.3-Tolerances
The American Concrete Institute disclaims any and all re- 3 A-Irregularities in formed surfaces
sponsibility for the stated principles. The Institute shall 3.S-Shoring and centering
not be liable for any loss or damage arising therefrom. 3.6-Inspection and adjustment of formwork
Reference to this document shall not be made in con-
tract documents. If items found in this document are de- AC I 3-l7·0 1 supersedes AC I 3-l-7R·9.t lRcappro\cd 1999) and beC3ll1e cfTc:cII\l'
D\.'ccmber 11.200 I
sired by the Arch itect Engineer to be a part of the contract COP) n ght ' ~ ~OO I. :\mcncan Co ncn:tc In"tllutc
All nght" rc ~en t:d II1cludlllg right-. of rL'productll1ll and U"C 1I1 an) form or b) elll)
documents, they shall be restated in mandatory language IllC,Ub, lllc\ udlllg the lllah1Jlg of copn: .. b) .111) photo proct:'''''''' or b) l'k·ctrOllH.: or
IllCrllilJllCal dc\ ICC. pnntecl. \\ nttcil. or omL 01 IL'cordln g 1\..11 s,o und or \ l"ual repn1duc-
for incorporation by the Archi tec t Engineer. 11 0 1\ lW fO I 11 ,,(..' III a ll ) kIl0\\ ledge 01 n:tnl:\ al ~: " It.:!ll (Ir dc\ Ice . 11Il1e ... :- PCJ"l111, ... ltlll III
\\ riling h l)bl.WlL'd fn~111 the CLIP) right pll1pnetor...
347-1
"
structures entirely different than for their aboveground coun- Concrete placement method and, for tunnel arch forms,
terparts. First, concrete to fill otherwise inaccessible areas whether the design is based on the unit or bulkhead sys-
can be placed pneumatically or by positive displacement tem of concrete placement or the continuously advanc-
pump and pipeline . Second, rock sometimes is used as a ing slope method; and
form backing, permitting the use of rock anchors and tie rods The capacity and working pressure of the pump and the
in lieu of ex tema I bracing and shores . Third, the limits of the size, length, and maximum embedment of the discharge
excavation demand special handling equipment that adds line when placement by pumping is anticipated.
particular emphasis to the removal and reuse of forms.
6.6.4 Constl'uctiol1- The two basic methods of placing a
Fourth, rock surfaces can sometimes be used for attaching tunnel arch entail problems in the construction of the fom1-
hoisting devices.
work that require special provisions to permit proper reuse.
When placement is done by pneumatic or positive dis- These two basic methods are commonly known as the bulk-
placement pump and pipeline methods, the plastic concrete head method and the continuously advancing slope method.
is forced under pressure into a void, such as the crown of a
The former is used exclusively where poor ground condi-
tunnel lining. For more infom1ation on the pumping process,
tions exist, requiring the lining to be placed concurrently
see ACI 304.2R.
with tunnel driving operations. It is also used when some fac-
6.6.2 Design loads
tor, such as the size of the tunnel , the introduction of rein-
6.6.2.1 Vertical loads-Vertical and constlUction
forcing steel, or the location of constlUction joints, precludes
loads assumed in design of formwork for underground
the advancing slope method. The advancing slope method, a
stlUctures are similar to those for surface stlUctures, with
continuous method of placement, usually is preferred for
the exception of unusual vertical loads occurring near the
tunnels driven through competent rock, ranging between 10
crown of arch or tunnel forms and flotation or buoyancy
and 25 ft (3 and 8 m) in diameter and at least I mi (1.6 km)
effect beneath tunnel forms.
in length.
In placing concrete in the crowns of tunnel forms, pres-
sures up to 3000 Ib/ft 2 (144 kN /m2) have been induced in ar- The arch fom1 for the bulk11ead method is usually fabricated
eas of overbreak and near vertical bulkheads from concrete into a single unit between 50 and ISO ft (15 and 45 m) long,
placed pneumatically or by positive displacement pump. Un- which is stripped, moved ahead, and reerected using screw
til more defin ite recommendations can be made, the magni- jacks or hydraulic rams. These are pem1anently attached to
tude and distribution of pressure should be determined by the the form and supporting traveling gantry. The arch form for
formwork engineer. In no case should the assumed pressure the continuously advancing slope method usually consists of
be less than 1500 Ib/ft2 (72 kN /m2) acting normally to the eight or more sections that range between IS and 30 ft (5 and
form plus the dead weight of the concrete placed pneumati- 9 m) in length. These are successively stripped or collapsed,
cally or by pump. telescoped through the other sections, and reerected using a
fom1 traveler.
6.6.2.2 Lateral loads-For shafts and exterior walls
against rock, the values listed in Sect IOn 2.2 .2 should apply. Although the minimum stripping time for tunnel arch
When the shaft f0I111 relie,sQl1 the single shear value of em- forms usually is established on the basis of experience, it can
bedded anchors in the previous placement as a means of sup- be safely predetem1ined by tests. At the start of a tunnel arch
port, the minimum time lapse between successive concreting operation, the recommended minimum stripping
placements (or minimum concrete strength) and maximum time is 12 h for exposed surfaces and 8 h for construction
allowable loading additional to the dead weight of the fom1 joints. If the specifications provide for a reduced minimum
should be specified. stripping time based on site experience, such reductions
For arch forms and portions of tunnel f0I111s above the should be in time increments of 30 min or less and should
maximum horizontal dimension or spring line of the form, be established by laboratory tests and visual inspection
the pressure should be compatible with the pressures dis- and surface scratching of sample areas exposed by opening
cussed under vertical loads in Section 6.6.2 .1. the fom1 access covers. Arch forms should not be stripped
6.6.3 Drall'ings~In addition to the provisions of Chapters prematurely when unve nted groundwater seepage could
1,2, and 3, the following data should be included on the draw- become trapped between the rock surface and the concrete
ings for specialized f0I111work and formwork for tunnels: lining .
All pressure diagrams used in the design of the form, 6.6.5 A1atel'ials- The choice of materials for underground
including diagrams for uplift, for unbalanced lateral or formwork usually is predicated on the shape, degree of reuse
vertical loads, for pressurized concrete, or for any other and mobility of the f0I111 , and the magnitude of pump or
load app licable to the particular insta llation; pneumatic pressures to which it is subj ected. Usually, tunnel
Recommended method of supplementa l stlUlling or and shaft forms are made of steel or a composite of wood and
bracing to be employed in areas where form pressures stee l. Experience is important in the design and fabr ication
can exceed those just listed due to abnormal conditions; ofa satisfactory tunnel f0I111, due to the nature of the pressures
Handling diagrams and procedures showing the pro- developed by the concrete. placing techniques, and the high
posed method of handling the form during erection or degree of mobility usually required.
installation for concrete placement plus the method of When reuse is not a factor. pl)'\\'ood and tongue-and-groove
bracing and anch orage during norm al operation; lumber are sometim es used for ex po sed surface fini shes .
347-14 ACt STANDARD
• 0 ,
..
'----=
"
..,
u<
;Um
"
m;u
(J)..,
~O
o ..,~~
'"'"eO ,0 3,350 C
Z
z
,
m
~ LINING CON'C
------- WATERSTOP
W=300mm
OJ,
WATERSTOP mO
fck=28MPa z~
W=300mm om
;JJ
C SECTION B-B )
o ( VERTICAL PRESSURE TUNNEL) o
'"'"<D \
LINING CON'C 'l: HEADRACE TUNNEL
I
\ LOWER
BEND
LINING CON'C
'l: HEAD RACE TUNNEL
I I
. JI ~ .
I
3n
I
z, ,
..,m "
..-.. ~
u< o
WATERSTOP ;um 0 0
o
m;u
(J).., 0 0 o 0
W=300mm r-- r-- c5
~o ro ro '"'"
;uf::
..,c
m "
o
a
o.
eO
0
o
'"
'"
eO
z ©
o -- 0
v.
z
c ,m
V
WA ERSTOP
W=300mm
a
'"'" ~
t
eO
~
POFILE
-g
_kdl_--=3~,3:::5::..0_ _ _ _::.:3,3:=;5:::0_ _k d _ 1ST STAGE CONCRETE
fck=21Mpa
t
C SECTION A-A ) __
C~ LO_W
__ER__
B_EN_D_P_R_O_F_IL_E__) C,-_S_EC_T_IO_N_C_-_C---,)
PLASTIC FIBER
REINFORCED SHOTCRETE
T=160, fck=21 Mpa SCALE = NONE
l
~
<J D
D 0 0 D 0
D o 0
01
NOTES
L-
/' 1st
CONCRETE ~
LINING /'
L 2nd
CONCRETE
LINING
7
11-~I ~~ 1. WATERSTOP SHOULD BE INSTALLED FOR PREVENTING LEAKAGE
FROM CONSTRUCTION JOINT OF WATERWAY TUNNEL EXCEPT
D
2017
18, Feb
DATE
For Approval
DESCRIPTION REMARK
1 N I C:...IENT
~
1 CROSS·SECTION CHANGE AREA AND STEEL PENSTOCK.
A A
2. THE POSITION OF CONSTRUCTION JOINT SHOULD BE DETERMINED
~C-O~NTAA~C~TO~R------------------~~~~~=-----~
WATERSTOP IN CONSIDERING OF STEEL FORM LENGTH AND CONSTRUCTION
W=300mm CONDITION OF LINING, ETC.
3. WATERSTOP SHOULD BE INSTALLED AT THE CENTER OF LINING, PROJ NAME
PAKISTAN GULPUR HYDROPOWER PROJECT
C~ ___C_O_N_S_TR_U_C_T_IO_N__JO_I_NT__D_ET_A_I_L___) AND IT CAN BE CHANGED BY DISCUSSION WITH OWNER'S
ENGINEER IN CONSIDERING OF CONSTRUCTION CONDITION.
TITLE
Duration
day 1 day 2 day 1 day 4
Activity
(Hours) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 # # # # # # # # # # # # # # # 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 1 2 3 4 5 6 7 8 9 # # # # # # # # # # # # # # #
Steel fixing 10
con. Spacer
2
and support
Liner shifting 5 hr
Liner fixing
7 hr
/Support
Liner
4 hr
Alignment
Pouring and
6
compaction
Fixing of steel 10
Con. Spacer
2
and support
stripping 5
Form removal 4
Liner shifting 5
Liner fixing
7
/Support
Liner
4
Alignment
Pouring and
6
compaction
Note: Time calculated in this sechuedle is based on smooth working conditions, Time cycle can be changed according to site conditions.
Attachment #12
Steel penstock tunnel concreting plan.
Attachment #13
Summary of concrete strength tests with early strength admixtures
Master Rheobuild® 1100
(Formerly known as Rheobuild 1100)
STATEMENT OF The technical information and application advice given in this BASF publication are based on the present state of
RESPONSIBILITY our best scientific and practical knowledge. As the information herein is of a general nature, no assumption can be
made as to a product’s suitability for a particular use or application and no warranty as to its accuracy, reliability or
completeness either expressed or implied is given other than those required by law. The user is responsible for
checking the suitability of products for their intended use.
Field service where provided does not constitute supervisory responsibility. Suggestions made by BASF either
NOTE orally or in writing may be followed, modified or rejected by the owner, engineer or contractor since they, and not
BASF, are responsible for carrying out procedures appropriate to a specific application.
email: mohsin.zia@basf.com
Lahore Islamabad
Karachi Tel: 042 111 550 550 Tel: 051 4446106-08
Tel:021 111 550 550
Website: www.master-builders-solutions.basf.pk
Master Rheobuild® 1100
(Formerly known as Rheobuild 1100)
CARBOPLAST E 3003
Ultra high range water reducing & accelerating hyper
plasticizer for Concrete
Produces highly impermeable, dense concrete with For self compacted concrete
enhanced durability.
DIRECTION OF USE:
E-3003 TECHNICAL DATA
MIXING:
TYPE E-3003
Color Light brown liquid CARBOPLAST E 3003 should be added to concrete
Chloride content to Nill
during mixing cycle at same time as the water and
aggregates. Never add CARBOPLAST E 3003 to the
BS5075 :1982 dry cement.
Nitrate content Nill
Consumption with 100kg 0.2 - 2% Setting Time:
Cement
CARBOPLAST E 3003 ensures that rheoplastic
High Dosages permissible subject to trial concrete remains workable in excess 3 hours at +20°C.
Specific gravity 1.01@ 25 °C Workability loss is dependent on temperature, and on
the type of cement, the nature of aggregates, the
Air contents Less than1 %
method of transport and initial workability. It is strongly
Freezing point: 0°C. can be reconstituted, recommended that concrete should be properly cured
if stirred after thawing particularly in hot and dry climates.
Flash Point: None
Effect of over dosage:
Synthetic fibers
Waterproofing admixture
.
CAUTION:
The information provided in this leaflet, is supplied by our consulting service and is the end result of exhaustive research work and extensive experience. They are, however, without
liability on our part, in particular with regard to third parties proprietary rights, and do not relieve the user of the responsibility for verifying that theproducts and processes are suitable
for the intended application. The data presented was derived from tests under normal climate conditions according to DIN 50014 and mean average values and analysis. Deviations
are possible when delivery takes place. Given that recommendations may differ from those shown in this leaflet written confirmation should be sought. It is the responsibility of the
purchaser to ensure they have the latest leaflet issue and that its contents are current. Our customer service staff will be glad to provide assistance at any time. We appreciate the
interest you have shown in our products. This technical data sheet supercedes pre viously issued information.