You are on page 1of 6

LIST PANEL MNS BITNG

No. Eq. No. Description Location Type Panel MV EFR Fasility KWH type/ Brand Remark

LVD Dan MCC Panel


Example Starter Panel Pump House Tank Farm Tank Farm ada Analog
Example Starter Panel Pump House Tank Farm Tank Farm ada Digital Scneider PM 5330
1 SP. 20.1 Starter Panel Pump House Tank Farm Tank Farm tidak ada Digital Scneider PM 710
2 SP. 20.2 Starter Panel Pump House Tank Farm BD Tank Farm tidak ada
3 SP.21.1 Starter Panel Refinery 500 MTD (OILTEK PANEL) ref 500 tidak ada Analog
4 SP.21.2 Starter Panel Refinery 500 MTD (LIPICO PANEL) ref 500 ada Digital Scneider PM 5330
5 SP.21.3 Starter Panel Refinery 500 MTD (DESMET PANEL) ref 500 tidak ada Analog
6 SP.21.4 Starter Panel Cooling Tower Refinery 500 MTD ref 500 tidak ada Analog
7 SP. 22 Starter Panel Water Treatment Utility ada
8 MSB41 Main Switch Board PK Plant I Crushing Plant ada Digital Scneider PM 5330
9 CAP 41 Capasitor Panel PK Plant I Crushing Plant
10 SP 41.1 Starter Panel PK Plant I Crushing Plant
11 SP 41.2 Starter Panel PK Plant I Crushing Plant
12 SP 41.3 Starter Panel PK Plant I Crushing Plant
13 SP 41.4 Starter Panel PK Plant I Crushing Plant
14 MSB42 Main Switch Board PK Plant II Crushing Plant
15 CAP 42 Capasitor Panel PK Plant II Crushing Plant
16 SP 42.1 Starter Panel PK Plant II Crushing Plant
17 SP 42.2 Starter Panel PK Plant II Crushing Plant
18 SP 42.3 Starter Panel PK Plant II Crushing Plant
19 MSB31 Main Switch Board Copra Plant I Crushing Plant ada Digital Scneider PM 750
20 MSB31.1 Main Switch Board Copra Plant I (Pre Press) Crushing Plant
21 CAP 31.1 Capasitor Panel CCP I (Pre Press) Crushing Plant
22 MSB31.2 Main Switch Board Copra Plant I (Final Press) Crushing Plant
23 CAP 31.2 Capasitor Panel CCP I (Final Press) Crushing Plant
24 SP 31.1 Starter Panel Copra Plant I Crushing Plant
25 SP 31.2 Starter Panel Copra Plant I Crushing Plant tidak ada
26 SP 31.3 Starter Panel Copra Plant I Crushing Plant tidak ada
27 SP 31.4 Starter Panel Copra Plant I Crushing Plant
28 SP 31.5 Starter Panel Copra Plant I Crushing Plant tidak ada
29 SP 31.6 Starter Panel Copra Plant I
30 SP 31.7 Starter Panel Copra Plant I
31 SP 31.8 Starter Panel Copra Plant I
32 MSB32 Main Switch Board Copra Plant II Crushing Plant ada Digital Scneider PM 5300
33 CAP32 Capasitor Panel CCP Plant II Crushing Plant
34 SP 32.1 Starter Panel Copra Plant II Crushing Plant tidak ada
35 SP 32.2 Starter Panel Copra Plant II
36 SP 32.3 Starter Panel Copra Plant II
37 SP 32.4 Starter Panel Copra Plant II
38 SP 32.5 Starter Panel Copra Plant II
39 MSB61A Main Swtch Board Solvent Plant SEP tidak ada Analog/CIC
40 CAP 61A Capasitor Panel SEP SEP tidak ada
41 SP 61.1 Starter Panel Solvent Plant SEP tidak ada
42 SP 61.2 Starter Panel Solvent Plant SEP tidak ada Analog/Circutor
43 MSB61B Main Swtch Board Solvent Plant SEP tidak ada Analog/Jetro
44 CAP 61B Capasitor Panel SEP SEP tidak ada
45 SP 61.11 SEP tidak ada Digital Scneider PM 5100
46 SP 61.3 Starter Panel Pelletizing Machine II SEP tidak ada Analog/Circutor
47 SP 62.3 Starter Panel Pelletizing Machine III SEP tidak ada Digital Scneider PM 710

48 SP 70 Starter Panel Packing Plant CPC ada


49 SP 70.1 Starter Panel Molding Machine I CPC tidak ada
50 SP 70.2 Starter Panel Molding Machine II CPC tidak ada Analog/Fuji Dharma
51 SP 71 Starter Panel RO System I Utility ada Digital Scneider PM 710
52 SP 72 Starter Panel RO System II
53 SP 73 Starter Panel Coal Boiler HPS Utility ada
54 SP 74 Starter Panel Coal Boiler 21T/h Utility tidak ada Square D PM710
55 SP 75 Starter Panel Coal Boiler 75T/h
56 SP 76 Starter Panel ESP Utility tidak ada
57 MSB 80 Main Switch Board I Utility ada Analog/ Fuji Dharma
58 CAP 80 Capasitor Panel MSB I Utility tidak ada
59 MSB 81 Main Switch Board II Utility ada Analog/ Fuji Dharma
60 CAP 81 Capasitor Panel MSB II Utility tidak ada
61 MSB 82 Main Switch Board III Utility ada Analog/ Fuji Dharma
62 CAP 82 Capasitor Panel MSB III Utility tidak ada
63 Syncron I Syncrohn Panel Genset 1 Utility ada Analog/ Fuji Dharma
64 Syncron II Syncrohn Panel Genset II Utility ada Digital Scneider PM 5300
65 MSB 23 Main Switch Board Refinery & Fractionation 1500 MTD ref 1500
66 MSB 23.1 Main Switch Board Refinery 1500MTD ref 1500 tidak ada Digital Scneider PM 710
67 MSB 23.2 Main Switch Board Fractionation 1500MTD ref 1500 tidak ada Digital Scneider PM 710
68 MSB 23.3 Main Switch Board Cooling System Ref. 1500 MTD ref 1500 tidak ada Digital Scneider PM 710
69 MSB 23.4 Main Switch Board Cooling System Frac. 1500 MTD ref 1500 tidak ada Digital Scneider PM 710
70 MSB 23.5 Main Switch Board Capasitor ref 1500 tidak ada
71 SP. 23.1 Starter Panel Refinery 1500MTD ref 1500 ada Rish master 3430
72 SP. 23.2 Starter Panel Fractionation 1500MTD ref 1500 ada Digital Scneider PM 700
73 SP. 23.3 Starter Panel Cooling System Refinery 1500MTD ref 1500 tidak ada Digital Scneider PM 710
74 SP. 23.4 Starter Panel Cooling System Fractionation 1500MTD ref 1500 tidak ada Digital Scneider PM 710
75 CAP 23 Capasitor Panel Refinery & Fractionation 1500 MTD ref 1500 tidak ada
76 LVD-101 BD-LVD-101 Bio Diesel 1200 MTD Biodiesel ada Digital Scneider PM 5300
77 PFC-101 BD-PFC-101 (Capasitor Panel) Biodiesel ada Digital Scneider PM 5300
78 LVD-102 BD-LVD-102 Bio Diesel 1200 MTD Biodiesel ada Digital Scneider PM 5300
79 PFC-102 BD-PFC-102(Capasitor Panel) Biodiesel ada Digital Scneider PM 5300
80 MCC-101 BD-MCC-101 (ISBL SECTION) Biodiesel ada Digital Scneider PM 5300
81 MCC-102 BD-MCC-102 (COOLING TOWER SECTION) Biodiesel ada Digital Scneider PM 5300
82 MCC-103 BD-MCC-103 (DAILY TANK & UTILITY SECTION) Biodiesel ada Digital Scneider PM 5300
83 MCC-104 BD-MCC-104 (TANK FARM SECTION) Biodiesel ada Digital Scneider PM 5300
84 MCC-105 BD-MCC-105 (PME & SODIUM MIXING SECTION) Biodiesel ada Digital Scneider PM 5300
85 MCC-106 BD-MCC-107 (R. MATERIAL & METHANOL TANK) Tank Farm ada
86 MCC-107 BD-MCC-108 (WATER SUPPLY SECTION) Utility ada

MEDIUM VOLTAGE PANEL


HT01 Medium Voltage Panel HT01 INCOMING PLN Utility SM6-DM1-A-IAC12. ada Digital Scneider PM 5500
HT01 Medium Voltage Panel HT01 SUPPLY PLN to HT02A CCP 1 Utility SM6-IM ada Digital Scneider PM 800
HT01 Medium Voltage Panel HT01 SUPPLY PLN to HT02B CCP 2 Utility SM6-IM ada Digital Scneider PM 800
HT01 Medium Voltage Panel HT01 SUPPLY PLN to HT02C KCP Utility SM6-IM ada Digital Scneider PM 800
HT01 Medium Voltage Panel HT01 SUPPLY PLN to HT05 SEP Utility SM6-IM ada Digital Scneider PM 800
HT01 Medium Voltage Panel HT01 SUPPLY PLN to HT10 BD Utility SM6-IM ada Digital Scneider PM 800
HT02 Medium Voltage Panel HT02A SUPPLY CCP 1 Utility SM6-DM1A ada Digital Scneider PM 5500
HT02B Medium Voltage Panel HT02B SUPPLY CCP 2 Utility SM6-DM1A ada Digital Scneider PM 5500
HT02A Medium Voltage Panel HT02C SUPPLY KCP Utility SM6-DM1A ada Digital Scneider PM 5500
HT03A Medium Voltage Panel HT03A CCP 1 Utility SM6-IM ada Digital Scneider PM 5500
HT03B Medium Voltage Panel HT03B CCP 2 Utility SM6-IM ada Digital Scneider PM 5500
HT04 Medium Voltage Panel HT04 KCP Utility SM6-IM ada Digital Scneider PM 5500
HT05 Medium Voltage Panel HT05 SUPPLY SEP
HT06 Medium Voltage Panel HT06 SEP
HT07 Medium Voltage Panel HT07 SUPPLY SUPPLY Utility SM6-DM1A ada Digital Scneider PM 800
HT07 Medium Voltage Panel HT07 SUPPLY to HT02A CCP 1 Utility SM6-DM1A ada Digital Scneider PM 710
HT07 Medium Voltage Panel HT07 SUPPLY to HT02B CCP 2 Utility SM6-DM1A ada Digital Scneider PM 710
HT07 Medium Voltage Panel HT07 SUPPLY to HT02C KCP Utility SM6-DM1A ada Digital Scneider PM 710
HT07 Medium Voltage Panel HT07 SUPPLY to HT05 SEP Utility SM6-DM1A ada Digital Scneider PM 710
HT07 Medium Voltage Panel HT07 SUPPLY to HT 23 REF&FRAC1500MT Utility SM6-DM1A ada Digital Scneider PM 710
HT07 Medium Voltage Panel HT07 SUPPLY to HT 12 ANDERSOON Utility SM6-DM1A ada Digital Scneider PM 710 NEW/FUTURE
HT07 Medium Voltage Panel HT07 SUPPLY to TRANSFORMER 01 Utility SM6-DM1A ada Digital Scneider PM 710
HT08A Medium Voltage Panel HT08A SUPPLY BOILER 75 TPH Utility
HT09 Medium Voltage Panel HT09 BOILER 75 TPH Utility
HT010 Medium Voltage Panel BUS-HT010 SUPPLY BD PLANT Utility SM6-DM1A ada Digital Scneider PM 710
HT011 Medium Voltage Panel BUS-HT011 BD PLANT Utility SM6-DM1A-IAC6 ada Digital Scneider PM 5500
HT012 Medium Voltage Panel BUS-HT011 ANDERSON PLANT NEW/FUTURE
HT23 Medium Voltage Panel BUS-HT023 REF&FRAC1500MTD Utility
HT025 Medium Voltage Panel BUS-HT025 FROM TRANSORMER 02A Utility SM6-DM1A ada
HT025 Medium Voltage Panel BUS-HT025 FROM TRANSORMER 02B Utility SM6-DM1A ada
HT025 Medium Voltage Panel BUS-HT025 OUT TO HT 07 Utility SM6-IM ada
HT02 C Medium Voltage Panel BUS HT-02C
-          Pada MV Panel yang diperlukan adalah data spesifikasi/Type, Jumlah proteksi  & Jumlah dari panel.
-          Unutk LV Panel data Jumlah Cell/ Columb Pada panel dan ACB unit, ermasuk Capacitor bank.
Jumlah dari panel.
acitor bank.

You might also like