You are on page 1of 2

For Columns at Ground Floor

1. L75X75X6mm ANGLE BAR, L3X3X1/4


Height, No. of Total
Structure Material Set Unit
m Columns Length

C1 L75X75X6mm ANGLE BAR, 3 4 8 96 m


L3X3X1/4
C2 3 4 2 24 m
Total Length 120 m
Total PCS of L75X75X6mm ANGLE BAR, L3X3X1/4 20 pcs

2. 6MM THICK PLATE


(A36 PLATE / FY=248MPa)
Length, No. of Total
Structure Material Set Unit
m Columns Length
C1 6MM THICK PLATE 0.6 40 8 192 m
C2 (A36 PLATE / FY=248MPa) 0.6 40 2 48 m
Total Length 240 m

Total PCS of 6MM THICK PLATE 40 pcs


(A36 PLATE / FY=248MPa)

3. 12mm∅-CHEMICAL BOLT x 100mm

No. of No. of Total


Structure Material Set Unit
PCS Columns Length
C1 12mm∅-CHEMICAL BOLT x 12 40 8 3840 pcs
C2 100mm 12 40 2 960 pcs
Total 12mm∅-CHEMICAL BOLT x 100mm 4800 pcs

For Beams at Ground Floor Level


Length, Width,
Structure Material Set Area
m m
5.4 0.075 6 2.43
2.58 0.075 24 4.64
1 PLYCFRP
6.4 0.075 1 0.48
3.08 0.075 6 1.39
BM1 2 PLYCFRP (@ 5.4m) 0.3 0.15 288 12.96
0.3 0.15 72 3.24
2 PLYCFRP (@ 6.4m)
0.15 0.15 3 0.07
BM1

3 PLYCFRP (@ 5.4m) 5.4 0.3 9 14.58


3 PLYCFRP (@ 6.4m) 6.4 0.3 2 3.84

For Beams at Second Floor Level


Length, Width,
Structure Material Set Area
m m
5.4 0.075 6 2.43
2.58 0.075 24 4.64
1 PLYCFRP
6.4 0.075 1 0.48
3.45 0.075 2 0.52
2 PLYCFRP (@ 5.4m) 0.3 0.15 288 12.96
BM1 0.3 0.15 36 1.62
2 PLYCFRP (@ 6.4m) 0.3 0.15 18 0.81
0.15 0.15 2 0.05
3 PLYCFRP (@ 5.4m) 5.4 0.3 9 14.58
3 PLYCFRP (@ 6.4m and 6.4 0.3 1 1.92
3.45m) 3.45 0.3 1 1.04

Summary : Area Units


1 PLYCFRP 17.01 sq.m
2 PLYCFRP 31.71 sq.m
3 PLYCFRP 35.96 sq.m

1. FOR DEMOLITION
a. At Ground Floor:
Area = 35.10 sq.m

2. FOR DEDUCTION (CHB LAYING NAD PLASTERING)


a. At Second Floor:
Area = 35.10 sq.m
b. At Third Floor:
Area 1= 30.80 sq.m
Area 2 = 11.04 sq.m
Summary:
CHB Laying Total = 76.94 sq.m
Plastering Total = 153.88 sq.m

3. FOR SW3 PANEL INSTALLATION


a. At Ground, 2nd and 3rd Floor:
Area = 112.04 sq.m

4. FOR ADDITIONAL REINFORCEMENT


QTY. = 150 PCS of 12mm Diam. RSB