16 16 May'15
EXAMINATION NO. 16
CONTENTS :
TIME SCHEDULE :
11:10 to 12:00
NOTE :
1. Check this Examination question sheets and confirm the category and grade
are proper for those which you are going to take.
3. Write your examinee's NO. on to this cover and all the answer sheets
at first.
If missing, it will be considered no answer written.
4 All the question sheets should be given back to the Observer after finish.
EXAMINEE'S NO.
0000001/5
L-1 No.16/16 May 2015
<Question 1>
Please choose the correct answer from (2points)
A). ③ B). ①
C). ② D). ④
E). ⑧ F). ⑦
Page 2 of 5
L-1 No.16/16 May 2015
G). ⑤ H). ⑥
Page 3 of 5
Level - 1 Mechanical (HVAC)
No.
Compulsory Spec., Regulation, Cost
The diagram below show the layout of a duct system. Please pick up materials necessary for
ducting and indicate necessary quantities based on following conditions.
A.H.U
Flexible
1.5 m
1.5 m
Total
Length Ducting Area (m²)
Duct Dimension length
(m.) (m.) #26 #24 #22 #20 #18
1000 x 500 12 12 36
700 x 500 8 8 19.2
500 x 500 8 + 2x3 14 28
400 x 400 6x3 18 28.8
Diffuser neck 400 x 400 0.5 x 6 3 4.8
SA chamber 2.0 x 1.5 x 0.7 10.9
Diffuser box 500 x 500 x 500 1.25 x 6 = 7.5
Total 33.6 54.7 36 10.9
Total
Length Cladding Area (m²)
Cladding Dimension length
(m.) (m.)
1050 x 550 12 12 38.4
750 x 550 8 8 20.8
550 x 550 8 + 1x3 11 24.2
Total 83.4