Professional Documents
Culture Documents
OWNER: BG M. GUILLERMO
LOCATION: URDANETA CITY, PANGASINAN
SUBJECT: CE322 QUANTITY SURVEYING
BILL OF MATERIALS
ITE PRICE
DESCRIPTION UNIT QUANTITY AMOUNT
M /UNIT
1 EARTHWORKS
EXCAVATION cu.m 4703.57 150 705535.5
BACKFILL cu.m 3588.8 250 897200
GRADING AND COMPACTION sq.m 1546.35 150 231952.5
GRAVEL BEDDING cu.m 200.7 350 70245
SOIL POISONING sq.m 895.75 80 71660
2 STRUCTURAL WORKS
CONCRETE WORKS
PORTLAND CEMENT bags 12839 225 2888775
WASHED SAND cu.m 763.4 700 534380
SCREENED GRAVEL cu.m 1526.5 700 1068550
STEEL
3
REINFORCEMENTS
FOOTING
REBAR @25 mm x 6m pcs 520.83 807 420309.81
G.I. TIE WIRES (GA #16) kgs 51.5 43 2214.5
COLUMN
REBAR @25 mm x 6m pcs 2416 807 1949712
REBAR @12 mm x 6m pcs 1900 218 414200
G.I. TIE WIRES (GA #16) kgs 172.4 43 7413.2
BEAM
REBAR @20 mm x 6m pcs 4475 563 2519425
REBAR @12 mm x 6m pcs 833 218 181594
REBAR @10mm x 6m pcs 4041 175 707175
G.I. TIE WIRES (GA #16) kgs 505.3 43 21727.9
SLAB
REBAR @12 mm x 6m pcs 10612 218 2313416
G.I. TIE WIRES (GA #16) kgs 882 43 37926
CHB REBARS
REBAR @12 mm x 6m pcs 2841 218 619338
G.I. TIE WIRES (GA #16) kgs 127.6 43 5486.8
FORMWORKS
2" x 3" x 8' LUMBER bd-ft. 50276.3 60 3016578
PLYWOOD pcs. 1772 385 682220
4 2 1/2'' CW NAILS kgs 407.9 43 17539.7
1'' CW NAILS kgs 168.4 43 7241.2
SCAFFOLDING &
5
STAGING
2" x 4" x 8' LUMBER bd-ft. 2579.54 250 644885
#4 CW NAILS kgs 125 43 5375
6 MASONRY
CHB – 20cm x 20cm x 40cm pcs. 23524 25 588100
CHB – 15cm x 20cm x 40cm pcs. 29174 18 525132
PORTLAND CEMENT bags 6421 225 1444725
WASHED SAND cu.m 434.23 700 303961
ARCHITECTURAL
7
FINISHES
CEILING FINISHES
2” x 3” x 14’ LUMBER bd-ft. 18900 60 1134000
MARINE PLYWOOD ¼” X4” X
pcs. 939 425 399075
8’
WALL FINISHES
WF1, PAINT FINISH gal. 379 550 208450
WF2, GLASS WALL sq. m 197 3000 591000
WF3, SLATE TILE pcs. 1559 145 226055
FLOOR FINISHES
CERAMIC TILES (600mm x
pcs. 3423 240 821520
600mm)
CERAMIC TILES (300mm x
pcs. 7017 120 842040
300mm)
SLATE TILES (300mm x
pcs. 965 145 139925
600mm)
WOOD PARQUET pcs. 1894 160 303040
CEMENT bags 866 225 194850
SAND cu.m 49 700 34300
8 TILLING WORKS
CEMENT MORTAR bags 198 225 44550
WHITE CEMENT FILLER kgs 1200 20 24000
ADHESIVE bags 250 195 48750
9 PAINTING WORKS
ACRYLIC LATEX PAINT gal. 145 2055 297975
ACRYLIC CONCRETE PRIMER gal. 40 500 20000
WOOD PRIMER gal. 30 365 10950
THINNER gal. 150 355 53250
PAINT BRUSH pcs. 40 45 1800
ROLLER BRUSH pcs. 30 90 2700
DOORS AND
10
WINDOWS
GLASS DOOR (D1) pcs. 25 25000 625000
WOODEN DOOR (D2) pcs. 50 4800 240000
PVC PANEL DOOR (D3) pcs. 26 1990 51740
METAL DOOR (D4) pcs. 8 7000 56000
D5 pcs. 8 3000 24000
WINDOW 1 pcs. 6 25760 154560
WINDOW 2 pcs. 40 7700 308000
WINDOW 3 pcs. 6 5000 30000
WINDOW 4 pcs. 8 4500 36000
11 ELECTRICAL WORKS
LIGHTING 97960
POWER 61500
WIRING 596000
OTHERS 18160
12 PLUMBING WORKS
WATER LINE 74984
DWV 95320
STORM SEWER 51640
FIXTURES & ACCESSORIES 757480
13 MECHANICAL WORKS
ALL INSTALLATION 15860000
TOTAL ( Php ) 47,449,567.11