PROJECT: PROPOSED 4 STOREY BUILDING WITH BASEMENT

OWNER: BG M. GUILLERMO
LOCATION: URDANETA CITY, PANGASINAN
SUBJECT: CE322 QUANTITY SURVEYING

BILL OF MATERIALS
ITE PRICE
DESCRIPTION UNIT QUANTITY AMOUNT
M /UNIT
1 EARTHWORKS  
  EXCAVATION cu.m 4703.57 150 705535.5
  BACKFILL cu.m 3588.8 250 897200
  GRADING AND COMPACTION sq.m 1546.35 150 231952.5
  GRAVEL BEDDING cu.m 200.7 350 70245
  SOIL POISONING sq.m 895.75 80 71660
2 STRUCTURAL WORKS  
  CONCRETE WORKS        
  PORTLAND CEMENT bags 12839 225 2888775
  WASHED SAND cu.m 763.4 700 534380
  SCREENED GRAVEL cu.m 1526.5 700 1068550
STEEL
3        
REINFORCEMENTS
  FOOTING        
  REBAR @25 mm x 6m pcs 520.83 807 420309.81
  G.I. TIE WIRES (GA #16) kgs 51.5 43 2214.5
  COLUMN        
  REBAR @25 mm x 6m pcs 2416 807 1949712
  REBAR @12 mm x 6m pcs 1900 218 414200
  G.I. TIE WIRES (GA #16) kgs 172.4 43 7413.2
BEAM        
  REBAR @20 mm x 6m pcs 4475 563 2519425
  REBAR @12 mm x 6m pcs 833 218 181594
  REBAR @10mm x 6m pcs 4041 175 707175
  G.I. TIE WIRES (GA #16) kgs 505.3 43 21727.9
  SLAB        
  REBAR @12 mm x 6m pcs 10612 218 2313416
  G.I. TIE WIRES (GA #16) kgs 882 43 37926
  CHB REBARS        
  REBAR @12 mm x 6m pcs 2841 218 619338
  G.I. TIE WIRES (GA #16) kgs 127.6 43 5486.8
           
  FORMWORKS        
  2" x 3" x 8' LUMBER bd-ft. 50276.3 60 3016578
  PLYWOOD pcs. 1772 385 682220
4 2 1/2'' CW NAILS kgs 407.9 43 17539.7
  1'' CW NAILS kgs 168.4 43 7241.2

SCAFFOLDING &
5        
STAGING
  2" x 4" x 8' LUMBER bd-ft. 2579.54 250 644885
  #4 CW NAILS kgs 125 43 5375
6 MASONRY        
  CHB – 20cm x 20cm x 40cm pcs. 23524 25 588100
  CHB – 15cm x 20cm x 40cm pcs. 29174 18 525132
  PORTLAND CEMENT bags 6421 225 1444725
  WASHED SAND cu.m 434.23 700 303961
ARCHITECTURAL
7        
FINISHES
  CEILING FINISHES        
  2” x 3” x 14’ LUMBER bd-ft. 18900 60 1134000
MARINE PLYWOOD ¼” X4” X
  pcs. 939 425 399075
8’
 
  WALL FINISHES        
  WF1, PAINT FINISH gal. 379 550 208450
  WF2, GLASS WALL sq. m 197 3000 591000
  WF3, SLATE TILE pcs. 1559 145 226055

  FLOOR FINISHES        
CERAMIC TILES (600mm x
  pcs. 3423 240 821520
600mm)
CERAMIC TILES (300mm x
  pcs. 7017 120 842040
300mm)
SLATE TILES (300mm x
  pcs. 965 145 139925
600mm)
  WOOD PARQUET pcs. 1894 160 303040
  CEMENT bags 866 225 194850
  SAND cu.m 49 700 34300
8 TILLING WORKS        
  CEMENT MORTAR bags 198 225 44550
  WHITE CEMENT FILLER kgs 1200 20 24000
  ADHESIVE bags 250 195 48750
9 PAINTING WORKS        
  ACRYLIC LATEX PAINT gal. 145 2055 297975
  ACRYLIC CONCRETE PRIMER gal. 40 500 20000
  WOOD PRIMER gal. 30 365 10950
  THINNER gal. 150 355 53250
  PAINT BRUSH pcs. 40 45 1800
  ROLLER BRUSH pcs. 30 90 2700

DOORS AND
10        
WINDOWS
  GLASS DOOR (D1) pcs. 25 25000 625000
  WOODEN DOOR (D2) pcs. 50 4800 240000
  PVC PANEL DOOR (D3) pcs. 26 1990 51740
  METAL DOOR (D4) pcs. 8 7000 56000
  D5 pcs. 8 3000 24000
  WINDOW 1 pcs. 6 25760 154560
  WINDOW 2 pcs. 40 7700 308000
  WINDOW 3 pcs. 6 5000 30000
  WINDOW 4 pcs. 8 4500 36000
11 ELECTRICAL WORKS        
  LIGHTING       97960
  POWER       61500
  WIRING       596000
  OTHERS       18160
12 PLUMBING WORKS        
  WATER LINE       74984
  DWV       95320
  STORM SEWER       51640
  FIXTURES & ACCESSORIES       757480
13 MECHANICAL WORKS        
  ALL INSTALLATION       15860000
TOTAL ( Php ) 47,449,567.11

PREPARED BY: ENGR. BG M, GUILLERMO


ENGINEER

Conform:
BG M. GUILLERMO
(OWNER)