Professional Documents
Culture Documents
Ppap Apqp Guide b45157 - Rev A
Ppap Apqp Guide b45157 - Rev A
BAE Systems
Supplier PPAP Guide
SUMMARY
The purpose of the PPAP Submission Guide is to assist the supplier to
complete the various aspects of the Enhanced First Article (PPAP).
Page 1 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Revision History
Rev Date Description
- 24 May 2018 Initial release per DCR DRB31135
A 12 Feb 2019 Updated for closer alignment to AS9145
2 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Table of Contents
1.0 Purpose...............................................................................................................................4
2.0 Scope - When is PPAP Submission Required?.................................................................4
3.0 Reference Documents.......................................................................................................4
4.0 Terms and Definitions........................................................................................................5
5.0 Requirements for PPAP Submission:................................................................................8
5.1 Submission Method............................................................................................................8
5.2 Submission Status..............................................................................................................9
5.3 Ongoing Requirements.......................................................................................................9
6.0 Instructions for completing a PPAP Submission.............................................................9
6.1 Design Records and Ballooned Drawings............................................................................10
6.2 Approved Engineering Change Documentation...................................................................11
6.3 Customer Engineering Approvals.......................................................................................11
6.4 Design Failure Mode and Effects Analysis (DFMEA).............................................................12
6.5 Process Flow Diagrams.....................................................................................................17
6.6 Process Failure Mode Effects Analysis (PFMEA)...................................................................18
6.7 Control Plan.....................................................................................................................22
6.8 Measurement System Analysis (MSA).................................................................................23
6.9 Packaging........................................................................................................................24
6.10 Dimensional Results..........................................................................................................25
6.11 Material and Performance Test Results..............................................................................27
6.12 Initial Process Study (Cpk, Ppk).........................................................................................27
6.13 Qualified Laboratory Documentation..................................................................................28
6.14 Sample Parts....................................................................................................................28
6.15 Checking Aids...................................................................................................................28
6.16 Customer Specific Requirements........................................................................................29
3 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
1.0 Purpose
The purpose of the PPAP Submission Guide is to assist the supplier to complete the various aspects
of the Enhanced First Article (PPAP) as part of a process in accordance with AS9145.
1. To provide the evidence that all engineering, design record and specification requirements
are properly understood and fulfilled by the manufacturing organization.
2. To demonstrate that the established manufacturing process has the potential to produce
consistently conforming product which meets all requirements during an actual production
run at the quoted production rate.
IEEE 1490:2011 Adoption of the Project Management Institute (PMI(R)) Standard; A Guide to the
Project Management Body of Knowledge
B25279: Supplier Requirements for FAI Reports
BAE Systems Supplier Variation Request (SVR)
J1739 JAN2009 PFMEA, DFMEA
Containment:
Recognition, identification and where possible, the segregation of the entire population affected by
the condition of nonconformance. Containment includes raw material, stock inventory, kits, work-
in-process, product in sell-off, finished goods inventory, goods in transit, and goods at BAE
Systems.
Control Plan:
A written description of the systems for controlling production parts, materials and processes.
Control plans identify the important characteristics and engineering specifications of the product
and how they are controlled to assure quality of the product. The control plan should be linked to
the process flow diagram and the process failures modes and effects analysis.
Correction:
Action taken to eliminate a detected nonconformity.
Customer:
The recipient of the supplier’s or organizations products or service.
Deliverables:
Outputs completed as part of the APQP/PPAP process.
Design Records:
The records of the engineering definition/specification, that fully define the product (system, part,
component, or assembly), including physical or electronic/digital drawings, electronic/digital
models, software, or other associated information. This includes records of authorized engineering
changes (Approved via SVR) not yet incorporated into the released engineering
definition/specification.
5 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Design Validation
The assurance that a product, service, or system fulfills the needs of the customer and other
identified stakeholders. It often involves acceptance with external customers (defined in IEEE
1490:2011). Relevant types of validation include: – Confirmation through the provision of objective
evidence, that the requirements for a specific intended use or application have been fulfilled.
Testing and/or analysis to ensure the product design conforms to defined user needs and/or
requirements. Design validation follows successful design verification and may involve
preproduction product (e.g., development, prototype) [reference AIAG Advanced Product Quality
Planning and Control Plan].
Design Verification
Testing to assure that all design outputs meet the requirements of the design inputs with objective
evidence that the specified product requirements have been fulfilled. Testing and/or analysis to
ensure that all design outputs satisfy requirements may include activities such as: design review,
performing alternate calculations, understanding tests and demonstrations, and review of design
stage documents before release (reference AIAG Advanced Product Quality Planning and Control
Plan).
Nonconformance:
The failure or potential failure of a characteristic to conform to the requirements specified in a
contract, purchase order, drawing, specification or other approved product description.
Potential/suspect non-conformances include improper handling, storage, transport, and exposure to
out-of-tolerance environmental, test or process conditions.
Nonconforming Material:
Any item, part, or product containing one or more nonconformance
6 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Preventive Action:
Action to eliminate the cause of a potential nonconformity or other undesirable condition. If a
nonconformance has not occurred, but an action is taken to proactively reduce the risk of a
nonconformance, the action is preventive.
Process Capability:
Comparing actual process performance with process specification limits using measure e.g.: Cpk,
CP, Sigma Level and parts defective parts per million.
Process Validation:
Confirmation through physical demonstration that a process consistently produces a result or
product fulfilling its predetermined specifications, including key product or process characteristics
which are stable and capable at the desired level.
Repair:
A procedure that reduces but does not eliminate a nonconformance and is approved by the
Customer when required by contract.
Rework:
A procedure applied to a nonconformance that will completely eliminate the nonconformance, and
result in a characteristic that conforms completely to the drawing, specification or contractual
requirement.
SCAR:
Supplier Corrective Action Request
Scrap:
Nonconforming material that is not usable for its intended purpose that cannot be economically
reworked.
Supplier:
The entity or party that supplies product or services to a customer in accordance with contract
requirements.
7 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
NOTE BAE Systems provides suggested templates of all forms for the PPAP submittal, however
: Supplier generated forms meeting the requirements of SAE INTERNATIONAL AS9145™ or
AIAG may also be utilized.
Completion and submission of PPAP records conveys no additional data rights to BAE
Systems than that defined in the respective Procurement Agreement
PPAPs are considered Technical Data and therefore must be controlled in accordance with
contractual requirements specified in the special provisions of the Purchase Order / Subcontract or
incorporated Terms and Conditions. Such requirements may include ITAR, Export Control, and
Proprietary Information Agreements. Unclassified technical data shall be submitted through BAE
Systems approved methods including but not necessarily limited to Secure File Transfer System
(SFTS), Exostar, or physical mail.
Classified technical data shall be specially handled as specified in the Purchase Order or
Subcontract.
Contact your BAE Systems procurement representative to confirm the approved transmittal
method.
8 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
APPROVED: A formal acceptance of the submission which has met all of the criteria set by BAE
Systems
REJECTED: The submission is not acceptable and does not meet the criteria set by BAE
Systems
INTERIM: An interim approval can be given if it is deemed by BAE Systems that product is
useable. The interim status is a temporary approval for a specified time-frame
which is determined by BAE Systems. The supplier must implement the required
corrective actions and re-submit PPAP for full approval during this time frame. If a
re-submission does not occur within the required time-frame the PPAP will be
rejected.
9 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
A ballooned drawing shows the parts or assemblies in a part print with numbered “balloons” that
point to individual requirements of the part. The numbers on the ballooned drawing correlate with
the numbers found on the Dimensional Data Sheet. A ballooned drawing must be submitted as
part of the PPAP for every submission when dimensional results are required.
All part requirements on the BAE Systems or Supplier print must be ballooned and numbered for
reference and measurement. These may include:
When dimensions are specified at multiple location on the drawing, the data for each location
should be numbered separately.
10 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
1. Material not in compliance with drawing(s) or specification(s) shall NOT be shipped without
prior BAE Systems Approval.
2. The supplier must receive an approved and closed SVR as authorization to ship product.
1. If the SVR disposition requires a drawing change then upon release of the ECO, a PO
revision change will be issued to reflect the new part revision Product should not
ship until ECO is completed and the SVR closed.
3. The supplier shall not perform any repair activity before getting BAE Systems approval via a
documented repair procedure approved on the SVR by BAE Systems.
A copy of the Supplier Variation Request form and submission instructions can be found on the BAE
Systems Supplier Quality Assurance Portal.
11 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
The DFMEA is only required when the supplier has design authority of the product. The DFMEA
must address all Critical Items (CI).
Severity, Occurrence and Detection ratings are used when performing FMEA activities. These
rating scales must be compliant with the AIAG guidelines for FMEA.
Any potential failure mode not mitigated in the DFMEA should be included in the PFMEA.
When completing the FMEA an action plan must be established in line with the risk analysis table
shown below:
NOTE BAE Systems only requires a Design Failure Mode and Effects Analysis (DFMEA) to be
: included if the supplier has design authority.
12 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Prevention is the preferred method to address the design failure mode. If prevention is not
possible, then highlight detection controls. The DFMEA is not a standalone document and should
also be linked to the PFMEA and Control Plans.
BAE Systems has developed a DFMEA form which can be utilized by suppliers. The form uses
embedded ratings which will automatically produce the initial Risk Priority Number (RPN)
Severity x Occurrence x Detection = RPN
DESIGN FAILURE MODE ANALYSIS
(DESIGN FMEA)
FMEA number
Item Process Responsibility No. of Pages
Part Number Key dates Prepared by
Core Team FMEA date (Orig.) Rev. Date
C O D
PROCESS Actions Results
S L Potential Cause(s) / C E R Responsibility &
FUNCTION Potential Failure Potential Effect(s) of Current Process Controls Current Process Controls Recommended S O D R
E A Mechanism(s) of C T P Target Completion E C E P
REQUIREMENTS Mode Failure V S U Prevention Detection E N Action(s) Actions Taken
S
Failure R C
Completion Date Date V C T N
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
0 0
13 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
14 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
15 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Product verification /validation after design freeze and prior to launch with
pass/fail testing (sub-system or system testing with acceptance criteria e.g. 8
Ride & handling, shipping evaluation, etc.)
Post Design
Product verification/validation after design freeze and prior to launch with
Freeze and
test to failure testing (Sub-system or system testing until failure occurs, 7
Prior to
testing of system interactions, etc.)
Launch
Product verification/validation after design freeze and prior to launch with
degradation testing (Sub-system or system testing after durability test e.g. 6
Function check)
Detection Failure cause or Failure mode cannot occur because it is fully prevented
not through design solutions (e.g. Proven design standard/best practice or
applicable; common material, etc.) 1
Error
Prevention
16 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
The Process Flow Diagram must also include key steps in the process and all offline activities (such
as measurement, inspection and handling). The flow of the nonconforming material such as scrap
parts, non-conforming parts and rework parts should also be included the supplier is not authorized
to perform a repair on a part.
NOTE: Suppliers may utilize their own Process Flow Diagram format.
17 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
A PFMEA should be performed for every part, piece or equipment or process involved in
manufacturing. The PFMEA is a cross functional activity and should not be conducted in isolation.
When calculating the Risk Priority Number (RPN) for the PFMEA the following rating mechanism
should be utilized to assess Severity, Occurrence, and Detection: ( Severity x Occurrence x Detection =
RPN)
PROCESS C O D Acti
S L Potential Cause(s) / C E R Responsibility &
FUNCTION Potential Failure Potential Effect(s) of Current Process Controls Current Process Controls Recommended
E A Mechanism(s) of C T P Target Completion Completion
Mode Failure V S U Prevention Detection E N Action(s)
REQUIREMENTS Failure Date Date
S R C
0
0
0
0
0
0
0
The PFMEA worksheet is a tool used to identify and show potential process risks associated with
the manufacture of each part. It also highlights the controls at each stage of the manufacturing
process; this detail should read across to the Control Plan.
18 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Significant A portion of the production run may have to be scrapped. Deviation from
primary process; decreased line speed or added manpower. 7
Disruption
100% of production run may have to be reworked off line and accepted.
6
Rework out-of-
station
A portion of the production run may have to be reworked off line and accepted
5
19 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
20 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Defect (Failure Mode) and/or Error (Cause) is not easily detected (e.g.
Difficult to Detect 9
Random Audits)
Defect Detection Post Defect (failure Mode) detection post-processing by operator through
visual/tactile/audible means 8
Processing
Error Detection and/or Error (Cause) detection in-station by automated controls that will detect
error and prevent discrepant part from being made. 2
Defect Prevention
Detection not Error (Cause) prevention as a result of figure design, machine design or
applicable; Error part design. 1
Prevention
21 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
1. Methods of production
2. Identification of KC characteristics
3. Secondary or Outsourced Operations
4. Materials and their physical and chemical characteristics
5. Types of process equipment at each operation
6. Types of test equipment used to measure each characteristic
7. Specifications, sampling strategy, control and reaction methods used.
8. Periodic conformance testing and product verification
All processes must have a control plan that defines all methods used for process control and
complies with BAE Systems specified requirements. The control plan must clearly state each step
in the process; the specification and all KC characteristics must be addressed for product and
process. The Process Flow Diagram, PFMEA and Control Plan must be linked. Each major process
step in the process flow diagram should correlate with PFMEA steps and there should be
documented control plan actions for each of the steps.
A control plan should address all testing requirements, inspection and measurements that are
required to verify product quality and conformity. The control plan must not be excessively
dependent on visual inspection and should always target prevention techniques wherever possible.
The control plan should be developed in stages, from Prototype to Pre-Production and then into
Production. The control plan is a “living” document and should be updated to reflect any changes to
the manufacturing process and its controls.
BAE Systems has developed a Control Plan format which is available for suppliers to utilize if
required.
22 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Part Name / Description Supplier / Plant Approval / Date (If Required) Customer Quality Approval / Date (If Required)
Supplier / Plant Supplier Code Other Approval / Date (If Required) Other Approval / Date (If Required)
BAE Systems requires an MSA study to be conducted on all measurement equipment that is used to
accept or fail the product. This generally covers all measurement tools identified in the control
plan.
A Gauge Repeatability and Reproducibility (GR&R) study is used to ensure that measurements
taken in the manufacturing process and reasonably consistent regardless of how many times they
are performed or how had performed them. It is important to select a sample size that
encompasses the full range of parts.
23 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Statistical software, IE: Mini-tab, SPC Excel or equivalent may be utilized to conduct the
measurement study. BAE Systems has also developed at GR&R worksheet for the suppliers to
utilize. Instructions on how to complete the GR&R are included in the worksheet.
Measurements
OPER1 OPER2 OPER3 OPER4 OPER5
Part trial 1 trial 2 Range trial 1 trial 2 Range trial 1 trial 2 Range trial 1 trial 2 Range trial 1 trial 2 Range
1
2
3
4
5
6
7
8
9
10
X-bar X-bar X-bar X-bar X-bar
# persons R-bar R-bar R-bar R-bar R-bar
# parts (n) MaxR MaxR MaxR MaxR MaxR
# trial (m)
LSL 0.000 USL 0.000 Max X-bar 0.0000 R-double bar =
a 0.00 Total Tolerance 0.0000 Min X-bar 0.0000 UCLR = R-double bar x D4
b 0.00 X-bar diff 0.0000 UCLR =
D4 = 0.00 If R values in study are greater
than UCLR , these are statistical
outlier and need evaluation
% EV = % AV = %R&R = 0.0%
6.9 Packaging
A packaging, preservation, and labeling plan shall at a minimum define:
24 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
The parts used for dimensional data must be from production tooling / process and randomly
sampled (if possible) from a run at production rate. The dimensional report must address all of the
following:
1. All dimensions
2. All applicable notes on the drawing
3. Any dimensions contained on reference prints
NOTE: The parts measured to obtain the dimensional results must be the same parts submitted for
PPAP approval
All dimensional requirements on the ballooned drawing must be listed on the dimensional data
sheet. All sections of the dimensional data sheet must be filled out completely. The measurement
method must be documented for every line item.
When a specific feature on the drawing has multiple requirements I.E. GD&T symbols the data
must be recorded on individual line items with the dimensional data sheet.
Example: This call out would require 3 lines of separate data on the dimensional report.
Dimensional Data and all requirements should be documented via the standard BAE Systems FAI
process per BAE Systems Supplier Requirements for First Article Inspections Reports, B25279:
25 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
NOTE: Any concerns identified in the Dimensional Data should be brought to the attention of BAE
Systems before submitting your PPAP.
26 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
Material test results should be provided in the form of a material composition report also called a
Certificate of Analysis (CofA) from an accredited lab that confirms the material content meets a
known standard, IE: Chemical and Physical Analysis Report.
It is the Supplier’s responsibility to confirm the composition of material not only at PPAP submission
stage but also ongoing during the life of the product / project. This step should be placed into the
FMEA process and the Control Plan.
Performance Test Results should be acceptable, and meet the agreed upon specifications to be
measured. Performance results may include data confirming any referenced specifications in the
part print or specific testing required by BAE Systems.
BAE Systems will communicate specific material, performance and testing requirements either in
the part print, reference specifications or by a specific request prior to PPAP approval. It is the
responsibility of the supplier to confirm the data and format of this requirement with the
appropriate BAE Systems representative.
Test Data should not be submitted with the PPAP unless the purchase order calls contains a
material clause such as 111, 134, 135 or 168. The prior list is not meant to be all inclusive as all
clauses should be reviewed and requirements identified as part of your contract review.
Cpk predicts future capability and should be used when developing new parts or revising
specifications on a part. Cpk should also be used when materials, processes, manufacturing
location, or equipment have changed or Material suppliers have changed.
Ppk indicates past performance. Use Ppk when you are a new supplier to BAE Systems but have
already been manufacturing the part which BAE Systems will purchase.
The capability study is to be performed on samples taken from an actual production run at the
quoted production rates. The minimum acceptance capability for all CIs is 1.33 and 1.67 for all
safety related CI’s. In some cases, it may be impossible or prohibitively expensive to meet the
stability and capability requirements. These exceptions shall be documented by the producer and
require customer approval. An alternative control method (such as 100% gauging) may be
required.
27 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
The supplier can submit the Capability data on the format of their choice, and Mini-tab, SPC Excel
or equivalent may be utilized.
All suppliers that have testing or measurement performed on site must provide the following in this
section of the PPAP submission:
A. Record / Scope that identifies the testing to be done and it must include:
B. List of your personnel’s competency and training to perform the testing.
C. List of all test equipment used in process and offline.
D. List of methods and standards used to calibrate the equipment.
If you are sending out for measurement and testing, you must ensure that you use an accredited
lab and can provide proof of accreditation. BAE Systems prefers external labs be accredited to
known standards such as ISO 17025, ISO 10012:2004, or ANSI/NCSL Z540-1-1994.
The PPAP samples should be delivered with the label identifying them as PPAP Samples.
This is to avoid the PPAP sample parts being inadvertently misplaced or mixed up with production
parts.
28 of 29
Document No. B45157
Revision: A
Date: 7 Feb 2019
There are many different types of checking aids. Examples of checking aids include but are not
limited to certified check fixtures, un-certified check fixtures, templates, custom gauges and test
equipment.
BAE Systems requires all checking aids to be verified as repeatable through an MSA study. The MSA
can be either attribute or variable depending on the type of checking aid in use.
BAE Systems will advise during the PPAP process on specific requirements as there may vary
depending on the scope of the project / product being supplied. This item is also utilized to flow
down requirements of BAE Systems customers to ensure these elements are captured during PPAP
submission.
29 of 29