Introduction:
In this Project, for the sake of choosing an event, the National Conference in college will be
analyzed following the process of CPM. Our company “EVENT MANAGEMENT” took the
responsibilities of this event. The Event date was fixed by our honorable customer .4th may for
Conference day. This event was held on Dhaka College. The objective of this project Network
Precedence diagram, Possible Paths, Expected Project duration, Slack Time and Gantt Chart will
be implemented based on the assuming sets of data.

(2)

List of the Activities:

Activity Indicating Letter

Select a conference date A

Confirm lead speaker and topic B

Prepare brochure C

Send letters to other speakers D

Get confirmation from speakers E

Send letters to participants F

Obtain travel plans from speaker G

Arrange for accommodation for H


speakers
Get Handout from speakers I

Finalize registrations J

Arrange Hall K

Conduct of programmed L
(3)
Data Table of the Activities:
Activity Immediate Estimated Normal
Predecessor Time (days)
A - 1

B - 5

C - 2

D A, C 2

E D 5

F D, E 2

G E 2

H G 1

I G 4

J H, I 10

K J 1

L K 1

(4)
Precedence Diagram:
Network Precedence Diagram using CPM method:

POSSIBLE PATHS:
A-D-F = 5
A-D-E-F= 10
A-D-E-G-H-J-K-L= 23
A-D-E-G-I-J-K-L= 26
B=5
C-D-F=5
C-D-E-F= 10
C-D-E-G-H-J-K-L= 24
C-D-E-G-I-J-K-L= 27
[Critical path is C-D-E-G-I-J-K-L]
[Expected Project Duration=27]
SLACK TIME:

A=1 F=16 K=0


B = 22 G=0 L=0
C=0 H=3
D=0 I=0 Gantt Chart:
E=0 J=0