Professional Documents
Culture Documents
Title: Page:
Electrical Isolation 1 of 8
Reference: Revision: Revision Date:
1
Table of Contents
Section Topic
1.0 Purpose 2
2.0 Scope 2
3.0 Definitions 2
4.0 Assignment and responsibilities 3
5.0 Electrical Isolation Certificates 3
6.0 Isolation Initiation Procedure 4
7.0 Procedure for Part A Electrical Isolation by Operations 4
8.0 Procedure for Part B Electrical Isolation by Electrical Authority
and Issuing Authority 5
9.0 Responsibility of Performing Authority 6
10.0 Procedure for Amendment to Isolation 6
11.0 Close Out 7
12.0 Exceptions 7
13.0 Revision Record and Approval Log 8
14.0 Certificates 8
Appendix 1: Electrical Isolation Certificate Part A 8
Appendix 2: Electrical Isolation Certificate Part B 8
1.0 Purpose
2.0 Scope
Electrical isolation and de-isolation for Margham, GCS, Jebel Ali Terminal,
LNG Jetty and Pipeline installations.
3.0 Definitions
The Operations and Electrical Authority are responsible for complying with the
requirements of this procedure and ensure they are not placing themselves or
others at risk or injury.
The Electrical Isolation Certificate can be valid for more than one
permit. This allows a piece of equipment to have different jobs and
Performing Authorities all protected by the same Electrical Isolation
Certificate. All Permit numbers must be quoted on the original Electrical
Isolation Certificate.
If any of the jobs are not completed by the end of the workday and are to
be carried over into the next day, the Electrical Isolation Certificate will
remain valid and be posted on the Permit Board and logged in the
Supervisor's log.
The Shift Supervisor responsible for the electrical work being carred out on
his shift shall validate the Electrical Isolation Certificate.
A Hot or Cold Work Permit may be initiated ( but not issued ) prior to any
action being taken to electrically isolate by lock-out and tagging of
switches, circuit breakers etc. However there is no separate Work Permit
issued for Electrical Isolation, the Electrical Isolation Certificate Part-A or
Part-B itself serves as the Work Permit.
The Issuing Authority will ensure that the Electrical Isolation is appropriate
for the work to be performed and initiate the isolation by completing
Sections 1, 2 and appropriate details of Section 3 of the Electrical
Isolation Certificate Part A or Part B (attached).
The Issuing Authority will ensure all associated work is complete, permits
are closed, signed off and equipment is safe to be energized. Issuing
Authority will then complete the de-isolation request section 6 of the
Electrical Isolation Certificate and arrange the removal of the final
Operation’s padlock hasp and tag before the equipment is re-energized.
For Electrical isolation Part A the Operator, or Electrical Authority at GCS,
will restore power to the process equipment and sign Section 3 of the
Electrical Isolation Certificate Part A as de-isolated.
For Electrical isolation Part B the Electrical Authority will restore power to
the equipment and will sign the Section 3 and Section 7 of the Electrical
Isolation certificate Part B as de-isolated.
The Issuing Authority will verify the de-isolation and sign section 7, De-
isolation verification of the Electrical Isolation Certificate Part A or Part B.
The Issuing Authority will approve the de-isolation verification of the
Isolation Certificate and sign off the entry in the Isolation Log Book (Lock
Register at Margham) as de-isolated.
12.0 Exceptions
At the periodic review or for entire plan revisions assign a new revision
number and date. For minor wording or paragraph revisions make the
change in blue font and note the date at the end of the SOP. Incorporate the
changes at the next periodic review.