You are on page 1of 7

Preliminary Design of Post-Tensioned Transfer Girders

Almıla Uzel, Ph.D., P.Eng. 1

Abstract: Posttensioned transfer girders offer elegant solutions to support vertical members that do not extend below lower levels of
high-rise buildings. The design of a posttensioned transfer girder involves selection of a preliminary section, and then optimization of girder
Downloaded from ascelibrary.org by CORNELL UNIV LIBRARIES on 09/10/20. Copyright ASCE. For personal use only; all rights reserved.

size and the prestressing force to satisfy serviceability and ultimate design requirements. In practice, typical span-to-depth ratios are used for
preliminary sizing of structures. However, in the case of transfer girders, it is not easy to set a rule-of-thumb because the depth of the member
depends on the transferred load and many other parameters. Herein, a simple approach is suggested to practicing engineers for determining
the depth of simply supported transfer girders with minimal trial and error. It is shown that the proposed expression gives reasonable pre-
liminary dimensions to achieve an acceptable design in terms of serviceability. DOI: 10.1061/(ASCE)SC.1943-5576.0000519. © 2020
American Society of Civil Engineers.
Author keywords: Staged prestressing; Preliminary sizing; Prestressed concrete; Posttensioning; Transfer girders.

Introduction checked. This check must be repeated until an economical and


sound design is achieved.
To have flexibility in the column layout of mixed-use buildings or The load balancing concept was first introduced by Lin (1961)
to create a wider space at lower floors of a building, the engineer to produce relatively simple preliminary designs without compli-
may need to terminate a column or a shear wall, and introduce cated calculations and has given a new approach to the design
other ones. In such design challenges, posttensioning can offer both of complex prestressed members (Lin 1963). This concept, where
structurally and architecturally efficient solutions. Advances in prestressing balances a portion of the applied load, relies on the
posttensioning techniques and materials have enabled structural en- principle of superposition, which is applicable in the elastic region,
gineers to more widely use posttensioned members during the last i.e., before cracking. If one assumes that prestressed members are
decade (Fig. 1). essentially uncracked under service loads, load balancing can be
Prestressing improves the response of a flexural member, be- used to decide on the effective prestressing force and section size.
cause precompression substantially increases the external load re- It is significant for a practicing engineer to answer this question
quired to crack the concrete. By using prestressing, for the same quickly: “What would be the depth of the girder if we transfer this
imposed load, a more slender structure can be designed. Control column?” This paper aims to propose a simple approach to derive
of creep deflections and cracking is one of the other reasons to an expression for preliminary sizing of posttensioned transfer gird-
choose posttensioned girders when transferring high-rise columns. ers based on the concept of balanced loading. Furthermore, a de-
The design process of almost any type of structural element starts sign example is included to illustrate the use of the proposed
with choosing appropriate cross-sectional dimensions for prelimi- expression for the serviceability design of a posttensioned transfer
nary calculations. In practice, typical span-to-depth ratios are used girder for which prestressing is applied in stages.
for preliminary sizing of structures. Basic ratios of span to overall
depth for reinforced concrete beams without axial compression are
given in Table 9.3.1.1 of ACI 318-19 (ACI 2019). These typical
Preliminary Design Process: Choosing Girder
ratios provide guidance for preliminary sizing under common oc-
Dimensions and Prestressing
cupancy loading. However, in the case of transfer girders, it is not
easy to set a rule-of-thumb because the depth of the member would In the design of prestressed concrete structures, loads on the
depend on many parameters such as the number of floors to be member must be assessed with the utmost care, and concrete
transferred and the layout of supporting structural members. On stresses under these loads must be checked at different stages
the other hand, transfer girders, whether posttensioned or conven- of the member’s life. Once service design requirements are satis-
tional reinforced concrete, are usually large members, and it is gen- fied, the ultimate strength design of the girder is carried out. Often
erally expected by the whole design team to have an idea on how satisfying the ultimate strength requirements of a posttensioned
large the beam would be so that the clear height under the beam is member is less complicated than satisfying stress limits at service
known, and any related design obstacles can be foreseen at the be- stages. To determine an appropriate tendon profile and the pre-
ginning of the project. A preliminary section is often assumed stressing force to be applied, the structural framing system and
based on past experience, and service design requirements are then cross-sectional dimensions of the transfer girder must be
1
determined.
Assistant Professor, Faculty of Engineering, Dept. of Civil Engineer- Fig. 2(a) shows a typical single span simply supported transfer
ing, Yeditepe Univ., Atasehir, Istanbul 34755, Turkey. ORCID: https://
girder, with a profiled tendon which supports a column at midspan.
orcid.org/0000-0001-9402-8757. Email: almila.uzel@yeditepe.edu.tr
Note. This manuscript was submitted on October 23, 2019; approved on
Ideally, the prestressing profile of a posttensioned girder transfer-
June 10, 2020; published online on August 11, 2020. Discussion period ring a column should be a harped profile to fully balance the load-
open until January 11, 2021; separate discussions must be submitted for ing from a point load (Lin 1963). However, harped tendons with
individual papers. This paper is part of the Practice Periodical on Struc- sharp deviations are not suitable for field installation because rup-
tural Design and Construction, © ASCE, ISSN 1084-0680. turing of the strands during stressing operation may occur due to

© ASCE 04020036-1 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2020, 25(4): 04020036


creep (Balázs et al. 2013). Therefore, it is usually suggested to
choose a prestressing force that balances the deflection due to dead
transferred columns
load so that the creep of both dead load deflection and upward cam-
ber are balanced, and the long-term deflection is only due to sus-
tained live load. If the actual live load is too high and will be
sustained, then the engineer may also choose to balance part
of the live load for better control of deflections. It is concluded that
the amount of loading to be balanced should be decided based on
the circumstances of each project.

Proposed Expression for Preliminary Sizing


Downloaded from ascelibrary.org by CORNELL UNIV LIBRARIES on 09/10/20. Copyright ASCE. For personal use only; all rights reserved.

In this work, a simple expression to determine the depth of a simply


supported single span transfer girder is derived by assuming that a
Fig. 1. Two tower columns being transferred at a lower story. (Image certain percentage of the applied downwards load is balanced with
by Almıla Uzel). the upwards push due to prestressing. Fig. 2(b) shows cross sec-
tions of a typical transfer girder, at midspan and the ends. The width
of the surrounding slab can be neglected when compared with the
large girder section, and the girder section can be assumed as a
rectangular section. Design variables are h, height of the section;
bw , width of the section; ep;mid , eccentricity of the tendon at mid-
span which is the distance from the center of gravity of steel (c.g.s)
Peff Peff
to the center of gravity of concrete (c.g.c) section and the effective
prestressing force after all losses, Peff [Fig. 2(a)].
There are practical and code limitations that enable the engineer
(a) to consider reasonable values for the effective prestressing force,
Peff , and the eccentricity of the tendons at midspan, ep;mid . Below,
anchor plates
the value assumed for these critical design parameters will be given
along with the reasoning behind it.

Effective Prestress Force, Pef f


h x Peff is the total prestressing force after all losses due to shrinkage,
creep, relaxation, anchorage seating, and friction due to the drape of
e p,mid tendons. In most design codes [ACI 318-19 (ACI 2019); CSA
A23.3-14 (CSA 2014)], a minimum value for average effective pre-
stress, f pc , which is the compressive stress at the centroid of the
section due to prestress after allowance for all prestress losses, is
bw specified. On the other hand, many codes do not specify upper lim-
its for average effective prestress, and it is often decided by the
section section
engineer based on previous experience (Aalami and Jurgens
at midspan at ends
ep=ep,mid ep=0 2003). It is recommended to limit the applied prestressing force
to limit restraint forces in the surrounding and supporting structural
(b)
members; to minimize creep of concrete and congestion of
Fig. 2. (a) Typical transfer girder supporting a column at midspan; and reinforcement at anchorage zones and to achieve an economical
(b) transfer girder cross sections at midspan and at ends. design. It is important to note that according to Chapter 18.6.3.5
(a) of ACI 318-19, fpc shall not exceed the lesser of 3.5 MPa
(500 psi) and f c0 =10 for beams in structures assigned to seismic
design category (SDC) D through F whether the beam is a part
of seismic-force-resisting system or not. For beams in structures
the kink in the tendon at high and low points, especially when the assigned to SDC B and C, this upper limit on f pc applies only
girder is continuous (Nawy 2006). There are different approaches to beams that are part of the seismic-force-resisting system, and
in practice, either the tendon is arranged in a parabolic profile and beams in structures assigned to SDC A are exempt from this limit.
then a profile close to a harped profile is achieved by smoothing the High prestressing forces may cause excessive restraint forces in the
curvatures, or the tendon is arranged in a harped profile, and then it surrounding members, which would result in cracking of concrete
is bent in a concentrated curvature with minimum radius at (Aalami and Jurgens 2003). Therefore, an effective compressive
deviation points. The center of gravity of tendons at the ends of stress of 4–6 MPa on gross cross section is a good design choice,
a member is arranged such that it coincides with the centroid of which also results in lower compression just behind the anchor
the gross cross section not to transmit any moments to the columns plates at the ends of the transfer girder [Fig. 2(b)].
supporting the girder.
The engineer then decides on sectional dimensions and the pre- Width of Transfer Girder, bw
stressing force to be applied. Service design requirements are As shown in Fig. 2(a), tendons approach into a relatively tight
checked, and this must be repeated a few times before an acceptable group at locations of maximum moment, and they are placed
design in terms of serviceability is achieved. Due to the high axial preferably in a single layer to maximize tendon eccentricity. On
compression that is sustained during the lifetime of a prestressed the other hand, a clear spacing must be provided between them
member, there is a greater tendency in prestressed structures to to evenly distribute the precompression and to allow for proper

© ASCE 04020036-2 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2020, 25(4): 04020036


concrete placement. Tendons are anchored at the stressing end with Peff ¼ fpc hbw ð2Þ
steel plates attached to them, as depicted in Fig. 2(b). Prestressing
force is applied and as the strands are anchored by means of conical where bw = width; and h = height of the transfer girder. Substituting
seats, compression is first applied to this small area. In the design of ep;mid ¼ 0.35h; bw ¼ h as practical values and assuming an effec-
posttensioned girders, large concentrated loads require high pre- tive compressive stress value of 5 MPa, the balancing moment can
stressing forces to be applied. In the anchorage zones of transfer be calculated as
girders transverse tensile stresses, i.e., bursting stresses occur
due to the high longitudinal compression applied by the prestress- Peff ep;mid ¼ ð5 MPaÞðh2 Þð0.35hÞ ¼ 1.75h3 ð3Þ
ing force over a small bearing area. As the ratio of bearing area
dimensions to member dimensions increases, bursting stresses will Assuming the engineer chooses to balance 100% of the moment
decrease; therefore, it is usually desired to have anchorage plates produced by the dead load of the transferred column, the following
distributed over the entire cross section. Also, the size of these equation can be written:
Downloaded from ascelibrary.org by CORNELL UNIV LIBRARIES on 09/10/20. Copyright ASCE. For personal use only; all rights reserved.

plates should be large enough such that the compressive stresses PDL L
behind the anchorage plates stay below reasonable limits, and these Peff ep;mid ¼ ð4Þ
4
anchorage plates should be placed within an acceptable distance
from the face of the girder to avoid spalling failure. Hence, the where PDL = total dead load of the transferred column; and L =
width of the transfer girder should be wide enough to accommodate span length of the transfer girder. Applied moment due to the dead
a proper arrangement of the tendons. In practice, considering a load of the supported column is calculated assuming that the point
beam width close to the height of the transfer girder is reasonable load acts at the midspan. Recall that because the profile of the ten-
and economical unless there are architectural constraints to limit the dons cannot be formed into a perfect harped profile to avoid sharp
width of the girder. kinks along the tendon, the profile will not match the applied
moment diagram. Consequently, exact load balancing is not
Tendon Eccentricity at Midspan, ep;mid achieved, and this will result in some unbalanced moments along
Cover requirements and minimum spacing between the tendons the beam. However, it is noted that the purpose here is to calculate a
dictate the value of the eccentricity of the tendon at the span where preliminary girder size that will require minimal trial and error.
the largest sag occurs. To determine concrete cover and minimum Substituting Eq. (3) into Eq. (4) and solving for h, the following
spacing between tendons, applicable standards and recommenda- simple expression to determine the required height of a simply sup-
tions should be followed. Fire protection and durability are ensured ported posttensioned transfer girder supporting a column dead load
by a sufficiently thick cover. Moreover, the cover must be thick of PDL at midspan, is obtained as
enough to ensure sufficient bond and to avoid spalling of concrete. pffiffiffiffiffiffiffiffiffiffiffiffi
The minimum specified cover for cast-in-place prestressed concrete h ¼ 52 3 PDL L kN; m ð5Þ
is given as 40 mm (1.5 in.) in Table 20.5.1.3.2 of ACI 318-19 (ACI
2019). The minimum spacing between the tendons should be large As is understood from the above, the coefficient in Eq. (5)
enough to provide clearance for proper concrete placement around changes depending on the value of the average effective compres-
the tendons. According to R25.6.2.1 of ACI 318R-19 (ACI 2019), sive stress, the location of the transferred column along the span,
it is suggested that the clear distance between parallel ducts is at percentage of the column dead load to be balanced, and the ratio of
least 1.33 times the nominal maximum size of aggregate but not width to height of the girder. This coefficient which is notated as ah
less than 25 mm (1 in.). Larger spacings based on the diameter in Eq. (6), can be tabulated.
of ducts are recommended in AASHTO (2017) and other technical pffiffiffiffiffiffiffiffiffiffiffiffi
guidance documents (Rogowsky and Marti 1991). Based on the h ¼ ah 3 PDL L ð6Þ
cover and spacing requirements of the ducts, it is suggested that
Table 1 gives values for ah in Eq. (6) considering different levels
the eccentricity of tendons at midspan can be approximately taken
of balanced column dead load percentage and width-to-height ra-
as 0.35 h for most design cases where h is the total height of the
tios. For all cases, tendon eccentricity at the midspan, ep;mid , is as-
transfer girder. It is believed that this approximation is conservative
sumed to be 0.35 h; an average effective prestress of 5 MPa is
and reasonable from the standpoint of practical design.
applied, and the column load is assumed to be applied at the mid-
Height of Transfer Girder, h span. Using the approach explained above, the ah value can easily
Herein, the load balancing concept is used to derive a simple ex- be calculated to meet the specific needs of any project, such as the
pression for the height of transfer girders. The balancing moment percentage of the balanced column load, average effective pre-
due to prestressing is the sum of the primary moment and the sec- stress, or location of the transferred column in the span.
ondary moment that occurs only in statically indeterminate systems In continuous beams, the tendon profile is effectively used with
resulting from restraint of deformations induced by prestressing. high points over the intermediate supports, and the moments gen-
The primary moment does not depend on the member’s support erated by the external loading will be less in statically indetermi-
conditions and applied loading (Aalami 1990). For a simply sup- nant systems. However, secondary moments, which occur in the
ported beam with a profiled tendon, the balanced moment at mid- opposite direction of primary moments at spans, lower the balanced
span is calculated as follows:

Table 1. ah values considering different levels of balanced load percentage


M bal ¼ Peff ep;mid ð1Þ
and width-to-height ratios for an average compression value of 5 MPa
Balanced dead
where ep;mid = eccentricity of the tendon at midspan; and Peff = load (%) bw ¼ 0.5h bw ¼ 0.8h bw ¼ h bw ¼ 1.2h
effective prestressing force after all losses. Effective prestressing
force (Peff ) can be calculated by simply multiplying the cross- 80 61 52 49 46
sectional area by the effective compressive stress value, fpc , as 100 66 56 52 49
120 70 60 56 52
follows:

© ASCE 04020036-3 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2020, 25(4): 04020036


Table 2. ah values for multispan transfer girders considering an average compression value of 5 MPa
Applied moment due to Balanced moment due to prestressing
Number of spans Span type column dead load at midspan at midspan Mprimary þ Msecondary ah
2 Exterior 0.156PDL L −Peff e þ 0.15Peff e 47.2
3 Exterior 0.175PDL L −Peff e þ 0.12Peff e 48.4
Interior 0.100PDL L −Peff e þ 0.24Peff e 42.2
4 Exterior 0.170PDL L −Peff e þ 0.13Peff e 48.1
Interior 0.116PDL L −Peff e þ 0.21Peff e 43.8

moments. Table 2 gives the results of calculations to determine the must be controlled with conventional steel reinforcement. In that case,
height of multispan transfer girders using the same approach. For camber calculations may not be correct because the concrete is
Downloaded from ascelibrary.org by CORNELL UNIV LIBRARIES on 09/10/20. Copyright ASCE. For personal use only; all rights reserved.

all girders, tendon eccentricity at the midspan, ep;mid , is assumed to cracked. If exact deflection calculations are required, then the section
be 0.35 h; an average effective prestress of 5 MPa is applied, and should be assumed as a cracked section. It is believed that the same
the girder width to height ratio is taken as 1. The girders have equal expression can still be used to determine a preliminary girder depth.
span lengths with a point load acting at each midspan. The midspan If stage prestressing is an option, then the loading and construc-
moment for the exterior and first interior span of continuous beams, tion history must be contemplated before developing a safe design
along with the primary and secondary moments generated by pre- and detailing of transfer girders. In their engineering report,
stressing at the same section, are given in Table 2. The secondary Rogowsky and Marti (1991) noted that, “A satisfactory design is
moments generated by prestressing in statically indeterminate sys- possible if one examines what can go wrong during the construction
tems are calculated by the method given in Collins and Mitchell and use of a structure, along with the resulting consequences.” It is
(1997). As seen from Table 2, governing ah values are those cal- preferable to grout ducts once stressed; however, in stage prestress-
culated for exterior spans in multispan girders with equal spans ing, grouting of ducts is usually carried out after all stressing stages
under equal point loads and for a four-span continuous girder are completed. If the ducts are grouted at the end of the final stage,
ah value in Eq. (6) is equal to 48.1, which is only about 10% less the tendons will be temporarily unbonded, and this must be taken
than that of a simply supported girder as calculated in Eq. (5). into account when detailing conventional steel reinforcement. At
Therefore, instead of performing complicated secondary moment the end of a stage, before the last prestressing takes place, the trans-
calculations, the same expression can be used to calculate a fer girder would be supporting the weight of several floors, and the
conservative value for the required height of a continuous transfer tendons would still be unbonded because stressing operations are
girder with the same loading and span length. not completed. Transfer girders are instrumental to the integrity of
the whole structure because the failure of the girder may cause
progressive collapse of the building. Therefore, it is prudent to
Stage Prestressing design the transfer girder reinforcement such that the ultimate re-
At the initial stage when the prestressing force is applied through sistance provided by only nonprestressed bonded steel reinforce-
tensioning of strands, the prestressing force is at its highest value, ment is sufficient to support the self-weight of floors existing at
and the strength of young concrete is lower than the specified de- the beginning of the final stage before the rest of the building is
sign strength. Large concentrated loads on transfer girders require constructed.
high prestressing forces to be applied, which may result in exces- The first step, in the design of stages, would be to choose the
sive cracking and crushing in the young concrete. Therefore, it is total effective prestressing force to be applied such that the stress
possible to damage a member during stressing operation, if stresses limits at the final stage are satisfied. Stress limits for tensile stresses
in young concrete exceed the tensile strength of concrete. Another in the concrete are given in Chapter 24.5 of ACI 318-19 (ACI
challenge in the construction of posttensioned transfer girders is 2019). Flexural stresses are calculated assuming uncracked section
that because the number of floors to be transferred is not there properties or fully cracked conditions, whichever is appropriate ac-
at the initial stage, excessive cambering due to large prestressing cording to Table R24.5.2.1. Compressive stresses under sustained
forces may occur. This can be prevented by applying stage post- loads should also be checked and limited to 0.45f c0 to avoid creep
tensioning (Slater 1975). In this method, the prestressing force is effects (Balázs et al. 2013).
chosen to balance the weight of several floors, such that these floors The initial jacking force is based on the required long-term ef-
are constructed without exceeding the code stress limits in the con- fective stress and includes all long-term prestress losses. Therefore,
crete, and the tendons are stressed gradually at several stages as the the initial prestressing force is usually 15–20% higher than the re-
building construction progresses. This process of stage posttension- quired effective force at a certain stage (Kelley 2000). When check-
ing is repeated until the structure is completed. Elastic behavior is ing concrete stresses at the end of each intermediate stage, it is
ensured by limiting the concrete stresses to the values suggested in suggested that a construction live load of 1 kPa (20 psf) as specified
relevant design codes at each stage, and the principle of superpo- in ASCE/SEI 37-14 (ASCE 2019), is considered in the calculation
sition can then be used. of applied loads.
By stage prestressing, the stresses can be controlled; however,
construction and operational issues may demand the stressing oper-
ations to end as early as possible. Grouting of tendons is usually per- Design Example
formed when all the prestressing operations end; therefore, specific
measures should be taken to prevent water ingression into the ducts.
Preliminary Sizing
This may not be desirable because there is always a risk of water
ingression. If lower stories are planned to be occupied sooner, no A posttensioned girder, with a span length of 12 m, is required to
major construction work can continue; therefore, stressing should support a 650 × 650 mm column at midspan. The column is 28
be finished earlier. In such cases, top cracking as a result of excessive stories high and does not extend below the second story of the
cambering due to large prestressing forces may be inevitable and building, which is assigned to SDC A. The total dead and live loads

© ASCE 04020036-4 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2020, 25(4): 04020036


to be supported after the completion of the building is PDL ¼
6,000 kN and PLL ¼ 2,000 kN, respectively. Because the live load
is not so high compared with the dead load, the design decision is to
balance only 80% of the dead load. Assuming an effective prestress
of 5 MPa, for a section where bw ¼ h, the ah value to calculate a h=2000
x
preliminary size for this member can be taken from Table 1 as
ah ¼ 49, and the height of the girder is determined as ep = 760
pffiffiffiffiffiffiffiffiffiffiffiffi p
3
ffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffiffi
h ¼ 49 3 PDL L ¼ 49 6000 × 12 ¼ 2038 mm ð7Þ

Based on this preliminary calculation, the cross-sectional dimen-


clear cover to tendons=75
sions of the girder are chosen as bw ¼ h ¼ 2,000 mm. A starting
value for Peff can be calculated by choosing an effective prestress
Downloaded from ascelibrary.org by CORNELL UNIV LIBRARIES on 09/10/20. Copyright ASCE. For personal use only; all rights reserved.

bw=2000
value equal to the one considered as one of the design choices when
determining the preliminary depth of the girder; thus, Peff is calcu-
lated as ð5 MPaÞð2 mÞ2 ¼ 20,000 kN. This effective prestressing Fig. 3. Transfer girder section at midspan showing only tendon
force can be achieved by using six tendons, with a parabolic profile arrangement.
that consists of 23–15 mm low-relaxation strands with a total
cross-sectional area of 19,320 mm2 and a duct diameter of
120 mm. The ultimate tensile strength of the prestressing steel is eccentricity was approximated as 0.35h ¼ 700 mm; therefore,
f pu ¼ 1,860 MPa. Assuming that the effective stress in the strands the prestressing force can be slightly lowered because the actual
after prestress losses is fse ¼ 1,070 MPa (PCI Committee on eccentricity of the tendons increased. Accordingly, the number
Prestress Losses 1975), the final effective prestressing force can of strands in each duct is lowered to 22, which results in an effective
be calculated as Peff ¼ 20,670 kN. The compressive strength of force of Peff ¼ 19,770 kN (Fig. 4). With this arrangement, Table 3
concrete is specified as f c0 ¼ 40 MPa. Because the supporting sys- gives the concrete stresses that are calculated at midspan section for
tem is statically determinate, secondary moments due to prestressing service loads and sustained loads assuming a 25% sustained live
do not occur. At the service stage, the total moment at midspan due to load. It is noted that because the load from the transferred column
the self-weight of the beam, loads on the second floor and loads from at the midspan is substantial, the critical section for stresses is al-
the transferred column is equal to M service ¼ 26,440 kN-m. ways at the midspan. As documented in Table 3, stresses due to
For this preliminary cross section with an eccentricity of ep ¼ total and sustained loading are below specified limits. The deflec-
0.35 · 2,000 ¼ 700 mm at midspan and a prestressing force of tion under the transferred column can be calculated assuming un-
Peff ¼ 20,670 kN, stresses at the final service stage, can be calcu- cracked section properties according to Table R24.5.2.1 of ACI
lated considering uncracked concrete section as below: 318-19 (ACI 2019). If 25% of the live load is assumed to be sus-
Peff Peff ep Mservice tained with a creep coefficient of 2, then the long-term total deflec-
f¼  ∓ y tion is calculated as 3.75 mm, which is only about 1/3,200 of the
Ac Ic Ic
span length.
−20670 × 103 20670 × 103 × 700 In the example above, if the engineer chooses to consider lower
f top ¼ þ × 1000
2000 × 2000 2000×20003
12
values for the height of the girder, the required average prestressing
to satisfy final service stress limits will increase accordingly. Aver-
26440 × 106 age prestressing, fpc , for h ¼ bw ¼ 1,900 mm is 6 MPa, with a
− 2000×20003
× 1000
12 maximum tensile stress value of 3.61 MPa at the final service stage,
f top ¼ −5.17 þ 10.85 − 19.83 whereas f pc , for h ¼ bw ¼ 1,800 mm should be increased to
7.2 MPa to satisfy the tensile stress limit at the final service stage.
¼ −14.15 MPa < 0.6ð40Þ ¼ −24 MPa The engineer must evaluate the resulting restraining due to the in-
fbot ¼ −5.17 − 10.85 þ 19.83 creased average prestressing if the girder height is taken less than
calculated by the proposed expression.
7.5 pffiffiffiffiffi
¼ 3.81 MPa < 40 ¼ 3.95 MPa ð8Þ Table 4 gives the results of preliminary height calculations for
12 two additional design cases: one with increased loading and one
As seen from the above calculations, stresses at the final stage with a longer span length. The same design decisions are made;
are below specified stress limits; therefore, the design will proceed therefore, an ah value to determine girder height is taken as 49.
with six ducts containing 23 strands each with a cross-sectional The first column of Table 4 summarizes the design parameters
area of 3,220 mm2 and a duct diameter of 120 mm which results and gives the girder height calculated by the proposed expression.
in a total prestressing steel area of Aps ¼ 19,320 mm2 for the If a girder height close to the calculated height is used in the design,
girder. Assuming that the effective tensile stress in the strands will then an effective prestress of 5 MPa is enough to satisfy the tensile
be f se ¼ 1,070 MPa after long-term losses occur, the final pre- stress limit at the final service stage. In the second row of each
stressing force Peff is calculated as 20,670 kN. As shown in Fig. 3, design case, the girder height is taken less than the calculated height
the clear cover is taken as 75 mm to the bottom of ducts, and the and as a result, the effective prestressing is increased to satisfy the
distance between the ducts is assumed to be equal to 50 mm, which stress limits. As determined from Table 4, the proposed method
are both acceptable values according to ACI 318-19. The tendon gives reasonable results for different design parameters.
eccentricity at the midspan can then be calculated as ep;mid ¼
2,000=2 − 240 ¼ 760 mm assuming a distance of Δe ¼ 20 mm
Application of Stage Prestressing
between the center of gravity of strands and duct centerline because
the strands will be pulled towards the inside wall of the curved duct It is assumed that the posttensioning will be completed in
during stressing. Recall that for preliminary calculations, tendon two stages, thus the first stressing takes place after the girder is

© ASCE 04020036-5 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2020, 25(4): 04020036


Roof

14 more stories transferred


29th floor

16th floor 16th floor

14 stories transferred
Downloaded from ascelibrary.org by CORNELL UNIV LIBRARIES on 09/10/20. Copyright ASCE. For personal use only; all rights reserved.

2nd floor

Stage1-initial Stage2-final
Stage Stage1-final Stage2-initial
INITIAL STAGE FINAL STAGE

Total P1-i =11870 kN P1-f =9890 kN P2-i =21760 kN Peff =19770 kN


Prestressing
force

Applied SW of transfer girder SW of girder and 14 SW of girder and 14 SW of structure above,


Loads and slab floors, floors, no construction SDL and LL on all floors
construction live load load during stressing.
PSW =2500 kN PSW =2500 kN PDL = 6000 kN
PCLL =500 kN PLL = 2000 kN
M=2120 kN-m M=11230 kN-m M=9620 kN-m M=26440 kN-m

Concrete
strength
30 MPa 40 MPa 40 MPa 40 MPa

ftop= 2.21 MPa ftop= -5.26 MPa ftop= -0.25 MPa ftop= -13.5 MPa
Total stress
fbot= -8.14 MPa fbot= 0.31 MPa fbot= -10.6 MPa fbot= 3.62 MPa

3 0.6(40) = -24 MPa 0.6(40) = -24 MPa


Permissable 30 = 1.36 MPa 0.6(40) = -24 MPa
12 7.5 7.5
stresses 0.6(30) = -18 MPa 40 = 3.95 MPa 0.6(40) = -24 MPa 40 = 3.95 MPa
12 12

Fig. 4. Application of stage prestressing.

cast provided that concrete reaches a compressive strength of stage. It is assumed that only the self-weight of the structure is
f ci0 ¼ 30 MPa, and the second stressing is carried out when the present during construction because finishes cannot be completed
building reaches the 16th floor (Fig. 4). The prestressing force ap- before the stressing operations end. During construction, a live load
plied at the first stage is chosen to transfer the first 14 floors is of 1 kPa on each floor is considered. However, at the time of
9,890 kN. At the second stage, an additional effective prestressing stressing, it is assumed that the construction live load within the
force of 9,890 kN will be applied to transfer the remaining 14 vicinity of the transferred column is removed. The actual live load
floors. In this example, for concrete stress checks, initial jacking is used to check stresses at the final service stage. Fig. 4 also gives
stress is taken as 20% greater than the effective prestressing concrete stresses at each stressing stage. The stresses are calculated
force, 1.2 × 1,070 ¼ 1,280 MPa. This initial stress value is less assuming that the section is not cracked and using gross section
than the limit stress in posttensioning tendons immediately after properties. As seen from Fig. 4, stresses at each stage are below
tendon anchorage, which is given as 0.7fpu ¼ 1,302 MPa in specified limits, and both the section size and prestressing satisfy
Table 20.3.2.5.1 of ACI 318-19 (ACI 2019). service stage requirements except at the first initial stage where the
Fig. 4 shows how the stage prestressing is applied along with top stress exceeds the stress limit. At the initial service stage, crack-
the loading on structure and applied prestressing force at each ing in the top concrete fibers is generally acceptable and can be

© ASCE 04020036-6 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2020, 25(4): 04020036


Table 3. Stresses at midspan due to total and sustained loads
Due to total load Due to sustained loads
Stresses f bot (MPa) ftop (MPa) f bot (MPa) f top (MPa)
Peff =Ag −4.94 −4.94 −4.94 −4.94
Peff ðep Þ=S −11.27 11.27 −11.27 11.27
M ext =S 19.83 −19.83 16.33 −16.33
Total stress 3.62 −13.5 0.12 −10
7.5 pffiffiffiffiffi 7.5 pffiffiffiffiffi
Permissible stresses 40 ¼ 3.95 0.6ð40Þ ¼ −24 40 ¼ 3.95 0.45ð40Þ ¼ −18
12 O.K. O.K. 12 O.K. O.K.
Downloaded from ascelibrary.org by CORNELL UNIV LIBRARIES on 09/10/20. Copyright ASCE. For personal use only; all rights reserved.

Table 4. Results for different design cases fpc = compressive stress at the centroid of the section due to
Design parameters Transfer Applied Tensile stress prestress after allowance for all prestress losses;
calculated girder height prestressing check at final fpu = specified tensile strength of prestressing reinforcement;
height (mm) f pc (MPa) stage (MPa) fse = effective tensile stress in prestressing reinforcement after
L ¼ 12 m 2,200 5 3.71 < 3.95 all prestress losses;
PDL ¼ 8,000 kN h = overall height of member;
PLL ¼ 3,000 kN 2,100 6 3.48 < 3.95 I c = Inertia moment of uncracked section;
h ¼ 2,240 mm Peff = effective prestressing force after all losses;
L ¼ 14 m 2,100 5 3.68 < 3.95 PCLL = total live load due to construction loads;
PDL ¼ 6,000 kN PDL = total dead load due to self-weight and superimposed loads;
PLL ¼ 2,000 kN 2,000 6 3.74 < 3.95 PLL = total live load; and
h ¼ 2,140 mm
PSW = total dead load due to only self-weight.

controlled by providing conventional steel reinforcement in the pre-


tensioned compressive zone. References
Aalami, B. O. 1990. “Load balancing: A comprehensive solution to
Conclusions post-tensioning.” ACI Struct. J. 87 (6): 662–670. https://doi.org/10
.14359/2970.
This paper proposes a simple expression to quickly calculate the pre- Aalami, B. O., and J. D. Jurgens. 2003. “Guidelines for the design of
liminary depth of a girder, which transfers a column and as Lin and post-tensioned floors.” Concr. Int. 25 (3): 77–83.
Scordelis mention in their (Lin and Scordelis 1953) paper, “ : : : thus AASHTO. 2017. AASHTO LRFD bridge design specifications and com-
enhance the interest and application of prestressed concrete struc- mentary. 8th ed. Washington, DC: AASHTO.
ACI (American Concrete Institute). 2019. Building code requirements for
tures.” The proposed simple expression gives reasonable values
reinforced concrete and commentary. ACI 318-19. Farmington Hills,
for preliminary sizing of simply supported single span posttensioned
MI: ACI.
transfer girders. Although the expression is derived to determine the
ASCE. 2019. Design loads on structures during construction ASCE/SEI
required height of a simply supported posttensioned transfer girder, 37-14. Reston, VA: ASCE.
the same expression can be used for continuous girders to calculate Balázs, G. L., et al. 2013. “Design for SLS according to fib Model Code
an initial value. By using the approach given in this paper, the pre- 2010.” Struct. Concr. 14 (2): 99–123. https://doi.org/10.1002/suco
liminary height of transfer girders can easily be calculated to meet the .201200060.
specific needs of any project, and the engineer can control and im- Collins, M. P., and D. Mitchell. 1997. Prestressed concrete structures.
pose design decisions for the preliminary design of transfer girders. It Toronto: Response Publications.
is noted that the design of transfer girders depends on many param- CSA (Canadian Standards Association). 2014. Design of concrete struc-
eters, and the proposed approach is suggested only to determine a tures. CSA A23.3-14. Toronto: CSA.
preliminary section for a more detailed design. Kelley, G. S. 2000. Prestress losses in post-tensioned structures. PTI Tech-
nical Note #10. Phoenix, AZ: Post Tensioning Institute.
Lin, T. Y. 1961. “A new concept for prestressed concrete.” PCI J. 6 (4):
36–52.
Data Availability Statement
Lin, T. Y. 1963. “Load balancing method for design and analysis of pre-
No data, models, or code were generated or used during the study. stressed concrete structures.” Am. Concr. Inst. 60 (6): 719–742. https://
doi.org/10.14359/7874.
Lin, T. Y., and A. C. Scordelis. 1953. “Selection and design of prestressed
Notation concrete beam sections.” Am. Concr. Inst. 50 (11): 209–224. https://doi
.org/0.14359/11757.
The following symbols are used in this paper: Nawy, E. G. 2006. Prestressed concrete: A fundamental approach. 5th ed.
Ac = area of uncracked section; Upper Saddle River, NJ: Prentice Hall.
PCI Committee on Prestress Losses. 1975. “Recommendations for estimat-
Aps = area of prestressed tension reinforcement;
ing prestress losses.” PCI J. 18 (8): 43–75.
bw = web width of member; Rogowsky, D. M., and P. Marti. 1991. Detailing for post-tensioned: VSL
ep = eccentricity of prestressing tendons, distance from centroid report series. Bern, Switzerland: VSL International Limited.
of prestressing steel to the centroid of gross cross section; Slater, W. M. 1975. “Stage post-tensioning: A versatile and economic con-
fc0 = specified compressive strength of concrete; struction technique.” PCI J. 20 (1): 14–27.

© ASCE 04020036-7 Pract. Period. Struct. Des. Constr.

Pract. Period. Struct. Des. Constr., 2020, 25(4): 04020036

You might also like