Professional Documents
Culture Documents
2020
1 2
21
21
0
9
9
9 e,
g, 6
1 7 6
c, 5
15
15
9
4
4
a, 4 9 15
0 15
4 d, 4
0 2
4 4
4 8
11 15
3 4
1
28.05.2020
21
21
0 Development projects and in projects where we
9
9
9 e,
g, 6
1 7 6 have a lot of uncertainties.
c, 5
15
15
9
4
4
a, 4 9 15
0 15
4 d, 4
2
0
4 4 4
8
11 15
5 6
ta tm tb
5 7 9
7 8
2
28.05.2020
PERT PERT
n How can we find standard deviation for any activity? n What is the probability of completion of the Network
Question within 24 days and 26 days?
n You have Z Table.
9 10
PERT PERT
§ 3s approach to probabilistic estimates
Z: The number of standard deviations of a § in PM we use 3s
normal distribution (the standard normal
deviate) § in aerospace engineering, they use 6 s
D: The desired project completion time
11 12
3
28.05.2020
13 14
21
21
0
9
9
9 e,
§ te for Activity C is 5.
g, 6
1 7 6
c, 5
15
15
9
4
4
§ te for Activity D is 4. a, 4 9 15
0 15
§ te for Activity E is 6. 4
2
d, 4
0
4 4
§ te for Activity F is 1. 4 8
§ te for Activity G is 6. 11 15
15 16
4
28.05.2020
21
21
0 n Question 2) What is the completion time
9
9
9 e,
g, 6
1 7 6
c, 5
corresponding to 95% probability?
15
15
9
4
4
a, 4 9 15
0 15
4 d, 4
2
0
4 4 4
8
11 15
17 18
PERT
Calculations PERT
n Calculate s2 for each Activity. n Question 1) What isthe probability of the
completion of the project in 23 days?
s2 for Activity A is 1, s2 for Activity E is 0.44,
s2 for Activity B is 0, s2 for Activity F is 1,
s2 for Activity C is 1, s2 for Activity G is 1.
Z=1.078 P = 85.9%
s 2
for Activity D is 0.11,
Check Z table for probability value.
19 20
5
28.05.2020
PERT PERT
n Question 1) What isthe probability of the n Question 2) What is the completion time
completion of the project in 23 days? corresponding to 95% probability?
21 22
0 86% probability.
9
9
9 e,
g, 6
1 7 6
c, 5
9
4
4
a, 4 15
9
15
50% probability.
0 4 d, 4
2 n This is how you report your manager about the
0
4 4 4
8 completion times of the project.
11 15
23 24
6
28.05.2020
PERT
n If there are more than 1 critical path, you do
separate calculations for each path and take
the one with the lower probability into
consideration.
n This is how you report your manager about the
completion times of the project.
25