Professional Documents
Culture Documents
2020
Scheduling defined.
ü The conversion of a project action plan into
Scheduling an operating timetable
1 2
Why to schedule?
• Costs and Time:
Some Benefits of
Project costs are closely related to project Successful Scheduling
duration time timetable schedule • Illustrates interdependence of all tasks
• Identifies times when resources must be
available
• Facilitates communication throughout the project
• Determines critical activities/critical path
• Affects client expectations through
establishment of activities, milestones, and
completion dates
3 4
1
8.05.2020
5 6
7 8
2
8.05.2020
9 10
11 12
3
8.05.2020
13 14
15 16
4
8.05.2020
17 18
19 20
5
8.05.2020
Notes
Making a Gantt chart
• Step 3 – add dependencies (which tasks
cannot start before another task finishes)
21 22
6
8.05.2020
• The amount of time a task can be extended before it Critical tasks, by definition, can have NO slack.
affects other tasks is called slack (or float).
• Task 6 can take an extra day before it affects the Tip:
project’s end date, and Task 8 can take two days so
If ever asked, Can task X’s duration be changed
Task 6 has 1 and Task 8 has 2 day’s slack.
without affecting the end date of the project?, if it
is a critical task the answer is always NO!
25 26
Network Schedules
Gantt Chart Builder System (Excel) 1.6
• There are several network scheduling techniques, all of
them based on the calculation of the length (in time) of
critical link of activities or ‘Critical Path.’ This procedure
is known as the Critical Path Method (CPM).
27 28
7
8.05.2020
29 30
31 32
8
8.05.2020
33 34
• Project: A planned undertaking that involves the § It is graphic depiction of the project.
performance of work.
§ Tasks that make up the project and the
• Task or Activity: Part of the work that makes up the logical relationships between them are
project. It needs to be defined (specifying the work that
encompasses) and its attributes (e.g. duration) need to represented by symbols.
be assigned.
• Event: Point in time at which something happens. For § Two types of logic diagrams:
example, the first event of a project is that the project
starts. The last event is that the project ends. Ø AOA or Arrow Diagrams
Ø AON or Precedence Diagrams
35 36
9
8.05.2020
37 38
Logical Relationships
Logical Relationships
(for both AOA and AON Diagrams) § Precedent Relationship:
If task A is precedent to task B, then at least part of task A must be
§ Precedence: Those activities that must be completed before a completed before task B can start.
given activity can start are called precedecessor activities.
(öncelikli/önceki aktiviteler)
Ø Example:
breaking an egg’s shell is precedent to frying the egg.
§ Succession: Those activities that can not start until
precedecessors completed are called successor activities.
(takip eden aktiviteler) following activities
39 40
10
8.05.2020
CPM Objective
• Determination of the critical path:
the minimum time for a project
41 42
43 44
11
8.05.2020
CPM Calculations
Backward Pass -Intuition
45 46
Slack or Float
47 48
12
8.05.2020
49 50
51 52
13
8.05.2020
53 54
55 56
14
8.05.2020
Convention:
Convention:
J-Node number Arrow point right, up
greater than or down, but not left
I-Node number
57 58
Convention:
Tasks have § Used to:
unique pair of Ø Split tasks to assure unique activity designation
node numbers Ø Show proper logic (as logical constraints)
Ø Change activity predecessors
Ø Create single start and ending activities.
59 60
15
8.05.2020
61 62
63 64
16
8.05.2020
65 66
67 68
17
8.05.2020
Answer Q (Cont’d)
The path from start to end that takes the longest time is
<A> 1,2,4,5.
• Can't be <B> because tasks 1 and 3 are concurrent.
In the table above how many tasks can run
• Can't be <C> because tasks 5 and 6 are concurrent.
over time without affecting the completion
• Can't be <D> because task 6 does not lead to the
date? 1,2,3 or 4?
longest possible path.
69 70
Question Floats
71 72
18
8.05.2020
AOA Calculations
73 74
AN AOA PROBLEM
• 1: Which tasks are on the critical path?
solved by memory • 2: What is the slack time for tasks C, D and G?
• 3: Task C is delayed by one day. What impact would this have on the
completion date of the project? Why?
• 4: Task A will be delayed by 2 days because some equipment has
arrived late. If the project manager wants to finish the project on time
he will need to shorten the duration of one or more of the tasks. How
can he achieve this?
• 5: The project manager reduces the durations of tasks D and F by one
day each. How will this affect the finishing date of the project?
75 76
19
8.05.2020
TASKS C and D…
1: Which tasks are on the critical path? Path C,E = 5 days, Path D,F = 6 days
Difference (slack) = 1 day for tasks C or E
compared to D,F
Possible paths:
A,B,C,E,I = 2+3+1+4+3 = 13 days
TASK G…
Path B,C,E = 8 days. Path B, D, F = 9 days
A,B,D,F,I = 2+3+3+3+3 = 14 days
Path G, H = 7 days.
A,G,H,I = 2+2+5+3 = 12 days So G & H have 2 days’ slack between them.
B,C or E have 1 day’s slack.
ANSWER: A,B,D,F,I B,D,F have no slack.
77 78
79 80
20
8.05.2020
A Family Routine
• 5: The project manager decides to reduce the time needed for tasks
D and F by one day each. How effective will this reduction be in
achieving his aim of reducing the finish time for the project?
81 82
Questions
Q1
Q1. What tasks are on the critical path? What is the critical path?
Q2. What is the minimum time it would take for the family to reach the Path 1 = 5+5+40+15+15+5+25 = 110 min
footy game after getting the alarm goes off? Path 2 = 5+5+30+15+5+25 = 85
Q3. How much more time could dad walk the dog before eating Path 3 = 5+5+10+15+15+5+25 = 80
breakfast got delayed? (Note: Mum insists the entire family eats
together)
Q4. What is this amount of time called? The critical path is the longest path : path 1
Q5. If mum skipped her 40 minutes shower, how much earlier would
they get to the game?
83 84
21
8.05.2020
Q2 Q3 & 4
How much more times could dad walk the dog before
What is the minimum time it would take for the eating breakfast without no delay caused?
family to reach the son’s school after the alarm
starts ringing? 30 minutes…
Shower + Prep Brekky = 55 min vs
Walk Dog + Dad Shower = 25 min … 30 min diff
The duration of the critical tasks… 110 minutes
What is this amount of time called?
+ driving minutes
Slack time (or float)
85 86
Q5
87
22