You are on page 1of 23

Check List-Industrial Project

For submission of Environmental clearance application


[Appraisal cases]
Provide authenticated (with stamp and signatures) hard copy of this check list during submission of
had copy of ToR/EC Application
Sr Particular Tick marks Page no of Application
no. as applicable
1 EIA report as per the ToR granted by SEIAA No(√) -
and as per the generic structure given I
Appendix III of EIA Notification 2006.
2 Foem-2 Application for prior Environmental No(√) -
Clearance as prescribed by MoEF & CC as per
OM detail 20/04/2018.
3 Documents related to land ownership including No (√) There is no change in existing
in EIA Report. condition
4 For 5(f) category
Project site is located within GIDC Yes(√) Attached separate sheet of the
same
If no, Compliance of Following conditions - -
 Water Consumption < 25 KLD
 Fuel Consumption < 25 MTPD
 Non-MAH Unit.
5 Contact details , Mobile No. and e-mail ID Yes(√) Details are given in page no---
included in Application
6 Format prescribed by SEAC [Salient Feature of Yes(√) Attached as 5(f) Formate
the Project] included with application.
7 General Condition applicability No(√) --
(5)Protected areas notified under the
wildlife(Protection)Act, 1972:
(6)CEPI areas
(7)Eco-Sensitive areas and
(8)Inter-state boundaries and international
boundaries: are not located within 5 km or 10
km (as the case may be0 area from the
boundaries of the proposed site.
8. Compliance status of existing project(in case of No (√) --
expansion) include in EIA report i.e
 Compliance report from MoEF & CC or
GPCB or CPCB as per the MOEF & CC’s
circular dated 07/09/2017.
9 Violation of EIA Notification 2006 (Yes or No) No(√) -
Product profile with CAS no. /Cl no. Yes(√) Given in 5(f) Format
10 Raw Material details and manufacturing Yes(√) Given in 5(f) Format
process of all products with CAS no. / Cl no.
11 Spent Acids (H2SO4,HCL etc.) generation. Yes(√) Given in 5(f) Format
12 Yes, it is considered as Haz. Waste? Yes Given in 5(f) Format

1|Page
13  Source of water, Water balance Yes(√) GIDC, permission letter is
included in EIA report. attached, Water balance diagram
is Given in 5(f) Format
 Permission letter to obtain fresh water. Yes(√) Attached with 5(f) Format
 Waste water management, Membership Yes(√) Attached with 5(f) Format
certificate of common facility (CETP,
CMEE, CSD etc.)
 Permission letter for discharge of waste Yes(√) Attached with 5(f) Format
water etc.
14 Flue gas & process gas emission details Yes(√) Given in 5(f) Format
included in Form-1.
15 Hazardous waste generation and its Yes(√) Given in 5(f) Format
management as per the HW Rules 2016
included in Form-1.
16 Spent Solvent generation. Yes(√) Given in 5(f) Format
17 If, Yes Management of spent solvent included Yes(√) Given in 5(f) Format
in application?
18 Details of Public hearing and time bound No(√) Not Applicable
compliance with details of budgetary provision
included in EIA report. (In case of public
hearing is applicable).
19 Documents regarding accreditation of EIA No(√) --
Consultant are included in EIA report.
20 Undertaking of project proponent and EIA No(√) --
Consultant regarding EIA report are included
in EIA report.
21 Environmental Management Plan (EMP) No(√) --
report and details of financial outlay & year
wise break up is included in EIA report.
22 Green belt details with budgetary outlay No(√) --
included in EIA Report.
23 Declaration by experts (Name, qualification, No(√) --
area of work, designation etc.) contributing to
the EIA report is included.
24 Compliance of MoEFCC’s OM dated No(√) --
01/05/2018 regarding ‘Corporate Environment
Responsibilities (CER)’.
Above details are true to the best of my knowledge and I am abided to respect the decision of the
SEIAA/SEAC if above information stands wrong in the future and also agree to initiated the legal
proceedings against my project.
Name & designation of the Applicant: Mr. Ashavin Patel.

Stamp &Signature of Applicant:


Date:-23-05-2019

2|Page
FORM – 1

APPLICATION OF EC-AMENDMENT

FOR
MANUFACTURING OF SYNTHETIC
ORGANIC CHEMICALS
By

M/s JAYCHEM INDUSTRIES


Location: Plot No. 6713-14/1, GIDC Estate,
Ankleshwar, Dist.: Bharuch, Gujarat.

Submitted To:
State Level Expert Appraisal Committee
[SEAC] – Gujarat.

Submitted By:

M/s JAYCHEM INDUSTRIES


Location: Plot No. 6713-14/1, GIDC Estate,
Ankleshwar, Dist.: Bharuch, Gujarat.

3|Page
BASIC INFORMATION
S. Item Details
No.

1 Name of the project/s M/s Jaychem Industries


2 S. No. in the schedule 5(f) of the Schedule I of EIA notification 2006 & its
Amendment
3 Proposed capacity / area / length / Total Production capacity:-115 MT/Month
tonnage to be handled/command area/ Total Plot Area:-1520.0 sq. M
number of wells to be drilled
4 New /Expansion / Modernization EC-Amendment Project.

5 Existing capacity /Area etc Total Production capacity:-115 MT/Month


Total Plot Area:-1520.0 sq. M
6 Category of project i.e. ‘A’ or ‘B’ “B”

7 Does it attract the general condition? If No.


yes, please specify.
8 Does it attract the specific condition? If No.
yes, please specify.
9 Location
Plot / Survey / Khasra No. Plot No. 6713-14/1, GIDC
Village Ankleshwar
Tehsil Ankleshwar
District Bharuch
State Gujarat
10 Nearest Railway Station / airport along Ankleshwar Railway Station – @ 4.0 km
with distance in Kms. Surat Airport - @ 55.0 km

11 Nearest Town, city, District Nearest City – Ankleshwar – 2.0 km


Headquarters along with distance in
Kms.
12 Village Panchayats, Zilla Parishad, Village : GIDC, Ankleshwar
Municipal Corporation , Local body Taluka : Ankleshwar
(complete postal addresses with Dist.: Bharuch.
telephone nos. to be given)
13 Name of the applicant Mr.Ashvin. F.Patel ., Partner
14 Registered Address Jaychem Industries., Plot No. 6713-14/1, G.I.D.C
Estate, Ankleshwar, District:Bharuch,Gujarat
15 Address for correspondence: Jaychem Industries.
Name Mr. Mr.Ashvin.F.Patel, Partner
Designation (Owner/Partner/CEO) Partner
Address Plot No. 6713-14/1, G.I.D.C Estate, Ankleshwar,
District:Bharuch,Gujarat
Pin code 393 002.
E-Mail jaychemind@gmail.com
Telephone No 02646-224192/226389
Fax No. --

4|Page
16 Details of Alternative Site examined, if No
any Location of these site should be
shown on a topo sheet.
17 Interlinked Projects Not applicable
18 Whether separate application of Not applicable
interlinked project has been submitted?
19 If yes, date of submission Not applicable
20 If no, reason Not applicable
21 Whether the proposal involves Not applicable
approval/clearance under : if yes,
details of the same and their status to
be given
1. The Forest (Conservation) Act,
1980
2. The Wildlife (Protection) Act,
1986
3. The CRZ Notification, 1991
22 Whether there is any government No
order/policy/relevant/relating to the
site?
23 Forest land involved(hectares) No
24 Whether there is any litigation pending No
against the project and/or land in
which the project is proposed to be set
up?
(a)Name of the court
(b) Case No.
(c)Order/direction of the court, if any
and its relevance with the proposed
project.

5|Page
Sr. Information/Checklist Yes / No Details thereof (with
No. confirmation approximate quantities /rates,
wherever possible) with
source of information data
1.1 Permanent or temporary change in No The project is in the notified GIDC
land use, land cover or topography Estate of Ankleshwar, in a land
including increase in intensity of area of 1520 Sq.mt. Hence, there
land use (with respect to local land will not be any change in land use
use plan) of the proposed project.
1.2 Clearance of existing land, No Not required.
vegetation and buildings?
1.3 Creation of new land uses? No The project is in the notified GIDC
Estate of Ankleshwar, in a land
area of 1520 Sq.mt. Hence, there
will not be any change in land use
of the proposed project.
1.4 Pre-construction investigations e.g. No The plant is in existence.
bore houses, soil testing?
1.5 Construction works? Yes The minor construction work for
vessel assembling, storage area,
etc. will be done.
1.6 Demolition works? No Not applicable.
1.7 Temporary sites used for No For construction, workers will be
construction works or housing of available from near by local area.
construction workers?
1.8 Above ground buildings, structures No. The plant is in existence.
or earthworks including linear
structures, cut and fill or
excavations
1.9 Underground works including No Not required.
mining or tunneling?
1.10 Reclamation works? No Not required.
1.11 Dredging? No Not applicable.
1.12 Offshore structures? No Not applicable.
1.13 Production and manufacturing No There is no change in proposed
processes? condition
1.14 Facilities for storage of goods or No There is no change in proposed
materials? condition
1.15 Facilities for treatment or disposal Yes Effluent Treatment Scheme and
of solid waste or liquid effluents?

6|Page
Machinery is attached as
Annexure B.
1.16 Facilities for long term housing of No There will not be requirement of
operational workers? long term housing of operational
workers.
1.17 New road, rail or sea traffic during No The unit being located in well-
Construction or Operation? established GIDC Estate, no new
road required.
1.18 New road, rail, air waterborne or No
other transport infrastructure
including new or altered routes and
stations, ports, airports etc?
1.19 Closure or diversion of existing No No diversion will take place.
transport routes or infrastructure
leading to changes in traffic
movements?
1.20 New or diverted transmission lines No The location of the unit is within
or pipelines? area where industrial activities
are in existence hence it is not
required.
1.21 Impoundment, damming, No The hydrology of watercourses or
culverting, realignment or other aquifers will not be affected, as it
changes to the hydrology of is to be set up within the
watercourses or aquifers? established industrial area where
industrial activities are in
existence.
1.22 Stream crossings? No There is no stream crossing.
1.23 Abstraction or transfers of water Yes The Water requirement will be
from ground or surface waters? satisfied through GIDC water
supply.
1.24 Changes in water bodies or the land No The drainage pattern will not be
surface affecting drainage or run- affected.
off?
1.25 Transport of personnel or materials No The existing infrastructure
for construction, operation or facilities will be utilized.
decommissioning?
1.26 Long-term dismantling or No Not required.
decommissioning or restoration
works?
1.27 Ongoing activity during No Not applicable.
decommissioning which could have
an impact on the environment?

7|Page
1.28 Influx of people to an area in either No The workers will be available
temporarily or permanently? from near by local area.
1.29 Introduction of alien species? No Not Applicable.
1.30 Loss of native species or genetic No Not Applicable.
diversity?
1.31 Any other actions? No --
2. Use of Natural resources for construction or operation of the Project (such as
land, water, materials or energy, especially any resources which are non-
renewable or in short supply):
2.1 Land especially undeveloped or No The proposed expansion project
agricultural land (ha) is in the notified GIDC Estate of
Ankleshwar, in a land area of
1520 Sq.mt. Hence, there will not
be any change in land use.
2.2 Water (expected source & Yes Water Consumption & Waste
competing users) unit: KLD Water Generation detail is
enclosed as Annexure-A.
2.3 Minerals (MT) No Not required.
2.4 Construction material – stone, Yes Locally available construction
aggregates, sand / soil (expected materials will be utilized for
source – MT) construction activities.
2.5 Forests and timber (source – MT) No Not required
2.6 Energy including electricity and No There is no change in proposed
fuels (source, competing users) Unit condition
: fuel (MT), energy (MW)
2.7 Any other natural resources (use No Not required.
appropriate standard units)
3. Use, storage, transport, handling or production of substances or materials, which
could be harmful to human health or the environment or raise concerns about
actual or perceived risks to human health.
3.1 Use of substances or materials, No There is no change in proposed
which are hazardous (as per MSIHC condition
rules) to human health or the
environment (flora, fauna, and
Water supplies)
3.2 Changes in occurrence of disease or No No such changes in the
affect disease vectors (e.g. insect or occurrence of diseases are
water borne diseases) anticipated.
3.3 Affect the welfare of people e.g. by No The living conditions of the
changing living conditions? people will not be affected. There
will be generation of employment

8|Page
for nearby people having positive
impact.
3.4 Vulnerable groups of people who No Not applicable.
could be affected by the project e.g.
hospital patients, children, the
elderly etc.,
3.5 Any other causes No --
4. Production of solid wastes during construction or operation or decommissioning
(MT/month) :
4.1 Spoil, overburden or mine wastes No Not Applicable.
4.2 Municipal waste (domestic and or No Not Applicable.
commercial wastes)
4.3 Hazardous wastes (as per Yes The details of Hazardous Waste
Hazardous Waste Management are given at Annexure -C. That
Rules) will be disposed off as per
prescribed guidelines.
4.4 Other industrial process wastes No --
4.5 Surplus product No Not Applicable.

4.6 Sewage sludge or other sludge from No The domestic effluent will be
effluent treatment disposed through the soak pit-
septic tank system.
4.7 Construction or demolition wastes No Demolition work is not required
and there will be minor
construction activity.
4.8 Redundant machinery or equipment No Not Applicable.
4.9 Contaminated soils or other No Not Applicable.
materials
4.10 Agricultural wastes No Not Applicable.
4.11 Other solid wastes No --
5. Release of pollutants or any hazardous, toxic or noxious substances to air
(Kg/hr)
5.1 Emissions from combustion of fossil No There is no change in proposed
fuels from stationary or mobile condition
sources
5.2 Emissions from production No There is no change in proposed
processes condition
5.3 Emissions from materials handling No If any, the fugitive emissions
including storage or transport during handling of material
within factory premises will be
controlled by taking appropriate
engineering control measures.

9|Page
5.4 Emissions from construction No There is no change in proposed
activities including plant and condition
equipment
5.5 Dust or odours from handling of No There is no change in proposed
materials including construction condition
materials, sewage and waste
5.6 Emissions from incineration of No Not applicable.
waste
5.7 Emissions from burning of waste in No Not Applicable.
open air (e.g. slash materials,
construction debris)
5.8 Emissions from any other sources No --
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
6.1 From operation of equipment e.g. No There is no change in proposed
engines, ventilation plant, crushers condition
6.2 From industrial or similar processes No Not Applicable.
6.3 From construction or demolition No ---
6.4 From blasting or piling No Not Applicable.
6.5 From construction or operational No Not Applicable.
traffic
6.6 From lighting or cooling systems No Not Applicable.
6.7 From any other sources No --
7. Risks of contamination of land or water from releases of pollutants into the
ground or into sewers, surface waters, groundwater, coastal waters or the sea:
7.1 From handling, storage, use or No There is no change in proposed
spillage of hazardous materials condition
7.2 From discharge of sewage or other No The domestic effluent will be
effluents to water or the land disposed through septic tank /
(expected mode and place of soak pit system.
discharge)
7.3 By deposition of pollutants emitted No Not Applicable.
to air into the land or into water
7.4 From any other sources No Not Applicable.
7.5 Is there a risk of long term build up No --
of pollutants in the environment
from these sources?
8. Risk of accidents during construction or operation of the Project, which could
affect human health or the environment
8.1 From explosions, spillages, fires etc No There is no change in proposed
from storage, handling, use or condition
production of hazardous substances
8.2 From any other causes No --

10 | P a g e
8.3 Could the project be affected by No Except from the Earthquake. The
natural disasters causing structural design will be in
environmental damage (e.g. floods, accordance with Seismic Zone
earthquakes, landslides, cloudburst specification.
etc)?
9. Factors which should be considered (such as consequential development)
which could lead to environmental effects or the potential for cumulative
impacts with other existing or planned activities in the locality.
9.1 Lead to development of supporting. The proposed industrial unit is to
Localities, ancillary development or be established within the
development stimulated by the No industrial estate. Hence, issues
project which could have impact on related to consequential
the environment e.g.: development will not be there.
• Supporting infrastructure (roads,
power supply, waste or waste water
treatment, etc.)
• housing development
• extractive industries
• supply industries
• other
9.2 Lead to after-use of the site, which No
could have an impact on the
environment
9.3 Set a precedent for later No
developments
9.4 Have cumulative effects due to No
proximity to other existing or
planned projects with similar effects
10. Environmental Sensitivity :
1 Areas protected under international No Not Applicable.
conventions, national or local
legislation for their ecological,
landscape, cultural or other related
value
2 Areas which are important or No Not Applicable.
sensitive for ecological reasons -
Wetlands, watercourses or other
water bodies, coastal zone,
biospheres, mountains, forests.
3 Areas used by protected, important No Not Applicable.
or sensitive species of flora or fauna

11 | P a g e
for breeding, nesting, foraging,
resting, over wintering, migration.
4 Inland, coastal, marine or No Not Applicable.
underground waters
5 State, National boundaries No Not Applicable.
6 Routes or facilities used by the No Not Applicable.
public for access to recreation or
other tourist, pilgrim areas
7 Defense installations No Not Applicable.
8 Densely populated or built-up area Yes Ankleshwar 2 km
9 Areas occupied by sensitive man- No --
made land uses (hospitals, schools,
places of worship, community
facilities)
10 Areas containing important, high No Not Applicable.
quality or scarce resources
(ground water resources, surface
resources, forestry, agriculture,
fisheries, tourism, minerals)
11 Areas already subjected to pollution No Not Applicable.
or environmental damage. (those
where existing legal environmental
standards are exceeded)
12 Areas susceptible to natural hazard No The project may be affected by
which could cause the project to natural disasters like
present environmental Problems earthquakes and adequate
(earthquakes, subsidence, landslides, measures during design and
erosion ,Flooding or extreme or construction shall be taken to
adverse climatic conditions) avoid such natural hazard.
“ I hereby given undertaking that the data and information given in the application and
enclosures are true to my best knowledge and belief and I am aware that if any part of the data
and information submitted is found to false or misleading at any stage, the project will be rejected
and clearance give, if any to the project will be revoked at our risk and cost”.
Date: 28-05-2019
Place: Ankleshwar, Dist. Bharuch

Mr. Ashvin.F.Patel. Partner


Jaychem Industries.
Plot No. 6713-14/1, G.I.D.C Estate, Ankleshwar,
District: Bharuch, Gujarat.
Signature of the application
With Name and Full Address
(Project Proponent / Authorized Signatory)

12 | P a g e
LIST OF CONTENTS AND ANNEXURE
Sr. No. Title Page No
Annexure-A Details of Water consumption and waste water generation 14-16
with water balance diagram
Annexure-B Effluent treatment scheme 17-18
Annexure-C Details of Hazardous waste generation and disposal 19-19
Annexure-D Details of Air Pollution Control Measures 20-20
Annexure-E ETL Discharge permission with additional Discharge. 21-23

13 | P a g e
Annexure A
DETAILS OF WATER CONSUMPTION AND WASTE WATER GENERATION

DETAILS OF WATER CONSUMPTION

Sr Category As per As per Proposed Total after


No. Existing EC EC Amendment Amendment
KLD KLD KLD
1. Domestic purpose 4.0 -- 4.0
2. Gardening Purpose 3.0 -- 3.0
3. Industrial
Process 37.5 -- 37.5
Washing 3.49 -- 3.49
Boiler 7.7 -3 4.2
Cooling 3.0 -- 3.0
Scrubber 0.31 -- 0.31
Boiler Scrubber 1.0 -- 1.0
Total Industrial 53.0 -3 49.5
water consumption
Total (Domestic + 60.0 -3 56.5
Gardening +
Industrial)

Final Conclusion for Water Consumption


Sr Purpose As per Existing EC As per Proposed
No. Condition EC condition
1. Total water requirement for the project: 60 KLD 56.5 KLD
2. Quantity to be recycled 38.9 KLD 0.0 KLD
3. Total fresh water requirement 21.1 KLD 56.5 KLD
*The overall quantity of water consumption will be decreases. Now Due to duel discharge
permission, MEE system will be discontinue in proposed condition and considering the
same, steam requirement will be decrease and water consumption for Boiler make up will
also decrease hence Overall quantity of water requirement will be reduced.

14 | P a g e
DETAILS OF WASTE WATER GENERATION

Sr no. Category As per As per Total after


Existing EC Proposed EC Amendment
KLD Amendment KLD
KLD
1. Domestic purpose 3.6 -- 3.6
2. Industrial purpose
Process 38.5 -- 38.5
Washing 3.49 -- 3.49
Boiler 1.7 -0.7 1.0
Cooling 0.5 -- 0.5
Scrubber 0.31 -- 0.31
Boiler Scrubber 0.5 -- 0.5
Total Industrial 45 -0.7 44.3
waste water

As per Existing EC Condition


Total 45.0 KLD waste water will be generated from which 1.5 KLD send to ETL-CETP and
remaining 43.5 KLD will be treated into in house ETP followed by in-house MEE system .After
evaporation MEE condensate water [38.6 KLD] will be reuse within the plant premises
As per Proposed EC Condition
Total 44.3 KLD waste water will be generated from which 36.88 KLD will be send to ETL-CETP,
and remaining 7.42 KLD will be send to PETL-Panoli for common Spry Dryer.
*The overall quantity of wastewater will be decrease. Due to duel discharge permission, MEE
system will be discontinue in proposed condition and considering the same, steam
requirement will be decrease and water generation for Boiler blowdown will also decrease
hence Overall quantity of waste water requirement will be reduced.
Final Conclusion for Waste Water Generation
Sr Purpose As per Existing EC As per Proposed EC
No. Condition condition
1. Total waste water generation 45 KLD 44.3 KLD
2. Effluent treated in ETP and then send 1.5 KLD 35.38 KLD
to ETL-CETP
3. Effluent treated in to ETP and then 43.45 KLD 0.0 KLD
subjected to in-house MEE
4. Effluent treated in to ETP and then 0.0 KLD 7.42 KLD
send to PETL-Panoli for Common Spry
Dryer.

15 | P a g e
Existing water Balance Diagram

16 | P a g e
Proposed water Balance Diagram

17 | P a g e
Annexure B

EFFLUENT TREATMENT SCHEME AND EQUIPMENT LIST

Effluent Treatment Scheme and Equipment List for Effluent Send to ETL-
CETP
 Effluent generated from process, washing, boiler & cooling blow down is collected in collection tank.
Then it is sent to neutralization tank to neutralize. After neutralization & Coagulation, treated effluent
is sent to settling tank for further treatment. After settling tank, this effluent is filtered through filter
press and the press cake (Filter Mass-ETP Sludge) is transfer to ETP sludge storage yard. The filtrate
effluent is transfer to treated effluent tank. After that waste water will be discharge at ETL- CETP for
further process and disposal.

EQUIPMENT LIST OF EFFLUENT TREATMENT PLANT

Sr Name of equipment Unit Dimensions (m) Liquid Volume


no Nos. in m3
Length With Height
1 Collection Tank 3 3.0 2.5 2.5 18.75
2 Oil & Grease Trap 1 2.5 2 2 10
3 Equalization Tank cum 2 4.1 4 2.1 35
Neutralization Tank
4 Precipitating/ settling tank 1 4Ø - 3 3
5 Filter Press 1 3.0 3.0 3.0 27
6 Final Collection Tank 1 5 3.5 3.5 61.25
7 Sludge Drying Beds 1 1.5 2 1 3

18 | P a g e
Effluent Treatment Scheme and Equipment List for Effluent Send to PETL
 Effluent generated from process, washing, boiler & cooling blow down is collected in collection tank.
Then it is sent to neutralization tank to neutralize. After neutralization & Coagulation, treated effluent
is sent to settling tank for further treatment. After settling tank, this effluent is filtered through filter
press and the press cake (Filter Mass-ETP Sludge) is transfer to ETP sludge storage yard. The filtrate
effluent is transfer to treated effluent tank. After that waste water will be discharge at PETL- Common
Spry Dryer for further process and disposal.

EQUIPMENT LIST OF EFFLUENT TREATMENT PLANT

Sr. No. Units Unit Dimensions Volume or


[l × b ×h] Area
1 Collection Tank 3.0 m × 2.0 m × 2.0 m 12.0 m3
2 Neutralization Tank 2.5 m × 1.0 m [l×r] 7.85 m2
3 Filter Press 1.21 m × 1.21 m × 1.21 m 3.63 m3
4 Final Treated water Storage Tank 4.14 m × 2.92 m × 1.6 m 19.34 m3

19 | P a g e
Annexure C

DETAILS OF HAZARDOUS WASTE MANAGEMENT

Sr. Type/Nam Specific Catego Quantity Management of HW


no e of Source of ry and (MT/Annum)
. Hazardous generation Schedu Exist Propo Total
waste (Name of le as
ing sed
the Activity, per
Product HW
etc.) Rules
1. Discarded Storage 33.3 5.0 -- 5.0 Collection, Storage,
Bags/ area/ Transportation,
Drums Packaging Decontamination and sell
/Container material to registered Vendors.
/Liners etc.
2. Distillation From the 20.3 12.0 -- 12.0 Collection, Storage,
Residue process Transportation and send
to Co-Processing or CHWIF
site.
3. Spent Mfg Process 20.2 2484 -- 2484 Collection, Storage, In-
Solvent House -. Distillation and
Reuse Recovered Solvent
within premises
4. ETP Sludge ETP 35.3 328 306 634 Collection, Storage,
Transportation and send
to BEIL-TSDF site.
5. Used Oil Plant & 5.1 0.05 -- 0.05 Collection, Storage,
machinery Transportation sell to
Registered Re-refiners.
6. Ammonium Scrubbing --- 12.0 -- 12.0 Collection, Storage,
Sulphate system Transportation and send
Salt to authorized users having
permission under rule 9.
7. Ammonia Scrubbing -- 4.14 -- 4.14 Collection, treated at own
Solution ETP and then discharge in
to CETP-ETL for further
treatment.
8. Hydrochlor From -- 108 -- 108 Collection, storage, treated
ic Acid Scrubber at own ETP.
9. Mechlor’s From -- 42 -- 42 Collection, Storage,
Ketone Product no 1 Transportation and send
to authorized users having
permission under rule 9.

20 | P a g e
Annexure D
DETAILS OF AIR POLLUTION CONTROL MEASURE AS PER EARLIER DEATILS

Type of
Air Pollution
Sr. Stack Quantity of emission
Source of emission Control
no Height Fuel s i.e. Air
With Capacity Measures
. (m) MT/Day Pollutant
(APCM)
s
1. Hot Air Generator 11 Natural Gas
Cap. [1 lac K Cal/ hr.] 50 m3/day PM
2. Non IBR Boiler Cap. 11 Natural Gas SO2 Adequate stack
[600 g/hr.] (Comm 100 m3/day NOX height
3. TFH Cap. [2 lac K Cal on Natural Gas
/ hr.] stack) 100 m3/day
4. Steam Boiler 12 m Natural Gas or Multi Cyclone +
PM
Cap. [2TPH] Briquettes Bag Filter +
SO2
100 SCM/Hrs. Water Scrubber
NOX
Or 1.5 MT/Day
5. Hot Air Dryer 10 m Natural Gas Adequate stack
PM
50 SCM/Hrs. height &
SO2
6. D. G. Set ( 187 KVA) 8m Natural Gas 20 acoustic
NOX
(Stand By) M3/Hr. enclosure
*Note : after EC-Amendment fuel consumption for Boiler will be decrease and there will
not be any changes in Process gas Emission.

21 | P a g e
Annexure E

No.AIA//DEE(WS)/ [6 3(
(W'S)
OfficeoftheDy.Ex.Engg.
NotifiedArea Office,
GIDC, Ankleshwar.

Dt.3t1,1 | W

To,

P l o xt o . 4 t l - l \ I L
GIDC, Ankleshwar.

Sub :- Water requirement of - 63.Q_r<LI day.


Ref :- Yours letter No. 61.ots i -Qa t.>

Dear Sir,

With reference to the above this office will supply the water quantity of
of GPCB, also as
69. O_KL I day as per your requirementand as per permission
per feasibitity of water and as per the rules of the corporation.

r.

This is for your information please.


a

Thanking you,
YoursFaithfully,

Dy. Ex. Engineer (WS)


NA, GIDC, Ankleshwar.

' r '

29-6-07 water requirement performa

oa
TDANOTI I]NITINO TI]CIINOIIMY ililIITIII)
Plot No.619-619/1, GIDC Estate, Panoli - 394116, Dist. Bharuch (Gujarat)
Accredited
Ph. : (02646) 272822, Fax: (02646) Zt20Z2, e-mail: p€flpanoti@gmail.com
Ccrtlllcrtlonr Pry. Ltd.

Ref : PETL / L2 /2OL9

M EM BERSH I P CERTI F ICATE

To Whom So Ever lt May Concern :

This isto certify that M/s. JAY CHEM INDUSTRIES having their unit at
Plot No.6713-14/1. GIDC Estate. Ankleshwar - 393002. Dist. Bharuch has
approached M ' Panoli Enviro Technology Ltd. Situated at Plot No.61$619/1.
GIDC Estate. Panoli. Dist. Bharuch. to obtain_membership for Spray Drying of
their effluent to obtain "Zero Liquid Dischar$e (ZLD)".

As on date we have spare capacity to accept their effluent for Spray Dryin$ and
we hereby issue "Membership" to M/s. JAY CHEM INDUSTRIES. Plot No.6713-
14u1. GIDC Estate. Ankleshwar - 393002. Dist. Bharuch for spray drying their
effluent at PETL Spray Dryer Plant.

We will accept the effluent for Spray drying provided it meets PETL inlet norms
and subject to available capacity.

Yours faithfully
For, Pfrt[QLl ENVIRO TECHNOLOGY LTD.

PANKA' BHARWADA Date : L4.O5.20L9


CHAIRMAN Place: Panoli GIDC