You are on page 1of 75

Lead Total Costs per

Description of Source of
S.No Distance Cart Sandy Metal Dista km per
material material
Track Track Track ce unit
Col.1 Col.2 Col.3 Col.4 Col.5 Col.6 Col.7 Col.8 Col.9
1 Sand for concrete Guntur 150 0 2.80 3 5.80 78.86951
25 25.00 11.83475
122 122.00 9.84789

2 Coarse aggregate Medak


80mm 20 0 2.8 3 5.8 78.86951
15 15 11.83475

Coarse aggregate
3 Medak
40mm 20 0 2.8 3 5.8 78.86951
15 15 11.83475

Coarse aggregate
4 20mm Medak
20 0 2.8 3 5.8 78.8691
15 15 11.83475

5 Coarse aggregate
10mm Medak 20 0 2.8 3 5.8 78.8691
15 11.83475

6 Cement Medak 50 0 0 5 5 49.32584


25 25 7.42911
20 20 6.133335
Seigniora Total Cost
Basic/ Blasting Crushing Loading Unloading Stacking
sub cost ge per unit Unit
intial cost Charges Charges Charges Charges Charges
Charges per km
Col.10 Col.11 Col.12 Col.13 Col.14 Col.15 Col.16 Col.17 Col.18 Col.19
457.4431
295.8686
1201.443 570 0 0 106.2536 38.0094 0 75 2744.017 cum
1954.754

457.4431
177.5213 315.5 67 127.5 126.0357 63.01494 0 75 1409.015 cum
634.9644

457.4431
177.5213 598 67 225 126.2536 63.01494 0 75 1789.233 cum
634.9644

457.4431
117.5213 675.5 67 247.5 126.2536 63.01494 0 75 1889.233
634.9644

457.4431
117.5213 503 67 190 126.0357 63.01494 0 75 1599.015 cum
574.9644
246.6292
185.7278
122.6667 4750 171.985 171.985 5093.97 tonne
1 Surface excavation not exceeding 30 cm deep, average 15cm deep,and getting
out.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
1.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil -
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.08 425 34
2 Basic cost Sqm 34 A
3 Overhead charges 5% 1.7 B
4 Establishment charges 2.5% 0.85 C
5 Total cost 36.55 D=A+B+C
6 Contractor's profit 10% 3.655 E
Rate to be quoted/tendering cost(rs/sqm 40.205 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
1.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.15 425 63.75
2 Basic cost Sqm 63.75 A
3 Overhead charges 5% 3.1875 B
4 Establishment charges 2.5% 1.59375 C
5 Total cost 68.53125 D=A+B+C
6 Contractor's profit 10% 6.853125 E
Rate to be quoted/tendering cost(rs/sqm 75.38438 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
1.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.31 425 131.75
2 Basic cost Sqm 131.75 A
3 Overhead charges 5% 6.5875 B
4 Establishment charges 2.5% 3.29375 C
5 Total cost 141.6313 D=A+B+C
6 Contractor's profit 10% 14.16313 E
Rate to be quoted/tendering cost(rs/sqm 155.7944 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
1.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
hard
1 Labour
1.1 Mazdoor Sqm 0.65 425 276.25
2 Basic cost Sqm 276.25 A
3 Overhead charges 5% 13.8125 B
4 Establishment charges 2.5% 6.90625 C
5 Total cost 296.9688 D=A+B+C
6 Contractor's profit 10% 29.69688 E
Rate to be quoted/tendering cost(rs/sqm 326.6656 F=E+D

2 Add to (or deduct from) item 1 above for every 3 cm above or below 15 cm average depth

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
2.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.01 425 4.25
2 Basic cost Sqm 4.25 A
3 Overhead charges 5% 0.2125 B
4 Establishment charges 2.5% 0.10625 C
5 Total cost 4.56875 D=A+B+C
6 Contractor's profit 10% 0.456875 E
Rate to be quoted/tendering cost(rs/sqm 5.025625 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
2.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.014 425 5.95
2 Basic cost Sqm 5.95 A
3 Overhead charges 5% 0.2975 B
4 Establishment charges 2.5% 0.14875 C
5 Total cost 6.39625 D=A+B+C
6 Contractor's profit 10% 0.639625 E
Rate to be quoted/tendering cost(rs/sqm 7.035875 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
2.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.034 425 14.45
2 Basic cost Sqm 14.45 A
3 Overhead charges 5% 0.7225 B
4 Establishment charges 2.5% 0.36125 C
5 Total cost 15.53375 D=A+B+C
6 Contractor's profit 10% 1.553375 E
Rate to be quoted/tendering cost(rs/sqm 17.08713 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
2.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.069 425 29.325
2 Basic cost Sqm 29.325 A
3 Overhead charges 5% 1.46625 B
4 Establishment charges 2.5% 0.733125 C
5 Total cost 31.52438 D=A+B+C
6 Contractor's profit 10% 3.152438 E
Rate to be quoted/tendering cost(rs/sqm 34.67681 F=E+D

3 Roughexcavation not exceeding 1.5 m deep and getting out.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
3.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.3 425 127.5
2 Basic cost Sqm 127.5 A
3 Overhead charges 5% 6.375 B
4 Establishment charges 2.5% 3.1875 C
5 Total cost 137.0625 D=A+B+C
6 Contractor's profit 10% 13.70625 E
Rate to be quoted/tendering cost(rs/sqm 150.7688 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
3.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.52 425 221
2 Basic cost Sqm 221 A
3 Overhead charges 5% 11.05 B
4 Establishment charges 2.5% 5.525 C
5 Total cost 237.575 D=A+B+C
6 Contractor's profit 10% 23.7575 E
Rate to be quoted/tendering cost(rs/sqm 261.3325 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
3.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 1.18 425 501.5
2 Basic cost Sqm 501.5 A
3 Overhead charges 5% 25.075 B
4 Establishment charges 2.5% 12.5375 C
5 Total cost 539.1125 D=A+B+C
6 Contractor's profit 10% 53.91125 E
Rate to be quoted/tendering cost(rs/sqm 593.0238 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
3.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 2.84 425 1207
2 Basic cost Sqm 1207 A
3 Overhead charges 5% 60.35 B
4 Establishment charges 2.5% 30.175 C
5 Total cost 1297.525 D=A+B+C
6 Contractor's profit 10% 129.7525 E
Rate to be quoted/tendering cost(rs/sqm 1427.278 F=E+D

4 Excavation over areas not exceedinding 1.5 m deep and getting out.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
4.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.4 425 170
2 Basic cost Sqm 170 A
3 Overhead charges 5% 8.5 B
4 Establishment charges 2.5% 4.25 C
5 Total cost 182.75 D=A+B+C
6 Contractor's profit 10% 18.275 E
Rate to be quoted/tendering cost(rs/sqm 201.025 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
4.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.68 425 289
2 Basic cost Sqm 289 A
3 Overhead charges 5% 14.45 B
4 Establishment charges 2.5% 7.225 C
5 Total cost 310.675 D=A+B+C
6 Contractor's profit 10% 31.0675 E
Rate to be quoted/tendering cost(rs/sqm 341.7425 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
4.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 1.59 425 675.75
2 Basic cost Sqm 675.75 A
3 Overhead charges 5% 33.7875 B
4 Establishment charges 2.5% 16.89375 C
5 Total cost 726.4313 D=A+B+C
6 Contractor's profit 10% 72.64313 E
Rate to be quoted/tendering cost(rs/sqm 799.0744 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
4.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 3.94 425 1674.5
2 Basic cost Sqm 1674.5 A
3 Overhead charges 5% 83.725 B
4 Establishment charges 2.5% 41.8625 C
5 Total cost 1800.088 D=A+B+C
6 Contractor's profit 10% 180.0088 E
Rate to be quoted/tendering cost(rs/sqm 1980.096 F=E+D

Excavation not exceeding 1.5 m deep and getting out in trenches not exceedind 1.5 m wide
5 or for shafts , well,cesspits, manholes and the like, not exceeding 10sq m on plan.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
5.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.55 425 233.75
2 Basic cost Sqm 233.75 A
3 Overhead charges 5% 11.6875 B
4 Establishment charges 2.5% 5.84375 C
5 Total cost 251.2813 D=A+B+C
6 Contractor's profit 10% 25.12813 E
Rate to be quoted/tendering cost(rs/sqm 276.4094 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
5.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.96 425 408
2 Basic cost Sqm 408 A
3 Overhead charges 5% 20.4 B
4 Establishment charges 2.5% 10.2 C
5 Total cost 438.6 D=A+B+C
6 Contractor's profit 10% 43.86 E
Rate to be quoted/tendering cost(rs/sqm 482.46 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
5.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 2.19 425 930.75
2 Basic cost Sqm 930.75 A
3 Overhead charges 5% 46.5375 B
4 Establishment charges 2.5% 23.26875 C
5 Total cost 1000.556 D=A+B+C
6 Contractor's profit 10% 100.0556 E
Rate to be quoted/tendering cost(rs/sqm 1100.612 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
5.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 4.9 425 2082.5
2 Basic cost Sqm 2082.5 A
3 Overhead charges 5% 104.125 B
4 Establishment charges 2.5% 52.0625 C
5 Total cost 2238.688 D=A+B+C
6 Contractor's profit 10% 223.8688 E
Rate to be quoted/tendering cost(rs/sqm 2462.556 F=E+D

Extra over items 3 and 4 above for each additional 1.5 m depth (or part thereof ) beyond
6 the first stage of 1.5 m depth.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
6.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.12 425 51
2 Basic cost Sqm 51 A
3 Overhead charges 5% 2.55 B
4 Establishment charges 2.5% 1.275 C
5 Total cost 54.825 D=A+B+C
6 Contractor's profit 10% 5.4825 E
Rate to be quoted/tendering cost(rs/sqm 60.3075 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
6.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.12 425 51
2 Basic cost Sqm 51 A
3 Overhead charges 5% 2.55 B
4 Establishment charges 2.5% 1.275 C
5 Total cost 54.825 D=A+B+C
6 Contractor's profit 10% 5.4825 E
Rate to be quoted/tendering cost(rs/sqm 60.3075 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
6.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.18 425 76.5
2 Basic cost Sqm 76.5 A
3 Overhead charges 5% 3.825 B
4 Establishment charges 2.5% 1.9125 C
5 Total cost 82.2375 D=A+B+C
6 Contractor's profit 10% 8.22375 E
Rate to be quoted/tendering cost(rs/sqm 90.46125 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
6.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.18 425 76.5
2 Basic cost Sqm 76.5 A
3 Overhead charges 5% 3.825 B
4 Establishment charges 2.5% 1.9125 C
5 Total cost 82.2375 D=A+B+C
6 Contractor's profit 10% 8.22375 E
Rate to be quoted/tendering cost(rs/sqm 90.46125 F=E+D

Extra over item 5 above for each additional 1.5 m depth (or parth thereof) beyond the first
7 stage of 1.5 m depth.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
7.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.41 425 174.25
2 Basic cost Sqm 174.25 A
3 Overhead charges 5% 8.7125 B
4 Establishment charges 2.5% 4.35625 C
5 Total cost 187.3188 D=A+B+C
6 Contractor's profit 10% 18.73188 E
Rate to be quoted/tendering cost(rs/sqm 206.0506 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
7.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.61 425 259.25
2 Basic cost Sqm 259.25 A
3 Overhead charges 5% 12.9625 B
4 Establishment charges 2.5% 6.48125 C
5 Total cost 278.6938 D=A+B+C
6 Contractor's profit 10% 27.86938 E
Rate to be quoted/tendering cost(rs/sqm 306.5631 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
7.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 1.23 425 522.75
2 Basic cost Sqm 522.75 A
3 Overhead charges 5% 26.1375 B
4 Establishment charges 2.5% 13.06875 C
5 Total cost 561.9563 D=A+B+C
6 Contractor's profit 10% 56.19563 E
Rate to be quoted/tendering cost(rs/sqm 618.1519 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
7.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 1.88 425 799
2 Basic cost Sqm 799 A
3 Overhead charges 5% 39.95 B
4 Establishment charges 2.5% 19.975 C
5 Total cost 858.925 D=A+B+C
6 Contractor's profit 10% 85.8925 E
Rate to be quoted/tendering cost(rs/sqm 944.8175 F=E+D

ramming around posts etc., and removing surplus soil to a distance not exceeding 50 m
8 spread and levelled.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
8.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.41 425 174.25
2 Basic cost Sqm 174.25 A
3 Overhead charges 5% 8.7125 B
4 Establishment charges 2.5% 4.35625 C
5 Total cost 187.3188 D=A+B+C
6 Contractor's profit 10% 18.73188 E
Rate to be quoted/tendering cost(rs/sqm 206.0506 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
8.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.61 425 259.25
2 Basic cost Sqm 259.25 A
3 Overhead charges 5% 12.9625 B
4 Establishment charges 2.5% 6.48125 C
5 Total cost 278.6938 D=A+B+C
6 Contractor's profit 10% 27.86938 E
Rate to be quoted/tendering cost(rs/sqm 306.5631 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
8.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 1.23 425 522.75
2 Basic cost Sqm 522.75 A
3 Overhead charges 5% 26.1375 B
4 Establishment charges 2.5% 13.06875 C
5 Total cost 561.9563 D=A+B+C
6 Contractor's profit 10% 56.19563 E
Rate to be quoted/tendering cost(rs/sqm 618.1519 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
8.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 1.88 425 799
2 Basic cost Sqm 799 A
3 Overhead charges 5% 39.95 B
4 Establishment charges 2.5% 19.975 C
5 Total cost 858.925 D=A+B+C
6 Contractor's profit 10% 85.8925 E
Rate to be quoted/tendering cost(rs/sqm 944.8175 F=E+D
Taking up excavated material from spoil heaps, filling borrows/ baskets and
9 wheeling/removing and depositing

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.1.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
- at 25 m
distance
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.1.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.1.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.1.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.2.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
- at 50m
distance
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.2.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.2.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.2.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.3.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
- at 100m
distance
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.3.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.3.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.3.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.4.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
at 200 m
distance
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.4.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.4.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.4.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Taking up excavated materials from spoil heaps and loading manually into dumpers or
10 lorries.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
10.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
10.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
10.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)

Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
10.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D

Item-11 Returning, filling and ramming excavated spoil around foundations(no lead
involved)
Productiv
Total Sum of
S.NO Description Unit ity/Mater Cost per Amount Amount(
ial Unit
(Rs.) Rs)
constant
Returning, filling
1 and ramming
excavated spoil
around
1 Labour
1.1 Mazdoor Sqm 0.21 425 89.25
2 Basic Cost(A) Sqm 89.25
3 Overhead Charges 5% (B) 4.46
4 Establishment Charges 2.5%(C) 2.23
5 Total Cost(D=A+B+C) 95.94
6 CP 10%( E) 9.59
Rate To be Quoted/Tendering Cost(Rs/Sqm) 105.54

Item-11 Returning, filling and ramming excavated spoil around foundations(no lead
involved)
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit ial Unit Amount Amount(
(Rs.) Rs)
constant
Returning, filling
1 and ramming
excavated spoil
around
1 Labour
1.1 Mazdoor Sqm 0.27 425 114.75
2 Basic Cost(A) Sqm 114.75
3 Overhead Charges 5% (B) 5.74
4 Establishment Charges 2.5%(C) 2.87
5 Total Cost(D=A+B+C) 123.36
6 CP 10%( E) 12.34
Rate To be Quoted/Tendering Cost(Rs/Sqm) 135.69

Item-12 Filling, Spreading/ levelling in layes of 25cm thickness, watering and well
ramming under floors, including lead upto 50 meters
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit (Rs.) Rs)
constant
Filling,
1 Spreading/
levelling in layes
of 25cm
1 Labour
1.1 Mazdoor Sqm 0.35 425 148.75
2 Basic Cost(A) Sqm 148.75
3 Overhead Charges 5% (B) 7.44
4 Establishment Charges 2.5%(C) 3.72
5 Total Cost(D=A+B+C) 159.91
6 CP 10%( E) 15.99
Rate To be Quoted/Tendering Cost(Rs/Sqm) 175.90

Item-13.1 Boreholes in clay, soft /loose or black cotton soil for single under-reamed piles
2 m deep and diposing off soil to a distance not exceeding 50m away, for bore
Productiv
Total Sum of
S.NO Description Unit ity/Mater Cost per Amount Amount(
ial Unit
(Rs.) Rs)
constant
Boreholes in
1 clay, soft /loose
or black cotton
soil for single
1 Labour
1.1 Mazdoor Sqm 1.14 425 484.5
2 Basic Cost(A) Sqm 484.5
3 Overhead Charges 5% (B) 24.23
4 Establishment Charges 2.5%(C) 12.11
5 Total Cost(D=A+B+C) 520.84
6 CP 10%( E) 52.08
Rate To be Quoted/Tendering Cost(Rs/Sqm) 572.92

Item-13.2 Boreholes in clay, soft /loose or black cotton soil for single under-reamed piles
2 m deep and diposing off soil to a distance not exceeding 50m away, for bore
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit
(Rs.) Rs)
constant
Boreholes in
1 clay, soft /loose
or black cotton
soil for single
1 Labour
1.1 Mazdoor Sqm 1.37 425 582.25
2 Basic Cost(A) Sqm 582.25
3 Overhead Charges 5% (B) 29.11
4 Establishment Charges 2.5%(C) 14.56
5 Total Cost(D=A+B+C) 625.92
6 CP 10%( E) 62.59
Rate To be Quoted/Tendering Cost(Rs/Sqm) 688.51

Item-13.2 Boreholes in clay, soft /loose or black cotton soil for single under-reamed piles
2 m deep and diposing off soil to a distance not exceeding 50m away, for bore
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit (Rs.) Rs)
constant
Boreholes in
1 clay, soft /loose
or black cotton
soil for single
1 Labour
1.1 Mazdoor Sqm 1.6 425 680
2 Basic Cost(A) Sqm 680
3 Overhead Charges 5% (B) 34.00
4 Establishment Charges 2.5%(C) 17.00
5 Total Cost(D=A+B+C) 731.00
6 CP 10%( E) 73.10
Rate To be Quoted/Tendering Cost(Rs/Sqm) 804.10

Item-14.1 Extra over item 13 above for each additional under reaming:-200mm Dia
Productiv Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit
constant (Rs.) Rs)

Extra over item


1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.45 425 191.25
2 Basic Cost(A) Sqm 191.25
3 Overhead Charges 5% (B) 9.56
4 Establishment Charges 2.5%(C) 4.78
5 Total Cost(D=A+B+C) 205.59
6 CP 10%( E) 20.56
Rate To be Quoted/Tendering Cost(Rs/Sqm) 226.15

Item-14.2 Extra over item 13 above for each additional under reaming:-250mm Dia
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit (Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.6 425 255
2 Basic Cost(A) Sqm 255
3 Overhead Charges 5% (B) 12.75
4 Establishment Charges 2.5%(C) 6.38
5 Total Cost(D=A+B+C) 274.13
6 CP 10%( E) 27.41
Rate To be Quoted/Tendering Cost(Rs/Sqm) 301.54

Item-14.3 Extra over item 13 above for each additional under reaming:-300mm Dia
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit
(Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.7 425 297.5
2 Basic Cost(A) Sqm 297.5
3 Overhead Charges 5% (B) 14.88
4 Establishment Charges 2.5%(C) 7.44
5 Total Cost(D=A+B+C) 319.81
6 CP 10%( E) 31.98
Rate To be Quoted/Tendering Cost(Rs/Sqm) 351.79

Item-15.1 Extra over item 13 above for each additional metre depth(intermidiate depth
pro rata)
Productiv
Total Sum of
ity/Mater Cost per Amount Amount(
S.NO Description Unit
ial Unit
(Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.31 425 131.75
2 Basic Cost(A) Sqm 131.75
3 Overhead Charges 5% (B) 6.59
4 Establishment Charges 2.5%(C) 3.29
5 Total Cost(D=A+B+C) 141.63
6 CP 10%( E) 14.16
Rate To be Quoted/Tendering Cost(Rs/Sqm) 155.79
Item-15.2 Extra over item 13 above for each additional metre depth(intermidiate depth
pro rata)
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit
(Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.4 425 170
2 Basic Cost(A) Sqm 170
3 Overhead Charges 5% (B) 8.50
4 Establishment Charges 2.5%(C) 4.25
5 Total Cost(D=A+B+C) 182.75
6 CP 10%( E) 18.28
Rate To be Quoted/Tendering Cost(Rs/Sqm) 201.03

Item-15.3 Extra over item 13 above for each additional metre depth(intermidiate depth
pro rata)
Productiv
Total Sum of
S.NO Description Unit ity/Mater Cost per Amount Amount(
ial Unit
(Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.45 425 191.25
2 Basic Cost(A) Sqm 191.25
3 Overhead Charges 5% (B) 9.56
4 Establishment Charges 2.5%(C) 4.78
5 Total Cost(D=A+B+C) 205.59
6 CP 10%( E) 20.56
Rate To be Quoted/Tendering Cost(Rs/Sqm) 226.15

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
16 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Surface dressing
or trimming of
natural ground
to remove small
unequalities not
exceeding 15cm
deep (including
removing
vegetation/shru
bs/brushwood/
undergrowth
and carrying
away rubbish
to a distance of
50 m. (Sundry Soil
labours - (Hard/de
Excavator) nse)
Labour
1 Mazdoor Sqm 0.06 425 25.5
25.5
2 Basic Cost 25.5 A
3 Overhead charges (5%) 1.275 B=5% A
4 Establishment charges (2.5%) 0.6375 C=2.5%*A
5 Total cost 27.4125 D=A+B+C
6 Profit (10%) 2.74125 E=10%*D

Rate to be
quoted or
7 tendering cost 30.15375 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
17.1 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Drilling holes
(for blasting) in
rock manually
with boring bars
and drill bits
for :- 20 to 25
mm dia holes.
(Note:-In item
17 above allow
0.02 days per m
for
pointing/sharpe Rock
ning of tools by (Granite/t
one smith and rap/Gneis
one helper) s)
Labour
1 Mazdoor Sqm 0.51 425 216.75
216.75
2 Basic Cost 216.75 A
3 Overhead charges (5%) 10.8375 B=5% A
4 Establishment charges (2.5%) 5.41875 C=2.5%*A
5 Total cost 233.0063 D=A+B+C
6 Profit (10%) 23.30063 E=10%*D

Rate to be
quoted or
7 tendering cost 256.3069 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
17.2 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Drilling holes
(for blasting) in
rock manually
with boring bars
and drill bits
for :- 50 mm dia
holes. (Note:-In
item 17 above
allow 0.02 days
per m for
pointing/sharpe Rock
ning of tools by (Granite/t
one smith and rap/Gneis
one helper) s)
Labour
1 Mazdoor Sqm 2.05 425 871.25
871.25
2 Basic Cost 871.25 A
3 Overhead charges (5%) 43.5625 B=5% A
4 Establishment charges (2.5%) 21.78125 C=2.5%*A
5 Total cost 936.5938 D=A+B+C
6 Profit (10%) 93.65938 E=10%*D

Rate to be
quoted or
7 tendering cost 1030.253 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
17.3 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Drilling holes
(for blasting) in
rock manually
with boring bars
and drill bits
for :- 75 mm dia
holes. (Note:-In
item 17 above
allow 0.02 days
per m for
pointing/sharpe Rock
ning of tools by (Granite/t
one smith and rap/Gneis
one helper) s)
Labour
1 Mazdoor Sqm 4.9 425 2082.5
2082.5
2 Basic Cost 2082.5 A
3 Overhead charges (5%) 104.125 B=5% A
4 Establishment charges (2.5%) 52.0625 C=2.5%*A
5 Total cost 2238.688 D=A+B+C
6 Profit (10%) 223.8688 E=10%*D

Rate to be
quoted or
7 tendering cost 2462.556 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
18.1 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Hardcore laid,
spread, levelled,
watered and
consolidated to
required levels
in layers of :-75
mm
consolidated
thickness.
Labour
1 Mazdoor Sqm 0.05 425 21.25
21.25
2 Basic Cost 21.25 A
3 Overhead charges (5%) 1.0625 B=5% A
4 Establishment charges (2.5%) 0.53125 C=2.5%*A
5 Total cost 22.84375 D=A+B+C
6 Profit (10%) 2.284375 E=10%*D

Rate to be
quoted or
7 tendering cost 25.12813 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
18.2 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark

Hardcore laid,
spread, levelled,
watered and
consolidated to
required levels
in layers of :-
150 mm
consolidated
thickness.
Labour
1 Mazdoor Sqm 0.09 425 38.25
38.25
2 Basic Cost 38.25 A
3 Overhead charges (5%) 1.9125 B=5% A
4 Establishment charges (2.5%) 0.95625 C=2.5%*A
5 Total cost 41.11875 D=A+B+C
6 Profit (10%) 4.111875 E=10%*D

Rate to be
quoted or
7 tendering cost 45.23063 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
18.3 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark

Hardcore laid,
spread, levelled,
watered and
consolidated to
required levels
in layers of :-
225 mm
consolidated
thickness.
Labour
1 Mazdoor Sqm 0.14 425 59.5
59.5
2 Basic Cost 59.5 A
3 Overhead charges (5%) 2.975 B=5% A
4 Establishment charges (2.5%) 1.4875 C=2.5%*A
5 Total cost 63.9625 D=A+B+C
6 Profit (10%) 6.39625 E=10%*D

Rate to be
quoted or
7 tendering cost 70.35875 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
18.4 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Hardcore laid,
spread, levelled,
watered and
consolidated to
required levels
in layers of :-
250 mm
consolidated
thickness and
above
Labour
1 Mazdoor Sqm 0.5 425 212.5
212.5
2 Basic Cost 212.5 A
3 Overhead charges (5%) 10.625 B=5% A
4 Establishment charges (2.5%) 5.3125 C=2.5%*A
5 Total cost 228.4375 D=A+B+C
6 Profit (10%) 22.84375 E=10%*D

Rate to be
quoted or
7 tendering cost 251.2813 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
19 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark

Stone pitching
150 mm thick.
Labour
1 Mazdoor Sqm 0.12 425 51
51
2 Basic Cost 51 A
3 Overhead charges (5%) 2.55 B=5% A
4 Establishment charges (2.5%) 1.275 C=2.5%*A
5 Total cost 54.825 D=A+B+C
6 Profit (10%) 5.4825 E=10%*D
Rate to be
quoted or
7 tendering cost 60.3075 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
20 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark

Stone pitching
250 mm thick.
Labour
1 Mazdoor Sqm 0.15 425 63.75
63.75
2 Basic Cost 63.75 A
3 Overhead charges (5%) 3.1875 B=5% A
4 Establishment charges (2.5%) 1.59375 C=2.5%*A
5 Total cost 68.53125 D=A+B+C
6 Profit (10%) 6.853125 E=10%*D

Rate to be
quoted or
7 tendering cost 75.38438 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
21 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark

Cut up or lift
existing turf into
suitable sods,
roll up and set
aside for reuse.
Labour
1 Mazdoor Sqm 0.06 425 25.5
25.5
2 Basic Cost 25.5 A
3 Overhead charges (5%) 1.275 B=5% A
4 Establishment charges (2.5%) 0.6375 C=2.5%*A
5 Total cost 27.4125 D=A+B+C
6 Profit (10%) 2.74125 E=10%*D

Rate to be
quoted or
7 tendering cost 30.15375 F=D+E

Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
22 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark

Relaying turf,
including
preparing
surface,
watering and
light rolling
Labour
1 Mazdoor Sqm 0.04 425 17
17
2 Basic Cost 17 A
3 Overhead charges (5%) 0.85 B=5% A
4 Establishment charges (2.5%) 0.425 C=2.5%*A
5 Total cost 18.275 D=A+B+C
6 Profit (10%) 1.8275 E=10%*D

Rate to be
quoted or
7 tendering cost 20.1025 F=D+E

23 Preparing surfaces and sowing grass seeds(0.05kg/sqm) and watering

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)

Preparing
surfaces and
sowing grass
seeds(0.05kg/sq
m) and watering
1 Labour
1.1 Mazdoor Sqm 0.04 425 17
2 Basic cost Sqm 17 A
3 Overhead charges 5% 0.85 B
4 Establishment charges 2.5% 0.425 C
5 Total cost 18.275 D=A+B+C
6 Contractor's profit 10% 1.8275 E
Rate to be quoted/tendering cost(rs/sqm 20.1025 F=E+D

24 Trimming sides of excavation

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)

Trimming sides
of excavation
1 Labour
1.1 Mazdoor Sqm 0.013 425 5.525
2 Basic cost Sqm 5.525 A
3 Overhead charges 5% 0.27625 B
4 Establishment charges 2.5% 0.138125 C
5 Total cost 5.939375 D=A+B+C
6 Contractor's profit 10% 0.593938 E
Rate to be quoted/tendering cost(rs/sqm 6.533313 F=E+D

25 Levelling grading and compacting bottom of excavation

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)

Levelling
grading and
compacting
bottom of
excavation
1 Labour
1.1 Mazdoor Sqm 0.026 425 11.05
2 Basic cost Sqm 11.05 A
3 Overhead charges 5% 0.5525 B
4 Establishment charges 2.5% 0.27625 C
5 Total cost 11.87875 D=A+B+C
6 Contractor's profit 10% 1.187875 E
Rate to be quoted/tendering cost(rs/sqm 13.06663 F=E+D

26 Ditto, but to falls or gradients.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)

Ditto, but to
falls or
gradients.
1 Labour
1.1 Mazdoor Sqm 0.028 425 11.9
2 Basic cost Sqm 11.9 A
3 Overhead charges 5% 0.595 B
4 Establishment charges 2.5% 0.2975 C
5 Total cost 12.7925 D=A+B+C
6 Contractor's profit 10% 1.27925 E
Rate to be quoted/tendering cost(rs/sqm 14.07175 F=E+D

27 Ditto but to falls and currents or crossfalls.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)

Ditto but to falls


and currents or
crossfalls.
1 Labour
1.1 Mazdoor Sqm 0.03 425 12.75
2 Basic cost Sqm 12.75 A
3 Overhead charges 5% 0.6375 B
4 Establishment charges 2.5% 0.31875 C
5 Total cost 13.70625 D=A+B+C
6 Contractor's profit 10% 1.370625 E
Rate to be quoted/tendering cost(rs/sqm 15.07688 F=E+D

28 Ditto but to falls and cambers.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)

Ditto but to falls


and cambers.
1 Labour
1.1 Mazdoor Sqm 0.032 425 13.6
2 Basic cost Sqm 13.6 A
3 Overhead charges 5% 0.68 B
4 Establishment charges 2.5% 0.34 C
5 Total cost 14.62 D=A+B+C
6 Contractor's profit 10% 1.462 E
Rate to be quoted/tendering cost(rs/sqm 16.082 F=E+D

29 Trimming sloping faces of embankments and cuttings

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)

Trimming
sloping faces of
embankments
and cuttings
1 Labour
1.1 Mazdoor Sqm 0.035 425 14.875
2 Basic cost Sqm 14.875 A
3 Overhead charges 5% 0.74375 B
4 Establishment charges 2.5% 0.371875 C
5 Total cost 15.99063 D=A+B+C
6 Contractor's profit 10% 1.599063 E
Rate to be quoted/tendering cost(rs/sqm 17.58969 F=E+D
30 Clear site of all rubbish, cut down shrubs, undergrowth and small trees not
exceedinding 600mm grith, grub up roots and burn or remove from site.

Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)

Clear site of all


rubbish, cut
down shrubs,
undergrowth
and small trees
not
exceedinding
600mm grith,
grub up roots
and burn or
remove from
site.
1 Labour
1.1 Mazdoor Sqm 0.035 425 14.875
2 Basic cost Sqm 14.875 A
3 Overhead charges 5% 0.74375 B
4 Establishment charges 2.5% 0.371875 C
5 Total cost 15.99063 D=A+B+C
6 Contractor's profit 10% 1.599063 E
Rate to be quoted/tendering cost(rs/sqm 17.58969 F=E+D
Basic Cost of Cement Mortar Var

Direct/Indirect Cost of CM 1 : 1
Sum of
Sr. Description of Work Unit of Productivity Cost/Unit Sum of Amount
No. Work Constant Amount of
Resourses

A Material 7704.89
i Cement Kg 1058.830 5.65 5977.11
ii Sand Cum 0.730 2341.43 1709.98
iii Water Lit 140.000 0.13 17.80
B Labour for Mixing 470.00
i Mazdoor Cum 1.0 425.00 425.00
ii Bhisti Cum 0.1 450.00 45.00
C Basic Cost 8174.89

Direct/Indirect Cost of CM 1 : 3
Sum of
Sr. Unit of Productivity Sum of Amount
No. Description of Work Work Constant Cost/Unit Amount of
Resourses

A Material 5368.93
i Cement Kg 493.030 5.65 2783.16
ii Sand Cum 1.097 2341.43 2567.97
iii Water Lit 140.000 0.13 17.80
B Labour for Mixing 470.00
i Mazdoor Cum 1.0 425.00 425.00
ii Bhisti Cum 0.1 450.00 45.00
C Basic Cost 5838.93

Direct/Indirect Cost of CM 1 : 6
Sum of
Sr. Unit of Productivity Sum of Amount
Description of Work Cost/Unit
No. Work Constant Amount of
Resourses
A Material 4020.73
i Cement Kg 254.200 5.65 1434.96
ii Sand Cum 1.097 2341.43 2567.97
iii Water Lit 140.000 0.13 17.80
B Labour for Mixing 470.00
i Mazdoor Cum 1.0 425.00 425.00
ii Bhisti Cum 0.1 450.00 45.00
C Basic Cost 4490.73

Basic Cost of Cement Mortar Various Pra

Direct/Indirect Cost of CM 1 : 1
Sum of
Sr. Unit of Productivity Sum of Amount
Description of Work Cost/Unit
No. Work Constant Amount of
Resourses

A Material 7843.65
i Cement Kg 1058.830 5.65 5977.11
ii Sand Cum 0.730 2531.43 1848.74
iii Water Lit 140.000 0.13 17.80
B Basic Cost 7843.65

Direct/Indirect Cost of CM 1 : 3
Sum of
Sr. Unit of Productivity Sum of Amount
No. Description of Work Work Constant Cost/Unit Amount of
Resourses

A Material 5577.31
i Cement Kg 493.030 5.65 2783.16
ii Sand Cum 1.097 2531.43 2776.35
iii Water Lit 140.000 0.13 17.80
B Basic Cost 5577.31

Direct/Indirect Cost of CM 1 : 6
Sum of
Sr. Unit of Productivity Sum of Amount
No. Description of Work Work Constant Cost/Unit Amount of
Resourses

A Material 4229.11
i Cement Kg 254.200 5.65 1434.96
ii Sand Cum 1.097 2531.43 2776.35
iii Water Lit 140.000 0.13 17.80
B Basic Cost 4229.11
Cement Mortar Various Praportion by Hand Mixing

Direct/Indirect Cost of CM 1 : 2

Remark Sr. No. Description of Work Unit of Productivit Cost/Unit


Work y Constant

A Material
i Cement Kg 699.050 5.65
2.5% Wastage ii Sand Cum 0.974 2341.43
iii Water Lit 140.000 0.13
B Labour for Mixing
i Mazdoor Cum 1.0 425.00
ii Bhisti Cum 0.1 450.00
C Basic Cost

Direct/Indirect Cost of CM 1 : 4

Unit of Productivit
Remark Sr. No. Description of Work Work y Constant Cost/Unit

A Material
i Cement Kg 382.330 5.65
2.5% Wastage ii Sand Cum 1.097 2341.43
iii Water Lit 140.000 0.13
B Labour for Mixing
i Mazdoor Cum 1.0 425.00
ii Bhisti Cum 0.1 450.00
C Basic Cost

Direct/Indirect Cost of CM 1 : 8

Unit of Productivit
Remark Sr. No. Description of Work Cost/Unit
Work y Constant
A Material
i Cement Kg 192.700 5.65
2.5% Wastage ii Sand Cum 1.097 2341.43
iii Water Lit 140.000 0.13
B Labour for Mixing
i Mazdoor Cum 1.0 425.00
ii Bhisti Cum 0.1 450.00
C Basic Cost

nt Mortar Various Praportion by Hand Mixing for Plastering

Direct/Indirect Cost of CM 1 : 2

Unit of Productivit
Remark Sr. No. Description of Work Cost/Unit
Work y Constant

A Material
i Cement Kg 699.050 5.65
2.5% Wastage ii Sand Cum 0.974 2531.43
iii Water Lit 140.000 0.13
B Basic Cost

Direct/Indirect Cost of CM 1 : 4

Unit of Productivit
Remark Sr. No. Description of Work Work y Constant Cost/Unit

A Material
i Cement Kg 382.330 5.65
2.5% Wastage ii Sand Cum 1.097 2531.43
iii Water Lit 140.000 0.13
B Basic Cost

Direct/Indirect Cost of CM 1 : 8
Unit of Productivit
Remark Sr. No. Description of Work Work y Constant Cost/Unit

A Material
i Cement Kg 192.700 5.65
2.5% Wastage ii Sand Cum 1.097 2531.43
iii Water Lit 140.000 0.13
B Basic Cost
of CM 1 : 2
Sum of
Sum of Amount Remark
Amount of
Resourses

6243.92
3946.15
2279.97 2.5% Wastage
17.80
470.00
425.00
45.00
6713.92

of CM 1 : 4
Sum of
Sum of Amount
Amount of Remark
Resourses

4744.02
2158.26
2567.97 2.5% Wastage
17.80
470.00
425.00
45.00
5214.02

of CM 1 : 8
Sum of
Sum of Amount
Remark
Amount of
Resourses
3673.56
1087.79
2567.97 2.5% Wastage
17.80
470.00
425.00
45.00
4143.56

of CM 1 : 2
Sum of
Sum of Amount
Remark
Amount of
Resourses

6428.93
3946.15
2464.98 2.5% Wastage
17.80
6428.93

of CM 1 : 4
Sum of
Sum of Amount
Amount of Remark
Resourses

4952.41
2158.26
2776.35 2.5% Wastage
17.80
4952.41

of CM 1 : 8
Sum of
Sum of Amount
Amount of Remark
Resourses

3881.94
1087.79
2776.35 2.5% Wastage
17.80
3881.94
Direct/Indirect Cost of PCC 1:5:10
Sum of
Sr. Unit of Productivit Cost/Uni Sum of Amount
No. Description of Work Work y Constant t of
Amount Resourse
s

Work out direct and indirect cost of PCC (1:5:10) for foundation bed (i.e. at a depth of 1.2m) Note: The
1 work site falls in both municipal and greater limits of Hyderabad. Work out percentages of all
resources.
A Material 3085.95
i Cement Kg 129.150 5.645 729.052
ii Fine Aggregate Cum 0.482 1276.300 614.858
iii Coarse Aggregate Cum 0.974 1778.900 1732.204
iv Water Lit 77.490 0.127 9.841
B Labour for Mixing 453.39
i Mazdoor Cum 0.5 425 212.5
ii Bhisti Cum 0.1 450 45
iii Mixer Operator Cum 0.07 500 35
iv Mixer Machine Cum 0.07 2298.4 160.888
C Labour for Conveying, Pouring, Curing etc. 812.48
i Mason Cum 0.1 470 47
ii Mazdoor Cum 1.13 425 480.25
iii Bhisti Cum 0.6 450 270
iv Vibrator Cum 0.07 217.6 15.232
D Basic Cost 4351.82
E Overhead Charges @ 5% 217.59
F Establishment Charges @ 2.5% 108.80
G Total Cost 4678.21
H Profit @ 10% 467.82
I Rate to be quoted/ Tendering Cost 5146.03
Remark

of 1.2m) Note: The Profit, 10%


centages of all
Establishme
nt, 2.5%
Overhead
3085.95 60
5%
1265.87 25 Labour
1
217.59 5 Overhead Charges
2
Labour MaterialCharges
108.824%2.5 Establishment 59% 3
467.82 10 Profit 4
5146.03 5

:
Direct/Indirect Cost of RCC 1:2:4
Sum of
Unit of Productivit Cost/Uni Sum of Amount
Sr. No. Description of Work Work y Constant t of
Amount Resourse
s

Work out direct and indirect cost of RCC (1:2:4) for footing bed (i.e. at a depth of 1.2m) Note:
1 The work site falls in both municipal and greater limits of Hyderabad. Work out percentages of
all resources.50%sand to be replaced with M Sand/Robo Sand,Mix super Plasticizer as
admixture, 1/3 of CA to be replaced with baby chips/10mm CA

A Material 3122.68
i Cement Kg 308.530 5.645 1741.652
ii Fine Aggregate Cum 0.226 1276.300 287.806
50% M Sand Cum 0.226
iii Coarse Aggregate Cum 0.601 1778.900 1069.712
1/3 Baby Chips/10 mm CA Cum 0.301
Super Plasticizer Kg 123.412 55.000 6787.660
iv Water Lit 185.118 0.127 23.510
B Labour for Mixing 453.39
i Mazdoor Cum 0.5 425 212.5
ii Bhisti Cum 0.1 450 45
iii Mixer Operator Cum 0.07 500 35
iv Mixer Machine Cum 0.07 2298.4 160.888
C Labour for Conveying, Pouring, Curing etc. 1092.63
i Mason Cum 0.17 470 79.9
ii Mazdoor Cum 1.5 425 637.5
iii Bhisti Cum 0.8 450 360
iv Vibrator Cum 0.07 217.6 15.232
D Basic Cost 4668.70
E Overhead Charges @ 5% 233.43
F Establishment Charges @ 2.5% 116.72
G Total Cost 5018.85
H Profit @ 10% 501.89
I Rate to be quoted/ Tendering Cost 5520.74
Remark

pth of 1.2m) Note:


out percentages of
r Plasticizer as
CA
Direct/Indirect Cost of Rebar Steel
Sum of
Sr. Unit of Productivit Sum of Amount
No. Description of Work Work y Constant Cost/Unit of
Amount Resours Remark

es

Cutting, bending, fabricating, placing in position and laying with MS wire at each intersection,
1 reinforcement using plain round/deformed/tor steel bars.( Consider 3% of steel as wastage Es
as salvage and 1.5% scrap )
A Material 5386.87 Overhe
i Rebar Quintel 1.000 5219.43 5219.43 5%
Wastage - Salvage Quintel 0.030 5219.43 156.58 Labour,
Wastage - Scrap Quintel -0.015 2609.72 -39.15 12%
ii Binding Wire kg 1.000 50.00 50.00
B Labour 895.00
i Blacksmith Quintel 1.00 470.00 470.00
ii Mazdoor Quintel 1.00 425.00 425.00
C Basic Cost 6281.87
D Overhead Charges @ 5% 314.09
E Establishment Charges @ 2.5% 157.05
F Total Cost 6753.01
G Profit @ 10% 675.30
H Rate to be quoted/ Tendering Cost 7428.31
Profit, 10%
Establishm
ent, 2%
Overhead, Material 72.5 5386.87
5% Labour 12.0 895.00
Material
Labour, Overhead Charges 5.0
Labour
314.09
12% Material,Charge
Establishment 2.5
Overhead 157.05
Charges
Profit 71% 10.0 675.30
Establishment Charges
Profit 7428.31
Direct/Indirect Cost of Burnt Brick Masonary Using Old S

Direct/Indirect Cost of One Brick Thick BBM (Traditional)


Sum of
Sr. Description of Work Unit of Productivity Cost/Unit Sum of Amount
No. Work Constant Amount of
Resourses

1 Work out unit cost for constructing a masonary using burnt clay brick (traditional) in CM 1 : 4 in
ground floor one brick thick wall

A Material 5044.69
i Cement Mortar(1 : 4) Cum 0.252 5214.02 1314.72
ii Bricks Nos 466.375 8.00 3729.97
B Labour for Construction 1370.85
i Mason Cum 0.98 470 460.6
ii Mazdoor Cum 1.93 425 820.25
iii Bhisti Cum 0.2 450 90
C Labour for Raking out of joints 17.90
i Mason Sqm 0.02 470 9.4
ii Mazdoor Sqm 0.02 425 8.5
D Basic Cost 6433.44
E Overhead Charges @ 5% 321.67
F Establishment Charges @ 2.5% 160.84
G Total Cost 6915.94
H Profit @ 10% 691.59
I Rate to be quoted/ Tendering Cost 7607.54

Direct/Indirect Cost of One Brick Thick BBM (Traditional)


Sum of
Sr. Unit of Productivity Sum of Amount
Description of Work Cost/Unit
No. Work Constant Amount of
Resourses

Work out unit cost for constructing a masonary using burnt clay brick (traditional) in CM 1 : 3 in
2 ground floor to radius of 5.3m one brick thick wall
A Material 5202.26
i Cement Mortar(1 : 3) Cum 0.252 5838.93 1472.29
ii Bricks Nos 466.375 8.00 3729.97
B Labour for Construction 1718.30
i Mason Cum 1.24 470 582.8
ii Mazdoor Cum 2.46 425 1045.5
iii Bhisti Cum 0.2 450 90
C Labour for Raking out of joints 17.90
i Mason Sqm 0.02 470 9.4
ii Mazdoor Sqm 0.02 425 8.5
D Basic Cost 6938.46
E Overhead Charges @ 5% 346.92
F Establishment Charges @ 2.5% 173.46
G Total Cost 7458.84
H Profit @ 10% 745.88
I Rate to be quoted/ Tendering Cost 8204.72

Direct/Indirect Cost of Half Brick Thick BBM (Traditional)


Sum of
Sr. Unit of Productivity Sum of Amount
Description of Work Cost/Unit
No. Work Constant Amount of
Resourses

Work out unit cost for constructing a reinforced (at every fourth layer) masonary using burnt
3
clay brick (traditional) in CM 1 : 3 in ground floor half brick thick wall
A Material 608.07
i Cement Mortar(1 : 3) Cum 0.024 5838.93 137.65
ii Bricks Nos 54.33 8.00 434.48

6 mm dia steel for strengthenig


iii walls every fourth course const = kg 0.69 52.19 35.94
3.13 m/Sqm @ 0.22kg/m

B Labour for Construction 168.35


i Mason Cum 0.13 470 61.1
ii Mazdoor Cum 0.21 425 89.25
iii Bhisti Cum 0.04 450 18
C Labour for Raking out of joints 17.90
i Mason Sqm 0.02 470 9.4
ii Mazdoor Sqm 0.02 425 8.5
D Basic Cost 794.32
E Overhead Charges @ 5% 39.72
F Establishment Charges @ 2.5% 19.86
G Total Cost 853.90
H Profit @ 10% 85.39
I Rate to be quoted/ Tendering Cost 939.29

Direct/Indirect Cost of Half Brick Thick Honeycomb BBM (Traditional)


Sum of
Sr. Unit of Productivity Sum of Amount
No. Description of Work Work Constant Cost/Unit Amount of
Resourses

Work out unit cost for constructing a honeycomb masonary using burnt clay brick (traditional) in
4 CM 1 : 3 in ground floor half brick thick wall
A Material 360.59
i Cement Mortar(1 : 3) Cum 0.008 5838.93 49.08
ii Bricks Nos 38.950 8.00 311.51
B Labour for Construction 184.25
i Mason Sqm 0.2 470 94
ii Mazdoor Sqm 0.17 425 72.25
iii Bhisti Sqm 0.04 450 18
C Labour for Raking out of joints 17.90
i Mason Sqm 0.02 470 9.4
ii Mazdoor Sqm 0.02 425 8.5
D Basic Cost 562.74
E Overhead Charges @ 5% 28.14
F Establishment Charges @ 2.5% 14.07
G Total Cost 604.95
H Profit @ 10% 60.49
I Rate to be quoted/ Tendering Cost 665.44

Direct/Indirect Cost of Brick on Edge Wall Masonary (Traditional)


Sum of
Sr. Unit of Productivity Sum of Amount
No. Description of Work Work Constant Cost/Unit Amount of
Resourses

Work out unit cost for constructing a reinforced (at every third layer) masonary using burnt clay
5
brick (traditional) in CM 1 : 3 in ground floor brick on edge wall
A Material 372.36
i Cement Mortar(1 : 3) Cum 0.009 5838.93 53.86
ii Bricks Nos 35.88 8.00 286.92

6 mm dia steel for strengthenig


iii walls every third course const = kg 0.61 52.19 31.58
2.75 m/Sqm @ 0.22kg/m

B Labour for Construction 178.65


i Mason Sqm 0.17 470 79.9
ii Mazdoor Sqm 0.19 425 80.75
iii Bhisti Sqm 0.04 450 18
C Labour for Raking out of joints 17.90
i Mason Sqm 0.02 470 9.4
ii Mazdoor Sqm 0.02 425 8.5
D Basic Cost 568.91
E Overhead Charges @ 5% 28.45
F Establishment Charges @ 2.5% 14.22
G Total Cost 611.58
H Profit @ 10% 61.16
I Rate to be quoted/ Tendering Cost 672.74
asonary Using Old Size Bricks (Traditional)

onal)

Remark

tional) in CM 1 : 4 in 10%
2%

5%
Material 66.31
Labour 18.25
Overhead 5.00 Material
Labour
Establishment 2.50
Overhead
18% Profit 10.00 Establishment
Profit
65%

onal)

Remark

tional) in CM 1 : 3 in

Material 63.41
Labour 10% 21.16
2%
Overhead 5.00
Establishment
5% 2.50

Material
Labour
Overhead
10%
2%

5%
Profit 10.00
Material
Labour
Overhead
21% Establishment
Profit
62%

nal)

Remark

onary using burnt


k wall

10%
2%

5%

Material
Labour
Material 64.74 Overhead
19% Labour 19.83 Establishment
Overhead 5.00 Profit
Establishment 2.50 63%
Profit 10.00

raditional)
Remark

brick (traditional) in

Material10% 54.19
2%
Labour 30.38
5%
Overhead 5.00
Establishment 2.50
Profit 10.00 Material
Labour
Overhead
53% Establishment
Profit
30%

ditional)

Remark

ary using burnt clay


wall

10%
2%

5%

Material
Labour
Material 55.35 Overhead
Labour 29.22 54% Establishment
Overhead 5.00 Profit
29% Establishment 2.50
Overhead
54% Establishment
Profit
29%
Profit 10.00
Direct/Indirect Cost of Stone masonary
Sum of
Producti
Sr. Unit of vity Sum of Amount
No. Description of Work Work Constan Cost/Unit of
Amount Resourse Remark
t s

1 Work out unit cost for constructing a CRS masonary in CM 1 : 6 in superstructure


A Material 2590.92
i Cement Mortar(1 : 6) Cum 0.280 4490.73 1257.40
ii Stones Cum 1.250 904.42 1130.52
Through Stone Nos 7.000 29.00 203.00
B Labour for Construction 1687.00
i Mason Cum 1.6 470 752
ii Mazdoor Cum 2.2 425 935
C Basic Cost 4277.92
D Overhead Charges @ 5% 213.90
E Establishment Charges @ 2.5% 106.95
F Total Cost 4598.77
G Profit @ 10% 459.88
H Rate to be quoted/ Tendering Cost 5058.64
10%
2%

5%
Material 51.22
Labour 33.35
Material
Overhead 5
Labour
Establishm 2.5 Overhead
50%
Profit 10 Establishment
Profit

33%
Direct/Indirect Cost of Two coat plastering
Sum of
Sr. Unit of Productivit Sum of Amount
No. Description of Work Work y Constant Cost/Unit Amount of Remark
Resourses

Work out unit cost for plastering on to a one brick ( old size brick ) thick masonary in two coat,
1
whereas first coat of 9 mm CM (1 : 4) and second coat thickness of 3mm in CM (1 : 3)

First coat of 9 mm thick CM 1 : 4 ( considering 10 sqm area )


A Material 690.37
i Cement Mortar(1 : 4) Cum 0.139 4952.41 690.37
B Labour for Plastering 721.40
i Mason/Plasterer Sqm 0.32 470 150.40
ii Mazdoor Sqm 0.92 425 391.00
Bhisti Sqm 0.4 450 180.00
C Basic Cost of 1 coat
For 10 Sqm 1411.77
For 1 Sqm 141.18
For 1 Sqft 13.12
Second coat of 3 mm thick CM 1 : 3 ( considering 10 sqm area )
D Material 171.50
i Cement Mortar(1 : 3) Cum 0.031 5577.31 171.50
E Labour for Plastering 560.30
i Mason/Plasterer Sqm 0.14 470 65.80
ii Mazdoor Sqm 0.74 425 314.50
Bhisti Sqm 0.4 450 180.00
F Basic Cost of 2 coat
For 10 Sqm 731.80
For 1 Sqm 73.18
For 1 Sqft 6.80
G Total Basic Cost 214.36
H Overhead Charges @ 5% 10.72
I Establishment Charges @ 2.5% 5.36
J Total Cost 230.43
K Profit @ 10% 23.04
253.48 For 1 sqm
L Rate to be quoted/ Tendering Cost
23.56 For 1 sqft
For mortar volume 1 coat of 9 mm
Area 10 Sqm
thickness 13.6 mm Consider uneven surface & key for next coat
volume 0.136 Cum
Add 2.50% for mortar dropping
Volume 0.1394 Cum

For Labour 1 coat of 9 mm


Thick in mm 15 5 1 9 For 10 Sqm
Mason/Sqm 0.05 0.015 0.003 0.032 0.32
Mazdoor/Sqm 0.11 0.015 0.003 0.092 0.92
Bhisti/Sqm 0.04 0.04 0.4

For mortar volume 2 coat of 3mm


Area 10 Sqm
thickness 3 mm
volume 0.030 Cum
Add 2.50% for mortar dropping
Volume 0.03075 Cum

For Labour 2 coat of 3 mm


Thick in mm 15 5 1 3 For 10 Sqm
Mason/Sqm 0.05 0.015 0.003 0.014 0.14
Mazdoor/Sqm 0.11 0.015 0.003 0.074 0.74
Bhisti/Sqm 0.04 0.04 0.4

Material 10% 34
Labour 2% 51
Overhead
5% 5
Establishment 2.5 33%
Material
Labour
Overhead
Establishment
10%
2%

5%
33%
Profit 10 Material
Labour
Overhead
Establishment
Profit

50%
Rs. Per
Sr.no Description unit
unit

work out cost per hour of a 4Cu.m tipper capital cost Rs 6 lakh
and life is 8000hours cost of tyres 0.75 lakh and life is 1500
hours
Soln:- Capital cost
deperciation of tipper = 90%*6lakh / 8000 hour 67.5 per hour
cost of per tyres = Rs. 75000/1500 hr 50 per hour
running repair of tipper = 40%*((90%*6lakh)/8000hour) 27 per hour
Total cost 144.5 per hour

Crew

1 No. operator @ Rs. 15000/- per month (8 hour per day*26


day) 15000 per month

1 No. helper @ Rs. 8000/- per month (8 hour per day*26 day) 8000 per month

1/4 No. mechanic @ Rs. 22000/- per month (8 hour per


day*26 day) 5500 per month

1/4 No. security @ Rs. 8000/- per month (8 hour per day*26
day) 2000 per month
Total cost 30500 per month
Add, 25% toward bonus, gratuity etc 7625 per year

Total amount = Rs. 7625+12month*total capital cost 373625 per month

Total cost = Rs. Total amount/(8hr*26day*12month) 149.690 per hour

Fule
8 lit per hour of H.S,D @71.11 per liter 568.88 per hour
Lubricant 33% of diesel charge 187.7304 per hour
sundries 10% of above diesel charges 56.888 per hour
Total cost 813.498 per hour
Grand Total 1107.688 per hour
Rs. Per
Sr.no Description unit unit

work out cost per hour of a dumper of 18Cu.m capacity.


Capital cost ; Rs. 1200000/- & life is 12000 hr
Cost of tyres ; Rs. 120000/- & life is 1500 hr
Capital cost may be depreciated by 90%
fule consumption is 20 lit per hour
Soln:- Capital cost
deperciation of dumper = 90%*12lakh / 12000 hour 90 per hour
cost of per tyres = Rs. 120000/1500 hr 80 per hour
running repair of dumper = 40%*((90%*12lakh)/12000hour) 36 per hour
Total cost 206 per hour

Crew
1 No. operator @ Rs. 15000/- per month (8 hour per day*26
day) 15000 per month

1 No. helper @ Rs. 8000/- per month (8 hour per day*26 day) 8000 per month

1/4 No. mechanic @ Rs. 22000/- per month (8 hour per


day*26 day) 5500 per month

1/4 No. security @ Rs. 8000/- per month (8 hour per day*26
day) 2000 per month
Total cost 30500 per month
Add, 25% toward bonus, gratuity etc 7625 per year

Total amount = Rs. 7625+12month*total capital cost 373625 per month

Total cost = Rs. Total amount/(8hr*26day*12month) 149.690 per hour

Fule
20 lit per hour of H.S,D @71.11 per liter 1422.2 per hour
Lubricant 33% of diesel charge 469.326 per hour
sundries 10% of above diesel charges 142.22 per hour
Total cost 2033.746 per hour
Grand Total 2389.436 per hour
Rs. Per
Sr.no Description unit unit

work out cost per hour of a transit mixer of 6Cu.m capacity.

Cost : Rs. 2100000/- (inclusive of tyres)


Life is 10000 hours
Depreciation : 90%

Repair : 20%

crew : a)1 no. of operator; b) 1 no. of helper; c) 1/4th


technician; d) 1/6th security guard

P.O.L : H.S.D. Diesel 30 lit per hour & lubricants etc.; 60%
diesel charges
Soln:- Capital cost
deperciation of transit mixer = 90%*21lakh / 10000 hour 189 per hour
running repair of transit mixer =
20%*((90%*21lakh)/10000hour) 37.8 per hour
Total cost 226.8 per hour

Crew

1 No. operator @ Rs. 15000/- per month (8 hour per day*26


day) 15000 per month

1 No. helper @ Rs. 8000/- per month (8 hour per day*26 day) 8000 per month

1/4 No. mechanic @ Rs. 22000/- per month (8 hour per


day*26 day) 5500 per month
1/6 No. security @ Rs. 8000/- per month (8 hour per day*26
day) 1333.333 per month
Total cost 29833.33 per month
Add, 25% toward bonus, gratuity etc 7458.333 per year

Total amount = Rs. 7458.33+12month*total capital cost 365458.3 per month

Total cost = Rs. Total amount/(8hr*26day*12month) 146.418 per hour

Fule
30 lit per hour of H.S,D @71.11 per liter 2133.3 per hour
Lubricant 60% of diesel charge 1279.98 per hour
sundries 10% of above diesel charges 213.33 per hour
Total cost 3626.610 per hour
Grand Total 3999.828 per hour
Rs. Per
Sr.no Description unit
unit

work out cost of excavator of 1.91 Cu.m 1.91 C


cycle time = 50 second

solve:- cycle per hour= ((60*60)/50) 72 per hour

Ideal Production = 72*1.91 137.52 Cu.m

Net Production = Ideal Production*Bucket


factor*Efficiency=137.52*0.8*0.7 77.0112 Cu.m/hr

Production per shift=Net production*6hr 462.0672 Cu.m


Assume:- Capital cost 4000000 Rs
life 12000 hr
Depreciation 90 %
repair 50 %
Diesel 18 lit/hr
Lubricants 28 %
crew (L.S) 50 Rs/hr
Soln:- Capital cost
deperciation of Excavator = 90%*40lakh / 12000 hour 300 per hour

running repair of Excavator = 50%*((90%*40lakh)/12000hour) 150 per hour


Total cost 450 per hour

Crew
Total cost = Rs. Total amount(L.S) 50.000 per hour

Fule
18 lit per hour of H.S,D @71.11 per liter 1279.98 per hour
Lubricant 28% of diesel charge 358.3944 per hour
Total cost 1638.374 per hour
Grand Total 2138.374 per hour
Sr.no Description Rs. Per unit
unit
Work out per hour cost of batching plant 30Cu.m/hr
Capital cost : Rs 2200000/-
Life : 12000 hr
Depreacition : 95%
Repair : 100 %
crew
1 No. operator
1 No. operator for concrete drum
1 No. operator for water pump
3 No. helper
1 No. mechanic
1/2 No. Foremen
1/2 No. elctrician
1 No. security guard
Add 20 % toward bonus
Assumption 8*30*6+8*31*6 hours
P.O.L

7 lit diesel per hr and oil i.e. 20% diesel charges sundries 25%
of diesel charges

Soln:- Capital cost


deperciation of transit mixer = 95%*22lakh / 12000 hour 174.1667 per hour

running repair of transit mixer =


100%*((95%*22lakh)/12000hour) 174.1667 per hour
Total cost 348.3333 per hour

Crew
1 No. operator = 15000/- 15000 per month
1 No. operator for concrete drum = 12000/- 12000 per month
1 No. operator for water pump = 10000/- 10000 per month
3 No. helper = 8000/- 24000 per month
1 No. mechanic = 22000/- 22000 per month
1/2 No. Foremen = 20000/- 10000 per month
1/2 No. elctrician = 20000/- 10000 per month
1 No. security guard = 8000/- 8000.000 per month
sum amount of salaries 111000 per month
Adding 20% towards bonus/ Gratvity 22200 per month
cost per year 1354200 per year
Total cost 462.5 per hour
Fule
7 lit per hour of H.S,D @71.11 per liter 497.77 per hour
Lubricant 20% of diesel charge 99.554 per hour
sundries 25% of above diesel charges 124.4425 per hour
Total cost 721.767 per hour
Grand Total 1532.600 per hour

You might also like