Professional Documents
Culture Documents
Description of Source of
S.No Distance Cart Sandy Metal Dista km per
material material
Track Track Track ce unit
Col.1 Col.2 Col.3 Col.4 Col.5 Col.6 Col.7 Col.8 Col.9
1 Sand for concrete Guntur 150 0 2.80 3 5.80 78.86951
25 25.00 11.83475
122 122.00 9.84789
Coarse aggregate
3 Medak
40mm 20 0 2.8 3 5.8 78.86951
15 15 11.83475
Coarse aggregate
4 20mm Medak
20 0 2.8 3 5.8 78.8691
15 15 11.83475
5 Coarse aggregate
10mm Medak 20 0 2.8 3 5.8 78.8691
15 11.83475
457.4431
177.5213 315.5 67 127.5 126.0357 63.01494 0 75 1409.015 cum
634.9644
457.4431
177.5213 598 67 225 126.2536 63.01494 0 75 1789.233 cum
634.9644
457.4431
117.5213 675.5 67 247.5 126.2536 63.01494 0 75 1889.233
634.9644
457.4431
117.5213 503 67 190 126.0357 63.01494 0 75 1599.015 cum
574.9644
246.6292
185.7278
122.6667 4750 171.985 171.985 5093.97 tonne
1 Surface excavation not exceeding 30 cm deep, average 15cm deep,and getting
out.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
1.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil -
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.08 425 34
2 Basic cost Sqm 34 A
3 Overhead charges 5% 1.7 B
4 Establishment charges 2.5% 0.85 C
5 Total cost 36.55 D=A+B+C
6 Contractor's profit 10% 3.655 E
Rate to be quoted/tendering cost(rs/sqm 40.205 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
1.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.15 425 63.75
2 Basic cost Sqm 63.75 A
3 Overhead charges 5% 3.1875 B
4 Establishment charges 2.5% 1.59375 C
5 Total cost 68.53125 D=A+B+C
6 Contractor's profit 10% 6.853125 E
Rate to be quoted/tendering cost(rs/sqm 75.38438 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
1.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.31 425 131.75
2 Basic cost Sqm 131.75 A
3 Overhead charges 5% 6.5875 B
4 Establishment charges 2.5% 3.29375 C
5 Total cost 141.6313 D=A+B+C
6 Contractor's profit 10% 14.16313 E
Rate to be quoted/tendering cost(rs/sqm 155.7944 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
1.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
hard
1 Labour
1.1 Mazdoor Sqm 0.65 425 276.25
2 Basic cost Sqm 276.25 A
3 Overhead charges 5% 13.8125 B
4 Establishment charges 2.5% 6.90625 C
5 Total cost 296.9688 D=A+B+C
6 Contractor's profit 10% 29.69688 E
Rate to be quoted/tendering cost(rs/sqm 326.6656 F=E+D
2 Add to (or deduct from) item 1 above for every 3 cm above or below 15 cm average depth
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
2.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.01 425 4.25
2 Basic cost Sqm 4.25 A
3 Overhead charges 5% 0.2125 B
4 Establishment charges 2.5% 0.10625 C
5 Total cost 4.56875 D=A+B+C
6 Contractor's profit 10% 0.456875 E
Rate to be quoted/tendering cost(rs/sqm 5.025625 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
2.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.014 425 5.95
2 Basic cost Sqm 5.95 A
3 Overhead charges 5% 0.2975 B
4 Establishment charges 2.5% 0.14875 C
5 Total cost 6.39625 D=A+B+C
6 Contractor's profit 10% 0.639625 E
Rate to be quoted/tendering cost(rs/sqm 7.035875 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
2.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.034 425 14.45
2 Basic cost Sqm 14.45 A
3 Overhead charges 5% 0.7225 B
4 Establishment charges 2.5% 0.36125 C
5 Total cost 15.53375 D=A+B+C
6 Contractor's profit 10% 1.553375 E
Rate to be quoted/tendering cost(rs/sqm 17.08713 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
2.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.069 425 29.325
2 Basic cost Sqm 29.325 A
3 Overhead charges 5% 1.46625 B
4 Establishment charges 2.5% 0.733125 C
5 Total cost 31.52438 D=A+B+C
6 Contractor's profit 10% 3.152438 E
Rate to be quoted/tendering cost(rs/sqm 34.67681 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
3.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.3 425 127.5
2 Basic cost Sqm 127.5 A
3 Overhead charges 5% 6.375 B
4 Establishment charges 2.5% 3.1875 C
5 Total cost 137.0625 D=A+B+C
6 Contractor's profit 10% 13.70625 E
Rate to be quoted/tendering cost(rs/sqm 150.7688 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
3.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.52 425 221
2 Basic cost Sqm 221 A
3 Overhead charges 5% 11.05 B
4 Establishment charges 2.5% 5.525 C
5 Total cost 237.575 D=A+B+C
6 Contractor's profit 10% 23.7575 E
Rate to be quoted/tendering cost(rs/sqm 261.3325 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
3.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 1.18 425 501.5
2 Basic cost Sqm 501.5 A
3 Overhead charges 5% 25.075 B
4 Establishment charges 2.5% 12.5375 C
5 Total cost 539.1125 D=A+B+C
6 Contractor's profit 10% 53.91125 E
Rate to be quoted/tendering cost(rs/sqm 593.0238 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
3.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 2.84 425 1207
2 Basic cost Sqm 1207 A
3 Overhead charges 5% 60.35 B
4 Establishment charges 2.5% 30.175 C
5 Total cost 1297.525 D=A+B+C
6 Contractor's profit 10% 129.7525 E
Rate to be quoted/tendering cost(rs/sqm 1427.278 F=E+D
4 Excavation over areas not exceedinding 1.5 m deep and getting out.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
4.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.4 425 170
2 Basic cost Sqm 170 A
3 Overhead charges 5% 8.5 B
4 Establishment charges 2.5% 4.25 C
5 Total cost 182.75 D=A+B+C
6 Contractor's profit 10% 18.275 E
Rate to be quoted/tendering cost(rs/sqm 201.025 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
4.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.68 425 289
2 Basic cost Sqm 289 A
3 Overhead charges 5% 14.45 B
4 Establishment charges 2.5% 7.225 C
5 Total cost 310.675 D=A+B+C
6 Contractor's profit 10% 31.0675 E
Rate to be quoted/tendering cost(rs/sqm 341.7425 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
4.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 1.59 425 675.75
2 Basic cost Sqm 675.75 A
3 Overhead charges 5% 33.7875 B
4 Establishment charges 2.5% 16.89375 C
5 Total cost 726.4313 D=A+B+C
6 Contractor's profit 10% 72.64313 E
Rate to be quoted/tendering cost(rs/sqm 799.0744 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
4.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 3.94 425 1674.5
2 Basic cost Sqm 1674.5 A
3 Overhead charges 5% 83.725 B
4 Establishment charges 2.5% 41.8625 C
5 Total cost 1800.088 D=A+B+C
6 Contractor's profit 10% 180.0088 E
Rate to be quoted/tendering cost(rs/sqm 1980.096 F=E+D
Excavation not exceeding 1.5 m deep and getting out in trenches not exceedind 1.5 m wide
5 or for shafts , well,cesspits, manholes and the like, not exceeding 10sq m on plan.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
5.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.55 425 233.75
2 Basic cost Sqm 233.75 A
3 Overhead charges 5% 11.6875 B
4 Establishment charges 2.5% 5.84375 C
5 Total cost 251.2813 D=A+B+C
6 Contractor's profit 10% 25.12813 E
Rate to be quoted/tendering cost(rs/sqm 276.4094 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
5.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.96 425 408
2 Basic cost Sqm 408 A
3 Overhead charges 5% 20.4 B
4 Establishment charges 2.5% 10.2 C
5 Total cost 438.6 D=A+B+C
6 Contractor's profit 10% 43.86 E
Rate to be quoted/tendering cost(rs/sqm 482.46 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
5.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 2.19 425 930.75
2 Basic cost Sqm 930.75 A
3 Overhead charges 5% 46.5375 B
4 Establishment charges 2.5% 23.26875 C
5 Total cost 1000.556 D=A+B+C
6 Contractor's profit 10% 100.0556 E
Rate to be quoted/tendering cost(rs/sqm 1100.612 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
5.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 4.9 425 2082.5
2 Basic cost Sqm 2082.5 A
3 Overhead charges 5% 104.125 B
4 Establishment charges 2.5% 52.0625 C
5 Total cost 2238.688 D=A+B+C
6 Contractor's profit 10% 223.8688 E
Rate to be quoted/tendering cost(rs/sqm 2462.556 F=E+D
Extra over items 3 and 4 above for each additional 1.5 m depth (or part thereof ) beyond
6 the first stage of 1.5 m depth.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
6.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.12 425 51
2 Basic cost Sqm 51 A
3 Overhead charges 5% 2.55 B
4 Establishment charges 2.5% 1.275 C
5 Total cost 54.825 D=A+B+C
6 Contractor's profit 10% 5.4825 E
Rate to be quoted/tendering cost(rs/sqm 60.3075 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
6.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.12 425 51
2 Basic cost Sqm 51 A
3 Overhead charges 5% 2.55 B
4 Establishment charges 2.5% 1.275 C
5 Total cost 54.825 D=A+B+C
6 Contractor's profit 10% 5.4825 E
Rate to be quoted/tendering cost(rs/sqm 60.3075 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
6.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.18 425 76.5
2 Basic cost Sqm 76.5 A
3 Overhead charges 5% 3.825 B
4 Establishment charges 2.5% 1.9125 C
5 Total cost 82.2375 D=A+B+C
6 Contractor's profit 10% 8.22375 E
Rate to be quoted/tendering cost(rs/sqm 90.46125 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
6.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.18 425 76.5
2 Basic cost Sqm 76.5 A
3 Overhead charges 5% 3.825 B
4 Establishment charges 2.5% 1.9125 C
5 Total cost 82.2375 D=A+B+C
6 Contractor's profit 10% 8.22375 E
Rate to be quoted/tendering cost(rs/sqm 90.46125 F=E+D
Extra over item 5 above for each additional 1.5 m depth (or parth thereof) beyond the first
7 stage of 1.5 m depth.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
7.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.41 425 174.25
2 Basic cost Sqm 174.25 A
3 Overhead charges 5% 8.7125 B
4 Establishment charges 2.5% 4.35625 C
5 Total cost 187.3188 D=A+B+C
6 Contractor's profit 10% 18.73188 E
Rate to be quoted/tendering cost(rs/sqm 206.0506 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
7.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.61 425 259.25
2 Basic cost Sqm 259.25 A
3 Overhead charges 5% 12.9625 B
4 Establishment charges 2.5% 6.48125 C
5 Total cost 278.6938 D=A+B+C
6 Contractor's profit 10% 27.86938 E
Rate to be quoted/tendering cost(rs/sqm 306.5631 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
7.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 1.23 425 522.75
2 Basic cost Sqm 522.75 A
3 Overhead charges 5% 26.1375 B
4 Establishment charges 2.5% 13.06875 C
5 Total cost 561.9563 D=A+B+C
6 Contractor's profit 10% 56.19563 E
Rate to be quoted/tendering cost(rs/sqm 618.1519 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
7.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 1.88 425 799
2 Basic cost Sqm 799 A
3 Overhead charges 5% 39.95 B
4 Establishment charges 2.5% 19.975 C
5 Total cost 858.925 D=A+B+C
6 Contractor's profit 10% 85.8925 E
Rate to be quoted/tendering cost(rs/sqm 944.8175 F=E+D
ramming around posts etc., and removing surplus soil to a distance not exceeding 50 m
8 spread and levelled.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
8.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.41 425 174.25
2 Basic cost Sqm 174.25 A
3 Overhead charges 5% 8.7125 B
4 Establishment charges 2.5% 4.35625 C
5 Total cost 187.3188 D=A+B+C
6 Contractor's profit 10% 18.73188 E
Rate to be quoted/tendering cost(rs/sqm 206.0506 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
8.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.61 425 259.25
2 Basic cost Sqm 259.25 A
3 Overhead charges 5% 12.9625 B
4 Establishment charges 2.5% 6.48125 C
5 Total cost 278.6938 D=A+B+C
6 Contractor's profit 10% 27.86938 E
Rate to be quoted/tendering cost(rs/sqm 306.5631 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
8.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 1.23 425 522.75
2 Basic cost Sqm 522.75 A
3 Overhead charges 5% 26.1375 B
4 Establishment charges 2.5% 13.06875 C
5 Total cost 561.9563 D=A+B+C
6 Contractor's profit 10% 56.19563 E
Rate to be quoted/tendering cost(rs/sqm 618.1519 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
8.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 1.88 425 799
2 Basic cost Sqm 799 A
3 Overhead charges 5% 39.95 B
4 Establishment charges 2.5% 19.975 C
5 Total cost 858.925 D=A+B+C
6 Contractor's profit 10% 85.8925 E
Rate to be quoted/tendering cost(rs/sqm 944.8175 F=E+D
Taking up excavated material from spoil heaps, filling borrows/ baskets and
9 wheeling/removing and depositing
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.1.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
- at 25 m
distance
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.1.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.1.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.1.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.2.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
- at 50m
distance
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.2.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.2.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.2.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.3.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
- at 100m
distance
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.3.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.3.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.3.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.4.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
at 200 m
distance
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.4.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.4.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
9.4.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Taking up excavated materials from spoil heaps and loading manually into dumpers or
10 lorries.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
10.1 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Soft/loose
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
10.2 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Soil-
Hard/den
se
1 Labour
1.1 Mazdoor Sqm 0.25 425 106.25
2 Basic cost Sqm 106.25 A
3 Overhead charges 5% 5.3125 B
4 Establishment charges 2.5% 2.65625 C
5 Total cost 114.2188 D=A+B+C
6 Contractor's profit 10% 11.42188 E
Rate to be quoted/tendering cost(rs/sqm 125.6406 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
10.3 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock- Soft
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
10.4 Sr. No. Descriptio unit constant unit(₹) ount₹) ₹)
Rock-
Hard
1 Labour
1.1 Mazdoor Sqm 0.28 425 119
2 Basic cost Sqm 119 A
3 Overhead charges 5% 5.95 B
4 Establishment charges 2.5% 2.975 C
5 Total cost 127.925 D=A+B+C
6 Contractor's profit 10% 12.7925 E
Rate to be quoted/tendering cost(rs/sqm 140.7175 F=E+D
Item-11 Returning, filling and ramming excavated spoil around foundations(no lead
involved)
Productiv
Total Sum of
S.NO Description Unit ity/Mater Cost per Amount Amount(
ial Unit
(Rs.) Rs)
constant
Returning, filling
1 and ramming
excavated spoil
around
1 Labour
1.1 Mazdoor Sqm 0.21 425 89.25
2 Basic Cost(A) Sqm 89.25
3 Overhead Charges 5% (B) 4.46
4 Establishment Charges 2.5%(C) 2.23
5 Total Cost(D=A+B+C) 95.94
6 CP 10%( E) 9.59
Rate To be Quoted/Tendering Cost(Rs/Sqm) 105.54
Item-11 Returning, filling and ramming excavated spoil around foundations(no lead
involved)
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit ial Unit Amount Amount(
(Rs.) Rs)
constant
Returning, filling
1 and ramming
excavated spoil
around
1 Labour
1.1 Mazdoor Sqm 0.27 425 114.75
2 Basic Cost(A) Sqm 114.75
3 Overhead Charges 5% (B) 5.74
4 Establishment Charges 2.5%(C) 2.87
5 Total Cost(D=A+B+C) 123.36
6 CP 10%( E) 12.34
Rate To be Quoted/Tendering Cost(Rs/Sqm) 135.69
Item-12 Filling, Spreading/ levelling in layes of 25cm thickness, watering and well
ramming under floors, including lead upto 50 meters
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit (Rs.) Rs)
constant
Filling,
1 Spreading/
levelling in layes
of 25cm
1 Labour
1.1 Mazdoor Sqm 0.35 425 148.75
2 Basic Cost(A) Sqm 148.75
3 Overhead Charges 5% (B) 7.44
4 Establishment Charges 2.5%(C) 3.72
5 Total Cost(D=A+B+C) 159.91
6 CP 10%( E) 15.99
Rate To be Quoted/Tendering Cost(Rs/Sqm) 175.90
Item-13.1 Boreholes in clay, soft /loose or black cotton soil for single under-reamed piles
2 m deep and diposing off soil to a distance not exceeding 50m away, for bore
Productiv
Total Sum of
S.NO Description Unit ity/Mater Cost per Amount Amount(
ial Unit
(Rs.) Rs)
constant
Boreholes in
1 clay, soft /loose
or black cotton
soil for single
1 Labour
1.1 Mazdoor Sqm 1.14 425 484.5
2 Basic Cost(A) Sqm 484.5
3 Overhead Charges 5% (B) 24.23
4 Establishment Charges 2.5%(C) 12.11
5 Total Cost(D=A+B+C) 520.84
6 CP 10%( E) 52.08
Rate To be Quoted/Tendering Cost(Rs/Sqm) 572.92
Item-13.2 Boreholes in clay, soft /loose or black cotton soil for single under-reamed piles
2 m deep and diposing off soil to a distance not exceeding 50m away, for bore
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit
(Rs.) Rs)
constant
Boreholes in
1 clay, soft /loose
or black cotton
soil for single
1 Labour
1.1 Mazdoor Sqm 1.37 425 582.25
2 Basic Cost(A) Sqm 582.25
3 Overhead Charges 5% (B) 29.11
4 Establishment Charges 2.5%(C) 14.56
5 Total Cost(D=A+B+C) 625.92
6 CP 10%( E) 62.59
Rate To be Quoted/Tendering Cost(Rs/Sqm) 688.51
Item-13.2 Boreholes in clay, soft /loose or black cotton soil for single under-reamed piles
2 m deep and diposing off soil to a distance not exceeding 50m away, for bore
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit (Rs.) Rs)
constant
Boreholes in
1 clay, soft /loose
or black cotton
soil for single
1 Labour
1.1 Mazdoor Sqm 1.6 425 680
2 Basic Cost(A) Sqm 680
3 Overhead Charges 5% (B) 34.00
4 Establishment Charges 2.5%(C) 17.00
5 Total Cost(D=A+B+C) 731.00
6 CP 10%( E) 73.10
Rate To be Quoted/Tendering Cost(Rs/Sqm) 804.10
Item-14.1 Extra over item 13 above for each additional under reaming:-200mm Dia
Productiv Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit
constant (Rs.) Rs)
Item-14.2 Extra over item 13 above for each additional under reaming:-250mm Dia
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit (Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.6 425 255
2 Basic Cost(A) Sqm 255
3 Overhead Charges 5% (B) 12.75
4 Establishment Charges 2.5%(C) 6.38
5 Total Cost(D=A+B+C) 274.13
6 CP 10%( E) 27.41
Rate To be Quoted/Tendering Cost(Rs/Sqm) 301.54
Item-14.3 Extra over item 13 above for each additional under reaming:-300mm Dia
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit
(Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.7 425 297.5
2 Basic Cost(A) Sqm 297.5
3 Overhead Charges 5% (B) 14.88
4 Establishment Charges 2.5%(C) 7.44
5 Total Cost(D=A+B+C) 319.81
6 CP 10%( E) 31.98
Rate To be Quoted/Tendering Cost(Rs/Sqm) 351.79
Item-15.1 Extra over item 13 above for each additional metre depth(intermidiate depth
pro rata)
Productiv
Total Sum of
ity/Mater Cost per Amount Amount(
S.NO Description Unit
ial Unit
(Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.31 425 131.75
2 Basic Cost(A) Sqm 131.75
3 Overhead Charges 5% (B) 6.59
4 Establishment Charges 2.5%(C) 3.29
5 Total Cost(D=A+B+C) 141.63
6 CP 10%( E) 14.16
Rate To be Quoted/Tendering Cost(Rs/Sqm) 155.79
Item-15.2 Extra over item 13 above for each additional metre depth(intermidiate depth
pro rata)
Productiv
Total Sum of
ity/Mater Cost per
S.NO Description Unit Amount Amount(
ial Unit
(Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.4 425 170
2 Basic Cost(A) Sqm 170
3 Overhead Charges 5% (B) 8.50
4 Establishment Charges 2.5%(C) 4.25
5 Total Cost(D=A+B+C) 182.75
6 CP 10%( E) 18.28
Rate To be Quoted/Tendering Cost(Rs/Sqm) 201.03
Item-15.3 Extra over item 13 above for each additional metre depth(intermidiate depth
pro rata)
Productiv
Total Sum of
S.NO Description Unit ity/Mater Cost per Amount Amount(
ial Unit
(Rs.) Rs)
constant
Extra over item
1 13 above for
each additional
under reaming:-
1 Labour
1.1 Mazdoor Sqm 0.45 425 191.25
2 Basic Cost(A) Sqm 191.25
3 Overhead Charges 5% (B) 9.56
4 Establishment Charges 2.5%(C) 4.78
5 Total Cost(D=A+B+C) 205.59
6 CP 10%( E) 20.56
Rate To be Quoted/Tendering Cost(Rs/Sqm) 226.15
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
16 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Surface dressing
or trimming of
natural ground
to remove small
unequalities not
exceeding 15cm
deep (including
removing
vegetation/shru
bs/brushwood/
undergrowth
and carrying
away rubbish
to a distance of
50 m. (Sundry Soil
labours - (Hard/de
Excavator) nse)
Labour
1 Mazdoor Sqm 0.06 425 25.5
25.5
2 Basic Cost 25.5 A
3 Overhead charges (5%) 1.275 B=5% A
4 Establishment charges (2.5%) 0.6375 C=2.5%*A
5 Total cost 27.4125 D=A+B+C
6 Profit (10%) 2.74125 E=10%*D
Rate to be
quoted or
7 tendering cost 30.15375 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
17.1 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Drilling holes
(for blasting) in
rock manually
with boring bars
and drill bits
for :- 20 to 25
mm dia holes.
(Note:-In item
17 above allow
0.02 days per m
for
pointing/sharpe Rock
ning of tools by (Granite/t
one smith and rap/Gneis
one helper) s)
Labour
1 Mazdoor Sqm 0.51 425 216.75
216.75
2 Basic Cost 216.75 A
3 Overhead charges (5%) 10.8375 B=5% A
4 Establishment charges (2.5%) 5.41875 C=2.5%*A
5 Total cost 233.0063 D=A+B+C
6 Profit (10%) 23.30063 E=10%*D
Rate to be
quoted or
7 tendering cost 256.3069 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
17.2 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Drilling holes
(for blasting) in
rock manually
with boring bars
and drill bits
for :- 50 mm dia
holes. (Note:-In
item 17 above
allow 0.02 days
per m for
pointing/sharpe Rock
ning of tools by (Granite/t
one smith and rap/Gneis
one helper) s)
Labour
1 Mazdoor Sqm 2.05 425 871.25
871.25
2 Basic Cost 871.25 A
3 Overhead charges (5%) 43.5625 B=5% A
4 Establishment charges (2.5%) 21.78125 C=2.5%*A
5 Total cost 936.5938 D=A+B+C
6 Profit (10%) 93.65938 E=10%*D
Rate to be
quoted or
7 tendering cost 1030.253 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
17.3 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Drilling holes
(for blasting) in
rock manually
with boring bars
and drill bits
for :- 75 mm dia
holes. (Note:-In
item 17 above
allow 0.02 days
per m for
pointing/sharpe Rock
ning of tools by (Granite/t
one smith and rap/Gneis
one helper) s)
Labour
1 Mazdoor Sqm 4.9 425 2082.5
2082.5
2 Basic Cost 2082.5 A
3 Overhead charges (5%) 104.125 B=5% A
4 Establishment charges (2.5%) 52.0625 C=2.5%*A
5 Total cost 2238.688 D=A+B+C
6 Profit (10%) 223.8688 E=10%*D
Rate to be
quoted or
7 tendering cost 2462.556 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
18.1 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Hardcore laid,
spread, levelled,
watered and
consolidated to
required levels
in layers of :-75
mm
consolidated
thickness.
Labour
1 Mazdoor Sqm 0.05 425 21.25
21.25
2 Basic Cost 21.25 A
3 Overhead charges (5%) 1.0625 B=5% A
4 Establishment charges (2.5%) 0.53125 C=2.5%*A
5 Total cost 22.84375 D=A+B+C
6 Profit (10%) 2.284375 E=10%*D
Rate to be
quoted or
7 tendering cost 25.12813 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
18.2 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Hardcore laid,
spread, levelled,
watered and
consolidated to
required levels
in layers of :-
150 mm
consolidated
thickness.
Labour
1 Mazdoor Sqm 0.09 425 38.25
38.25
2 Basic Cost 38.25 A
3 Overhead charges (5%) 1.9125 B=5% A
4 Establishment charges (2.5%) 0.95625 C=2.5%*A
5 Total cost 41.11875 D=A+B+C
6 Profit (10%) 4.111875 E=10%*D
Rate to be
quoted or
7 tendering cost 45.23063 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
18.3 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Hardcore laid,
spread, levelled,
watered and
consolidated to
required levels
in layers of :-
225 mm
consolidated
thickness.
Labour
1 Mazdoor Sqm 0.14 425 59.5
59.5
2 Basic Cost 59.5 A
3 Overhead charges (5%) 2.975 B=5% A
4 Establishment charges (2.5%) 1.4875 C=2.5%*A
5 Total cost 63.9625 D=A+B+C
6 Profit (10%) 6.39625 E=10%*D
Rate to be
quoted or
7 tendering cost 70.35875 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
18.4 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Hardcore laid,
spread, levelled,
watered and
consolidated to
required levels
in layers of :-
250 mm
consolidated
thickness and
above
Labour
1 Mazdoor Sqm 0.5 425 212.5
212.5
2 Basic Cost 212.5 A
3 Overhead charges (5%) 10.625 B=5% A
4 Establishment charges (2.5%) 5.3125 C=2.5%*A
5 Total cost 228.4375 D=A+B+C
6 Profit (10%) 22.84375 E=10%*D
Rate to be
quoted or
7 tendering cost 251.2813 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
19 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Stone pitching
150 mm thick.
Labour
1 Mazdoor Sqm 0.12 425 51
51
2 Basic Cost 51 A
3 Overhead charges (5%) 2.55 B=5% A
4 Establishment charges (2.5%) 1.275 C=2.5%*A
5 Total cost 54.825 D=A+B+C
6 Profit (10%) 5.4825 E=10%*D
Rate to be
quoted or
7 tendering cost 60.3075 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
20 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Stone pitching
250 mm thick.
Labour
1 Mazdoor Sqm 0.15 425 63.75
63.75
2 Basic Cost 63.75 A
3 Overhead charges (5%) 3.1875 B=5% A
4 Establishment charges (2.5%) 1.59375 C=2.5%*A
5 Total cost 68.53125 D=A+B+C
6 Profit (10%) 6.853125 E=10%*D
Rate to be
quoted or
7 tendering cost 75.38438 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
21 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Cut up or lift
existing turf into
suitable sods,
roll up and set
aside for reuse.
Labour
1 Mazdoor Sqm 0.06 425 25.5
25.5
2 Basic Cost 25.5 A
3 Overhead charges (5%) 1.275 B=5% A
4 Establishment charges (2.5%) 0.6375 C=2.5%*A
5 Total cost 27.4125 D=A+B+C
6 Profit (10%) 2.74125 E=10%*D
Rate to be
quoted or
7 tendering cost 30.15375 F=D+E
Sum of
Productivi Amount
ty/ Sum of
Material Cost ( Rs ) /Amount Resource
22 Sr. No. Description Unit constant Per Unit (Rs) (Rs) Remark
Relaying turf,
including
preparing
surface,
watering and
light rolling
Labour
1 Mazdoor Sqm 0.04 425 17
17
2 Basic Cost 17 A
3 Overhead charges (5%) 0.85 B=5% A
4 Establishment charges (2.5%) 0.425 C=2.5%*A
5 Total cost 18.275 D=A+B+C
6 Profit (10%) 1.8275 E=10%*D
Rate to be
quoted or
7 tendering cost 20.1025 F=D+E
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)
Preparing
surfaces and
sowing grass
seeds(0.05kg/sq
m) and watering
1 Labour
1.1 Mazdoor Sqm 0.04 425 17
2 Basic cost Sqm 17 A
3 Overhead charges 5% 0.85 B
4 Establishment charges 2.5% 0.425 C
5 Total cost 18.275 D=A+B+C
6 Contractor's profit 10% 1.8275 E
Rate to be quoted/tendering cost(rs/sqm 20.1025 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)
Trimming sides
of excavation
1 Labour
1.1 Mazdoor Sqm 0.013 425 5.525
2 Basic cost Sqm 5.525 A
3 Overhead charges 5% 0.27625 B
4 Establishment charges 2.5% 0.138125 C
5 Total cost 5.939375 D=A+B+C
6 Contractor's profit 10% 0.593938 E
Rate to be quoted/tendering cost(rs/sqm 6.533313 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)
Levelling
grading and
compacting
bottom of
excavation
1 Labour
1.1 Mazdoor Sqm 0.026 425 11.05
2 Basic cost Sqm 11.05 A
3 Overhead charges 5% 0.5525 B
4 Establishment charges 2.5% 0.27625 C
5 Total cost 11.87875 D=A+B+C
6 Contractor's profit 10% 1.187875 E
Rate to be quoted/tendering cost(rs/sqm 13.06663 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)
Ditto, but to
falls or
gradients.
1 Labour
1.1 Mazdoor Sqm 0.028 425 11.9
2 Basic cost Sqm 11.9 A
3 Overhead charges 5% 0.595 B
4 Establishment charges 2.5% 0.2975 C
5 Total cost 12.7925 D=A+B+C
6 Contractor's profit 10% 1.27925 E
Rate to be quoted/tendering cost(rs/sqm 14.07175 F=E+D
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)
Trimming
sloping faces of
embankments
and cuttings
1 Labour
1.1 Mazdoor Sqm 0.035 425 14.875
2 Basic cost Sqm 14.875 A
3 Overhead charges 5% 0.74375 B
4 Establishment charges 2.5% 0.371875 C
5 Total cost 15.99063 D=A+B+C
6 Contractor's profit 10% 1.599063 E
Rate to be quoted/tendering cost(rs/sqm 17.58969 F=E+D
30 Clear site of all rubbish, cut down shrubs, undergrowth and small trees not
exceedinding 600mm grith, grub up roots and burn or remove from site.
Sum of
Productiv amount
ity/Mater of
ial Cost per Sum/Am resource(
Sr. No. Description unit constant unit(₹) ount₹) ₹)
Direct/Indirect Cost of CM 1 : 1
Sum of
Sr. Description of Work Unit of Productivity Cost/Unit Sum of Amount
No. Work Constant Amount of
Resourses
A Material 7704.89
i Cement Kg 1058.830 5.65 5977.11
ii Sand Cum 0.730 2341.43 1709.98
iii Water Lit 140.000 0.13 17.80
B Labour for Mixing 470.00
i Mazdoor Cum 1.0 425.00 425.00
ii Bhisti Cum 0.1 450.00 45.00
C Basic Cost 8174.89
Direct/Indirect Cost of CM 1 : 3
Sum of
Sr. Unit of Productivity Sum of Amount
No. Description of Work Work Constant Cost/Unit Amount of
Resourses
A Material 5368.93
i Cement Kg 493.030 5.65 2783.16
ii Sand Cum 1.097 2341.43 2567.97
iii Water Lit 140.000 0.13 17.80
B Labour for Mixing 470.00
i Mazdoor Cum 1.0 425.00 425.00
ii Bhisti Cum 0.1 450.00 45.00
C Basic Cost 5838.93
Direct/Indirect Cost of CM 1 : 6
Sum of
Sr. Unit of Productivity Sum of Amount
Description of Work Cost/Unit
No. Work Constant Amount of
Resourses
A Material 4020.73
i Cement Kg 254.200 5.65 1434.96
ii Sand Cum 1.097 2341.43 2567.97
iii Water Lit 140.000 0.13 17.80
B Labour for Mixing 470.00
i Mazdoor Cum 1.0 425.00 425.00
ii Bhisti Cum 0.1 450.00 45.00
C Basic Cost 4490.73
Direct/Indirect Cost of CM 1 : 1
Sum of
Sr. Unit of Productivity Sum of Amount
Description of Work Cost/Unit
No. Work Constant Amount of
Resourses
A Material 7843.65
i Cement Kg 1058.830 5.65 5977.11
ii Sand Cum 0.730 2531.43 1848.74
iii Water Lit 140.000 0.13 17.80
B Basic Cost 7843.65
Direct/Indirect Cost of CM 1 : 3
Sum of
Sr. Unit of Productivity Sum of Amount
No. Description of Work Work Constant Cost/Unit Amount of
Resourses
A Material 5577.31
i Cement Kg 493.030 5.65 2783.16
ii Sand Cum 1.097 2531.43 2776.35
iii Water Lit 140.000 0.13 17.80
B Basic Cost 5577.31
Direct/Indirect Cost of CM 1 : 6
Sum of
Sr. Unit of Productivity Sum of Amount
No. Description of Work Work Constant Cost/Unit Amount of
Resourses
A Material 4229.11
i Cement Kg 254.200 5.65 1434.96
ii Sand Cum 1.097 2531.43 2776.35
iii Water Lit 140.000 0.13 17.80
B Basic Cost 4229.11
Cement Mortar Various Praportion by Hand Mixing
Direct/Indirect Cost of CM 1 : 2
A Material
i Cement Kg 699.050 5.65
2.5% Wastage ii Sand Cum 0.974 2341.43
iii Water Lit 140.000 0.13
B Labour for Mixing
i Mazdoor Cum 1.0 425.00
ii Bhisti Cum 0.1 450.00
C Basic Cost
Direct/Indirect Cost of CM 1 : 4
Unit of Productivit
Remark Sr. No. Description of Work Work y Constant Cost/Unit
A Material
i Cement Kg 382.330 5.65
2.5% Wastage ii Sand Cum 1.097 2341.43
iii Water Lit 140.000 0.13
B Labour for Mixing
i Mazdoor Cum 1.0 425.00
ii Bhisti Cum 0.1 450.00
C Basic Cost
Direct/Indirect Cost of CM 1 : 8
Unit of Productivit
Remark Sr. No. Description of Work Cost/Unit
Work y Constant
A Material
i Cement Kg 192.700 5.65
2.5% Wastage ii Sand Cum 1.097 2341.43
iii Water Lit 140.000 0.13
B Labour for Mixing
i Mazdoor Cum 1.0 425.00
ii Bhisti Cum 0.1 450.00
C Basic Cost
Direct/Indirect Cost of CM 1 : 2
Unit of Productivit
Remark Sr. No. Description of Work Cost/Unit
Work y Constant
A Material
i Cement Kg 699.050 5.65
2.5% Wastage ii Sand Cum 0.974 2531.43
iii Water Lit 140.000 0.13
B Basic Cost
Direct/Indirect Cost of CM 1 : 4
Unit of Productivit
Remark Sr. No. Description of Work Work y Constant Cost/Unit
A Material
i Cement Kg 382.330 5.65
2.5% Wastage ii Sand Cum 1.097 2531.43
iii Water Lit 140.000 0.13
B Basic Cost
Direct/Indirect Cost of CM 1 : 8
Unit of Productivit
Remark Sr. No. Description of Work Work y Constant Cost/Unit
A Material
i Cement Kg 192.700 5.65
2.5% Wastage ii Sand Cum 1.097 2531.43
iii Water Lit 140.000 0.13
B Basic Cost
of CM 1 : 2
Sum of
Sum of Amount Remark
Amount of
Resourses
6243.92
3946.15
2279.97 2.5% Wastage
17.80
470.00
425.00
45.00
6713.92
of CM 1 : 4
Sum of
Sum of Amount
Amount of Remark
Resourses
4744.02
2158.26
2567.97 2.5% Wastage
17.80
470.00
425.00
45.00
5214.02
of CM 1 : 8
Sum of
Sum of Amount
Remark
Amount of
Resourses
3673.56
1087.79
2567.97 2.5% Wastage
17.80
470.00
425.00
45.00
4143.56
of CM 1 : 2
Sum of
Sum of Amount
Remark
Amount of
Resourses
6428.93
3946.15
2464.98 2.5% Wastage
17.80
6428.93
of CM 1 : 4
Sum of
Sum of Amount
Amount of Remark
Resourses
4952.41
2158.26
2776.35 2.5% Wastage
17.80
4952.41
of CM 1 : 8
Sum of
Sum of Amount
Amount of Remark
Resourses
3881.94
1087.79
2776.35 2.5% Wastage
17.80
3881.94
Direct/Indirect Cost of PCC 1:5:10
Sum of
Sr. Unit of Productivit Cost/Uni Sum of Amount
No. Description of Work Work y Constant t of
Amount Resourse
s
Work out direct and indirect cost of PCC (1:5:10) for foundation bed (i.e. at a depth of 1.2m) Note: The
1 work site falls in both municipal and greater limits of Hyderabad. Work out percentages of all
resources.
A Material 3085.95
i Cement Kg 129.150 5.645 729.052
ii Fine Aggregate Cum 0.482 1276.300 614.858
iii Coarse Aggregate Cum 0.974 1778.900 1732.204
iv Water Lit 77.490 0.127 9.841
B Labour for Mixing 453.39
i Mazdoor Cum 0.5 425 212.5
ii Bhisti Cum 0.1 450 45
iii Mixer Operator Cum 0.07 500 35
iv Mixer Machine Cum 0.07 2298.4 160.888
C Labour for Conveying, Pouring, Curing etc. 812.48
i Mason Cum 0.1 470 47
ii Mazdoor Cum 1.13 425 480.25
iii Bhisti Cum 0.6 450 270
iv Vibrator Cum 0.07 217.6 15.232
D Basic Cost 4351.82
E Overhead Charges @ 5% 217.59
F Establishment Charges @ 2.5% 108.80
G Total Cost 4678.21
H Profit @ 10% 467.82
I Rate to be quoted/ Tendering Cost 5146.03
Remark
:
Direct/Indirect Cost of RCC 1:2:4
Sum of
Unit of Productivit Cost/Uni Sum of Amount
Sr. No. Description of Work Work y Constant t of
Amount Resourse
s
Work out direct and indirect cost of RCC (1:2:4) for footing bed (i.e. at a depth of 1.2m) Note:
1 The work site falls in both municipal and greater limits of Hyderabad. Work out percentages of
all resources.50%sand to be replaced with M Sand/Robo Sand,Mix super Plasticizer as
admixture, 1/3 of CA to be replaced with baby chips/10mm CA
A Material 3122.68
i Cement Kg 308.530 5.645 1741.652
ii Fine Aggregate Cum 0.226 1276.300 287.806
50% M Sand Cum 0.226
iii Coarse Aggregate Cum 0.601 1778.900 1069.712
1/3 Baby Chips/10 mm CA Cum 0.301
Super Plasticizer Kg 123.412 55.000 6787.660
iv Water Lit 185.118 0.127 23.510
B Labour for Mixing 453.39
i Mazdoor Cum 0.5 425 212.5
ii Bhisti Cum 0.1 450 45
iii Mixer Operator Cum 0.07 500 35
iv Mixer Machine Cum 0.07 2298.4 160.888
C Labour for Conveying, Pouring, Curing etc. 1092.63
i Mason Cum 0.17 470 79.9
ii Mazdoor Cum 1.5 425 637.5
iii Bhisti Cum 0.8 450 360
iv Vibrator Cum 0.07 217.6 15.232
D Basic Cost 4668.70
E Overhead Charges @ 5% 233.43
F Establishment Charges @ 2.5% 116.72
G Total Cost 5018.85
H Profit @ 10% 501.89
I Rate to be quoted/ Tendering Cost 5520.74
Remark
es
Cutting, bending, fabricating, placing in position and laying with MS wire at each intersection,
1 reinforcement using plain round/deformed/tor steel bars.( Consider 3% of steel as wastage Es
as salvage and 1.5% scrap )
A Material 5386.87 Overhe
i Rebar Quintel 1.000 5219.43 5219.43 5%
Wastage - Salvage Quintel 0.030 5219.43 156.58 Labour,
Wastage - Scrap Quintel -0.015 2609.72 -39.15 12%
ii Binding Wire kg 1.000 50.00 50.00
B Labour 895.00
i Blacksmith Quintel 1.00 470.00 470.00
ii Mazdoor Quintel 1.00 425.00 425.00
C Basic Cost 6281.87
D Overhead Charges @ 5% 314.09
E Establishment Charges @ 2.5% 157.05
F Total Cost 6753.01
G Profit @ 10% 675.30
H Rate to be quoted/ Tendering Cost 7428.31
Profit, 10%
Establishm
ent, 2%
Overhead, Material 72.5 5386.87
5% Labour 12.0 895.00
Material
Labour, Overhead Charges 5.0
Labour
314.09
12% Material,Charge
Establishment 2.5
Overhead 157.05
Charges
Profit 71% 10.0 675.30
Establishment Charges
Profit 7428.31
Direct/Indirect Cost of Burnt Brick Masonary Using Old S
1 Work out unit cost for constructing a masonary using burnt clay brick (traditional) in CM 1 : 4 in
ground floor one brick thick wall
A Material 5044.69
i Cement Mortar(1 : 4) Cum 0.252 5214.02 1314.72
ii Bricks Nos 466.375 8.00 3729.97
B Labour for Construction 1370.85
i Mason Cum 0.98 470 460.6
ii Mazdoor Cum 1.93 425 820.25
iii Bhisti Cum 0.2 450 90
C Labour for Raking out of joints 17.90
i Mason Sqm 0.02 470 9.4
ii Mazdoor Sqm 0.02 425 8.5
D Basic Cost 6433.44
E Overhead Charges @ 5% 321.67
F Establishment Charges @ 2.5% 160.84
G Total Cost 6915.94
H Profit @ 10% 691.59
I Rate to be quoted/ Tendering Cost 7607.54
Work out unit cost for constructing a masonary using burnt clay brick (traditional) in CM 1 : 3 in
2 ground floor to radius of 5.3m one brick thick wall
A Material 5202.26
i Cement Mortar(1 : 3) Cum 0.252 5838.93 1472.29
ii Bricks Nos 466.375 8.00 3729.97
B Labour for Construction 1718.30
i Mason Cum 1.24 470 582.8
ii Mazdoor Cum 2.46 425 1045.5
iii Bhisti Cum 0.2 450 90
C Labour for Raking out of joints 17.90
i Mason Sqm 0.02 470 9.4
ii Mazdoor Sqm 0.02 425 8.5
D Basic Cost 6938.46
E Overhead Charges @ 5% 346.92
F Establishment Charges @ 2.5% 173.46
G Total Cost 7458.84
H Profit @ 10% 745.88
I Rate to be quoted/ Tendering Cost 8204.72
Work out unit cost for constructing a reinforced (at every fourth layer) masonary using burnt
3
clay brick (traditional) in CM 1 : 3 in ground floor half brick thick wall
A Material 608.07
i Cement Mortar(1 : 3) Cum 0.024 5838.93 137.65
ii Bricks Nos 54.33 8.00 434.48
Work out unit cost for constructing a honeycomb masonary using burnt clay brick (traditional) in
4 CM 1 : 3 in ground floor half brick thick wall
A Material 360.59
i Cement Mortar(1 : 3) Cum 0.008 5838.93 49.08
ii Bricks Nos 38.950 8.00 311.51
B Labour for Construction 184.25
i Mason Sqm 0.2 470 94
ii Mazdoor Sqm 0.17 425 72.25
iii Bhisti Sqm 0.04 450 18
C Labour for Raking out of joints 17.90
i Mason Sqm 0.02 470 9.4
ii Mazdoor Sqm 0.02 425 8.5
D Basic Cost 562.74
E Overhead Charges @ 5% 28.14
F Establishment Charges @ 2.5% 14.07
G Total Cost 604.95
H Profit @ 10% 60.49
I Rate to be quoted/ Tendering Cost 665.44
Work out unit cost for constructing a reinforced (at every third layer) masonary using burnt clay
5
brick (traditional) in CM 1 : 3 in ground floor brick on edge wall
A Material 372.36
i Cement Mortar(1 : 3) Cum 0.009 5838.93 53.86
ii Bricks Nos 35.88 8.00 286.92
onal)
Remark
tional) in CM 1 : 4 in 10%
2%
5%
Material 66.31
Labour 18.25
Overhead 5.00 Material
Labour
Establishment 2.50
Overhead
18% Profit 10.00 Establishment
Profit
65%
onal)
Remark
tional) in CM 1 : 3 in
Material 63.41
Labour 10% 21.16
2%
Overhead 5.00
Establishment
5% 2.50
Material
Labour
Overhead
10%
2%
5%
Profit 10.00
Material
Labour
Overhead
21% Establishment
Profit
62%
nal)
Remark
10%
2%
5%
Material
Labour
Material 64.74 Overhead
19% Labour 19.83 Establishment
Overhead 5.00 Profit
Establishment 2.50 63%
Profit 10.00
raditional)
Remark
brick (traditional) in
Material10% 54.19
2%
Labour 30.38
5%
Overhead 5.00
Establishment 2.50
Profit 10.00 Material
Labour
Overhead
53% Establishment
Profit
30%
ditional)
Remark
10%
2%
5%
Material
Labour
Material 55.35 Overhead
Labour 29.22 54% Establishment
Overhead 5.00 Profit
29% Establishment 2.50
Overhead
54% Establishment
Profit
29%
Profit 10.00
Direct/Indirect Cost of Stone masonary
Sum of
Producti
Sr. Unit of vity Sum of Amount
No. Description of Work Work Constan Cost/Unit of
Amount Resourse Remark
t s
5%
Material 51.22
Labour 33.35
Material
Overhead 5
Labour
Establishm 2.5 Overhead
50%
Profit 10 Establishment
Profit
33%
Direct/Indirect Cost of Two coat plastering
Sum of
Sr. Unit of Productivit Sum of Amount
No. Description of Work Work y Constant Cost/Unit Amount of Remark
Resourses
Work out unit cost for plastering on to a one brick ( old size brick ) thick masonary in two coat,
1
whereas first coat of 9 mm CM (1 : 4) and second coat thickness of 3mm in CM (1 : 3)
Material 10% 34
Labour 2% 51
Overhead
5% 5
Establishment 2.5 33%
Material
Labour
Overhead
Establishment
10%
2%
5%
33%
Profit 10 Material
Labour
Overhead
Establishment
Profit
50%
Rs. Per
Sr.no Description unit
unit
work out cost per hour of a 4Cu.m tipper capital cost Rs 6 lakh
and life is 8000hours cost of tyres 0.75 lakh and life is 1500
hours
Soln:- Capital cost
deperciation of tipper = 90%*6lakh / 8000 hour 67.5 per hour
cost of per tyres = Rs. 75000/1500 hr 50 per hour
running repair of tipper = 40%*((90%*6lakh)/8000hour) 27 per hour
Total cost 144.5 per hour
Crew
1 No. helper @ Rs. 8000/- per month (8 hour per day*26 day) 8000 per month
1/4 No. security @ Rs. 8000/- per month (8 hour per day*26
day) 2000 per month
Total cost 30500 per month
Add, 25% toward bonus, gratuity etc 7625 per year
Fule
8 lit per hour of H.S,D @71.11 per liter 568.88 per hour
Lubricant 33% of diesel charge 187.7304 per hour
sundries 10% of above diesel charges 56.888 per hour
Total cost 813.498 per hour
Grand Total 1107.688 per hour
Rs. Per
Sr.no Description unit unit
Crew
1 No. operator @ Rs. 15000/- per month (8 hour per day*26
day) 15000 per month
1 No. helper @ Rs. 8000/- per month (8 hour per day*26 day) 8000 per month
1/4 No. security @ Rs. 8000/- per month (8 hour per day*26
day) 2000 per month
Total cost 30500 per month
Add, 25% toward bonus, gratuity etc 7625 per year
Fule
20 lit per hour of H.S,D @71.11 per liter 1422.2 per hour
Lubricant 33% of diesel charge 469.326 per hour
sundries 10% of above diesel charges 142.22 per hour
Total cost 2033.746 per hour
Grand Total 2389.436 per hour
Rs. Per
Sr.no Description unit unit
Repair : 20%
P.O.L : H.S.D. Diesel 30 lit per hour & lubricants etc.; 60%
diesel charges
Soln:- Capital cost
deperciation of transit mixer = 90%*21lakh / 10000 hour 189 per hour
running repair of transit mixer =
20%*((90%*21lakh)/10000hour) 37.8 per hour
Total cost 226.8 per hour
Crew
1 No. helper @ Rs. 8000/- per month (8 hour per day*26 day) 8000 per month
Fule
30 lit per hour of H.S,D @71.11 per liter 2133.3 per hour
Lubricant 60% of diesel charge 1279.98 per hour
sundries 10% of above diesel charges 213.33 per hour
Total cost 3626.610 per hour
Grand Total 3999.828 per hour
Rs. Per
Sr.no Description unit
unit
Crew
Total cost = Rs. Total amount(L.S) 50.000 per hour
Fule
18 lit per hour of H.S,D @71.11 per liter 1279.98 per hour
Lubricant 28% of diesel charge 358.3944 per hour
Total cost 1638.374 per hour
Grand Total 2138.374 per hour
Sr.no Description Rs. Per unit
unit
Work out per hour cost of batching plant 30Cu.m/hr
Capital cost : Rs 2200000/-
Life : 12000 hr
Depreacition : 95%
Repair : 100 %
crew
1 No. operator
1 No. operator for concrete drum
1 No. operator for water pump
3 No. helper
1 No. mechanic
1/2 No. Foremen
1/2 No. elctrician
1 No. security guard
Add 20 % toward bonus
Assumption 8*30*6+8*31*6 hours
P.O.L
7 lit diesel per hr and oil i.e. 20% diesel charges sundries 25%
of diesel charges
Crew
1 No. operator = 15000/- 15000 per month
1 No. operator for concrete drum = 12000/- 12000 per month
1 No. operator for water pump = 10000/- 10000 per month
3 No. helper = 8000/- 24000 per month
1 No. mechanic = 22000/- 22000 per month
1/2 No. Foremen = 20000/- 10000 per month
1/2 No. elctrician = 20000/- 10000 per month
1 No. security guard = 8000/- 8000.000 per month
sum amount of salaries 111000 per month
Adding 20% towards bonus/ Gratvity 22200 per month
cost per year 1354200 per year
Total cost 462.5 per hour
Fule
7 lit per hour of H.S,D @71.11 per liter 497.77 per hour
Lubricant 20% of diesel charge 99.554 per hour
sundries 25% of above diesel charges 124.4425 per hour
Total cost 721.767 per hour
Grand Total 1532.600 per hour