Professional Documents
Culture Documents
Quality Improvement Project Worksheet: (Apa Yang Terjadi Dengan Mutu ?)
Quality Improvement Project Worksheet: (Apa Yang Terjadi Dengan Mutu ?)
Methods Manpower
Ketrampilan staf yang berbeda Belum ada SOP stock obat minimal
Ketidaktersediaan …………..
…………. ……………..
……………. …………
Environment Machines
ONE DIAGRAM
……………
………….
Material
╗
╝
1
1
1
1
1
1
Supervisi Belum ada
Ketrampilan dan
Kriteria Pengawasan staf yang Ketidakterse konsultasi SOP stock
diaan obat
berbeda (kurang
minimal
Dampak Pada Pasien 5 5 5 tanggap)
5 5
Reputasi 5 5 5 5 5
Acceptance 4 5 2 4 5
Waktu yang
Dibutuhkan 3 5 2 5 5
Total Score 17 20 14 19 20
Duration (Days)
different for to the end date end of the End calculated, it
different of that task.
day. is calculated as
% Complete
levels. End Date minus
the Start Date
plus 1 day, so
that a task
Task (who) starting and
WBS Tasks (what) Lead Start (when) End ending on the
Pertemuan Penyusunan same day has a
1 SOP yayuk 10/17/18 10/26/18 10 duration
38% of 1
day.
1.1 membuat undangan 10/17/18 10/17/18 1 50%
1.2 menyiapkan tempat 10/18/18 10/18/18 1 100%
menyiapkan bahan
1.2.2 presentasi 10/20/18 10/26/18 7 25%
TEMPLATE ROWS: Copy and insert the entire section, or just the specific sub tasks, depending on which level you want to use (formulas are different for
Catatan
Kolom B Task --> Tulis tugas apa yang ingin dikerjakan pada action di "sheet plan"
Sub Task --> Tulis sub action dari yang ingin dikerjakan
Kolom C Task Lead --> Tulis siapa PIC untuk action plan yang akan dikerjakan
Kolom D Start : Masukkan tanggal kapan action plan atau sub action akan dimulai
Kolom E End : Masukkan tanggal kapan action plan atau sub action akan berakhir
Kolom F Duration Days : Masukkan jumlah hari waktu durasi untuk menyelesaikan action plan dan breakdown
Kolom G % Complete : Masukkan persentase sejauh mana action plan atau sub action sudah dilakukan (0% - 10
Kolom H Working Days : Jumlah hari durasi dikurangi hari libur kerja (waktu kerja efektif)
Kolom I Days Complete : Hasil perkalian kolom F dengan kolom G (persentase jumlah hari durasi yang sudah d
Kolom J Days Remaining : Pengurangan hasil di kolom F dengan kolom I (sisa hari yang masih tersisa untuk me
Duration
(Calendar Days) Terms of Use and
Enter the number Copyright:
of calendar days See the Terms Of
for the given Use worksheet
task. Refer to and the license
the Working Days agreement 0on
column or use a Working Days Vertex42.com.
calendar to Counts the HELP Copyright
determine the number of notices may not
corresponding working days be removed.
working days. using the Calendar Days
7/12/2015
The duration isPercent Complete NETWORKDAYS() Complete Minggu
Calendar Days
from the (vertical
Update the
red line) formula, which This column is Remaining
beginning of the
status of this excludes calculated by This column is
Start date to task by entering weekends. When multiplying thecalculated by
the ending of the percent planning work Duration by thesubtracting the
the End Date. complete based upon the %Complete and Days Complete
(between 0% andnumber of rounding down to from the
When the 100%). First Day
working of Week
days, the (Mon=2):
nearest 2
Duration. ### 10/22/2018
### 10/29/2018
duration is adjust the integer.
Days Remaining
Days Complete
15 - Oct - 18
22 - Oct - 18
is calculated as the desired # of
End Date minus working days is
the Start Date reached.
plus 1 day, so
that a task
starting and
ending on the
same day has a
duration of 1 8 3 7
day.
1 0 1
1 1 0
1 0 1
5 1 6
19 6 19
4 1 4
5 1 4
5 1 4
5 1 4
1770 0 2480
3 0 5
3 0 5
3 0 5
4 0 5
1 0 1
1 0 1
1 0 1
1 0 1
29 - Oct - 18
11/6/2018 11/7/2018 11/8/2018 11/9/2018 11/10/2018 11/11/2018 11/12/2018
05 - Nov - 18
11/13/2018 11/14/2018 11/15/2018 11/16/2018 11/17/2018 11/18/2018 11/19/2018
12 - Nov - 18
11/20/2018 11/21/2018 11/22/2018 11/23/2018 11/24/2018 11/25/2018 11/26/2018
19 - Nov - 18
11/27/2018 11/28/2018 11/29/2018 11/30/2018 12/1/2018 12/2/2018 12/3/2018
26 - Nov - 18
12/4/2018 12/5/2018 12/6/2018 12/7/2018 12/8/2018 12/9/2018 12/10/2018
03 - Dec - 18
12/11/2018 12/12/2018 12/13/2018 12/14/2018 12/15/2018 12/16/2018 12/17/2018
10 - Dec - 18
12/18/2018 12/19/2018 12/20/2018 12/21/2018 12/22/2018 12/23/2018 12/24/2018
17 - Dec - 18
12/25/2018 12/26/2018 12/27/2018 12/28/2018 12/29/2018 12/30/2018 12/31/2018
24 - Dec - 18
1/1/2019 1/2/2019 1/3/2019 1/4/2019 1/5/2019 1/6/2019 1/7/2019
31 - Dec - 18
1/8/2019 1/9/2019 1/10/2019 1/11/2019 1/12/2019 1/13/2019 1/14/2019
07 - Jan - 19
1/15/2019 1/16/2019 1/17/2019 1/18/2019 1/19/2019 1/20/2019 1/21/2019
14 - Jan - 19
1/22/2019 1/23/2019 1/24/2019 1/25/2019 1/26/2019 1/27/2019 1/28/2019
21 - Jan - 19
1/29/2019 1/30/2019 1/31/2019 2/1/2019 2/2/2019 2/3/2019 2/4/2019
28 - Jan - 19
2/5/2019 2/6/2019 2/7/2019 2/8/2019 2/9/2019 2/10/2019 2/11/2019
04 - Feb - 19
2/12/2019 2/13/2019 2/14/2019 2/15/2019 2/16/2019 2/17/2019 2/18/2019
11 - Feb - 19
2/19/2019 2/20/2019 2/21/2019 2/22/2019 2/23/2019 2/24/2019 2/25/2019
18 - Feb - 19
2/26/2019 2/27/2019 2/28/2019 3/1/2019 3/2/2019 3/3/2019 3/4/2019
25 - Feb - 19
3/5/2019 3/6/2019 3/7/2019 3/8/2019 3/9/2019 3/10/2019 3/11/2019
04 - Mar - 19
3/12/2019 3/13/2019 3/14/2019 3/15/2019 3/16/2019 3/17/2019 3/18/2019
11 - Mar - 19
3/19/2019 3/20/2019 3/21/2019 3/22/2019 3/23/2019 3/24/2019 3/25/2019
18 - Mar - 19
3/26/2019 3/27/2019 3/28/2019 3/29/2019 3/30/2019 3/31/2019 4/1/2019
25 - Mar - 19
4/2/2019 4/3/2019 4/4/2019 4/5/2019 4/6/2019 4/7/2019 4/8/2019
01 - Apr - 19
4/9/2019 4/10/2019 4/11/2019 4/12/2019 4/13/2019 4/14/2019 4/15/2019
08 - Apr - 19
4/16/2019 4/17/2019 4/18/2019 4/19/2019 4/20/2019 4/21/2019 4/22/2019
15 - Apr - 19
4/23/2019 4/24/2019 4/25/2019 4/26/2019 4/27/2019 4/28/2019 4/29/2019
22 - Apr - 19
4/30/2019 5/1/2019 5/2/2019 5/3/2019 5/4/2019 5/5/2019 5/6/2019
29 - Apr - 19
5/7/2019 5/8/2019 5/9/2019 5/10/2019 5/11/2019 5/12/2019 5/13/2019
06 - May - 19
5/14/2019 5/15/2019 5/16/2019 5/17/2019 5/18/2019 5/19/2019 5/20/2019
13 - May - 19
5/21/2019 5/22/2019 5/23/2019 5/24/2019 5/25/2019 5/26/2019 5/27/2019
20 - May - 19
5/28/2019 5/29/2019 5/30/2019 5/31/2019 6/1/2019 6/2/2019 6/3/2019
27 - May - 19
6/4/2019 6/5/2019 6/6/2019 6/7/2019 6/8/2019 6/9/2019
03 - Jun - 19
Pareto Analysis
[Chart Title]
25 100%
20 80%
Vital Few
Cumulative %
坐标轴标题
15 60%
Useful Many
Labels
Cumulative%
10 40%
Cut Off %
5 20%
[42]
0 0%
坐标轴标题
Pengawasan
Ketidaktersediaan Obat
ACTION PLAN TOOL
WHAT WHO
60
50
40
30
20
Jan feb maret april mei juni juli agustus september okt nov des
K
e
y
M
e
a
s
u
r
e
Graphs of Key Measures Put Your Center Name Here
LATIHAN SOAL ENTRI DATA INDIKATOR
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60
100 60