PROJECT TITLE : PROPOSED TWO (2) STOREY RESIDENTIAL BUILDING

PROJECT LOCATION : L24, B3, Greenwoods Subd., Brgy. Sampaga, Batangas City
PROJECT OWNER : Sps. Christopher & Rischel Leynes
TOTAL LOT AREA : 270 square meter

SUBJECT : CONCRETE WORKS

DIMENSIONS
MARK QUANTITY VOLUME
Width Length THK/Height
COLUMNS
I. Column Footing
F1 1.20 1.20 0.30 19 8.21
F2 0.80 0.80 0.30 4 0.77
Total Volume (cu.m.) 8.98
II. Column (Ground Floor)
C1 0.25 0.45 3.50 19 7.48
C2 0.15 0.30 3.50 4 0.63
Total Volume (cu.m.) 8.11
III. Column (Second Floor)
C1 0.25 0.45 3.00 9 3.04
PC-1 0.15 0.40 3.00 12 2.16
Total Volume (cu.m.) 5.20

BEAMS
I. Beams (Second Floor)
B1-a 0.20 4.25 0.45 1 0.38
B1-b 0.20 4.75 0.45 1 0.43
B1-c 0.20 2.40 0.45 2 0.43
B1-d 0.20 3.40 0.45 2 0.61
B1-e 0.20 5.10 0.45 1 0.46
B1-f 0.20 1.70 0.45 1 0.15
B1-g 0.20 4.00 0.45 3 1.08
B1-h 0.20 3.70 0.45 1 0.33
B1-i 0.20 4.20 0.45 1 0.38
B2-a 0.20 2.40 0.45 1 0.22
B2-b 0.20 4.25 0.45 1 0.38
B2-c 0.20 3.50 0.45 5 1.58
B2-d 0.20 2.75 0.45 1 0.25
B2-e 0.20 3.25 0.45 4 1.17
B2-f 0.20 2.00 0.45 3 0.54
B2-g 0.20 1.00 0.45 8 0.72
B2-h 0.20 1.60 0.45 3 0.43
B2-i 0.20 1.80 0.45 2 0.32
B2-j 0.20 3.70 0.45 2 0.67
B2-k 0.20 2.50 0.45 2 0.45
Total Volume (cu.m.) 10.98
II. Roof Beams
RB-a 0.20 4.25 0.30 2 0.51
RB-b 0.20 4.75 0.30 2 0.57
RB-c 0.20 3.30 0.30 4 0.79
RB-d 0.20 4.70 0.30 3 0.85
RB-e 0.20 1.00 0.30 2 0.12
RB-f 0.20 2.40 0.30 3 0.43
RB-g 0.20 5.10 0.30 4 1.22
RB-h 0.20 2.50 0.30 2 0.30
RB-i 0.20 4.00 0.30 2 0.48
RB-j 0.20 3.70 0.30 2 0.44
RB-k 0.20 4.20 0.30 2 0.50
Total Volume (cu.m.) 6.22
DIMENSIONS
MARK QUANTITY VOLUME
Width Length THK/Height
SLABS
I. Slab (Ground Floor)
SOG 102.30 0.15 15.35
I. Slabs (Second Floor)
S2-1a 2.40 4.25 0.10 1 1.02
S2-1b 1.50 4.75 0.10 1 0.71
S2-1c 0.90 2.75 0.10 1 0.25
S2-1d 1.60 3.50 0.10 2 1.12
S2-1e 1.60 2.00 0.10 1 0.32
S2-1f 1.60 1.00 0.10 1 0.16
S2-1g 1.80 3.50 0.10 1 0.63
S2-1h 1.80 2.00 0.10 1 0.36
S2-1i 1.80 1.00 0.10 1 0.18
S2-1j 3.50 3.50 0.10 1 1.23
S2-1k 1.70 3.00 0.10 1 0.51
S2-1l 1.70 2.00 0.10 1 0.34
S2-1m 1.70 1.00 0.10 1 0.17
S2-1n 2.50 3.50 0.10 1 0.88
S2-1o 1.55 3.50 0.10 1 0.54
S2-1p 3.70 3.30 0.10 1 1.22
S2-2 4.00 1.00 0.10 2 0.80
Total Volume (cu.m.) 10.43

STAIRS
Stair (Ground to Second Floor) 1.41 1.20 1.69

Total Concrete Volume (cu.m.) 66.95

PREPARED BY : GUTIERREZ, John Paul B


ILANO, Mikko Anesor A.
BSCE-3B

CHECKED BY : Engr. Edgardo Legaspi