Professional Documents
Culture Documents
Jason Ng
Geotechnical Engineering Graduate
Housing Department of HKSAR
28 May 2013
1
CONTENT
• Case Studies
• Concluding
C l di remarks
k
1
6/9/2013
• Ground Investigations
in Stages
t update
to d t andd obtain
bt i
information to complete
Site Investigation
Project Programme
2
6/9/2013
Stage 1
Stage 2
3
6/9/2013
Stage 3
• More specific
• Boreholes planned at locations of bored piles
7
• Verifying the depth of rock stratum
Project 1
Block 2
- 3 Building
B ildi Blocks
Bl k supported
t d by
b
50 bored piles
Block 1
- ~100 nos. of boreholes in 3
stages
Block 3
4
6/9/2013
30 m Grid 20 m Grid
5
6/9/2013
98 5
% of P
4
97 3
10 m Grid 2
96 20 m Grid (182 nos.)
30 m Grid (20 nos.) (42 nos.) 1
0.2%
95 0
1 10 100 1000 10000
Drillhole Number
• In comparison, Grid Approach requires 10 times more no. of boreholes than Staged Approach
11
12
6
6/9/2013
Acknowledgments:
Thank you
13
Questions?
or
Discussions?
14
7
6/9/2013
Project 1
Project 2
Project 3
15
Project 1 Project 1*
Block 2 Block 2
Block 1 Block 1
Block 3 Block 3
16
8
6/9/2013
10m 5m
100 20m 8
30m
Project 1
7
% of P
5
80 4
30m
• 5 m Grid gives relatively 75% 3
60 0
1 10 100 1000 10000
Drillhole Number
x 100 nos.
x 10 nos.
100 8
Multi-Staged line
% of Similarity of Rockheead Level 7
90 6
• Similar Results for
Project 1* and Project 2* 5
% of P
80 4
60 0
1 10 100 1000 10000
Drillhole Number
17
Depends on
Boreholes Spacing
planning
l i
30 m 20m 10m 5m
% of to Planned
1 0.2 0.4 1.7 6.7
Total Expenditure (P)
Similarity to as-built
Rockhead Level
100% Finer the Grid, Higher the Similarity
18