Professional Documents
Culture Documents
Vedanta Group
The InSites
Takeaways from site visits
During March 1-4, we visited mines and plant sites of Vedanta group of companies
across India. The companies covered were (1) Hindustan Zinc, (2) Sterlite Energy,
(3) Vedanta Aluminium and (4) Sesa Goa. We present our key takeaways below.
7 March 2011 2
The InSites
Source: Company/MOSL
Evonics Energy, a German contractor, has been given O&M contract. This unit is
supplying power to state grid through 450MW line, which can take maximum of 500MW.
PLF ramp up remains slow due to lack of demand from state. State grid (Gridco) is
buying power at Rs3.2/kwh. Coal cost is pass-through in agreement with state grid.
600MW Unit 1 too has been started. Though the unit was ready operationally some
time ago, power generation was delayed due to delay in getting transmission line.
600MW Line-in Line-out (LILO-1) was charged towards end of February i.e. couple
of days before our site visit. The unit was being readied for charging to the grid. As
shown in the following picture, the control shows 0% PLF. Chinese contractor has
been hired for O&M of this unit as seen in the following picture.
Unit 1 (600MW)
Source: Company/MOSL
The power plants are heavily dependent on purchase of coal through e-auction and
forward auctions because linkage coal from Coal India is only 65%. Nearly 10% of
coal consumed is imported. Though the coal mines are in proximity, the availability of
rakes remains poor. Nearly 60% of coal is transported through roads. An average
2,500 trucks remain engaged for delivery of coal. Since the e-auction coal is not
uniformly distributed through the month, the number of trucks touches 6,000 in peak
days. Commercial generation of 1,200MW i.e. first 2 units is expected to start from
April, 2011.
7 March 2011 3
The InSites
Unit 3 and 4 are expected to start generation by September and December 2011
respectively. The power evacuation will remain dependent on getting 1,000MW LILO-
2 and IB-Meramundli tansmission line. Though LILO-2 will be ready in next 6 months,
the IB-Meramundli line will take 12-15 months.
Boiler house: 3rd units (blue) completion; 4th unit (brown) VAL’s 0.5mtpa aluminum smelter potline
still under construction
Source: Company/MOSL
To strengthen the logistics to handle huge requirement of raw materials, the company
is laying out 85km of railway lines at cost of Rs4b. Two projects have been completed.
3rd project will be completed by March 2011. 17-18km of Dhutra line is expected in
4QFY11. A merry-go-around to connect to captive coal mines is expected by 2013.
Currently 50,000 tons per month of coal is being imported, which will go to 100,000tpm
at full production rate. At Jharsuguda, 4,400 acres of land has been acquired. Land for
ash pond is under acquisition.
7 March 2011 4
The InSites
Reserves Resources
197
183
152
133
109
98
92
102
89
80
77
69
67
54
Source: Company/MOSL
7 March 2011 5
The InSites
Source: Company/MOSL
After a presentation on Hindustan Zinc, we visited Dariba complex. Zinc smelter was
operating at full capacity, while lead and silver smelters are expected to start production
by end of March 2011. Thereafter, we visited underground SK mine.
7 March 2011 6
The InSites
Dariba Zinc Smelter: Cell house and output of zinc in sheet form
Source: Company/MOSL
Rampura Agucha: Elevation (left) and mine cutting plan (right) - replica of actual mine
Chanderiya smelter: Cell house (left) and robot stacking zinc slabs (right)
Source: Company/MOSL
7 March 2011 8
The InSites
Sesa Goa: Shonshi mines - full mine view (left) and zoomed to ore body (right)
Sesa: North Goa mines map (left) and out going barge (right) loaded with iron ore
Source: Company/MOSL
The site visit was followed by presentation by management. Sesa continues to pursue
mine capacity expansion. Currently, the R&R stand at 275m tons, which has been
increased by 120m tons since acquisition by Vedanta. Nearly 85m tons of R&R were
added to erstwhile Sesa and 35m tons of R&R have been added to Dempo's assets
through continuous drilling and exploration. Sesa indicated that R&R are further
expected to be enhanced once the results of exploration are announced along with the
annual results for FY11.
7 March 2011 9
The InSites
Sesa has permission to mine total of 22mtpa (16mtpa in Goa and 6mtpa in Karnataka).
The shipments are expected to be flat at 20.5m tons in FY11 and 25m tons in FY12
subject to getting permission to expand Karnataka mines from 6mtpa to 10mtpa and
lifting of export ban. Karnataka mines are currently selling to domestic producers at
discount of US$35/ton to the export parity prices. The realization is likely to further dip
due to enhancement of export duty to 20%. Karnataka mines dispatched 3.5m tons in
FY10 and 2.5m tons in FY11, while the target for FY12 is 6m tons. Though Karnataka
mine expansion and logistics debottlenecking have achieved many milestones, some
more approvals are still pending. There is apparently no visibility over mine expansion
permission for Goa mines though management is targeting to expand total mine capacity
to 30mtpa by end of FY12 and 40mtpa by end of FY13.
We met couple of local mining companies to understand the sentiments. Goa miners
are very disappointed with the recent hike in export duty to 20% on fines. Most miners
are currently sharpening the axe to make presentation to ministry against hike in duty.
There is very high probability that export duty on fines may be lowered because
exports of very low grade like 48% Fe, which fetches as low as US$30/ton (though
63% Fe grade ore is selling at US$170/dmt) have become unviable. Also, there are
possibilities of introducing more slabs for low-grade ore to reduce the burden of royalty
on very low grade ore.
DCF valuation
Rs Million Case Iron ore DCF Sesa’s Remarks
WACC (%) 10 63% Fe Rs/share Realization
Terminal Growth (%) 3 (US$/dmt fob) (US$/wmt fob)
NPV of cashflows post 1 70 145 43.0 Most Chinese mines become unviable
FY12 (a) 180,858 2 80 180 52.0
Cash surplus (b) 95,915 3 90 215 61.0
Terminal Value (c ) 10,152 4 100 249 70.0
Equity value (a+b+c) 286,925 5 120 319 87.3 Some Chinese mines become unviable
Number of shares (m) 900 6 140 388 105.0
DCF value/share (Rs) 319 7 160 458 106.0
Source: MOSL
7 March 2011 10
The InSites
7 March 2011 11
The InSites
7 March 2011 12
The InSites
7 March 2011 13
Motilal Oswal
Product Gallery
The report is based upon information that we consider reliable, but we do not represent that it is accurate or complete, and it should not be relied upon such. MOSt or
any of its affiliates or employees shall not be in any way responsible for any loss or damage that may arise to any person from any inadvertent error in the information
contained in this report. MOSt or any of its affiliates or employees do not provide, at any time, any express or implied warranty of any kind, regarding any matter
pertaining to this report, including without limitation the implied warranties of merchantability, fitness for a particular purpose, and non-infringement. The recipients of
this report should rely on their own investigations.
MOSt and/or its affiliates and/or employees may have interests/ positions, financial or otherwise in the securities mentioned in this report. To enhance transparency,
MOSt has incorporated a Disclosure of Interest Statement in this document. This should, however, not be treated as endorsement of the views expressed in the report.
The MOSt group and its Directors own shares in the following companies covered in this report: Nil
MOSt has no broking relationships with the companies covered in this report.
MOSt is engaged in providing investment-banking services in the following companies covered in this report: Nil
This information is subject to change without any prior notice. MOSt reserves the right to make modifications and alternations to this statement as may be required
from time to time. Nevertheless, MOSt is committed to providing independent and transparent recommendations to its clients, and would be happy to provide
information in response to specific client queries.