Professional Documents
Culture Documents
PowerLogic
Solutions
Volume 4, Issue 2 Complex PQ Problem Yields
Simple Solutions
In this issue, we Problem
present a voltage
transients problem A metal-casting plant producing ductile iron castings for the auto-
resolved through motive industry suffered catastrophic shutdowns (figure 1) of both of
comprehensive its induction melting furnaces. The furnace failures occurred within
engineering analysis. three days of each other, shortly after the plant returned to production
after Christmas shutdown. After investigating the first failure, plant
and utility personnel assumed the cause of
the first failure had been found. They
resumed the start-up procedure three days
later, only to have an almost identical
failure of their backup furnace, causing
another shutdown.
Figure 1. This
busbar, serving Plant engineers were concerned that
induction furnace recent changes in the electric utility’s
power supplies, distribution system might have initiated
failed catas- the failures. The utility denied any
trophically on
twin furnaces
relationship between the changes and the
during two failures. The discussion reached an
separate events. impasse. The plant shutdown continued
for nearly a week, while repairs were being
completed, jeopardizing the plant’s just-in-time status with its
automotive customers.
1544V
39,525A
Voltage, across fuses
Current
Figure 3. Induction furnace fuse testing at Square D’s High-Power Test Lab eliminated the current
chop theory.
PowerLogic
Solutions
Figure 6. Analysis revealed a simple cause of the failures: busbars were inadequately braced to withstand the
forces generated during a short circuit.
Bulletin No. 3000HO9802 10M DL 8/98 1998 Square D All Rights Reserved